Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 131

INSERT NAME AND LOGO OF BIDDER HERE

DETAILED COST ESTIMATE


PROJECT: CONSTRUCTION OF SECOND FLOOR FOR DOH CENTRAL OFFICE WAREHOUSE
LOCATION: QMMC COMPOUND, PROJECT 4, QUEZON CITY

ITEM NO. DESCRIPTION QUANTITY UNIT UNIT COST TOTAL COST

1.00 GENERAL REQUIREMENTS


1.01 Project Billboard 1.00 ea 0.00
1.02 Temporary Facility 1.00 l.s. 0.00
1.03 Mobilization/Demobilization 1.00 l.s. 0.00
1.04 Permits & Clearances 1.00 l.s. 0.00
Sub-total _ Item 1.00 0.00
2.00 EARTHWORKS
2.01 Structure Excavation 58.32 cu.m 0.00
2.02 Embankment from Structure Excavation 58.32 cu.m 0.00
2.02 Gravel Bedding 3.89 cu.m 0.00
2.03 Soil Poisoning 2.00 liters 0.00
Sub-total _ Item 2.00 0.00
3.00 CONCRETE WORKS
3.01 Structural Concrete 15.31 cu.m 0.00
3.02 Reinforcing Steel 1767.30 kgs 0.00
3.03 Formworks & Falsework 32.40 sq.m 0.00
Sub-total _ Item 3.00 0.00
4.00 STRUCTURAL STEEL WORKS
4.01 W8x48 Columns 3373.92 kgs 0.00
4.02 W12x35 Main Girder 4976.40 kgs 0.00
4.03 W8x31 Secondary Beams 2326.00 kgs 0.00
4.04 C4x7.25 Floor Joists and Bridging 4653.00 kgs 0.00
4.05 16'x16'x 1 1/4' Base Plate 12.00 sets 0.00
4.06 4"x8"x1/4" thk Checkered Plate 62.00 pcs 0.00
4.07 Steel Stairs 1.00 l.s. 0.00
Sub-total _Item 4.00 0.00

TOTAL APPROVED BUDGET FOR CONTRACT : 0.00


NOTE: The visible quantity in the Detailed Cost Estimate and Detailed Unit Price Analysis (DUPA) attached to it are based on the calculation of the value
of the whole project. You can change the quantities here if you have uncertainty on the number, but the total estimate should represent the completion
and functionality of the project based in Detailed Architectural & Engineering Drawing (DAED) and Specifications.

NAME OF REPRESENTATIVE
DESIGNATION
CONSTRUCTION OF SECOND FLOOR FOR DOH CENTRAL OFFICE WAREHOUSE
QMMC COMPOUND, PROJECT 4, QUEZON CITY

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1.01 Project Billboard


Unit of Measurement : ea
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 4.00 -


b. Skilled Laborer 1 4.00 -
c. Unskilled Laborer 1 4.00 -

Sub - Total for A -

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

-
Minor Tools (10% of labor cost)

Sub - Total for B -


C. Total (A + B) -
D. Output = 1 each
E. Direct Unit Cost (C ÷ D) -

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 8' x 8' Tarpaulin sq.ft. 64.00 -


b. Good Lumber (Frames) bd-ft 48.00 -
c. Assorted Common Working Nails kg 1.00 -

Sub - Total for F -


G. Direct Unit Cost (E + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G -
I. Contractor's Profit (CP) 8% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -

Prepared By:

NAME OF REPRESENTATIVE
DESIGNATION
CONSTRUCTION OF SECOND FLOOR FOR DOH CENTRAL OFFICE WAREHOUSE
QMMC COMPOUND, PROJECT 4, QUEZON CITY

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1.02 Temporary Facility


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Month/s Hourly Rate Amount (PhP)

A. Labor

Sub - Total for A

Name and Capacity No of Unit/s No. of Month/s Monthly Rate Amount (PhP)

B. Equipment

Sub - Total for B -


C. Total (A + B) -
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) -

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Temporary Facility l.s. 1.00 -

-
G. Direct Unit Cost (E + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 0% of G -
I. Contractor's Profit (CP) 0% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -

Prepared By:

NAME OF REPRESENTATIVE
DESIGNATION
CONSTRUCTION OF SECOND FLOOR FOR DOH CENTRAL OFFICE WAREHOUSE
QMMC COMPOUND, PROJECT 4, QUEZON CITY

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1.03 Mobilization/Demobilization


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Sub - Total for A -

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Mobilization/ Demobilization (1.00% of Civil Works)

Sub - Total for B -


C. Total (A + B) -
D. Output = 1.00 l.s.
E. Direct Unit Cost (C ÷ D) -

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

G. Direct Unit Cost (E + F) -


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 0% of G -
I. Contractor's Profit (CP) 0% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -

Prepared By:

NAME OF REPRESENTATIVE
DESIGNATION
CONSTRUCTION OF SECOND FLOOR FOR DOH CENTRAL OFFICE WAREHOUSE
QMMC COMPOUND, PROJECT 4, QUEZON CITY

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1.04 Permits & Clearances


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Sub - Total for A -

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B -


C. Total (A + B) -
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) -

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a) Contractor's tax, Certificate of Non-Coverage l.s. 1.00 -


(CNC), Zoning, Fire

-
G. Direct Unit Cost (E + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 0% of G -
I. Contractor's Profit (CP) 0% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -

Prepared By:

NAME OF REPRESENTATIVE
DESIGNATION
CONSTRUCTION OF SECOND FLOOR FOR DOH CENTRAL OFFICE WAREHOUSE
QMMC COMPOUND, PROJECT 4, QUEZON CITY

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 2.01 Structure Excavation


Unit of Measurement : cu.m.
Output per hour : 20.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 -


b. Unskilled Laborer 3 1.00 -

Sub - Total for A -

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) -


a. Backhoe (0.80 m³) 1 1.00 -
b. Dumptruck (12 yd³) 2 1.00 -

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 20.00 cu.m.
E. Direct Unit Cost (C ÷ D) -

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G -
I. Contractor's Profit (CP) 8% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -

Prepared By:

NAME OF REPRESENTATIVE
DESIGNATION
CONSTRUCTION OF SECOND FLOOR FOR DOH CENTRAL OFFICE WAREHOUSE
QMMC COMPOUND, PROJECT 4, QUEZON CITY

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 2.02 Embankment from Structure Excavation


Unit of Measurement : cu.m.
Output per hour : 9.84

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 -


b. Unskilled Laborer 3 1.00 -

Sub - Total for A -

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Plate Compactor (5 hp) 1 0.75 -


b. Backhoe (0.80 m³) 1 0.75 -
Minor Tools (10% of Labor Cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 9.84 cu.m.
E. Direct Unit Cost (C ÷ D) -

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

G. Direct Unit Cost (E + F) -


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G -
I. Contractor's Profit (CP) 8% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -

Prepared By:

NAME OF REPRESENTATIVE
DESIGNATION
CONSTRUCTION OF SECOND FLOOR FOR DOH CENTRAL OFFICE WAREHOUSE
QMMC COMPOUND, PROJECT 4, QUEZON CITY

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 2.02 Gravel Bedding


Unit of Measurement : m3
Output per hour : 1.20

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 -


b. Unskilled Laborer 3 1.00 -

Sub - Total for A -

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Plate Compactor 1 0.50 -


Minor Tools (10% of Labor Cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 1.20 m3
E. Direct Unit Cost (C ÷ D) -

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Gravel Bedding (G1) m3 1.05 -


(w/ 5% Shrinkage Factor)

Sub - Total for F -


G. Direct Unit Cost (E + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G -
I. Contractor's Profit (CP) 8% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -

Prepared By:

NAME OF REPRESENTATIVE
DESIGNATION
CONSTRUCTION OF SECOND FLOOR FOR DOH CENTRAL OFFICE WAREHOUSE
QMMC COMPOUND, PROJECT 4, QUEZON CITY

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 2.03 Soil Poisoning


Unit of Measurement : liters
Output per hour : 5.40

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 -


b. Skilled Laborer 1 1.00 -
c. Unskilled Laborer 2 1.00 -

Sub - Total for A -

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 5.4 liters
E. Direct Unit Cost (C ÷ D) -

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Soil Poisoning liter 1.00 -

Sub - Total for F -


G. Direct Unit Cost (E + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G -
I. Contractor's Profit (CP) 8% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -

Prepared By:

NAME OF REPRESENTATIVE
DESIGNATION
CONSTRUCTION OF SECOND FLOOR FOR DOH CENTRAL OFFICE WAREHOUSE
QMMC COMPOUND, PROJECT 4, QUEZON CITY

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 3.01 Structural Concrete


Unit of Measurement : cu.m.
Output per hour : 0.27

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 -


b. Skilled Laborer 1 1.00 -
c. Unskilled Laborer 4 1.00 -

Sub - Total for A -

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. One Bagger Mixer 1 1.00 -


Minor Tools (10% of Labor Cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 0.27 cu.m.
E. Direct Unit Cost (C ÷ D) -

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Cement bag 9.100 -


b. Sand cu.m 0.50 -
c. Gravel cu.m 1.00 -

Sub - Total for F -


G. Direct Unit Cost (E + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G -
I. Contractor's Profit (CP) 8% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -

Prepared By:

NAME OF REPRESENTATIVE
DESIGNATION
CONSTRUCTION OF SECOND FLOOR FOR DOH CENTRAL OFFICE WAREHOUSE
QMMC COMPOUND, PROJECT 4, QUEZON CITY

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 3.02 Reinforcing Steel


Unit of Measurement : kg.
Output per hour : 129.094

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 94.05 94.05


b. Skilled Laborer 3 1.00 67.95 203.85
c. Unskilled Laborer 12 1.00 52.42 629.04

Sub - Total for A 926.94

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Bar Cutter 1 0.50 -


b. Bar Bender 1 0.50 -
Minor Tools (10% of Labor Cost) 92.69

Sub - Total for B 92.69


C. Total (A + B) 1,019.63
D. Output per Hour = 129.094 kg
E. Direct Unit Cost (C ÷ D) 7.90

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Deformed Reinforcing Steel, Grade 40 kg 1.00 -


Grade
b. #16 60/GradeIron
Galvanized 40 Wire kg 0.015 -
c. Consumables (5% of Materials Cost) -

Sub - Total for F -


G. Direct Unit Cost (E + F) 7.90
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 0.95
I. Contractor's Profit (CP) 8% of G 0.63
J. Value Added Tax (VAT) 5% of (G + H + I) 0.47
K. Total Unit Cost (G + H + I + J) 9.95

Prepared By:

NAME OF REPRESENTATIVE
DESIGNATION
CONSTRUCTION OF SECOND FLOOR FOR DOH CENTRAL OFFICE WAREHOUSE
QMMC COMPOUND, PROJECT 4, QUEZON CITY

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 3.03 Formworks & Falsework


Unit of Measurement : sq.m.
Output per hour : 4.5

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor
Installation
a. Construction Foreman 1 1.00 -
b. Skilled Laborer 4 1.00 -
c. Unskilled Laborer 6 1.00 -
Stripping
a. Construction Foreman 1 0.56 -
b. Unskilled Laborer 6 0.56 -
Sub - Total for A -

Name and Capacity Quantity No. of Day/s Daily Rental Rate Amount (PhP)

B. Equipment
Area = 205.01 m2
a. H-Frame 1.7 m x 1.2m, set 40 14.00 -
2 pcs H-frames
4 pcs diagonal cross braces
4 pcs horizontal braces
8 pcs joint pins
b. Shoring Jack, 3.8 m full extension 62 14.00 -
c. Adjustable U-head Jack, 0.6m 80 14.00 -
d. Adjustable Base Jack, 0.6m 80 14.00 -
e. 1-1/2" GI Pipe x 6.0 m 62 14.00 -
f. 1-1/2" GI Pipe x 3.0 m 16 14.00 -
g. 1-1/2" GI Pipe x 4.0 m 32 14.00 -
h. 1-1/2" GI Pipe x 1.0 m 216 14.00 -
i. Tie Rod x 0.60m 278 14.00 -
j. Round Wing Nut 558 14.00 -
Sub - Total for B -
C. Sub-Total for C (B/Area) -
D. Output per Hour = 4.5 sq.m.
E. Direct Unit Cost (A ÷ D) + C -

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials
a. Phenolic Board (0.019 x 1.2 x 2.4) - 4 uses pc 0.347 -
b. Good Lumber - 3 uses bd ft 4.727 -
c. Consumables (5% of Materials Cost) -
Sub - Total for F -
G. Direct Unit Cost (E + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G -
I. Contractor's Profit (CP) 8% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -

Prepared By:

NAME OF REPRESENTATIVE
DESIGNATION
CONSTRUCTION OF SECOND FLOOR FOR DOH CENTRAL OFFICE WAREHOUSE
QMMC COMPOUND, PROJECT 4, QUEZON CITY

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 4.01 W8x48 Columns


Unit of Measurement : kgs
Output per hour : 85

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 -


b. Skilled Laborer 3 0.49 -
c. Unskilled Laborer 3 0.49 -

Sub - Total for A -

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Welding Machine 1 0.75 -


b. Cutting Outfit 1 0.25 -
c. Truck Mounted Crane (20-25mt) 1 0.49 -
Minor Tools (10% of Labor Cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 85
E. Direct Unit Cost (C ÷ D) -

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. W8x48 kgs 1.00 -


b. Acetylene kgs 0.011 -
c. Oxygen kgs 0.02 -
d. Welding Rod kg 0.02 -
e. Consumables (5% of Material Cost) -

Sub - Total for F -


G. Direct Unit Cost (E + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G -
I. Contractor's Profit (CP) 8% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -

Prepared By:

NAME OF REPRESENTATIVE
DESIGNATION
CONSTRUCTION OF SECOND FLOOR FOR DOH CENTRAL OFFICE WAREHOUSE
QMMC COMPOUND, PROJECT 4, QUEZON CITY

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 4.02 W12x35 Main Girder


Unit of Measurement : kgs
Output per hour : 85

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 -


b. Skilled Laborer 3 0.49 -
c. Unskilled Laborer 3 0.49 -

Sub - Total for A -

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Welding Machine 1 0.75 -


b. Cutting Outfit 1 0.25 -
c. Truck Mounted Crane (20-25mt) 1 0.49 -
Minor Tools (10% of Labor Cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 85
E. Direct Unit Cost (C ÷ D) -

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. W12x35 kgs 1.00 -


b. Acetylene kgs 0.011 -
c. Oxygen kgs 0.02 -
d. Welding Rod kg 0.02 -
e. Consumables (5% of Material Cost) -

Sub - Total for F -


G. Direct Unit Cost (E + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G -
I. Contractor's Profit (CP) 8% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -

Prepared By:

NAME OF REPRESENTATIVE
DESIGNATION
CONSTRUCTION OF SECOND FLOOR FOR DOH CENTRAL OFFICE WAREHOUSE
QMMC COMPOUND, PROJECT 4, QUEZON CITY

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 4.03 W8x31 Secondary Beams


Unit of Measurement : kgs
Output per hour : 85

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 -


b. Skilled Laborer 3 0.49 -
c. Unskilled Laborer 3 0.49 -

Sub - Total for A -

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Welding Machine 1 0.75 -


b. Cutting Outfit 1 0.25 -
c. Truck Mounted Crane (20-25mt) 1 0.49 -
Minor Tools (10% of Labor Cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 85
E. Direct Unit Cost (C ÷ D) -

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. W8x31 kgs 1.00 -


b. Acetylene kgs 0.011 -
c. Oxygen kgs 0.02 -
d. Welding Rod kg 0.02 -
e. Consumables (5% of Material Cost) -

Sub - Total for F -


G. Direct Unit Cost (E + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G -
I. Contractor's Profit (CP) 8% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -

Prepared By:

NAME OF REPRESENTATIVE
DESIGNATION
CONSTRUCTION OF SECOND FLOOR FOR DOH CENTRAL OFFICE WAREHOUSE
QMMC COMPOUND, PROJECT 4, QUEZON CITY

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 4.04 C4x7.25 Floor Joists and Bridging


Unit of Measurement : kgs
Output per hour : 85

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 -


b. Skilled Laborer 3 0.49 -
c. Unskilled Laborer 3 0.49 -

Sub - Total for A -

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Welding Machine 1 0.75 -


b. Cutting Outfit 1 0.25 -
c. Truck Mounted Crane (20-25mt) 1 0.49 -
Minor Tools (10% of Labor Cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 85
E. Direct Unit Cost (C ÷ D) -

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. C4x7.25 kgs 1.00 -


b. Acetylene kgs 0.011 -
c. Oxygen kgs 0.02 -
d. Welding Rod kg 0.02 -
e. Consumables (5% of Material Cost) -

Sub - Total for F -


G. Direct Unit Cost (E + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G -
I. Contractor's Profit (CP) 8% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -

Prepared By:

NAME OF REPRESENTATIVE
DESIGNATION
CONSTRUCTION OF SECOND FLOOR FOR DOH CENTRAL OFFICE WAREHOUSE
QMMC COMPOUND, PROJECT 4, QUEZON CITY

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 4.05 16'x16'x 1 1/4' Base Plate


Unit of Measurement : pcs
Output per hour : 5

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 -


b. Skilled Laborer 3 1.00 -
c. Unskilled Laborer 3 1.00 -

Sub - Total for A -

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Welding Machine 1 0.75 -


b. Cutting Outfit 1 0.25 -
Minor Tools (10% of Labor Cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 85
E. Direct Unit Cost (C ÷ D) -

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 16"x16"x1 1/4" Base Plate kgs 1.00 -


b. Non Shrink Grout bags 0.100 -
c. Anchor Bolt pcs 6.00 -
d. Welding Rod kg 0.02 -
e. Consumables (5% of Material Cost) -

Sub - Total for F -


G. Direct Unit Cost (E + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G -
I. Contractor's Profit (CP) 8% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -

Prepared By:

NAME OF REPRESENTATIVE
DESIGNATION
CONSTRUCTION OF SECOND FLOOR FOR DOH CENTRAL OFFICE WAREHOUSE
QMMC COMPOUND, PROJECT 4, QUEZON CITY

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 4.06 4"x8"x1/4" thk Checkered Plate


Unit of Measurement : pcs
Output per hour : 5

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 -


b. Skilled Laborer 3 0.49 -
c. Unskilled Laborer 3 0.49 -

Sub - Total for A -

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Welding Machine 1 0.75 -


b. Cutting Outfit 1 0.25 -
Minor Tools (10% of Labor Cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 5
E. Direct Unit Cost (C ÷ D) -

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 4"x8"x1/4 "thk Checkered Plate pcs 1.00 -


b. Welding Rod kg 0.20 -
c. Consumables (5% of Material Cost) -

Sub - Total for F -


G. Direct Unit Cost (E + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G -
I. Contractor's Profit (CP) 8% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -
Prepared By:

NAME OF REPRESENTATIVE
DESIGNATION
CONSTRUCTION OF SECOND FLOOR FOR DOH CENTRAL OFFICE WAREHOUSE
QMMC COMPOUND, PROJECT 4, QUEZON CITY

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : #REF! #REF!


