Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 17

PROJECT : WTC PLAZA AT 106 , GURGAON PHASE-II

Brief summary of Project


1 Total Land Area 5.35623 Acres
2 Total Nos of Residential Plots 97
3 Total Nos of Commercial Plots 2
4 Total Green Area 0.4621 Acres
5 Total Area under Community Facilities 0.5360 Acres
6 Milk Booth
Community Center
Substation
Other Services
Underground Water Tank (UGT)

Sewerage Treatment Plant (STP)

APPROXIMATE AMOUNT FOR COMPLETION OF BALANCE WORK


S.N. Description of item Amount in Rs.

1 Roads Works including all works #REF!

2 Civil Works including finishing

3 Waterproofing works

4 De-watering works

Sewerage Treatment Plant (STP) & Water


6 Treatment Plant (WTP) including control Panels

7 Plumbing Works including all works

8 Electrical Works

9 Entrance Control of CLS & VA

Grand Total excluding GST #REF!


PROJECT : PROPOSED 5.35625 ACRE RESIDENTIAL PLOTTED COLONY UNDER DEEN
DAYAL JAN AWAS YOJNA
SUBJECT : SEWAGE TREATMENT PLANT (STP) ON MBBR, CAPACITY : 250 KLD

SUMMARY OF COST

Item No. Description

WATER TREATMENT

A. SEWAGE TREATMENT PLANT 260 KLD

B. CONTROL PANEL FOR SEWAGE TREATMENT PLANT

GRAND TOTAL

Item No. Description Unit Qty. Rate


A. SEWAGE TREATMENT PLANT ( 250 KLD)

1 Design, supplying, installing, testing & commissioning of


Sewage Treatment Plant (excluding excavation, back
filling & disposal of surplus earth Civil construction work)
for the following duty:

Nature of effluent - Domestic Sewage from Public


toilets, Kitchen etc.

Daily average flow -250 Cum / Day

pH - 7.5 – 8.5

BOD5 - 250 – 350 Mg/L

S. Solids - 300 – 450 Mg/L

COD - 400 – 600 Mg/L

Oil & Grease - 50 Mg / L

Effluent discharge standard after treatment

pH - 6.0 – 8.5
BOD5 - Less than 20 Mg/L

S. Solids - Less than 20 Mg/L

COD - Less than 60 Mg/L

Oil & Grease - Less than 5 Mg/L

Sewage treatment plant shall include the following items:

Screen Chamber
Oil & Grease Chamber
Sewage Equalization Tank/Sump
FAB Tank. (2 Nos)
Secondary Tube Settler Tank (1 Nos)
Clarified Contact Tank
Sludge Holding Tank
Soft Water Tank (OPTIONAL)
Irrigation Water Tank
Air Blowers, Pumps & equipment
Sludge Feed Pump & Centrifuge
Piping, valves etc
Electrical Panel & Cabling
Common plant room adjacent to STP.

1.1 Supply, installation, testing & commissioning of 2 Nos


Stainless Steel Bar Screen with suitable lifting arrangement
(size 700 mm wide x 900 mm high approx) Set 1 50,000.00

1.2 Supply, installation, testing & commissioning of electronic


type level indicator and controller for automatic operation of
the system with high/low level complete with auxillary
NO/NC contacts.
Sets 3 6,000.00

1.3 Supply, installation, testing & commissioning of sight


tube (of 3.5 to 4.5 m length) with isolation valve at
top/bottom, demarcation on tube & for making the
installation complete- this is in civil contractor scope.
Nos. 3

Contractor shall ensure submission of detailed GA


drawings (Plan & Section), P & I diagram, schematic
diagram for the above mentioned component and
additional component if so required for the complete
working of the STP and got it approved by the Owner’s
Architect / Project Manager / Consultants. .
1.4 Supply, installation, testing & commissioning of non
clogging type pumps capable of handling solids upto 30-35
mm having CI casing & impeller complete with all
accessories, motor of required capacity. Delivery header
with isolation valve, pressure gauge on delivery line with
isolation cock, level controller (with wiring) to control the
level of sump automatically. Pumps shall have following
duty (At EQT. Tank)

1.4.1 Submersible Sump Pumps 1 Set = 2 Nos ( 1W + 1SB)

Flow rate (each) = 13 m3/hr


Head = 8 - 10 Mtr Set 1 120,000.00
Make: KSB / WILO / Grundfos

1.4.2 Plant room sump pump with CI body & CI impeller pump,
Solid Handling capacity should be 12-15mm
( 1W + 1 SB)
Flow rate (each) = 18 m3/hr
Head = 10 - 12 Mtr Nos. 2 72,000.00
Make: KSB / WILO / Grundfos

1.4.3 Horizontal Self Priming Sludge Recirculation pump with CI


body & CI impeller pump
( 1W + 1 SB)
Flow rate (each) = 13 m3/hr
Head = 10 - 12 Mtr Nos. 2 28,000.00
Make: Kirloskar, Mode : SP0M
(Solid handling size for this pump shall be 7 mm).

