Concrete Placing of 100mm Balast
Concrete Placing of 100mm Balast
Concrete Placing of 100mm Balast
Table of Contents
1. Procedure ......................................................................................................................................... 1
6.1 Setting Out, .........................................................................................................................................1
6.2 Installation of Formwork (Lip Channel) ...............................................................................................1
6.3 Concrete Placement and Finishing .....................................................................................................1
6.4 Curing of Concrete and saw cut on joints. ..........................................................................................2
6.5 Post Concrete .....................................................................................................................................2
2. Equipment ........................................................................................................................................ 2
3. Quality Control ................................................................................................................................. 3
4. Environmental Requirements ........................................................................................................... 3
5. Safety Requirements........................................................................................................................ 3
6. Records ............................................................................................................................................ 3
7. Attachments ..................................................................................................................................... 3
1. Procedure
- As the bidim and liner are both 9m wide a 3m gap will be left open to allow tie-in to the following
liner section and a 6m wide panel will be cast.
- The first panel will be cast against the 100mm HDPE Geo-Cell coming down from the batters
and extending 1m onto the basin past the toe line.
- While placing concrete, a roller will be used with poker vibrators to ensure a 100mm thickness is
achieved throughout.
- The concrete slump shall be such that it can be easily placed without segregation. If the
concrete is acceptable, it will continue to be discharged. Slump test shall be taken at every load
of concrete. The load shall be accepted if the concrete slump at the point of discharge is within
tolerance for the design mix ordered. A tolerance of ±40mm will be used to reject deliveries.
- Slump checks need to be recorded on the Slump Check Record Form
- The concrete is to be agitated continuously by rotation of the mixer drum during transport to the
Site and while waiting for discharge. Concrete shall be discharged from the delivery vehicle
within 1 hour after arriving on site.
- Concrete shall be deposited as quickly as practicable in its final position to avoid segregation
and cold joints.
- Concrete that has partially hardened or been contaminated with foreign materials shall not be
deposited in the structure.
- Concrete vibrators will be used to ensure an even flow of concrete to all edges. Vibrators shall
be inserted and used to move concrete to the edges. Plastic shovels are to be used to move
concrete to the edges to avoid damage to the liner.
- Concrete Placement will be achieved by use of direct placement from concrete truck and use of
a small conveyor or pump if required.
- A total of 6 test cubes will be taken for every 50m3 of concrete cast.
- All concrete finishes shall be as per design (wood float, steel float power float etc.).
2. Equipment
• Medium sized concrete breaker (scabble)
• Poker vibrator
• Drive units
• Consumables (Groutex, shutter board, etc.)
• Hand tools (Trowels,straight, shovels, racks, straight edge, Steel Rod, etc.)
• Wheelbarrow
• Scaffolding
• Ready-mix Trucks
• Concrete pump
Method Statement
3. Quality Control
4. Environmental Requirements
5. Safety Requirements
6. Records
7. Attachments