Unit of Measurement : l.s
Output per hour : 1.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 40.00 -


b. Skilled Laborer 3 40.00 -
c. Unskilled Laborer 3 40.00 -

Sub - Total for A -

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) -


Welding Machine 1 40.00 -

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 1 sq.m.
E. Direct Unit Cost (C ÷ D) -

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. HSS 4x4x11ga a500 lm 4.000 -


b. C8x11.5 lm 9.000 -
c. 1.5"x1.5" square tubular lm 18.000 -
d. 2"x3" Rectangular Tubular lm 9.000 -
e. L2x2x1/4 lm 88.4 -
f. Checkered plate pcs 5 -
g. Welding Rod kgs 5 -
g. Consumables (3% of Materials Cost) -

Sub - Total for F -


G. Direct Unit Cost (E + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G -
I. Contractor's Profit (CP) 8% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -

Prepared By:

NAME OF REPRESENTATIVE
DESIGNATION
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : II.7 Occupational Safety and Health (20 CL)


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Day/s Daily Rate Amount (PhP)

A. Labor

a. Part Time Safety Officer 1 16.00 690.72 11,051.52

Sub - Total for A 11,051.52

Name and Capacity Unit Quantity Daily Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B) 11,051.52
D. Output = 1 mo.
E. Direct Unit Cost (C ÷ D) 11,051.52

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

First Aid Kit l.s. 1.00 1,000.00 133.33

Personal Protective Equipment(PPE)


a. Safety Helmet man-days 21,362.00 0.25 5,340.50
b. Safety Shoes man-days 21,362.00 2.77 59,172.74
c. Safety Gloves man-days 21,362.00 7.67 163,846.54

Signages and Barricades


a. PPE Signage (4' x 8') set 1.00 506.37 84.40
b. Safety First (4' x 4') set 1.00 270.87 45.15
c. Warning Signs (2' x 3') sets 35.00 123.68 721.47
d. Caution Tape, 100ft roll 1.00 800.00 133.33

Sub - Total for F 229,477.45


G. Direct Unit Cost (E + F) 240,528.97
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 0% of G -
I. Contractor's Profit (CP) 8% of G 19,242.32
J. Value Added Tax (VAT) 5% of (G + H + I) 12,988.56
K. Total Unit Cost (G + H + I + J) 272,759.86
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : II.7 Occupational Safety and Health (16 CL)


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Day/s Daily Rate Amount (PhP)

A. Labor

a. Part Time Safety Officer 1 16.00 690.72 11,051.52

Sub - Total for A 11,051.52

Name and Capacity Unit Quantity Daily Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B) 11,051.52
D. Output = 1 mo.
E. Direct Unit Cost (C ÷ D) 11,051.52

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

First Aid Kit l.s. 1.00 1,000.00 142.86

Personal Protective Equipment(PPE)


a. Safety Helmet man-days 18,920.00 0.25 4,730.00
b. Safety Shoes man-days 18,920.00 2.77 52,408.40
c. Safety Gloves man-days 18,920.00 7.67 145,116.40

Signages and Barricades


a. PPE Signage (4' x 8') set 1.00 506.37 86.81
b. Safety First (4' x 4') set 1.00 270.87 46.43
c. Warning Signs (2' x 3') sets 34.00 123.68 720.88
d. Caution Tape, 100ft roll 1.00 800.00 137.14

Sub - Total for F 203,388.92


G. Direct Unit Cost (E + F) 214,440.44
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 0% of G -
I. Contractor's Profit (CP) 8% of G 17,155.24
J. Value Added Tax (VAT) 5% of (G + H + I) 11,579.78
K. Total Unit Cost (G + H + I + J) 243,175.46
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : II.7 Occupational Safety and Health (12 CL)


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Day/s Daily Rate Amount (PhP)

A. Labor

a. Part Time Safety Officer 1 14.00 690.72 9,670.08

Sub - Total for A 9,670.08

Name and Capacity Unit Quantity Daily Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B) 9,670.08
D. Output = 1 mo.
E. Direct Unit Cost (C ÷ D) 9,670.08

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

First Aid Kit l.s. 1.00 1,000.00 153.85

Personal Protective Equipment(PPE)


a. Safety Helmet man-days 16,412.00 0.25 4,103.00
b. Safety Shoes man-days 16,412.00 2.77 45,461.24
c. Safety Gloves man-days 16,412.00 7.67 125,880.04

Signages and Barricades


a. PPE Signage (4' x 8') set 1.00 506.37 101.27
b. Safety First (4' x 4') set 1.00 270.87 54.17
c. Warning Signs (2' x 3') sets 31.00 123.68 766.82
d. Caution Tape, 100ft roll 1.00 800.00 160.00

Sub - Total for F 176,680.39


G. Direct Unit Cost (E + F) 186,350.47
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 0% of G -
I. Contractor's Profit (CP) 8% of G 14,908.04
J. Value Added Tax (VAT) 5% of (G + H + I) 10,062.93
K. Total Unit Cost (G + H + I + J) 211,321.43
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : II.7 Occupational Safety and Health (4 CL)


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Day/s Daily Rate Amount (PhP)

A. Labor

a. Part Time Safety Officer 1 10.00 690.72 6,907.20

Sub - Total for A 6,907.20

Name and Capacity Unit Quantity Daily Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B) 6,907.20
D. Output = 1 mo.
E. Direct Unit Cost (C ÷ D) 6,907.20

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

First Aid Kit l.s. 1.00 1,000.00 200.00

Personal Protective Equipment(PPE)


a. Safety Helmet man-days 9,724.00 0.25 2,431.00
b. Safety Shoes man-days 9,724.00 2.77 26,935.48
c. Safety Gloves man-days 9,724.00 7.67 74,583.08

Signages and Barricades


a. PPE Signage (4' x 8') set 1.00 506.37 132.10
b. Safety First (4' x 4') set 1.00 270.87 70.66
c. Warning Signs (2' x 3') sets 17.00 123.68 548.49
d. Caution Tape, 100ft roll 1.00 800.00 208.70

Sub - Total for F 105,109.51


G. Direct Unit Cost (E + F) 112,016.71
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 0% of G -
I. Contractor's Profit (CP) 8% of G 8,961.34
J. Value Added Tax (VAT) 5% of (G + H + I) 6,048.90
K. Total Unit Cost (G + H + I + J) 127,026.95
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : II.9 Mobilization/Demobilization (20 CL)


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Sub - Total for A -

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

#REF!
a. Mobilization/ Demobilization (0.75% of Civil Works)

Sub - Total for B #REF!


C. Total (A + B) #REF!
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) #REF!

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

G. Direct Unit Cost (E + F) #REF!


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 0% of G #REF!
I. Contractor's Profit (CP) 8% of G #REF!
J. Value Added Tax (VAT) 5% of (G + H + I) #REF!
K. Total Unit Cost (G + H + I + J) #REF!
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : II.9 Mobilization/Demobilization (16 CL)


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Sub - Total for A -

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

#REF!
a. Mobilization/ Demobilization (0.75% of Civil Works)

Sub - Total for B #REF!


C. Total (A + B) #REF!
D. Output = 1.00 l.s.
E. Direct Unit Cost (C ÷ D) #REF!

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

G. Direct Unit Cost (E + F) #REF!


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 0% of G #REF!
I. Contractor's Profit (CP) 8% of G #REF!
J. Value Added Tax (VAT) 5% of (G + H + I) #REF!
K. Total Unit Cost (G + H + I + J) #REF!
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : II.9 Mobilization/Demobilization (12 CL)


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Sub - Total for A -

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

#REF!
a. Mobilization/ Demobilization (0.75% of Civil Works)

Sub - Total for B #REF!


C. Total (A + B) #REF!
D. Output = 1.00 l.s.
E. Direct Unit Cost (C ÷ D) #REF!

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

G. Direct Unit Cost (E + F) #REF!


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 0% of G #REF!
I. Contractor's Profit (CP) 8% of G #REF!
J. Value Added Tax (VAT) 5% of (G + H + I) #REF!
K. Total Unit Cost (G + H + I + J) #REF!
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : II.9 Mobilization/Demobilization (4 CL)


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Sub - Total for A -

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

#REF!
a. Mobilization/ Demobilization (0.75% of Civil Works)

Sub - Total for B #REF!


C. Total (A + B) #REF!
D. Output = 1.00 l.s.
E. Direct Unit Cost (C ÷ D) #REF!

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

G. Direct Unit Cost (E + F) #REF!


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 0% of G #REF!
I. Contractor's Profit (CP) 8% of G #REF!
J. Value Added Tax (VAT) 5% of (G + H + I) #REF!
K. Total Unit Cost (G + H + I + J) #REF!
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 801(1) Removal of Structures and Obstruction


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 15.85 94.05 1,490.74


b. Skilled Laborer 2 15.85 67.95 2,154.08
c. Unskilled Laborer 4 15.85 52.42 3,323.53

Sub - Total for A 6,968.36

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Backhoe with Breaker (0.80 m3) 1 7.93 1,998.10 15,835.44


a. Backhoe (0.80 m3) 1 7.93 1,537.00 12,181.11
b. Dump Truck (12 yd3) 1 15.85 1,420.00 22,507.71
Minor Tools (10% of Labor Cost) 696.84

Sub - Total for B 51,221.10


C. Total (A + B) 58,189.45
D. Output per Hour = 1.00 l.s.
E. Direct Unit Cost (C ÷ D) 58,189.45

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F) 58,189.45
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 8,728.42
I. Contractor's Profit (CP) 10% of G 5,818.95
J. Value Added Tax (VAT) 5% of (G + H + I) 3,636.84
K. Total Unit Cost (G + H + I + J) 76,373.66
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 807(13) Fence


Unit of Measurement : sq.m.
Output per hour : 1.63

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 94.05 94.05


b. Skilled Laborer 2 1.00 67.95 135.90
c. Unskilled Laborer 8 1.00 52.42 419.36

Sub - Total for A 649.31

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Welding Machine 1 1.00 371.00 371.00


b. One Bagger Mixer 1 1.00 172.00 172.00
Minor Tools (10% of Labor Cost) 64.93

Sub - Total for B 607.93


C. Total (A + B) 1,257.24
D. Output per Hour = 1.63 sq.m.
E. Direct Unit Cost (C ÷ D) 771.31

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Cyclone Wire Fence:


a. Cement bag 1.07 240.00 256.80
b. Sand cu.m 0.07 868.30 60.78
c. Gravel cu.m 0.07 753.30 55.88
d. Deformed Reinforcing Steel, Grade 40 kg 13.92 44.00 612.48
e. #16 Galvanized Tie Wire kg 0.19 75.00 14.41
f. Phenolic Board (0.019 x 1.2 x 2.4) pc 0.27 1,450.00 384.67
g. Good Lumber bd ft 3.61 42.00 151.78
h. 100 mm thk CHB (Non-Load Bearing) pc 4.46 13.00 57.94
i. Concrete Neutralizer gal 0.05 130.00 7.10
j. Concrete Sealer/Primer gal 0.03 644.00 17.59
k. Patching Compound gal 0.03 550.00 18.78
l. Semi Gloss Latex (two coats) gal 0.05 581.00 31.74
m. Red Oxide Primer gal 0.04 420.30 15.90
n. Enamel Paint gal 0.09 600.00 56.76
o. Paint thinner gal 0.24 350.00 82.78
p. GI Pipe 50mm dia. pc 0.19 2,400.00 463.11
q. 25mm x 4mm flat bar kg 2.01 57.33 115.32
r. Steel Plate kg 0.43 45.00 19.46
s. Cyclone Wire 5' l.m. 0.49 495.00 242.84
t. Anchor Bolts with Nuts and Washers kg 0.08 193.33 15.76
u. Welding Rod kg 0.77 120.00 92.62
v. Consumables (5% of Material Cost) 138.73

Gate:
a. GI Pipe 50mm dia. pc 0.05 2,400.00 125.59
b. 19mm sq. bar kg 1.52 55.00 83.46
c. Heavy Duty Hinge pc 0.10 2,350.00 245.94
d. Welding Rod kg 0.10 120.00 12.56
e. Red Oxide Primer gal 0.03 420.30 14.55
f. Enamel Paint gal 0.03 600.00 20.77
g. Paint thinner gal 0.03 300.00 10.38
h. Consumables (5% of Material Cost) 25.66

Sub - Total for F 3,452.14


G. Direct Unit Cost (E + F) 4,223.45
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 506.81
I. Contractor's Profit (CP) 8% of G 337.88
J. Value Added Tax (VAT) 5% of (G + H + I) 253.41
K. Total Unit Cost (G + H + I + J) 5,321.55
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 900(1)c1 Structural Concrete


Unit of Measurement : cu.m.
Output per hour : 3.72

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 94.05 94.05


b. Skilled Laborer 2 1.00 67.95 135.90
b. Unskilled Laborer 6 1.00 52.42 314.52

Sub - Total for A 544.47

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Concrete Vibrator 2 1.00 91.25 182.50


b. Pumpcrete 1 0.27 2,076.00 560.52
Minor Tools (10% of Labor Cost) 54.45

Sub - Total for B 797.47


C. Total (A + B) 1,341.94
D. Output per Hour = 3.72 cu.m.
E. Direct Unit Cost (C ÷ D) 360.74

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Ready Mix, Class A, 28 days cu.m. 1.00 5,065.00 5,065.00

Sub - Total for F 5,065.00


G. Direct Unit Cost (E + F) 5,425.74
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 813.86
I. Contractor's Profit (CP) 10% of G 542.57
J. Value Added Tax (VAT) 5% of (G + H + I) 339.11
K. Total Unit Cost (G + H + I + J) 7,121.28
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 901(1) Lean Concrete


Unit of Measurement : cu.m.
Output per hour : 0.357

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 94.05 94.05


b. Skilled Laborer 1 1.00 67.95 67.95
b. Unskilled Laborer 4 1.00 52.42 209.68

Sub - Total for A 371.68

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. One Bagger Mixer 1 1.00 172.00 172.00


Minor Tools (10% of Labor Cost) 37.17

Sub - Total for B 209.17


C. Total (A + B) 580.85
D. Output per Hour = 0.357 cu.m.
E. Direct Unit Cost (C ÷ D) 1,627.03

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Gravel cu.m. 1.00 1,053.30 1,053.30


b. Sand cu.m. 0.50 868.30 434.15
c. Portland Cement bags 6.00 240.00 1,440.00

Sub - Total for F 2,927.45


G. Direct Unit Cost (E + F) 4,554.48
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 546.54
I. Contractor's Profit (CP) 8% of G 364.36
J. Value Added Tax (VAT) 5% of (G + H + I) 273.27
K. Total Unit Cost (G + H + I + J) 5,738.64
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 902(1)b Reinforcing Steel (Deformed)