Cost shall be inclusive of PVC flexible Hose pipe ( for


piping submeged in effluent) with M S epoxy piping (for
piping non-submerged in effluent)

Provision of guide ropes to guide submersible pump from


upper level to operational level in sump basin with
channels / angle section shall be made by the STP
contractor.
1.5 Air diffusion system shall include the following:

1.5.1 Twin lobe rotary air blowers capable of delivering 275


m3/hr. of free air at 5 Mts. driven through “V” belt or
directly coupled through flexible coupling to a TEFCmotor
of suitable HP Suitable for 415 ± 10% volts, 3 phase, 50
cycles A/C supply. ( 1W + 1 SB)
Nos. 2 215,000.00
Make: Beta / Everest / Subhash
1.5.2 Air piping shall comprise of pipes droppers / laterals with
SS 304 / CPVC Header complete with all fittings such as
tees, crosses, plugs, sockets, elbows, reducers, supports &
clamps, puddle flanges etc cutting chases & making good.
Contactor to submit detailed P & I indicating their proposal
Lot 1 200,000.00

1.5.3 Non clog type air dispersion system capable of handling 3-


5 cfm of air with oxygen transfer efficiency of 3-4%
per/meter water depth. Air dispersion grid shall be
assembled in modular form so that they can be replaced /
repaired easily from platform at the top. (Min Number of
Diffuser: 32)
Lot 1 180,000.00
Make: Welcome/MM Aqua/Cooldeck

1.5.4 Bronze Ball valve and air dispersion grid as required for
STP as described above. Lot 1 120,000.00

1.6 Supply, installation, testing & commissioning of PVC FAB


media in FAB Tank & PVC Tube Deck media Secondary
Tube Settler Tank. (Approx Qty of FAB Media: 25m 3)
Job 1 270,000.00

1.7 Providing and fixing all piping (as described below) and
isolation control valves for making the system complete.

SS 304 : Submerged air piping


MS Epoxy : Air piping
uPVC Piping : Pumped effluent & tank overflow pipe line
uPVC Piping : Interconnecting pipe line after delivery
header of pump/ filter Job 1 200,000.00

1.8 Supplying, installing, testing & commissioning of


Horizontal centrifugal filter feed water pumps CI Body,
CI Impeller, SS Shaft, with mechanical seal along with
Coupled motor, pressure gauge with isolation cock,
Isolation valve, NRV on delivery line. Isolation valve,
stainer at suction. Mechanical seal, suitable vibration
elimination pads of approved design. The pump shall
be suitable for 415±10% volts 3 phase AC supply. ( 1W +
1SB )

Capacity : 18 m3/hr
Head : 30 - 35 M Nos. 2 38,000.00
Make : Kirloskar
1.9 Supplying, installing, testing & commissioning of
Horizontal centrifugal Irrigation water transfer pumps
CI Body, CI Impeller, SS Shaft, with mechanical seal
along with Coupled motor, pressure gauge with isolation
cock, Isolation valve, NRV on delivery line. Isolation valve,
stainer at suction. Mechanical seal, suitable vibration
elimination pads of approved design. The pump shall
be suitable for 415±10% volts 3 phase AC supply. ( 1W
+ 1SB )

Capacity : 20 m3/hr ( 1W + 1 SB)


Head : 48 - 50 M
Purpose : Irrigation Water Transfer Pump Nos. 1 140,000.00
Make : Kirloskar

1.10 Supplying, installing, testing & commissioning of


Horizontal centrifugal Flushing water transfer pumps CI
Body, CI Impeller, SS Shaft, with mechanical seal along
with Coupled motor, pressure gauge with isolation cock,
Isolation valve, NRV on delivery line. Isolation valve,
stainer at suction. Mechanical seal, suitable vibration
elimination pads of approved design. The pump shall
be suitable for 415±10% volts 3 phase AC supply. ( 1W
+ 1SB )

Capacity : 20 m3/hr ( 1W + 1 SB)


Head : 48 - 50 M
Purpose : Flushing Water Transfer Pump Nos. 1 140,000.00
Make : Kirloskar

Note:
Operation of pump shall be based on level controller
proposed to be installed in tank as per site location. The
contractor to recheck the Head required for pumps as per
site conditions and provide accordingly.

1.11 Supplying, installing, testing and commissioning of dosing


system consisting of one HDPE tank of 100 litres capacity
with a positive displacement diphragm dosing pump
having variable flowrate of 0-6 lph. The motor shall be
suitable for operation at 240 V / single phase /50 Hz.
Supply. The pump shall be supplied complete with
necessary polypropylene piping, valves, strainers, low level
switch and injection fittings. The pump shall be speed &
stroke control Make: Toschon / Asia LMI / equivalent
make.
Set 1 23,000.00
1.12 Supplying, installing, testing and commissioning of MS
epoxy coated vessel filter. Filter shall be suitable for
working pressure of 3.0 kg / cm2 and shall include media,
standard fittings like pressure gauges, sampling cock,
backwash, rinse drain, vacuum breaker, including frontal
piping.

