PROJECT: MANEL BRIDGE

SEE BLOW UP
BORED PILE SCHEMATIC
TOP OF PDA EXTENSION

CUT STEEL CASING / BREAK CONCRETE AFTER


PDA USING HYDRAULIC BREAKER LOW IMPULSE
COLUMN CUT-OFF COLUMN CUT-OFF

CONCRETE = 4000 psi CONCRETE = 5000 psi


COLUMN

COLUMN
NO STEEL CASING PERMANENT STEEL CASING

BORED PILE CUT-OFF (ELEV = - 3.117m BORED PILE CUT-OFF (ELEV = -3.117m
BORED PILE

BORED PILE
CONCRETE = 4000 psi CONCRETE = 5000 psi

PERMANENT STEEL CASING PERMANENT STEEL CASING

NOTE:
BORED PILE AND COLUMN
IS MONOLITHIC CONCRETE AT 5000 PSI
WITH FULL STEEL CASING UP TO COLUM
AS PLAN ACTUAL CUT-OFF LEVEL

Bored Pile Chipping_1/2


TOP OF PDA EXTENSION

INSTALLED TRAPAL SEPARATOR TO AVOID MONOLITHIC


CONCRETE DURING POURING AND TO MAKE
CRACK FREE DURING DEMOLATION
TYPICAL COPING DEMOLATION METHOD:
AT THE COLUMN SECTION

FOR PDA COPING TO BE DEMOLISH AFTER


COLUMN EXTENSION THAT SERVE AS COPING FOR
PDA TESTING AND EXPOSE BAR PDA TESTING WILL BE DEMOLISHED USING
HYDRAULIC BREAKER WITH LOW IMPULSE/ IMPACT
CUT STEEL CASING AFTER PDA MODE TO AVOID TOO MUCH ENERGY INDUCED BY
HYDRAULIC BREAKER DURING DEMOLATION, THE
COLUMN CUT-OFF CONCRETE WILL BREAK ONLY AT COLUMN CUT-OFF
LEVEL, CRACK CAN NOT GO BEYOND THE LEVEL
SINCE IT IS PROVIDED WITH TRAPAL SEPARATOR AT
THE JOINT BEFORE CONCRETE WAS POURED, THE
STEEL CASING ALSO SERVE ADDTIONAL COLUMN
REINFORCEMENT TO MAKE COLUMN MORE SAFE .
PART OF COLUMN

USING HYDRAULIC BREAKER WAS DONE BEFORE IN


SIMOKOY BRIDGE SIDEWALK DEMOLATION AND WAS
OBSERVED NO CRACK BEYOND THE SECTION AT MAIN
DECK SLAB

CONCRETE = use 5000 psi instead of 4000 psi

PERMANENT STEEL CASING INSTALLED SOPPOSED TO BE NO CASING PER PLAN

NOTE:
BORED PILE AND COLUMN IS MONOLITHIC CONCRETE OF 5000 psi
INSTEAD OF 4000 psi

BLOW UP SECTION

Bored Pile Chipping_2/2