Unit of Measurement : kg
Output per hour : 129.094

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 94.05 94.05


b. Skilled Laborer 3 1.00 67.95 203.85
c. Unskilled Laborer 12 1.00 52.42 629.04

Sub - Total for A 926.94

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Bar Cutter 1 0.50 219.75 109.88


b. Bar Bender 1 0.50 351.50 175.75
Minor Tools (10% of Labor Cost) 92.69

Sub - Total for B 378.32


C. Total (A + B) 1,305.26
D. Output per Hour = 129.094 kg
E. Direct Unit Cost (C ÷ D) 10.11

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Deformed Reinforcing Steel, Grade 60 kg 1.00 46.00 46.00


Grade
b. #16 60/GradeIron
Galvanized 40 Wire kg 0.015 75.00 1.13
c. Consumables (5% of Materials Cost) 2.36

Sub - Total for F 49.48


G. Direct Unit Cost (E + F) 59.59
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 7.15
I. Contractor's Profit (CP) 8% of G 4.77
J. Value Added Tax (VAT) 5% of (G + H + I) 3.58
K. Total Unit Cost (G + H + I + J) 75.09
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(29) Micro Piles in Drilled Holes, 0.2m Ø (Ordinary Soil Condition)
Unit of Measurement : m
Output per hour : 3.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor
Installation
a. Construction Foreman 1 1.00 94.05 94.05
b. Skilled Laborer 5 1.00 67.95 339.75
c. Unskilled Laborer 6 1.00 52.42 314.52
Fabrication of Cage Bar
a. Construction Foreman 4 0.25 94.05 94.05
b. Unskilled Laborer 8 0.25 52.42 104.84
Sub - Total for A 947.21
Hourly Rental
Name and Capacity Quantity No. of Day/s Amount (PhP)
Rate
B. Equipment

a. Drill Rig, Mechanical Rotary 1 0.74 3,932.00 2,909.68


b. Truck Mounted Crane (25T) 1 0.95 1,631.00 1,549.45
c. Bar Bender 1 0.04 351.50 12.33
d. Bar Cutter 1 0.04 219.75 8.79
e. Bentonite Mixer 1 0.50 173.00 86.50
f. Bentonite Bin 1 0.50 280.00 140.00
g. Water Pump 1 0.50 123.38 61.69
h.Water Truck 1 0.50 2,450.00 1,225.00
i. Welding Machine 1 0.50 371.00 185.50
j. Tremie Pipe Set 1 0.24 320.00 76.80
k. SPT & Desanding Machine 1 0.24 559.00 134.16
l. Tower Light 1 0.50 543.50 271.75
m. Minor Tools (10% of Labor Cost) 94.72

Sub - Total for B 6,756.37


C. Total (A + B) 7,703.58
D. Output per Hour = 3.00 m.
E. Direct Unit Cost (C ÷ D) 2,567.86

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Ready Mix m3 0.033 5,065.00 55.68


b. Reinforced Steel Bar* kg 12.626 44.00 555.54
c. Welding Rod (1kg/2000kg of RSB) kg 0.006 120.00 0.72
d. Miscellaneous (3% of Materials, Bentonite & etc.) 18.36

Sub - Total for F 630.30


G. Direct Unit Cost (E + F) 3,198.16
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 383.78
I. Contractor's Profit (CP) 8% of G 255.85
J. Value Added Tax (VAT) 5% of (G + H + I) 191.89
K. Total Unit Cost (G + H + I + J) 4,029.68
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1000(1) Soil Poisoning


Unit of Measurement : li.
Output per hour : 5.40

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 94.05 94.05


b. Skilled Laborer 1 1.00 67.95 67.95
c. Unskilled Laborer 2 1.00 52.42 104.84

Sub - Total for A 266.84

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 26.68

Sub - Total for B 26.68


C. Total (A + B) 293.52
D. Output per Hour = 5.40 li.
E. Direct Unit Cost (C ÷ D) 54.36

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Soil Poisoning li. 1.00 320.00 320.00

Sub - Total for F 320.00


G. Direct Unit Cost (E + F) 374.36
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 44.92
I. Contractor's Profit (CP) 8% of G 29.95
J. Value Added Tax (VAT) 5% of (G + H + I) 22.46
K. Total Unit Cost (G + H + I + J) 471.69
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(8) Sewer Line Works


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 13.25 94.05 1,246.16


b. Skilled Laborer 1 13.25 67.95 900.34
c. Unskilled Laborer 2 13.25 52.42 1,389.13

Sub - Total for A 3,535.63

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment
Minor Tools (10% of labor cost) 353.56
Sub - Total for B 353.56
C. Total (A + B) 3,889.19
D. Output = 1.00 l.s.
E. Direct Unit Cost (C ÷ D) 3,889.19

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials
a. PVC Pipe, 50mm Ø x 3m, S-1000 lgths. 2.00 300.00 600.00
b. PVC Pipe, 101mm Ø x 3m, S1000 lgths. 5.00 652.00 3,260.00
c. Elbow, 50mm dia. x 90 deg. Bend pc 1.00 26.00 26.00
d. Elbow, 100mm dia. x 90 deg. bend pc 1.00 81.00 81.00
e. WYE, 50mm Ø pc 3.00 82.00 246.00
f. WYE, 100mm Ø pc 1.00 165.00 165.00
g.WYE Reducer, 100mm Ø x 50mm Ǿ pc 1.00 100.00 100.00
h. Clean Out w/ Cover, 100mm dia. pc 1.00 110.00 110.00
i. P-trap, 50mm dia. pc 1.00 120.00 120.00
j. PVC Solvent, 400cc cans 5.00 245.00 1,225.00
k. Consumables (5% of Material Cost) 296.65

Sub - Total for F 6,229.65


G. Direct Unit Cost (E + F) 10,118.84
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 1,517.83
I. Contractor's Profit (CP) 10% of G 1,011.88
J. Value Added Tax (VAT) 5% of (G + H + I) 632.43
K. Total Unit Cost (G + H + I + J) 13,280.98
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(11) Septic Vault


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 6.00 94.05 564.30


b. Skilled Laborer 2 6.00 67.95 815.40
c. Unskilled Laborer 6 6.00 52.42 1,887.12

Sub - Total for A 3,266.82

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 326.68

Sub - Total for B 326.68


C. Total (A + B) 3,593.50
D. Output = 1.00 l.s.
E. Direct Unit Cost (C ÷ D) 3,593.50

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Reinforcing Bars Grade 40 kg 63.96 44.00 2,814.24


b. Concrete cu.m. 0.81 5,065.00 4,102.65
c. Formworks sq.m. 6.75 #REF! #REF!
d. CHB Non-Load Bearing sq.m. 11.40 #REF! #REF!
f. Consumables (5% of Materials Cost) #REF!

Sub - Total for F #REF!


G. Direct Unit Cost (E + F) #REF!
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G #REF!
I. Contractor's Profit (CP) 10% of G #REF!
J. Value Added Tax (VAT) 5% of (G + H + I) #REF!
K. Total Unit Cost (G + H + I + J) #REF!
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(24) Cold Water Lines


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 5.00 94.05 470.25


b. Skilled Laborer 1 5.00 67.95 339.75
c. Unskilled Laborer 2 5.00 52.42 524.20

Sub - Total for A 1,334.20

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 133.42

Sub - Total for B 133.42


C. Total (A + B) 1,467.62
D. Output = 1.00 l.s.
E. Direct Unit Cost (C ÷ D) 1,467.62

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. PPRC Pipe, 20mm dia. X 4m, PN 16 lgths 14.00 275.50 3,857.00


b. PPRC Elbow, 20mm Ǿ pc 7.00 12.64 88.48
c. PPRC Tee, 20mm Ǿ pc 2.00 14.80 29.60
d. Water Meter 20mm dia. pc 1.00 11,500.00 11,500.00
e. PVC Solvent pc 3.00 245.00 735.00
f. Consumables (5% of Material Cost) 810.50

Sub - Total for F 17,020.58


G. Direct Unit Cost (E + F) 18,488.20
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 2,773.23
I. Contractor's Profit (CP) 10% of G 1,848.82
J. Value Added Tax (VAT) 5% of (G + H + I) 1,155.51
K. Total Unit Cost (G + H + I + J) 24,265.77
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1005(5) Steel Window


Unit of Measurement : l.s.
Output per hour : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 6.00 94.05 564.30


b. Skilled Laborer 1 6.00 67.95 407.70
c. Unskilled Laborer 1 6.00 52.42 314.52

Sub - Total for A 1,286.52

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Welding Machine 1 1.50 391.00 586.50


Minor Tools (10% of Labor Cost) 128.65

Sub - Total for B 715.15


C. Total (A + B) 2,001.67
D. Output per Hour = 1.00 l.s.
E. Direct Unit Cost (C ÷ D) 2,001.67

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 12 mm x 12 mm square bar kg 477.28 55.00 26250.40


b. 25 x 4 mm flat bar kg 30.78 55.00 1692.90
c. Consumables (3% of Materials Cost) 838.30

Sub - Total for F 28,781.60


G. Direct Unit Cost (E + F) 30,783.27
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 4,617.49
I. Contractor's Profit (CP) 10% of G 3,078.33
J. Value Added Tax (VAT) 5% of (G + H + I) 1,923.95
K. Total Unit Cost (G + H + I + J) 40,403.04

PART C - Finishing and other Civil Works


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1008(1)a Aluminum Glass Windows


Unit of Measurement : sq.m.
Output per hour : 0.36

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 94.05 94.05


b. Skilled Laborer 1 1.00 67.95 67.95
c. Unskilled Laborer 1 1.00 52.42 52.42

Sub - Total for A 214.42

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 21.44

Sub - Total for B 21.44


C. Total (A + B) 235.86
D. Output per Hour = 0.36 sq.m.
E. Direct Unit Cost (C ÷ D) 655.17

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Aluminum Glass Window (Sliding) m2 1.00 2,850.00 2850.00


b. Ordinary Window & Sheet Glass m2 1.00 450.00 450.00
b. Consumables (3% of Materials Cost) 99.00

Sub - Total for F 3,399.00


G. Direct Unit Cost (E + F) 4,054.17
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 486.50
I. Contractor's Profit (CP) 8% of G 324.33
J. Value Added Tax (VAT) 5% of (G + H + I) 243.25
K. Total Unit Cost (G + H + I + J) 5,108.26

PART C - Finishing and other Civil Works


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1008(1)c Aluminum Glass Windows


Unit of Measurement : sq.m.
Output per hour : 0.36

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 94.05 94.05


b. Skilled Laborer 1 1.00 67.95 67.95
c. Unskilled Laborer 1 1.00 52.42 52.42

Sub - Total for A 214.42

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 21.44

Sub - Total for B 21.44


C. Total (A + B) 235.86
D. Output per Hour = 0.36 sq.m.
E. Direct Unit Cost (C ÷ D) 655.172

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Aluminum Glass Window (Awning) m2 1.00 2,550.00 2550.00


b. Ordinary Window & Sheet Glass m2 1.00 450.00 450.00
b. Consumables (3% of Materials Cost) 90.00

Sub - Total for F 3,090.00


G. Direct Unit Cost (E + F) 3,745.17
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 449.42
I. Contractor's Profit (CP) 8% of G 299.61
J. Value Added Tax (VAT) 5% of (G + H + I) 224.71
K. Total Unit Cost (G + H + I + J) 4,718.92

PART C - Finishing and other Civil Works


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1010(1) Frames (Jambs, Sill, Head, Transoms and Mullions)
Unit of Measurement : set
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 2.00 94.05 188.10


b. Skilled Laborer 1 2.00 67.95 135.90
c. Unskilled Laborer 1 2.00 52.42 104.84

Sub - Total for A 428.84

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 42.88

Sub - Total for B 42.88


C. Total (A + B) 471.72
D. Output = 1 set
E. Direct Unit Cost (C ÷ D) 471.72

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Door Jambs set 1.00 2,000.00 2,000.00


b. Consumables (5% of Materials Cost) 100.00

Sub - Total for F 2,100.00


G. Direct Unit Cost (E + F) 2,571.72
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 308.61
I. Contractor's Profit (CP) 8% of G 205.74
J. Value Added Tax (VAT) 5% of (G + H + I) 154.30
K. Total Unit Cost (G + H + I + J) 3,240.37
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1010(2)b Wooden Panel Door


Unit of Measurement : m2
Output : 0.36

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 94.05 94.05


b. Skilled Laborer 1 1.00 67.95 67.95
c. Unskilled Laborer 1 1.00 52.42 52.42

Sub - Total for A 214.42

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 21.44

Sub - Total for B 21.44


C. Total (A + B) 235.86
D. Output = 0.36 m2
E. Direct Unit Cost (C ÷ D) 655.17

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Wooden Panel Door m2 1.00 5,250.00 5,250.00

Sub - Total for F 5,250.00


G. Direct Unit Cost (E + F) 5,905.17
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 708.62
I. Contractor's Profit (CP) 8% of G 472.41
J. Value Added Tax (VAT) 5% of (G + H + I) 354.31
K. Total Unit Cost (G + H + I + J) 7,440.52
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1010(4) Wooden Doors and Windows


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 510.50 94.05 48,012.53


b. Skilled Laborer 1 510.50 67.95 34,688.48
c. Unskilled Laborer 1 510.50 52.42 26,760.41

Sub - Total for A 109,461.41

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 10,946.14

Sub - Total for B 10,946.14


C. Total (A + B) 120,407.55
D. Output = 0.36 m2
E. Direct Unit Cost (C ÷ D) 120,407.55

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Wood Panel Doors m2 86.40 5,250.00 453,600.00


b. Hollow Core Flush Door m 2
52.80 650.00 34,320.00
c. Door Frames set 73.00 2,000.00 146,000.00
d. Bar Doors
d. Consumbale (5% of Material Cost of Door 7,300.00
Frames)

Sub - Total for F 641,220.00


G. Direct Unit Cost (E + F) 761,627.55
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 91,395.31
I. Contractor's Profit (CP) 8% of G 60,930.20
J. Value Added Tax (VAT) 5% of (G + H + I) 45,697.65
K. Total Unit Cost (G + H + I + J) 959,650.71
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1010(4) Wooden Doors and Windows


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 446.50 94.05 41,993.33


b. Skilled Laborer 1 446.50 67.95 30,339.68
c. Unskilled Laborer 1 446.50 52.42 23,405.53

Sub - Total for A 95,738.53

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 9,573.85

Sub - Total for B 9,573.85


C. Total (A + B) 105,312.38
D. Output = 0.36 m2
E. Direct Unit Cost (C ÷ D) 105,312.38

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Wood Panel Doors m2 69.12 5,250.00 362,880.00


b. Hollow Core Flush Door m 2
52.80 650.00 34,320.00
c. Door Frames set 65.00 2,000.00 130,000.00
d. Bar Doors
d. Consumbale (5% of Material Cost of Door 6,500.00
Frames)

Sub - Total for F 533,700.00


G. Direct Unit Cost (E + F) 639,012.38
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 76,681.49
I. Contractor's Profit (CP) 8% of G 51,120.99
J. Value Added Tax (VAT) 5% of (G + H + I) 38,340.74
K. Total Unit Cost (G + H + I + J) 805,155.60
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1010(4) Wooden Doors and Windows


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 382.50 94.05 35,974.13


b. Skilled Laborer 1 382.50 67.95 25,990.88
c. Unskilled Laborer 1 382.50 52.42 20,050.65

Sub - Total for A 82,015.65

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 8,201.57

Sub - Total for B 8,201.57


C. Total (A + B) 90,217.22
D. Output = 0.36 m2
E. Direct Unit Cost (C ÷ D) 90,217.22

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Wood Panel Doors m2 51.84 5,250.00 272,160.00


d. Consumbale 650.00
b. Hollow
(5% Core Flush Door
of Material m 2
52.80 34,320.00
c. Door
Cost of Frames
Door set 57.00 2,000.00 114,000.00
Frames) 5,700.00
d. Bar Doors
d. Consumbale (5% of Material Cost of Door 285.00
Frames)
Sub - Total for F 426,465.00
G. Direct Unit Cost (E + F) 516,682.21
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 62,001.87
I. Contractor's Profit (CP) 8% of G 41,334.58
J. Value Added Tax (VAT) 5% of (G + H + I) 31,000.93
K. Total Unit Cost (G + H + I + J) 651,019.59
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1006(3) Grille Door


Unit of Measurement : sq.m.
Output per hour : 0.26

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 94.05 94.05


b. Skilled Laborer 1 1.00 67.95 67.95
c. Unskilled Laborer 1 1.00 52.42 52.42

Sub - Total for A 214.42

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Welding Machine 1 0.25 391.00 97.75