1.12. Multigrade pressure sand filter


1 Nos. 1 260,000.00
Flow rate : 18 m3/hr
Dia : 1300 mm

1.12.
2 Activated Carbon Filter Nos. 1 290,000.00
Flow rate : 18 m3/hr
Dia : 1300 mm

1.13 Supply, installation, testing & commissioning of water


softening plant (MS with FRP Lining) for make-up water
for cooling towers comprising of face piping with butterfly
valve with brine ejector and plastic piping complete with
brine tank with fittings and brine filtering media and
complete charge of cation exchange resin as per
speciftication for the capacity as given below:

Water Flow : 18 m3/hr


(Incoming hardness 300 mg / Ltr (Approx))
Working pressure 3.0 Kg / Cum)
Outgoing hardness less than 50 ppm
Water Softening plant as described above
Resin Qty : 1550 litrs
OBR - 250 m3 Nos. 1 380,000.00

1.14 Supplying, installation & commissioning of Centrifuge

M.O.C. : MS with SS Internals


Dia : 600 mm
Filter cloth : PP Bag Set 1 160,000.00

1.15 Supplying, installation & commissioning of sludge feed


pump of capacity 1.0 m3 / hr. at 15 mtr. Head ( 1 W + 1SB)
Set 1 52,000.00
1.16 Supply, installation, testing & commissioning of Ultra voilet
syetm for disinfection having 4 nos. quartz jacket, inlet
outlet 3" 150 lb raised face flange. Cabinet size of
600x600x210 mm as per IP 54. UV doses should be >
60000 m W -sec/cm2. Make : Alfa,
Set 1 210,000.00
Flow- 20 m / hr.
3

1.17 Supplying, installation & commissioning of sumersile mixer


for Anoxic Tank. Make: CRI/ Eqv Set 1 34,000.00

1.18 Supplying, installation & commissioning of Electromagnetic


Flow Meter at inlet after Raw Sewage Transfer Pump and
Outlet after Activated Carbon Filter. Make: Aster/ UKL/
Eqv.
Set 2 38,000.00

1.19 Supplying, installation & commissioning of Online pH


meter. Make: Aster/ UKL/ Eqv. Set 1 23,000.00
Sub Total : "A"
B. Control Panel for Sewage Treatment Plant

Design, fabrication, assembling, wiring, supply, installation,


testing and commissioning of motor control centre shall be
fabricated out of 14 gauge CRCA sheet steel in form in 3
formation with reinforcement of suitable size angle iron,
channel ‘T’ sections irons and/or flats wherever necessary.
Cable gland plates shall be provided on top as well as at the
bottom of the panels. Panels shall be treated with all
anticorrosive process before painting as per specifications
with 2 coats of red oxide primer and final approved shade of
powder coated paint. 2 Nos. earthing terminals shall be
provided for 3 phase, 4 wire, 50 Hz supply system. Lifting
hooks shall also be provided in case of large panels.
Approval shall be taken for each panel before fabrication.
Galvanised hardware with zinc passivation shall be used in
fabrication of panels.

MCC-1 (STP Motor Control Centre)

Incoming

100 amps TPN MCCB with the following accessories:

a. 0-500 volts 96 x 96 mm square digital electronic


voltmeter with selector switch shall be protected by 2 amps
TP MCB. 1 Set
b. 0-100 amps 96 x 96 mm square digital electronic ammeter
with selector switch and 100/5 amps 15 VA CL: 1 CTs. 1
Set

c. Phase indicating lamps shall be protected by 2 amp SP


MCB 3 Sets

Bus Bar

100 amps TPN (25 KA) copper bus bar with heat shrinkable
insulation sleeves.

Outgoing

As per the STP equipment rating Set 1 290,000.00

TOTAL "B" CARRIED TO SUMMARY

GST Extra @18%

Payment Terms - 40% advance along with order, 50% against PI before material dispath, 10% after
installation and testing.

Delivery- withien 10-12 weeks from the date of your order.

Warranty- 18montsh from the date of supply.

Thanks & Regards


For Shine Water Experts
B C Bhagat
9336045174
LONY UNDER DEEN

Y : 250 KLD

Amount

Amount
50,000.00
-

18,000.00
-

-
-

-
-
-
-
-
-
-
120,000.00
-
-

-
-
-
144,000.00
-
-

-
-
-
56,000.00
-
-
-

-
-

-
-
-
-

430,000.00
-
-
200,000.00
-

180,000.00
-
-

120,000.00
-

270,000.00
-

-
-
-
-
-
-
200,000.00
-

-
-
-
76,000.00
-
-
-
-
-
-
140,000.00
-
-

-
-
-
-
140,000.00
-
-
-

-
-

23,000.00
-
-
-

260,000.00
-
-
-

290,000.00
-
-
-

-
-
-
-
-
-
-
-
380,000.00
-
-
-
-
-
160,000.00
-

52,000.00
-
210,000.00
-
-

34,000.00
-

76,000.00
-

23,000.00
3,652,000.00
-
-

-
-
-
-
-
-
-
-

-
-
-
-

-
-
-
-

-
-
-
-
290,000.00

3,942,000.00

rial dispath, 10% after

You might also like