Minor Tools (10% of Labor Cost) 21.44

Sub - Total for B 119.19


C. Total (A + B) 333.61
D. Output per Hour = 0.26 sq.m.
E. Direct Unit Cost (C ÷ D) 1,283.12

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 19mm square bar kg 30.14 55.00 1657.86


b. Welding Rod kg 0.48 95.00 45.24
Consumables (3% of Materials Cost) 51.09

Sub - Total for F 1,754.19


G. Direct Unit Cost (E + F) 3,037.31
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 364.48
I. Contractor's Profit (CP) 8% of G 242.98
J. Value Added Tax (VAT) 5% of (G + H + I) 182.24
K. Total Unit Cost (G + H + I + J) 3,827.01

PART C - Finishing and other Civil Works


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1010(4) Wooden Doors and Windows


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 191.50 94.05 18,010.58


b. Skilled Laborer 1 191.50 67.95 13,012.43
c. Unskilled Laborer 1 191.50 52.42 10,038.43

Sub - Total for A 41,061.43

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 4,106.14

Sub - Total for B 4,106.14


C. Total (A + B) 45,167.57
D. Output = 0.36 m2
E. Direct Unit Cost (C ÷ D) 45,167.57

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Wood Panel Doors m2 17.28 5,250.00 90,720.00


b. Hollow Core Flush Door m 2
35.28 650.00 22,932.00
c. Door Frames set 29.00 2,000.00 58,000.00
d. Bar Doors
d. Consumbale (5% of Material Cost of Door 2,900.00
Frames)

Sub - Total for F 174,552.00


G. Direct Unit Cost (E + F) 219,719.57
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 26,366.35
I. Contractor's Profit (CP) 8% of G 17,577.57
J. Value Added Tax (VAT) 5% of (G + H + I) 13,183.17
K. Total Unit Cost (G + H + I + J) 276,846.66
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1010(2)a Hollow Core Flush Door


Unit of Measurement : m2
Output : 0.32

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 94.05 94.05


b. Skilled Laborer 1 1.00 67.95 67.95
c. Unskilled Laborer 1 1.00 52.42 52.42

Sub - Total for A 214.42

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 21.44

Sub - Total for B 21.44


C. Total (A + B) 235.86
D. Output = 0.32 m2
E. Direct Unit Cost (C ÷ D) 737.07

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Hollow Core Flush Door m2 1.00 650.00 650.00

Sub - Total for F 650.00


G. Direct Unit Cost (E + F) 1,387.07
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 166.45
I. Contractor's Profit (CP) 8% of G 110.97
J. Value Added Tax (VAT) 5% of (G + H + I) 83.22
K. Total Unit Cost (G + H + I + J) 1,747.71
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1009(1)a Jalousie Window (Glass)


Unit of Measurement : m2
Output per hour : 0.27

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 94.05 94.05


b. Skilled Laborer 1 1.00 67.95 67.95
c. Unskilled Laborer 1 1.00 52.42 52.42

Sub - Total for A 214.42

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 21.44

Sub - Total for B 21.44


C. Total (A + B) 235.86
D. Output per Hour = 0.27 m2
E. Direct Unit Cost (C ÷ D) 873.56

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Jalousie Window (Glass) m2 1.00 650.00 650.00


b. Consumables (3% of Materials Cost) 19.50

Sub - Total for F 669.50


G. Direct Unit Cost (E + F) 1,543.06
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 185.17
I. Contractor's Profit (CP) 8% of G 123.45
J. Value Added Tax (VAT) 5% of (G + H + I) 92.58
K. Total Unit Cost (G + H + I + J) 1,944.26
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1006 (6) Steel Doors and Frames


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 94.05 94.05


b. Skilled Laborer 1 1.00 67.95 67.95
c. Unskilled Laborer 1 1.00 52.42 52.42

Sub - Total for A 214.42

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 21.44

Sub - Total for B 21.44


C. Total (A + B) 235.86
D. Output = 0.36 m2
E. Direct Unit Cost (C ÷ D) 235.86

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Steel Door m2 3.04 2,350.00 7,144.00


b. Door Frames (0.8 x 1.9m) set 2.00 1,650.00 3,300.00
c. Consumable (5% of Material Cost of Door 165.00
Frames)

Sub - Total for F 10,609.00


G. Direct Unit Cost (E + F) 10,844.86
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 1,301.38
I. Contractor's Profit (CP) 8% of G 867.59
J. Value Added Tax (VAT) 5% of (G + H + I) 650.69
K. Total Unit Cost (G + H + I + J) 13,664.53
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1003(9) Carpentry and Joinery Works


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Installation
a. Construction Foreman 1 60.00 94.05 5,643.00
b. Skilled Laborer 1 80.00 67.95 5,436.00
c. Unskilled Laborer 1 80.00 52.42 4,193.60

Sub - Total for A 15,272.60

Name and Capacity Quantity No. of Day/s Daily Rental Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost) 1,527.26

Sub - Total for B 1,527.26


C. Sub - Total for C (B ÷ Area) 16,799.86
D. Output = 1.00 l.s.
E. Direct Unit Cost (A ÷ D) + C 16,799.86

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Blackboard set 20.000 3,100.00 62,000.00

Sub - Total for F 62,000.00


G. Direct Unit Cost (E + F) 78,799.86
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 9,455.98
I. Contractor's Profit (CP) 8% of G 6,303.99
J. Value Added Tax (VAT) 5% of (G + H + I) 4,727.99
K. Total Unit Cost (G + H + I + J) 99,287.82
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1003(9) Carpentry and Joinery Works


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Installation
a. Construction Foreman 1 48.00 94.05 4,514.40
b. Skilled Laborer 1 64.00 67.95 4,348.80
c. Unskilled Laborer 1 64.00 52.42 3,354.88

Sub - Total for A 12,218.08

Name and Capacity Quantity No. of Day/s Daily Rental Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost) 1,221.81

Sub - Total for B 1,221.81


C. Sub - Total for C (B ÷ Area) 13,439.89
D. Output = 1.00 l.s.
E. Direct Unit Cost (A ÷ D) + C 13,439.89

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Blackboard set 16.000 3,100.00 49,600.00

Sub - Total for F 49,600.00


G. Direct Unit Cost (E + F) 63,039.89
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 7,564.79
I. Contractor's Profit (CP) 8% of G 5,043.19
J. Value Added Tax (VAT) 5% of (G + H + I) 3,782.39
K. Total Unit Cost (G + H + I + J) 79,430.26
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1003(9) Carpentry and Joinery Works


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Installation
a. Construction Foreman 1 36.00 94.05 3,385.80
b. Skilled Laborer 1 48.00 67.95 3,261.60
c. Unskilled Laborer 1 48.00 52.42 2,516.16

Sub - Total for A 9,163.56

Name and Capacity Quantity No. of Day/s Daily Rental Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost) 916.36

Sub - Total for B 916.36


C. Sub - Total for C (B ÷ Area) 10,079.92
D. Output = 1.00 l.s.
E. Direct Unit Cost (A ÷ D) + C 10,079.92

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Blackboard set 12.000 3,100.00 37,200.00

Sub - Total for F 37,200.00


G. Direct Unit Cost (E + F) 47,279.92
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 5,673.59
I. Contractor's Profit (CP) 8% of G 3,782.39
J. Value Added Tax (VAT) 5% of (G + H + I) 2,836.79
K. Total Unit Cost (G + H + I + J) 59,572.69
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1003(17) Carpentry and Joinery Works


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Installation
a. Construction Foreman 1 60.00 94.05 5,643.00
b. Skilled Laborer 1 80.00 67.95 5,436.00
c. Unskilled Laborer 1 80.00 52.42 4,193.60

Sub - Total for A 15,272.60

Name and Capacity Quantity No. of Day/s Daily Rental Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost) 1,527.26

Sub - Total for B 1,527.26


C. Sub - Total for C (B ÷ Area) 16,799.86
D. Output = 1.00 l.s.
E. Direct Unit Cost (A ÷ D) + C 16,799.86

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Blackboard set 20.000 3,100.00 62,000.00

Sub - Total for F 62,000.00


G. Direct Unit Cost (E + F) 78,799.86
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 9,455.98
I. Contractor's Profit (CP) 8% of G 6,303.99
J. Value Added Tax (VAT) 5% of (G + H + I) 4,727.99
K. Total Unit Cost (G + H + I + J) 99,287.82
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1003(9) Carpentry and Joinery Works


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Installation
a. Construction Foreman 1 12.00 94.05 1,128.60
b. Skilled Laborer 1 16.00 67.95 1,087.20
c. Unskilled Laborer 1 16.00 52.42 838.72

Sub - Total for A 3,054.52

Name and Capacity Quantity No. of Day/s Daily Rental Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost) 305.45

Sub - Total for B 305.45


C. Sub - Total for C (B ÷ Area) 3,359.97
D. Output = 1.00 l.s.
E. Direct Unit Cost (A ÷ D) + C 3,359.97

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Blackboard set 4.000 3,100.00 12,400.00

Sub - Total for F 12,400.00


G. Direct Unit Cost (E + F) 15,759.97
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 1,891.20
I. Contractor's Profit (CP) 8% of G 1,260.80
J. Value Added Tax (VAT) 5% of (G + H + I) 945.60
K. Total Unit Cost (G + H + I + J) 19,857.56
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1053(2)a1 38 mm Ø G.I. Pipe Railings


Unit of Measurement : m
Output per hour : 6.255

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 94.05 94.05


b. Skilled Laborer 1 1.00 67.95 67.95
c. Unskilled Laborer 2 1.00 52.42 104.84

Sub - Total for A 266.84

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Welding Machine 1 0.75 391.00 293.25


b. Cutting Outfit 1 0.25 45.45 11.36
Minor Tools (10% of labor cost) 26.68

Sub - Total for B 331.30


C. Total (A + B) 598.14
D. Output per Hour = 6.255 m
E. Direct Unit Cost (C ÷ D) 95.63

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 38 mm Ø G.I. Pipe pc 0.330 1,100.00 363.00


c. Welding Rod pcs 0.015 120.00 1.80
d. Consumables (5% of material cost) 18.24

Sub - Total for F 383.04


G. Direct Unit Cost (E + F) 478.67
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 57.44
I. Contractor's Profit (CP) 8% of G 38.29
J. Value Added Tax (VAT) 5% of (G + H + I) 28.72
K. Total Unit Cost (G + H + I + J) 603.12
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1038(1) Reflective Insulation


Unit of Measurement : sq.m.
Output per hour : 5.56

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 94.05 94.05


b. Skilled Laborer 1 1.00 67.95 67.95
c. Unskilled Laborer 2 1.00 52.42 104.84

Sub - Total for A 266.84

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 26.68

Sub - Total for B 26.68


C. Total (A + B) 293.52
D. Output per Hour = 5.56 sq.m.
E. Direct Unit Cost (C ÷ D) 52.79

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Reflective Insulation, 10 mm thk sq.m. 1.000 135.00 135.00


b. Consumbles (5% of Materials Cost) 6.75

Sub - Total for F 141.75


G. Direct Unit Cost (E + F) 194.54
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 29.18
I. Contractor's Profit (CP) 10% of G 19.45
J. Value Added Tax (VAT) 5% of (G + H + I) 12.16
K. Total Unit Cost (G + H + I + J) 255.34
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(2)a Structural Steel


Unit of Measurement : kg.
Output per hour : 85.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Fabrication
a. Construction Foreman 1 1.00 94.05 94.05
b. Skilled Laborer 2 1.00 67.95 135.90
c. Unskilled Laborer 2 1.00 52.42 104.84

Erection
a. Skilled Laborer 3 0.49 67.95 99.89
b. Unskilled Laborer 3 0.49 52.42 77.06

Sub - Total for A 511.73

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Welding Machine 1 0.75 371.00 278.25


b. Cutting Outfit 1 0.25 45.45 11.36
c. Truck Mounted Crane (20-25 mt) 1 0.49 1,631.00 799.19
Minor Tools (10 % of Labor Cost) 51.17

Sub - Total for B 1,139.98


C. Total (A + B) 1,651.71
D. Output per Hour = 85.00 kg
E. Direct Unit Cost (C ÷ D) 19.43

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Structural Steel Truss kg 1.05 50.00 52.50


b. Acetylene kg 0.011 65.00 0.72
c. Oxygen kg 0.022 55.00 1.21
d. Welding Rod kg 0.020 120.00 2.40
e. Consumables (5% of Materials Cost) 2.84

Sub - Total for F 59.67


G. Direct Unit Cost (E + F) 79.10
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 9.49
I. Contractor's Profit (CP) 8% of G 6.33
J. Value Added Tax (VAT) 5% of (G + H + I) 4.75
K. Total Unit Cost (G + H + I + J) 99.66
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(2)b Structural Steel


Unit of Measurement : kg.
Output per hour : 90.45

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 94.05 94.05


b. Skilled Laborer 2 1.00 67.95 135.90
c. Unskilled Laborer 4 1.00 52.42 209.68

Sub - Total for A 439.63

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Welding Machine 2 1.00 371.00 742.00


Minor Tools (10% of Labor Cost) 43.96

Sub - Total for B 785.96


C. Total (A + B) 1,225.59
D. Output per Hour = 90.45 kg
E. Direct Unit Cost (C ÷ D) 13.55

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Structural Steel Purlins kg 1.05 55.00 57.75


b. Welding Rod kg 0.02 120.00 2.40
b. Consumables (5% of Materials Cost) 3.01

Sub - Total for F 63.16


G. Direct Unit Cost (E + F) 76.71
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 9.20
I. Contractor's Profit (CP) 8% of G 6.14
J. Value Added Tax (VAT) 5% of (G + H + I) 4.60
K. Total Unit Cost (G + H + I + J) 96.65
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(6) Metal Structure Accessories


Unit of Measurement : kg
Output per hour : 12.995

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 94.05 94.05


b. Skilled Laborer 1 1.00 67.95 67.95
c. Unskilled Laborer 1 1.00 52.42 52.42

Sub - Total for A 214.42

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 21.44

Sub - Total for B 21.44


C. Total (A + B) 235.86
D. Output per Hour = 12.995 kg
E. Direct Unit Cost (C ÷ D) 18.15

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Steel Plates kg 1.05 45.00 47.25


b. Consumables (3% of Materials Cost) 1.42

Sub - Total for F 48.67


G. Direct Unit Cost (E + F) 66.82
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 8.02
I. Contractor's Profit (CP) 8% of G 5.35
J. Value Added Tax (VAT) 5% of (G + H + I) 4.01
K. Total Unit Cost (G + H + I + J) 84.19
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(7)b Metal Structure Accessories


Unit of Measurement : kg.
Output : 12.995

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 94.05 94.05


b. Skilled Laborer 1 1.00 67.95 67.95
c. Unskilled Laborer 1 1.00 52.42 52.42

Sub - Total for A 214.42

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 21.44

Sub - Total for B 21.44


C. Total (A + B) 235.86
D. Output = 12.995 kg
E. Direct Unit Cost (C ÷ D) 18.15

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Sagrod with nuts and bolts kg 1.05 37.88 39.77

Sub - Total for F 39.77


G. Direct Unit Cost (E + F) 57.92
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 6.95
I. Contractor's Profit (CP) 8% of G 4.63
J. Value Added Tax (VAT) 5% of (G + H + I) 3.48
K. Total Unit Cost (G + H + I + J) 72.98
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(4) Metal Structure Accessories (Crossbracing)


Unit of Measurement : kg
Output per hour : 12.995

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 94.05 94.05


b. Skilled Laborer 1 1.00 67.95 67.95
c. Unskilled Laborer 1 1.00 52.42 52.42

Sub - Total for A 214.42

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 21.44

Sub - Total for B 21.44


C. Total (A + B) 235.86
D. Output per Hour = 12.995 kg
E. Direct Unit Cost (C ÷ D) 18.15

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Cross Bracing kg 1.05 37.88 39.77


b. Consumables (3% of Material Cost) 1.19

Sub - Total for F 40.97


G. Direct Unit Cost (E + F) 59.12
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 7.09
I. Contractor's Profit (CP) 8% of G 4.73
J. Value Added Tax (VAT) 5% of (G + H + I) 3.55
K. Total Unit Cost (G + H + I + J) 74.49
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(3)c Metal Structure Accessories (Turnbuckle)


Unit of Measurement : pc
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.15 94.05 14.11


b. Skilled Laborer 1 0.15 67.95 10.19
c. Unskilled Laborer 1 0.15 52.42 7.86

Sub - Total for A 32.16

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 0.03

Sub - Total for B 0.03


C. Total (A + B) 32.20
D. Output = 1 pc
E. Direct Unit Cost (C ÷ D) 32.20

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Standard Turnbuckle pc 1.00 164.08 164.08

Sub - Total for F 164.08


G. Direct Unit Cost (E + F) 196.28
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 23.55
I. Contractor's Profit (CP) 8% of G 15.70
J. Value Added Tax (VAT) 5% of (G + H + I) 11.78
K. Total Unit Cost (G + H + I + J) 247.31
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(10) Metal Structure Accessories


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 40.91 94.05 3,847.59


b. Skilled Laborer 1 40.91 67.95 2,779.83
c. Unskilled Laborer 1 40.91 52.42 2,144.50

Sub - Total for A 8,771.92

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Welding Machine 1 40.91 391.00 15,995.81


Minor Tools (10% of Labor Cost) 877.19

Sub - Total for B 16,873.00


C. Total (A + B) 25,644.92
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 25,644.92

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials
Spiral Steel Staircase:
a. Checkered Plate kgs. 220.88 45.00 9,939.60
b. 25 x 25 x 4.5mm Angle Bar kgs. 44.06 50.00 2,203.00
c. 19mm square bar kgs. 175.99 55.00 9,679.18
d. 50mm dia. GI Pipe (Handrail) pcs. 3.00 2,400.00 7,200.00
f. 150mm dia. GI Pipe (Pole) pcs. 2.00 4,100.00 8,200.00
g. 100mm dia. GI Pipe (Strut) pcs. 1.00 9,900.00 9,900.00
f. 200 x 100mm C Purlins kgs. 8.40 55.00 462.00
g. Base Plate kgs. 46.83 50.15 2,348.52
h. Anchor Bolts with Washers kgs. 35.52 193.33 6,867.08
i. Welding Rod kgs. 18.00 120.00 2,160.00
Consumables (5% of Material Cost) 2,947.97

Sub - Total for F 61,907.35


G. Direct Unit Cost (E + F) 87,552.27
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 10,506.27
I. Contractor's Profit (CP) 8% of G 7,004.18
J. Value Added Tax (VAT) 5% of (G + H + I) 5,253.14
K. Total Unit Cost (G + H + I + J) 110,315.87
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(8) Sewer Line Works (20 CL)


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 85.00 94.05 7,994.25


b. Skilled Laborer 1 85.00 67.95 5,775.75
c. Unskilled Laborer 2 85.00 52.42 8,911.40

Sub - Total for A 22,681.40

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment
Minor Tools (10% of labor cost) 2,268.14
Sub - Total for B 2,268.14
C. Total (A + B) 24,949.54
D. Output = 1
E. Direct Unit Cost (C ÷ D) 24,949.54

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials
a. PVC Pipe, 50mm Ø x 3m, S-1000 lgths. 6.00 300.00 1,800.00
b. PVC Pipe, 50mm Ø x 3m, S-1000 (Vent) lngths 40.00 300.00 12,000.00
c. PVC Pipe. 75mm dia. X 3m, S-1000 (Vent) lngths 9.00 435.00 3,915.00
d. PVC Pipe, 101mm Ø x 3m, S1000 lgths. 23.00 652.00 14,996.00
e. PVC Pipe, 150mm Ø x 3m, S-1000 lgths. 19.00 1,975.29 37,530.51
f. Elbow, 50mm dia. x 90 deg. Bend pc 16.00 26.00 416.00
g. Elbow, 150mm dia. x 90 deg. bend pc 5.00 538.33 2,691.65
h. WYE, 50mm Ø pc 18.00 82.00 1,476.00
i. WYE, 100mm Ø pc 20.00 165.00 3,300.00
j. WYE, 150mm Ø pc 4.00 1,136.21 4,544.84
k.WYE Reducer, 100mm Ø x 75mm Ǿ pc 2.00 120.00 240.00
l.WYE Reducer, 150mm Ø x 100mm Ǿ pc 4.00 807.29 3,229.16
m. PVC Tee, 50mm dia. X 50mm dia pc 48.00 60.00 2,880.00
n. PVC Tee,150mm x150mm pc 4.00 926.89 3,707.56
o. Clean Out w/ Cover, 50mm dia. pc 4.00 45.00 180.00
p. Clean Out w/ Cover, 100mm dia. pc 4.00 110.00 440.00
q. Clean Out w/ Cover, 150mm dia. pc 9.00 627.90 5,651.10
r. P-trap, 50mm dia. pc 63.00 120.00 7,560.00
s. PVC Solvent, 400cc cans 10.00 245.00 2,450.00
t. Consumables (5% of Material Cost) 3,512.08

Sub - Total for F 112,519.90


G. Direct Unit Cost (E + F) 137,469.44
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 16,496.33
I. Contractor's Profit (CP) 8% of G 10,997.55
J. Value Added Tax (VAT) 5% of (G + H + I) 8,248.17
K. Total Unit Cost (G + H + I + J) 173,211.49
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(6) Waterline Works (20 CL)


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 19.75 94.05 1,857.49


b. Skilled Laborer 1 19.75 67.95 1,342.01
c. Unskilled Laborer 2 19.75 52.42 2,070.59

Sub - Total for A 5,270.09

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 527.01

Sub - Total for B 527.01


C. Total (A + B) 5,797.10
D. Output = 1
E. Direct Unit Cost (C ÷ D) 5,797.10

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

c. PPRC Pipe, 20mm dia. X 4m, PN 16 lgths 10.00 275.50 2,755.00


b. PPRC Pipe, 25mm dia. X 4m, PN 16 lgths 13.00 425.92 5,536.96
a. PPRC Pipe, 32mm dia. X 4m, PN 16 lgths 2.00 736.28 1,472.56
d. PPRC Pipe, 38mm dia. X 4m, PN16 lgths 15.00 1,117.85 16,767.75
l. PPRC Elbow, 20mm Ǿ pcs. 20.00 12.64 252.80
n. PPRC Elbow, 25mm Ǿ pcs. 6.00 20.54 123.24
m. PPRC Elbow, 32mm Ǿ pcs. 2.00 31.60 63.20
y. PP-R Elbow 38mm dia. - 90deg pcs. 2.00 53.91 107.82
bb. PP- R Elbow Reducer 25mm x 20mm pcs 8.00 163.07 1,304.56
aa. PP- R Elbow Reducer 32mm x 25mm pcs 2.00 50.00 100.00
z. PP- R Elbow Reducer 38mm x 32mm pcs. 2.00 53.91 107.82
g. PPRC Tee, 20mm Ǿ pc. 22.00 14.80 325.60
y. Consumables (5% of Material Cost) 1,326.61

Sub - Total for F 30,243.92


G. Direct Unit Cost (E + F) 36,041.02
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 4,324.92
I. Contractor's Profit (CP) 8% of G 2,883.28
J. Value Added Tax (VAT) 5% of (G + H + I) 2,162.46
K. Total Unit Cost (G + H + I + J) 45,411.69
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(9) Storm Drainage and Downspout (20 CL)


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 79.75 94.05 7,500.49


b. Skilled Laborer 2 79.75 67.95 10,838.03
c. Unskilled Laborer 4 79.75 52.42 16,721.98

Sub - Total for A 35,060.49

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Minor Tools (10% of labor cost) 3,506.05


b. Plate Compactor (5hp) 1 12.41 123.00 1,526.43

Sub - Total for B 5,032.48


C. Total (A + B) 40,092.97
D. Output = 1
E. Direct Unit Cost (C ÷ D) 40,092.97

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a.PVC 150mm dia x3m lgths. 40.00 1,975.29 79,011.60


b. Roof Drain ( Dome-type strainer) pcs. 26.00 1,500.00 39,000.00
c. PVC Pipe, 100mm Ø x 3m, S-1000 lgths. 66.00 652.00 43,032.00
d. Elbow, 100mm dia. x 90 deg. Bend pcs. 36.00 81.00 2,916.00
e. PVC Solvent, 400cc cans 7.00 245.00 1,715.00
f. Consumables (5% of Material Cost) 2,151.60

Sub - Total for F 167,826.20


G. Direct Unit Cost (E + F) 207,919.17
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 24,950.30
I. Contractor's Profit (CP) 8% of G 16,633.53
J. Value Added Tax (VAT) 5% of (G + H + I) 12,475.15
K. Total Unit Cost (G + H + I + J) 261,978.16
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(5) Sanitary/Plumbing Fixtures (20 CL)


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 257.75 94.05 24,241.39


b. Skilled Laborer 1 257.75 67.95 17,514.11
c. Unskilled Laborer 1 257.75 52.42 13,511.26

Sub - Total for A 55,266.76

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 5,526.68

Sub - Total for B 5,526.68


C. Total (A + B) 60,793.43
D. Output = 1
E. Direct Unit Cost (C ÷ D) 60,793.43

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Water Closet complete w/ fittings & accs. sets 20.00 5,500.00 110,000.00
b. Wall Hung Lavatory, complete w/ fittings & accs. sets 2.00 6,500.00 13,000.00
c. Urinal (trough) sets 4.00 9,500.00 38,000.00
d. Floor Drain pcs 63.00 280.00 17,640.00
e. Faucet pcs 24.00 195.00 4,680.00
f. Gate Valve 20mm pcs 4.00 450.00 1,800.00
g. Gate Valve 32mm pcs 8.00 627.00 5,016.00
h. Gate Valve 50mm pcs 3.00 980.00 2,940.00
i. Check Valve 50mm pcs 1.00 954.00 954.00
j. Concrete Sink 3 faucet sets 8.00 6,028.00 48,224.00
k. Mirror m2 40.00 500.00 20,000.00
l. PWD handrail sets 2.00 4,500.00 9,000.00
m. Consumables (5% of Materials Cost) 13,562.70

Sub - Total for F 284,816.70


G. Direct Unit Cost (E + F) 345,610.13
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 41,473.22
I. Contractor's Profit (CP) 8% of G 27,648.81
J. Value Added Tax (VAT) 5% of (G + H + I) 20,736.61
K. Total Unit Cost (G + H + I + J) 435,468.76
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL-3 Fire Protection System (20CL)


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 866.00 94.05 81,447.30


b. Skilled Laborer 2 866.00 67.95 117,689.40
c. Unskilled Laborer 4 866.00 52.42 181,582.88

Sub - Total for A 380,719.58

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 38,071.96

Sub - Total for B 38,071.96


C. Total (A + B) 418,791.54
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) 418,791.54

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. B.I. Pipe 100mm dia lm 30.00 1,889.00 56,670.00


b. B.I. Pipe 75mm dia lm 90.00 984.00 88,560.00
c. B.I. Pipe 65mm dia lm 150.00 708.00 106,200.00
d. B.I. Pipe 50mm dia lm 30.00 425.00 12,750.00
e. B.I. Pipe 40mm dia lm 540.00 317.00 171,180.00
f. B.I. Pipe 25mm dia lm 93.00 192.00 17,856.00
g. Fittings (Elbow, Tee, Reducer, etc) l.s. 1.00 181,286.40 181,286.40
h. Pendent 12mm dia pc 177.00 503.00 89,031.00
i. Side Wall 12mm dia pc 8.00 518.00 4,144.00
j. Fire Hose Cabinet with Fire Extinguisher set 8.00 24,000.00 192,000.00
k. Fire Extinguisher, 10 lbs Capacity, Wall set 20.00 6,825.00 136,500.00
Mounted, HCFC 123
l. FP-1, Horizontal Split Case Centrifugal Pump
with A.C. Motor & Controller, UL/FM Approved, assy 1.00 1,116,923.00 1,116,923.00
350 GPM, 125psi, 40 HP, 230/3/60
m. JP-1 Vertical In-Line Centrifugal Pump with AC
Motor & Controller, UL/FM Approved, 10GPM, assy 1.00 300,000.00 300,000.00
5HP, 130psi, 230, 3/60
n. Gate Valve (OS & Y), 100mm dia unit 1.00 31,680.00 31,680.00
o. Y-Strainer unit 1.00 36,118.45 36,118.45
p.Check Valve unit 1.00 17,500.00 17,500.00
q. Alarm Check Valve Assembly unit 1.00 63,360.00 63,360.00
r. Globe Valve unit 1.00 9,114.00 9,114.00
s. Pressure Reducing Valve unit 1.00 104,099.33 104,099.33
t. Float Valve unit 1.00 77,396.68 77,396.68
u. Water Flow Switch unit 1.00 6,468.00 6,468.00
v.Floor Control Valve unit 1.00 8,303.00 8,303.00
w. Pressure Gauge unit 1.00 971.13 971.13
x. FDC Siamese Twin: Two-Way unit 1.00 6,500.00 6,500.00
y. Isolation Valve unit 1.00 18,000.00 18,000.00
z. Water Flow Meter unit 1.00 58,084.99 58,084.99
aa. Drain Off Valve unit 1.00 19,557.51 19,557.51
bb. Roof Manifold unit 1.00 16,199.14 16,199.14
cc. Hangers and Support l.s. 1.00 45,321.60 45,321.60

dd. Electrical Works for Pumps from Main Breaker l.s. 1.00 15,000.00 15,000.00

ee. Miscellaneous and Consumables l.s. 1.00 5,000.00 5,000.00


ff. Testing and Commissioning l.s. 1.00 70,846.15 70,846.15
gg. Overhead Water Tank 2000 US Gal unit 2.00 167,000.00 334,000.00
hh. Fire Reserve Tank 11000 US gal unit 1.00 162,962.00 162,962.00
ii. End-Suction Centrifugal Water Pump, TDH 27m,
3.0HP, 80GPM unit 2.00 47,000.00 94,000.00

Sub - Total for F 3,673,582.38


G. Direct Unit Cost (E + F) 4,092,373.92
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 491,084.87
I. Contractor's Profit (CP) 8% of G 327,389.91
J. Value Added Tax (VAT) 5% of (G + H + I) 245,542.44
K. Total Unit Cost (G + H + I + J) 5,156,391.14

* Please Check the Summation for Sub-Total A, B,


and F
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL-3 Septic Vault Type E (20 CL)


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 59.00 94.05 5,548.95


b. Skilled Laborer 2 59.00 67.95 8,018.10
c. Unskilled Laborer 4 59.00 52.42 12,371.12

Sub - Total for A 25,938.17

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 2,593.82

Sub - Total for B 2,593.82


C. Total (A + B) 28,531.99
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) 28,531.99

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Reinforcing Bars Grade 40 kgs 1045.71 44.00 46,011.24


b. Concrete m3 14.92 5,065.00 75,569.80
c. Plaster Finish m2 137.38 84.25 11,574.27
d. Waterproofing, Sahara bag 332.00 45.00 14,940.00
e. 6" thk. CHB m2 8.00 187.50 1,500.00
f. 4" thk. CHB m2 4.00 162.50 650.00

Sub - Total for F 150,245.31


G. Direct Unit Cost (E + F) 178,777.29
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 21,453.28
I. Contractor's Profit (CP) 8% of G 14,302.18
J. Value Added Tax (VAT) 5% of (G + H + I) 10,726.64
K. Total Unit Cost (G + H + I + J) 225,259.39
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(6)b1 Catch Basin -1 (20 CL)


Unit of Measurement : ea
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 94.05 94.05


b. Skilled Laborer 1 1.00 67.95 67.95
c. Unskilled Laborer 1 1.00 52.42 52.42

Sub - Total for A 214.42

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 21.44

Sub - Total for B 21.44


C. Total (A + B) 235.86
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) 235.86

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 10 mm dia x 6.0 Reinforcing Steel Bars kg 8.63 44.00 379.72


b. Concrete m3 0.07 5,065.00 354.55
c. Masonry m2 0.80 162.50 130.00
d. Plaster Finish m 2
1.76 84.25 148.28

Sub - Total for F 1,012.55


G. Direct Unit Cost (E + F) 1,248.41
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 149.81
I. Contractor's Profit (CP) 8% of G 99.87
J. Value Added Tax (VAT) 5% of (G + H + I) 74.90
K. Total Unit Cost (G + H + I + J) 1,573.00
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(10) Conduit, Boxes, and Fittings


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 11.00 94.05 1,034.55


b. Skilled Laborer 1 15.00 67.95 1,019.25
c. Unskilled Laborer 1 15.00 52.42 786.30

Sub - Total for A 2,840.10

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 284.01

Sub - Total for B 284.01


C. Total (A + B) 3,124.11
D. Output = 1.00 l.s.
E. Direct Unit Cost (C ÷ D) 3,124.11

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 20mmØ PVC conduit length 51.00 69.00 3,519.00


b. 25mmØ PVC pipe length 25.00 92.00 2,300.00
c. 80mmØ RSC pipe length 3.00 2,961.70 8,885.10
d. 80mmØ RSC Elbow pc 3.00 1,483.35 4,450.05
b. 20mmØ PVC adapter pc 2.00 8.00 16.00
f. 25mmØ PVC Adapter pc 3.00 14.00 42.00
c. 20mmØ L&B pc 5.00 8.00 40.00
h. 25mmØ L&B pc 5.00 14.00 70.00
f. utility box, deep type pc 37.00 50.00 1,850.00
g. junction box, deep type pc 9.00 50.00 450.00
m. 80mmØ entrance cap pc 1.00 608.00 608.00
n. 16mmØ x 2.4m ground rod w/ connector pc 1.00 1,200.00 1,200.00

Sub - Total for F 23,430.15


G. Direct Unit Cost (E + F) 26,554.26
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 3,186.51
I. Contractor's Profit (CP) 8% of G 2,124.34
J. Value Added Tax (VAT) 5% of (G + H + I) 1,593.26
K. Total Unit Cost (G + H + I + J) 33,458.37
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1102(1) Panelboard with Main & Branch Breakers


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 7.00 94.05 658.35


b. Skilled Laborer 1 7.00 67.95 475.65
c. Unskilled Laborer 2 7.00 52.42 733.88

Sub - Total for A 1,867.88

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 186.79

Sub - Total for B 186.79


C. Total (A + B) 2,054.67
D. Output = 1.00 l.s.
E. Direct Unit Cost (C ÷ D) 2,054.67

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

LPA - Flush Mounted, NEMA 1 Enclosure w/ Ground Ter set 1.00 5,185.00 5,185.00
Main: 1 - 60 AMP, 2P
Branches: 4 - 30 AMP, 2P
2 - 30 AMP, 2P

1 - 40at, 100af, 3p, 240v

Automatic Transfer Switch set 0.00 128,000.00 -


Main: 700AT, 800AF, 240V, 65KAIC

LPB, LPC and LPD - Flush Mounted, NEMA 1 Enclosure set 0.00 14,346.80 -
Main: 50at, 2p, 240v, 1KAIC
Branches: 3 - 15at, 50af, 2p, 230v
7 - 20at, 50af, 2p, 240v

40at, 50af, 2p, 240v, in NEMA 3R enclosure set 0.00 1,200.00 -


30at, 50af, 2p, 240v, in NEMA 3R enclosure set 0.00 1,200.00 -
20at, 50af, 2p, 240v, in NEMA 3R enclosure set 0.00 1,200.00 -

Sub - Total for F 5,185.00


G. Direct Unit Cost (E + F) 7,239.67
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 868.76
I. Contractor's Profit (CP) 8% of G 579.17
J. Value Added Tax (VAT) 5% of (G + H + I) 434.38
K. Total Unit Cost (G + H + I + J) 9,121.98
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1103(1) Lighting Fixtures (20 CL)


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 61.00 94.05 5,737.05


b. Skilled Laborer 1 61.00 67.95 4,144.95
c. Unskilled Laborer 2 61.00 52.42 6,395.24

Sub - Total for A 16,277.24

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 1,627.72

Sub - Total for B 1,627.72


C. Total (A + B) 17,904.96
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 17,904.96

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 2 x 36 watts FL fixture box type w/ canopy base


and stem 1.5 ft. (450mm) length similar to amco set 80.00 1,173.00 93,840.00
AP-113-1.5 or aproved equal.
b. 2 x 36 watts FL fixture. set 40.00 650.00 26,000.00
c. 1 x 36 watts FL fixture box type. set 78.00 355.00 27,690.00
d. 1 - 18 watts CFL w/ medium base keyless type
porcelain receptacle. set 7.00 320.00 2,240.00

e. Wall Fan with control Switch set 40.00 1,200.00 48,000.00

Sub - Total for F 197,770.00


G. Direct Unit Cost (E + F) 215,674.96
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 25,881.00
I. Contractor's Profit (CP) 8% of G 17,254.00
J. Value Added Tax (VAT) 5% of (G + H + I) 12,940.50
K. Total Unit Cost (G + H + I + J) 271,750.45
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1208(1) Fire Alarm System (20 CL)


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Skilled Laborer 1 897.00 67.95 60,951.15


47,020.74
b. Unskilled Laborer 1 897.00 52.42

Sub - Total for A 107,971.89

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 10,797.19

Sub - Total for B 10,797.19


C. Total (A + B) 118,769.08
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 118,769.08

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. B.I. Pipe 100mm dia lm 30.00 1,889.00 56,670.00


b. B.I. Pipe 75mm dia lm 90.00 984.00 88,560.00
c. B.I. Pipe 65mm dia lm 150.00 708.00 106,200.00
d. B.I. Pipe 50mm dia lm 30.00 425.00 12,750.00
e. B.I. Pipe 40mm dia lm 540.00 317.00 171,180.00
f. B.I. Pipe 25mm dia lm 93.00 192.00 17,856.00
g. Fittings (Elbow, Tee, Reducer, etc) l.s. 1.00 181,286.40 181,286.40
h. Pendent 12mm dia pc 177.00 503.00 89,031.00
i. Side Wall 12mm dia pc 8.00 518.00 4,144.00
j. Fire Hose Cabinet with Fire Extinguisher set 8.00 24,000.00 192,000.00
k. Fire Extinguisher, 10 lbs Capacity, Wall set 28.00 6,825.00 191,100.00
Mounted, HCFC 123
l. FP-1, Horizontal Split Case Centrifugal Pump
with A.C. Motor & Controller, UL/FM Approved, assy 1.00 1,116,923.00 1,116,923.00
350 GPM, 125psi, 40 HP, 230/3/60
m. JP-1 Vertical In-Line Centrifugal Pump with AC
Motor & Controller, UL/FM Approved, 10GPM, assy 1.00 300,000.00 300,000.00
5HP, 130psi, 230, 3/60
n. Gate Valve (OS & Y), 100mm dia unit 1.00 31,680.00 31,680.00
o. Y-Strainer unit 1.00 36,118.45 36,118.45
p.Check Valve unit 1.00 17,500.00 17,500.00
q. Alarm Check Valve Assembly unit 1.00 63,360.00 63,360.00
r. Globe Valve unit 1.00 9,114.00 9,114.00
s. Pressure Reducing Valve unit 1.00 104,099.33 104,099.33
t. Float Valve unit 1.00 77,396.68 77,396.68
u. Water Flow Switch unit 1.00 6,468.00 6,468.00
v.Floor Control Valve unit 1.00 8,303.00 8,303.00
w. Pressure Gauge unit 1.00 971.13 971.13
x. FDC Siamese Twin: Two-Way unit 1.00 6,500.00 6,500.00
y. Isolation Valve unit 1.00 18,000.00 18,000.00
z. Water Flow Meter unit 1.00 58,084.99 58,084.99
aa. Drain Off Valve unit 1.00 19,557.51 19,557.51
bb. Roof Manifold unit 1.00 16,199.14 16,199.14
cc. Hangers and Support l.s. 1.00 45,321.60 45,321.60

dd. Electrical Works for Pumps from Main Breaker l.s. 1.00 15,000.00 15,000.00

ee. Miscellaneous and Consumables l.s. 1.00 5,000.00 5,000.00


ff. Testing and Commissioning l.s. 1.00 70,846.15 70,846.15
gg. Overhead Water Tank 2000 US Gal unit 2.00 167,000.00 334,000.00
hh. Fire Reserve Tank 11000 US gal unit 1.00 162,962.00 162,962.00
ii. End-Suction Centrifugal Water Pump, TDH 27m,
3.0HP, 80GPM unit 2.00 47,000.00 94,000.00

a. Fire Alarm Control Panel set 1.00 13,890.00 13,890.00


b. Fire Alarm Bell set 8.00 1,350.00 10,800.00
c. Manual Pull Station Switch set 8.00 1,600.00 12,800.00
d. Smoke Detector set 20 1,150.00 23,000.00
e. Pull Box set 8 1,250.00 10,000.00
Sub - Total for F 3,798,672.38
G. Direct Unit Cost (E + F) 3,917,441.46
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 470,092.98
I. Contractor's Profit (CP) 8% of G 313,395.32
J. Value Added Tax (VAT) 5% of (G + H + I) 235,046.49
K. Total Unit Cost (G + H + I + J) 4,935,976.24
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(8) Sewer Line Works (16CL)


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 84.50 94.05 7,947.22


b. Skilled Laborer 1 84.50 67.95 5,741.78
c. Unskilled Laborer 2 84.50 52.42 8,858.98

Sub - Total for A 22,547.98

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment
Minor Tools (10% of labor cost) 2,254.80
Sub - Total for B 2,254.80
C. Total (A + B) 24,802.78
D. Output = 1
E. Direct Unit Cost (C ÷ D) 24,802.78

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials
a. PVC Pipe, 50mm Ø x 3m, S-1000 lgths. 6.00 300.00 1,800.00
b. PVC Pipe, 101mm Ø x 3m, S1000 lgths. 23.00 652.00 14,996.00
c. PVC Pipe, 150mm Ø x 3m, S-1001 lgths. 19.00 1,975.29 37,530.51
d. PVC Pipe, 50mm Ø x 3m, S-1000 vent lgths. 16.00 300.00 4,800.00
e. PVC Pipe, 75mm Ø x 3m, S-1000 vent lgths. 9.00 435.00 3,915.00
f. Elbow, 50mm dia. x 90 deg. Bend pc 16.00 26.00 416.00
g. Elbow, 150mm dia. x90 deg. Bend pc 5.00 538.33 2,691.65
h. WYE, 50mm Ø pc 18.00 82.00 1,476.00
i. WYE, 100mm Ø pc 20.00 165.00 3,300.00
j. WYE, 150mm Ø pc 4.00 1,136.21 4,544.84
k.WYE Reducer, 100mm Ø x 75mm Ǿ pc 2.00 120.00 240.00
l.WYE Reducer, 150mm Ø x 100mm Ǿ pc 4.00 807.29 3,229.16
m. Single Sweep Branch Tee, 50mm dia pc 48.00 60.00 2,880.00
n. Single Sweep Branch Tee,150mm x 150mm pc 4.00 926.89 3,707.56
o. Clean Out w/ Cover, 50mm dia. pc 4.00 45.00 180.00
p. Clean Out w/ Cover, 100mm dia. pc 4.00 110.00 440.00
q. Clean Out w/ Cover, 150mm dia. pc 9.00 627.90 5,651.10
r. P-trap, 50mm dia. pc 61.00 120.00 7,320.00
s. PVC Solvent, 400cc cans 10.00 245.00 2,450.00
t. Consumables (5% of Material Cost) 2,716.33

Sub - Total for F 104,284.15


G. Direct Unit Cost (E + F) 129,086.92
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 15,490.43
I. Contractor's Profit (CP) 8% of G 10,326.95
J. Value Added Tax (VAT) 5% of (G + H + I) 7,745.22
K. Total Unit Cost (G + H + I + J) 162,649.52
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(6) Waterline Works (16CL)


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 14.25 94.05 1,340.21


b. Skilled Laborer 1 14.25 67.95 968.29
c. Unskilled Laborer 2 14.25 52.42 1,493.97

Sub - Total for A 3,802.47

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 380.25

Sub - Total for B 380.25


C. Total (A + B) 4,182.72
D. Output = 1
E. Direct Unit Cost (C ÷ D) 4,182.72

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. PPRC Pipe, 20mm dia. X 4m, PN 16 lgths 10.00 275.50 2,755.00


b. PPRC Pipe, 25mm dia. X 4m, PN 16 lgths 13.00 425.92 5,536.96
c. PPRC Pipe, 38mm dia. X 4m, PN16 lgths 12.00 1,117.85 13,414.20
d. PPRC Pipe, 32mm dia. X 4m, PN16 lgths 2.00 736.28 1,472.56
e. PPRC Elbow, 20mm Ǿ pcs. 20.00 12.64 252.80
f. PPRC Elbow, 25mm Ǿ pc 6.00 20.54 123.24
g. PPRC Elbow, 32mm Ǿ pc 2.00 31.60 63.20
h. PPRC Elbow, 38mm Ǿ pc 2.00 53.91 107.82
i. PPRC Tee, 20mm Ǿ pc 22.00 14.80 325.60
j. PPRC Reducer, 25mm Ǿ x 20mm Ǿ pc 8.00 14.00 112.00
k. PPRC Reducer, 32mm Ǿ x 25mm Ǿ pc 2.00 15.80 31.60
l. PPRC Reducer, 38mm Ǿ x 32mm Ǿ pc 2.00 25.28 50.56
m. Consumables (5% of Material Cost) 1,085.31

Sub - Total for F 25,330.85


G. Direct Unit Cost (E + F) 29,513.57
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 3,541.63
I. Contractor's Profit (CP) 8% of G 2,361.09
J. Value Added Tax (VAT) 5% of (G + H + I) 1,770.81
K. Total Unit Cost (G + H + I + J) 37,187.09
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(9) Storm Drainage and Downspout (16CL)


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 71.50 94.05 6,724.58


b. Skilled Laborer 2 71.50 67.95 9,716.85
c. Unskilled Laborer 4 71.50 52.42 14,992.12

Sub - Total for A 31,433.55

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Minor Tools (10% of labor cost) 3,143.35


b. Plate Compactor (5hp) 1 10.73 123.00 1,319.18

Sub - Total for B 4,462.53


C. Total (A + B) 35,896.07
D. Output = 1
E. Direct Unit Cost (C ÷ D) 35,896.07

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a.PVC 150mm dia x 3m lgths. 35.00 1,975.29 69,135.15


b. PVC Pipe, 100mm Ø x 3m, S-1000 lgths. 66.00 652.00 43,032.00
c. Elbow, 100mm dia. x 45 deg. Bend pcs. 36.00 60.00 2,160.00
d. Roof Drain (Dome-type strainer) pcs. 22.00 1,500.00 33,000.00
e. PVC Solvent, 400cc cans 7.00 245.00 1,715.00
f. Consumables (5% of Material Cost) 2,151.60

Sub - Total for F 151,193.75


G. Direct Unit Cost (E + F) 187,089.82
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 22,450.78
I. Contractor's Profit (CP) 8% of G 14,967.19
J. Value Added Tax (VAT) 5% of (G + H + I) 11,225.39
K. Total Unit Cost (G + H + I + J) 235,733.18
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(5) Sanitary/Plumbing Fixtures (16CL)


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 305.00 94.05 28,685.25


b. Skilled Laborer 1 305.00 67.95 20,724.75
c. Unskilled Laborer 1 305.00 52.42 15,988.10

Sub - Total for A 65,398.10

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 6,539.81

Sub - Total for B 6,539.81


C. Total (A + B) 71,937.91
D. Output = 1
E. Direct Unit Cost (C ÷ D) 71,937.91

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Water Closet complete w/ fittings & accs. sets 20.00 5,500.00 110,000.00
b. Wall Hung Lavatory, complete w/ fittings & accs. sets 2.00 6,500.00 13,000.00
c. Floor Drain pcs 61.00 280.00 17,080.00
d. Faucet pcs 24.00 195.00 4,680.00
e. Gate Valve 32mm sets 8.00 627.00 5,016.00
f. Mirror m2 40.00 500.00 20,000.00
g. Urinal (trough) set 4.00 9,500.00 38,000.00
h. Concrete Sink 3 faucet set 8.00 6,028.00 48,224.00
i. Gate Valve 50mm pcs 3.00 980.00 2,940.00
j. Gate Valve 20mm pcs 4.00 450.00 1,800.00
k. Check Valve 50mm pcs 1.00 954.00 954.00
l. PWD handrail set 2.00 4,500.00 9,000.00
m. Consumables (5% of Materials Cost) 13,534.70

Sub - Total for F 284,228.70


G. Direct Unit Cost (E + F) 356,166.61
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 42,739.99
I. Contractor's Profit (CP) 8% of G 28,493.33
J. Value Added Tax (VAT) 5% of (G + H + I) 21,370.00
K. Total Unit Cost (G + H + I + J) 448,769.93
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL-3 Fire Protection System (16CL)


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 790.50 94.05 74,346.53


b. Skilled Laborer 2 790.50 67.95 107,428.95
c. Unskilled Laborer 4 790.50 52.42 165,752.04

Sub - Total for A 347,527.52

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 34,752.75

Sub - Total for B 34,752.75


C. Total (A + B) 382,280.27
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) 382,280.27

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. B.I. Pipe 100mm dia lm 30.00 1,889.00 56,670.00


b. B.I. Pipe 75mm dia lm 90.00 984.00 88,560.00
c. B.I. Pipe 65mm dia lm 150.00 708.00 106,200.00
d. B.I. Pipe 50mm dia lm 30.00 425.00 12,750.00
e. B.I. Pipe 40mm dia lm 129.00 317.00 40,893.00
f. B.I. Pipe 25mm dia lm 76.00 192.00 14,592.00
g. Fittings (Elbow, Tee, Reducer, etc) l.s. 1.00 127,866.00 127,866.00
h. Pendent 12mm dia pc 144.00 503.00 72,432.00
i. Side Wall 12mm dia pc 8.00 518.00 4,144.00
j. Fire Hose Cabinet with Fire Extinguisher set 8.00 24,000.00 192,000.00
k. Fire Extinguisher, 10 lbs Capacity, Wall set 16.00 6,825.00 109,200.00
Mounted, HCFC 123
l. FP-1, Horizontal Split Case Centrifugal Pump
with A.C. Motor & Controller, UL/FM Approved, assy 1.00 1,116,923.00 1,116,923.00
350 GPM, 125psi, 40 HP, 230/3/60
m. JP-1 Vertical In-Line Centrifugal Pump with AC
Motor & Controller, UL/FM Approved, 10GPM, assy 1.00 300,000.00 300,000.00
5HP, 130psi, 230, 3/60
n. Gate Valve (OS & Y), 100mm dia unit 1.00 31,680.00 31,680.00
o. Y-Strainer unit 1.00 36,118.45 36,118.45
p.Check Valve unit 1.00 17,500.00 17,500.00
q. Alarm Check Valve Assembly unit 1.00 63,360.00 63,360.00
r. Globe Valve unit 1.00 9,114.00 9,114.00
s. Pressure Reducing Valve unit 1.00 104,099.33 104,099.33
t. Float Valve unit 1.00 77,396.68 77,396.68
u. Water Flow Switch unit 1.00 6,468.00 6,468.00
v.Floor Control Valve unit 1.00 8,303.00 8,303.00
w. Pressure Gauge unit 1.00 971.13 971.13
x. FDC Siamese Twin: Two-Way unit 1.00 6,500.00 6,500.00
y. Isolation Valve unit 1.00 18,000.00 18,000.00
z. Water Flow Meter unit 1.00 58,084.99 58,084.99
aa. Drain Off Valve unit 1.00 19,557.51 19,557.51
bb. Roof Manifold unit 1.00 16,199.14 16,199.14
cc. Hangers and Support l.s. 1.00 31,966.50 31,966.50
dd. Electrical Works for Pumps from Main Breaker l.s. 1.00 15,000.00 15,000.00
ee. Miscellaneous and Consumables l.s. 1.00 5,000.00 5,000.00
ff. Testing and Commissioning l.s. 1.00 70,846.15 70,846.15
gg. Overhead Water Tank 2000 US Gal unit 2.00 167,000.00 334,000.00
hh. Fire Reserve Tank 11000 US gal unit 1.00 162,962.00 162,962.00
ii. Concrete m³ 18.75 5,065.00 94,968.75
jj. Rebar kg 787.50 44.00 34,650.00
kk. Plaster Finish m² 78.00 84.25 6,571.50
ll. Cement Based Waterproofing bag 188.00 45.00 8,460.00
mm. .60 x .60 Manhole ea 2.00 21,000.00 42,000.00
nn. End-Suction Centrifugal Water Pump, TDH
unit 2.00 47,000.00 94,000.00
27m, 3.0HP, 80GPM

Sub - Total for F 3,616,007.13


G. Direct Unit Cost (E + F) 3,998,287.40
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 479,794.49
I. Contractor's Profit (CP) 8% of G 319,862.99
J. Value Added Tax (VAT) 5% of (G + H + I) 239,897.24
K. Total Unit Cost (G + H + I + J) 5,037,842.12

* Please Check the Summation for Sub-Total A, B,


and F
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL-3 Septic Vault Type E (16CL)


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 51.00 94.05 4,796.55


b. Skilled Laborer 2 51.00 67.95 6,930.90
c. Unskilled Laborer 4 51.00 52.42 10,693.68

Sub - Total for A 22,421.13

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 2,242.11

Sub - Total for B 2,242.11


C. Total (A + B) 24,663.24
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) 24,663.24

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Reinforcing Bars Grade 40 kgs 901.76 44.00 39,677.44


b. Concrete m3 12.64 5,065.00 64,021.60
c. Plaster Finish m2 122.22 84.25 10,297.04
d. Cement Based Waterproofing, Sahara bag 295.00 45.00 13,275.00
e. 6" thk. CHB m2 7.00 187.50 1,312.50
f. 4" thk. CHB m2 3.50 162.50 568.75

Sub - Total for F 129,152.33


G. Direct Unit Cost (E + F) 153,815.57
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 18,457.87
I. Contractor's Profit (CP) 8% of G 12,305.25
J. Value Added Tax (VAT) 5% of (G + H + I) 9,228.93
K. Total Unit Cost (G + H + I + J) 193,807.62
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(6)b1 Catch Basin -1 (16CL)


Unit of Measurement : ea
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 94.05 94.05


b. Skilled Laborer 1 1.00 67.95 67.95
c. Unskilled Laborer 1 1.00 52.42 52.42

Sub - Total for A 214.42

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 21.44

Sub - Total for B 21.44


C. Total (A + B) 235.86
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) 235.86

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 10 mm dia x 6.0 Reinforcing Steel Bars kg 8.63 44.00 379.72


b. Concrete m3 0.07 5,065.00 354.55
c. Masonry m2 0.80 162.50 130.00
d. Plaster Finish m2 1.76 84.25 148.28

Sub - Total for F 1,012.55


G. Direct Unit Cost (E + F) 1,248.41
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 149.81
I. Contractor's Profit (CP) 8% of G 99.87
J. Value Added Tax (VAT) 5% of (G + H + I) 74.90
K. Total Unit Cost (G + H + I + J) 1,573.00
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(19) Conduit, Boxes, and Fittings (16CL)


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 64.00 94.05 6,019.20


b. Skilled Laborer 1 115.00 67.95 7,814.25
c. Unskilled Laborer 1 115.00 52.42 6,028.30

Sub - Total for A 19,861.75

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 1,986.18

Sub - Total for B 1,986.18


C. Total (A + B) 21,847.93
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 21,847.93

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 80mmØ RSC pipe length 4.00 2,961.70 11,846.80


b. 80mmØ RSC Elbow pc 2.00 1,483.35 2,966.70
c. 40mmØ RSC L&B pc 2.00 30.70 61.40
d. 25mmØ PVC pipe length 13.00 92.00 1,196.00
e. 25mmØ PVC Adapter pc 10.00 14.00 140.00
f. 20mmØ PVC conduit length 606.00 69.00 41,814.00
g. 20mmØ PVC adapter pc 930.00 8.00 7,440.00
h. 20mmØ L&B pc 930.00 8.00 7,440.00
i. utility box, deep type pc 154.00 50.00 7,700.00
j. junction box, deep type pc 215.00 50.00 10,750.00
k. 80mmØ entrance cap pc 1.00 608.00 608.00
l. 16mmØX2.4m ground rod w/ connector pc 2.00 1,200.00 2,400.00
m. 40mmØ PVC pipe length 2.00 246.58 493.16
n. 40mmØ PVC Adapter pc 2.00 20.00 40.00
o. 25mmØ L&B pc 2.00 14.00 28.00
p. 20mmØ Flexible metal Conduit length 6.00 20.00 120.00
q. 20mmØ Connector pc 2.00 10.00 20.00

Sub - Total for F 95,064.06


G. Direct Unit Cost (E + F) 116,911.99
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 14,029.44
I. Contractor's Profit (CP) 8% of G 9,352.96
J. Value Added Tax (VAT) 5% of (G + H + I) 7,014.72
K. Total Unit Cost (G + H + I + J) 147,309.10
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(18) Wires and Wiring Devices (16CL)


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 105.00 94.05 9,875.25


b. Skilled Laborer 1 135.00 67.95 9,173.25
c. Unskilled Laborer 1 135.00 52.42 7,076.70

Sub - Total for A 26,125.20

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 2,612.52

Sub - Total for B 2,612.52


C. Total (A + B) 28,737.72
D. Output = 1 l.s. .
E. Direct Unit Cost (C ÷ D) 28,737.72

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 2.0mm2 TW wire,stranded m 264.00 24.00 6,336.00


b. 3.5mm2 THWN wire,stranded m 3,860.00 23.00 88,780.00
c. 3.5mm2 TW wire,stranded m 1,930.00 23.00 44,390.00
d. 5.5mm2 THWN wire,stranded m 36.00 24.00 864.00
e. 8.0mm2 THWN wire,stranded m 54.00 65.00 3,510.00
f. 14mm2 THWN wire,stranded m 6.00 86.00 516.00
g. 125mm2 THWN wire,stranded m 12.00 864.00 10,368.00
h. 150mm2 THWN wire,stranded m 112.00 1,031.04 115,476.48
i. 5.5mm2 TW wire,stranded m 66.00 24.00 1,584.00
j. 22mm2 TW wire,stranded m 30.00 156.00 4,680.00
k. one gang switch set 31.00 150.00 4,650.00
l. two gang switch set 24.00 230.00 5,520.00
m. one gang 3 way switch set 12.00 145.00 1,740.00
n. two gang 3 way switch set 8.00 175.00 1,400.00
o. duplex C.O. grounding type, 15A, 250V set 32.00 138.00 4,416.00
p. duplex C.O. grounding type, 15A, 250V, WP set 8.00 420.00 3,360.00
q. KWHR meter round with base set 1.00 2,200.00 2,200.00
r. Consumables (5% of Materials Cost) 1.00 14,989.52 14,989.52

Sub - Total for F 314,780.00


G. Direct Unit Cost (E + F) 343,517.72
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 41,222.13
I. Contractor's Profit (CP) 8% of G 27,481.42
J. Value Added Tax (VAT) 5% of (G + H + I) 20,611.06
K. Total Unit Cost (G + H + I + J) 432,832.33
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1102(21) Power Load Center, Switchgear, and Panel Boards (16CL)
Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 18.00 94.05 1,692.90


b. Skilled Laborer 1 18.00 67.95 1,223.10
c. Unskilled Laborer 2 18.00 52.42 1,887.12

Sub - Total for A 4,803.12

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 480.31

Sub - Total for B 480.31


C. Total (A + B) 5,283.43
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 5,283.43

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

MDP - Flush Mounted, NEMA 1 Enclosure w/ Ground Te set 1.00 123,749.60 123,749.60
Main: 700at, 800af, 3p, 240v, 65KAIC
Branches: 1 - 60at, 100af, 2p, 230v
4 - 50at, 100af, 2p, 230v
1 - 30at, 100af, 2p, 230v
1 - 600at, 600af, 3p, 230v

LPA - Flush Mounted, NEMA 1 Enclosure w/ Ground Ter set 1.00 5,185.00 5,185.00
Main: 60at, 2p, 240v (lugs only)
Branches: 3 - 15at, 50af, 2p, 230v
7 - 20at, 50af, 2p, 240v
2 - 30at, 50af, 2p, 240v

FPP set 1.00 63,442.60 63,442.60


Main: 600at, 600af, 3p, 240v, 42KAIC
Branches: 1 - 600at, 600af, 3p, 240v
3 - 40at, 100af, 2p, 240v
1 - 40at, 100af, 3p, 240v

Automatic Transfer Switch set 1.00 128,000.00 128,000.00


Main: 700AT, 800AF, 240V, 65KAIC

LPB, LPC and LPD - Flush Mounted, NEMA 1 Enclosure set 2.00 14,346.80 28,693.60
Main: 50at, 2p, 240v, 1KAIC
Branches: 3 - 15at, 50af, 2p, 230v
7 - 20at, 50af, 2p, 240v
40at, 50af, 2p, 240v, in NEMA 3R enclosure set 2.00 1,200.00 2,400.00
30at, 50af, 2p, 240v, in NEMA 3R enclosure set 1.00 1,200.00 1,200.00
20at, 50af, 2p, 240v, in NEMA 3R enclosure set 1.00 1,200.00 1,200.00

Sub - Total for F 353,870.80


G. Direct Unit Cost (E + F) 359,154.23
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 43,098.51
I. Contractor's Profit (CP) 8% of G 28,732.34
J. Value Added Tax (VAT) 5% of (G + H + I) 21,549.25
K. Total Unit Cost (G + H + I + J) 452,534.33
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1103(1) Lighting Fixtures (16CL)


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 51.00 94.05 4,796.55


b. Skilled Laborer 1 51.00 67.95 3,465.45
c. Unskilled Laborer 2 51.00 52.42 5,346.84

Sub - Total for A 13,608.84

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 1,360.88

Sub - Total for B 1,360.88


C. Total (A + B) 14,969.72
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 14,969.72

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 2 x 36 watts FL fixture box type w/ canopy base


and stem 1.5 ft. (450mm) length similar to amco set 64.00 1,173.00 75,072.00
AP-113-1.5 or aproved equal.
b. 2 x 36 watts FL fixture. set 32.00 650.00 20,800.00
c. 1 x 36 watts FL fixture box type. set 70.00 355.00 24,850.00
d. 1 - 18 watts CFL w/ medium base keyless type set 7.00 320.00 2,240.00
porcelain
e. Wall Fanreceptacle.
with control Switch set 32.00 1,200.00 38,400.00

Sub - Total for F 161,362.00


G. Direct Unit Cost (E + F) 176,331.72
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 21,159.81
I. Contractor's Profit (CP) 8% of G 14,106.54
J. Value Added Tax (VAT) 5% of (G + H + I) 10,579.90
K. Total Unit Cost (G + H + I + J) 222,177.97
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1208(1) Fire Alarm System (16CL)


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Skilled Laborer 1 31.00 67.95 2,106.45


b. Unskilled Laborer 1 31.00 52.42 1,625.02

Sub - Total for A 3,731.47

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 373.15

Sub - Total for B 373.15


C. Total (A + B) 4,104.62
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 4,104.62

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Fire Alarm Control Panel set 1.00 13,890.00 13,890.00


b. Fire Alarm Bell set 8.00 1,350.00 10,800.00
c. Manual Pull Station Switch set 8.00 1,600.00 12,800.00

Sub - Total for F 37,490.00


G. Direct Unit Cost (E + F) 41,594.62
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 4,991.35
I. Contractor's Profit (CP) 8% of G 3,327.57
J. Value Added Tax (VAT) 5% of (G + H + I) 2,495.68
K. Total Unit Cost (G + H + I + J) 52,409.22
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(8) Sewer Line Works (12CL)


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 60.00 94.05 5,643.00


b. Skilled Laborer 1 60.00 67.95 4,077.00
c. Unskilled Laborer 2 60.00 52.42 6,290.40

Sub - Total for A 16,010.40

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment
Minor Tools (10% of labor cost) 1,601.04
Sub - Total for B 1,601.04
C. Total (A + B) 17,611.44
D. Output = 1
E. Direct Unit Cost (C ÷ D) 17,611.44

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials
a. PVC Pipe, 50mm Ø x 3m, S-1000 lgths. 6.00 300.00 1,800.00
b. PVC Pipe, 101mm Ø x 3m, S1000 lgths. 23.00 652.00 14,996.00
c. PVC Pipe, 150mm Ø x 3m, S-1001 lgths. 13.00 1,975.29 25,678.77
d. PVC Pipe, 75mm Ø x 3m, S-1000 vent lgths. 9.00 435.00 3,915.00
e. PVC Pipe, 50mm Ø x 3m, S-1000 vent lgths. 16.00 300.00 4,800.00
f. Elbow, 150mm dia. x90 deg. Bend pc 3.00 538.33 1,614.99
g. Elbow, 50mm dia. x 90 deg. bend pc 16.00 26.00 416.00
h. WYE, 50mm Ø pc 18.00 82.00 1,476.00
i. WYE, 100mm Ø pc 20.00 165.00 3,300.00
j. WYE, 150mm Ø pc 2.00 1,136.21 2,272.42
k.WYE Reducer, 150mm Ø x 100mm Ǿ pc 4.00 807.29 3,229.16
l.WYE Reducer, 100mm Ø x 75mm Ǿ pc 2.00 120.00 240.00
m. Single Sweep Branch Tee,150mm x150mm pc 4.00 926.89 3,707.56
n. Single Sweep Branch Tee, 50mm dia pc 48.00 60.00 2,880.00
o. Clean Out w/ Cover, 50mm dia. pc 7.00 45.00 315.00
p. Clean Out w/ Cover, 100mm dia. pc 4.00 110.00 440.00
q. Clean Out w/ Cover, 150mm dia. pc 4.00 627.90 2,511.60
r. P-trap, 50mm dia. pc 59.00 120.00 7,080.00
s. PVC Solvent, 400cc cans 10.00 245.00 2,450.00
t. Consumables (5% of Material Cost) 2,123.74

Sub - Total for F 85,246.24


G. Direct Unit Cost (E + F) 102,857.68
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 12,342.92
I. Contractor's Profit (CP) 8% of G 8,228.61
J. Value Added Tax (VAT) 5% of (G + H + I) 6,171.46
K. Total Unit Cost (G + H + I + J) 129,600.67
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(6) Waterline Works (12CL)


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 12.50 94.05 1,175.63


b. Skilled Laborer 1 12.50 67.95 849.38
c. Unskilled Laborer 2 12.50 52.42 1,310.50

Sub - Total for A 3,335.50

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 333.55

Sub - Total for B 333.55


C. Total (A + B) 3,669.05
D. Output = 1
E. Direct Unit Cost (C ÷ D) 3,669.05

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. PPRC Pipe, 20mm dia. X 4m, PN 16 lgths 10.00 275.50 2,755.00


b. PPRC Pipe, 25mm dia. X 4m, PN 16 lgths 13.00 425.92 5,536.96
c. PPRC Pipe, 32mm dia. X 4m, PN16 lgths 2.00 736.28 1,472.56
d. PPRC Pipe, 38mm dia. X 4m, PN16 lgths 10.00 1,117.85 11,178.50
e. PPRC Elbow, 20mm Ǿ pcs. 20.00 12.64 252.80
f. PPRC Elbow, 25mm Ǿ pc 6.00 20.54 123.24
g. PPRC Elbow, 32mm Ǿ pc 2.00 31.60 63.20
h. PPRC Elbow, 38mm Ǿ pc 2.00 53.91 107.82
i. PPRC Tee, 20mm Ǿ pc 22.00 14.80 325.60
j. PPRC Reducer, 25mm Ǿ x 20mm Ǿ pc 8.00 14.00 112.00
k. PPRC Reducer, 32mm Ǿ x 25mm Ǿ pc 2.00 15.80 31.60
l. PPRC Reducer, 38mm Ǿ x 32mm Ǿ pc 2.00 25.28 50.56
m. Consumables (5% of Material Cost) 1,047.15
Sub - Total for F 23,056.99
G. Direct Unit Cost (E + F) 26,726.04
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 3,207.12
I. Contractor's Profit (CP) 8% of G 2,138.08
J. Value Added Tax (VAT) 5% of (G + H + I) 1,603.56
K. Total Unit Cost (G + H + I + J) 33,674.81
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(9) Storm Drainage and Downspout (12CL)


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 54.75 94.05 5,149.24


b. Skilled Laborer 2 54.75 67.95 7,440.53
c. Unskilled Laborer 4 54.75 52.42 11,479.98

Sub - Total for A 24,069.74

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Minor Tools (10% of labor cost) 2,406.97


b. Plate Compactor (5hp) 1 9.35 123.00 1,150.05

Sub - Total for B 3,557.02


C. Total (A + B) 27,626.77
D. Output = 1
E. Direct Unit Cost (C ÷ D) 27,626.77

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a.PVC 150mm dia x 3m lgths. 28.00 1,975.29 55,308.12


b. Roof Drain (Dome-type strainer) 18.00 1,500.00 27,000.00
c. PVC Pipe, 100mm Ø x 3m, S-1000 lgths. 44.00 652.00 28,688.00
d. Elbow, 100mm dia. x 45 deg. Bend pcs. 24.00 60.00 1,440.00
e. PVC Solvent, 400cc cans 5.00 245.00 1,225.00
f. Consumables (5% of Material Cost) 1,434.40

Sub - Total for F 115,095.52


G. Direct Unit Cost (E + F) 142,722.29
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 17,126.67
I. Contractor's Profit (CP) 8% of G 11,417.78
J. Value Added Tax (VAT) 5% of (G + H + I) 8,563.34
K. Total Unit Cost (G + H + I + J) 179,830.08
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(5) Sanitary/Plumbing Fixtures (12CL)


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 304.75 94.05 28,661.74


b. Skilled Laborer 1 304.75 67.95 20,707.76
c. Unskilled Laborer 1 304.75 52.42 15,975.00

Sub - Total for A 65,344.50

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 6,534.45

Sub - Total for B 6,534.45


C. Total (A + B) 71,878.94
D. Output = 1
E. Direct Unit Cost (C ÷ D) 71,878.94

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Water Closet complete w/ fittings & accs. sets 20.00 5,500.00 110,000.00
b. Wall Hung Lavatory, complete w/ fittings & accs. sets 2.00 6,500.00 13,000.00
c. Floor Drain pcs 59.00 280.00 16,520.00
d. Faucet pcs 24.00 195.00 4,680.00
e. Gate Valve 32mm sets 8.00 627.00 5,016.00
f. Mirror m2 40.00 500.00 20,000.00
g. Urinal (trough) set 4.00 9,500.00 38,000.00
h. Concrete Sink 3 faucet set 8.00 6,028.00 48,224.00
i. Gate Valve 50mm pcs 3.00 980.00 2,940.00
j. Gate Valve 20mm pcs 4.00 450.00 1,800.00
k. Check Valve 50mm pcs 1.00 954.00 954.00
l. PWD handrail set 2.00 4,500.00 9,000.00
m. Consumables (5% of Materials Cost) 8,460.80

Sub - Total for F 278,594.80


G. Direct Unit Cost (E + F) 350,473.74
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 42,056.85
I. Contractor's Profit (CP) 8% of G 28,037.90
J. Value Added Tax (VAT) 5% of (G + H + I) 21,028.42
K. Total Unit Cost (G + H + I + J) 441,596.92
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL-3 Fire Protection System (12CL)


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 725.50 94.05 68,233.28


b. Skilled Laborer 2 725.50 67.95 98,595.45
c. Unskilled Laborer 4 725.50 52.42 152,122.84

Sub - Total for A 318,951.56

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 31,895.16

Sub - Total for B 31,895.16


C. Total (A + B) 350,846.72
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) 350,846.72

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. B.I. Pipe 100mm dia lm 30.00 1,889.00 56,670.00


b. B.I. Pipe 75mm dia lm 60.00 984.00 59,040.00
c. B.I. Pipe 65mm dia lm 66.00 708.00 46,728.00
d. B.I. Pipe 50mm dia lm 30.00 425.00 12,750.00
e. B.I. Pipe 40mm dia lm 180.00 317.00 57,060.00
f. B.I. Pipe 25mm dia lm 54.00 192.00 10,368.00
g. Fittings (Elbow, Tee, Reducer, etc) l.s. 1.00 97,046.40 97,046.40
h. Pendent 12mm dia pc 100.00 503.00 50,300.00
i. Side Wall 12mm dia pc 8.00 518.00 4,144.00
j.k.Fire
FireHose Cabinet with
Extinguisher, Fire
10 lbs Extinguisher
Capacity, Wall set 4.00 24,000.00 96,000.00
Mounted, HCFC 123 set 12.00 6,825.00 81,900.00
l. FP-1, Horizontal Split Case Centrifugal Pump
with A.C. Motor & Controller, UL/FM Approved, assy 1.00 1,116,923.00 1,116,923.00
350 GPM, 125psi, 40 HP, 230/3/60
m. JP-1 Vertical In-Line Centrifugal Pump with AC
Motor & Controller, UL/FM Approved, 10GPM, assy 1.00 300,000.00 300,000.00
5HP, 130psi, 230, 3/60
n. Gate Valve (OS & Y), 100mm dia unit 1.00 31,680.00 31,680.00
o. Y-Strainer unit 1.00 36,118.45 36,118.45
p.Check Valve unit 1.00 17,500.00 17,500.00
q. Alarm Check Valve Assembly unit 1.00 63,360.00 63,360.00
r. Globe Valve unit 1.00 9,114.00 9,114.00
s. Pressure Reducing Valve unit 1.00 104,099.33 104,099.33
t. Float Valve unit 1.00 77,396.68 77,396.68
u. Water Flow Switch unit 1.00 6,468.00 6,468.00
v.Floor Control Valve unit 1.00 8,303.00 8,303.00
w. Pressure Gauge unit 1.00 971.13 971.13
x. FDC Siamese Twin: Two-Way unit 1.00 6,500.00 6,500.00
y. Isolation Valve unit 1.00 18,000.00 18,000.00
z. Water Flow Meter unit 1.00 58,084.99 58,084.99
aa. Drain Off Valve unit 1.00 19,557.51 19,557.51
bb. Roof Manifold unit 1.00 16,199.14 16,199.14
cc. Hangers and Support l.s. 1.00 24,261.60 24,261.60

dd. Electrical Works for Pumps from Main Breaker l.s. 1.00 15,000.00 15,000.00

ee. Miscellaneous and Consumables l.s. 1.00 5,000.00 5,000.00


ff. Testing and Commissioning l.s. 1.00 70,846.15 70,846.15
gg. Overhead Water Tank 2000 US Gal unit 2.00 167,000.00 334,000.00
hh. Fire Reserve Tank 11000 US gal unit 1.00 162,962.00 162,962.00
ii. Concrete m³ 18.75 5,065.00 94,968.75
jj. Rebar kg 787.50 44.00 34,650.00
kk. Plaster Finish m² 78.00 84.25 6,571.50
ll. Cement Based Waterproofing bag 188.00 45.00 8,460.00
mm. .60 x .60 Manhole ea 2.00 21,000.00 42,000.00
nn. End-Suction Centrifugal Water Pump, TDH
27m, 3.0HP, 80GPM unit 2.00 47,000.00 94,000.00

Sub - Total for F 3,355,001.63


G. Direct Unit Cost (E + F) 3,705,848.35
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 444,701.80
I. Contractor's Profit (CP) 8% of G 296,467.87
J. Value Added Tax (VAT) 5% of (G + H + I) 222,350.90
K. Total Unit Cost (G + H + I + J) 4,669,368.92

* Please Check the Summation for Sub-Total A, B,


and F
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL-3 Septic Vault Type E (12CL)


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 44.00 94.05 4,138.20


b. Skilled Laborer 2 44.00 67.95 5,979.60
c. Unskilled Laborer 4 44.00 52.42 9,225.92

Sub - Total for A 19,343.72

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 1,934.37

Sub - Total for B 1,934.37


C. Total (A + B) 21,278.09
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) 21,278.09

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Reinforcing Bars Grade 40 kgs 786.46 44.00 34,604.24


b. Concrete m3 10.87 5,065.00 55,056.55
c. Plaster Finish m2 107.00 84.25 9,014.75
d. Water Based Waterproofing, Sahara bag 259.00 45.00 11,655.00
e. 6" thk. CHB m2 6.00 187.50 1,125.00
f. 4" thk. CHB m2 3.00 162.50 487.50

Sub - Total for F 111,943.04


G. Direct Unit Cost (E + F) 133,221.13
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 15,986.54
I. Contractor's Profit (CP) 8% of G 10,657.69
J. Value Added Tax (VAT) 5% of (G + H + I) 7,993.27
K. Total Unit Cost (G + H + I + J) 167,858.63
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(6)b1 Catch Basin -1 (12CL)


Unit of Measurement : ea
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 94.05 94.05


b. Skilled Laborer 1 1.00 67.95 67.95
c. Unskilled Laborer 1 1.00 52.42 52.42

Sub - Total for A 214.42

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 21.44

Sub - Total for B 21.44


C. Total (A + B) 235.86
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) 235.86

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 10 mm dia x 6.0 Reinforcing Steel Bars kg 8.63 44.00 379.72


b. Concrete m3 0.07 5,065.00 354.55
c. Masonry m2 0.80 187.50 150.00
d. Plaster Finish m2 1.76 84.25 148.28

Sub - Total for F 1,032.55


G. Direct Unit Cost (E + F) 1,268.41
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 152.21
I. Contractor's Profit (CP) 8% of G 101.47
J. Value Added Tax (VAT) 5% of (G + H + I) 76.10
K. Total Unit Cost (G + H + I + J) 1,598.20
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(19) Conduit, Boxes, and Fittings (12CL)


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 40.00 94.05 3,762.00


b. Skilled Laborer 1 82.00 67.95 5,571.90
c. Unskilled Laborer 1 82.00 52.42 4,298.44

Sub - Total for A 13,632.34

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 1,363.23

Sub - Total for B 1,363.23


C. Total (A + B) 14,995.57
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 14,995.57

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 40mmØ PVC pipe length 2.00 246.58 493.16


b. 40mmØ PVC Adapter pc 2.00 20.00 40.00
c. 25mmØ PVC pipe length 13.00 92.00 1,196.00
d. 25mmØ PVC Adapter pc 10.00 14.00 140.00
e. 20mmØ PVC conduit length 412.00 69.00 28,428.00
f. 20mmØ PVC adapter pc 750.00 8.00 6,000.00
g. 20mmØ L&B pc 750.00 8.00 6,000.00
h. utility box, deep type pc 125.00 50.00 6,250.00
i. junction box, deep type pc 175.00 50.00 8,750.00
j. 80mmØ entrance cap pc 1.00 608.00 608.00
k. 16mmØX2.4m ground rod w/ connector pc 2.00 1,200.00 2,400.00
l. 20mmØ Flexible metal Conduit length 6.00 20.00 120.00
m. 20mmØ Connector pc 2.00 10.00 20.00
n. 25mmØ L&B pc 2.00 14.00 28.00
o. 40mmØ L&B pc 2.00 30.70 61.40
p. 80mmØ RSC Conduit length 4.00 2,961.70 11,846.80
q. 80mmØ RSC Elbow pc 2.00 1,483.35 2,966.70

Sub - Total for F 75,348.06


G. Direct Unit Cost (E + F) 90,343.63
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 10,841.24
I. Contractor's Profit (CP) 8% of G 7,227.49
J. Value Added Tax (VAT) 5% of (G + H + I) 5,420.62
K. Total Unit Cost (G + H + I + J) 113,832.98
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(18) Wires and Wiring Devices (12CL)


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 79.00 94.05 7,429.95


b. Skilled Laborer 1 105.00 67.95 7,134.75
c. Unskilled Laborer 1 105.00 52.42 5,504.10

Sub - Total for A 20,068.80

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 2,006.88

Sub - Total for B 2,006.88


C. Total (A + B) 22,075.68
D. Output = 1 l.s. .
E. Direct Unit Cost (C ÷ D) 22,075.68

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 2.0mm2 TW wire,stranded m 132.00 24.00 3,168.00


b. 3.5mm2 THWN wire,stranded m 2,670.00 23.00 61,410.00
c. 3.5mm2 TW wire,stranded m 1,335.00 23.00 30,705.00
d. 5.5mm2 THWN wire,stranded m 96.00 24.00 2,304.00
e. 5.5mm2 TW wire,stranded m 48.00 24.00 1,152.00
f. 22mm2 THWN wire,stranded m 30.00 156.00 4,680.00
g. 14mm2 THWN wire,stranded m 6.00 86.00 516.00
h. 125mm2 THWN wire,stranded m 12.00 864.00 10,368.00
i. 150mm2 THWN wire,stranded m 112.00 1,031.04 115,476.48
j. one gang switch set 27.00 150.00 4,050.00
k. two gang switch set 20.00 230.00 4,600.00
l. one gang 3 way switch set 12.00 145.00 1,740.00
m. two gang 3 way switch set 8.00 175.00 1,400.00
n. duplex C.O. grounding type, 15A, 250V set 24.00 138.00 3,312.00
o. duplex C.O. grounding type, 15A, 250V, WP set 4.00 420.00 1,680.00
p. KWHR meter round with base set 1.00 2,200.00 2,200.00
q. Consumables (5% of Materials Cost) 1.00 12,438.07 12,438.07

Sub - Total for F 261,199.55


G. Direct Unit Cost (E + F) 283,275.23
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 33,993.03
I. Contractor's Profit (CP) 8% of G 22,662.02
J. Value Added Tax (VAT) 5% of (G + H + I) 16,996.51
K. Total Unit Cost (G + H + I + J) 356,926.79
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1102(21) Power Load Center, Switchgear, and Panel Boards (12CL)
Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 18.00 94.05 1,692.90


b. Skilled Laborer 1 18.00 67.95 1,223.10
c. Unskilled Laborer 2 18.00 52.42 1,887.12

Sub - Total for A 4,803.12

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 480.31

Sub - Total for B 480.31


C. Total (A + B) 5,283.43
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 5,283.43

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

MDP - Flush Mounted, NEMA 1 Enclosure w/ Ground Te set 1.00 121,076.80 121,076.80
Main: 700at, 800af, 3p, 240v, 65KAIC
Branches: 1 - 60at, 100af, 2p, 230v
4 - 40at, 100af, 2p, 230v
1 - 600at, 600af, 3p, 230v

LPA - Flush Mounted, NEMA 1 Enclosure w/ Ground Ter set 1.00 11,674.00 11,674.00
Main: 60at, 2p, 240v (lugs only)
Branches: 2 - 15at, 50af, 2p, 230v
6 - 20at, 50af, 2p, 240v
2 - 30at, 50af, 2p, 240v

FPP set 1.00 57,605.60 57,605.60


Main: 600at, 600af, 3p, 240v, 42KAIC
Branches: 1 - 600at, 600af, 3p, 240v
3 - 40at, 100af, 2p, 240v
1 - 40at, 100af, 3p, 240v

Automatic Transfer Switch set 1.00 128,000.00 128,000.00


Main: 700AT, 800AF, 240V, 65KAIC

LPB, LPC and LPD - Flush Mounted, NEMA 1 Enclosure set 2.00 9,677.20 19,354.40
Main: 40at, 2p, 240v, 1KAIC
Branches: 2 - 15at, 50af, 2p, 230v
4 - 20at, 50af, 2p, 240v

40at, 50af, 2p, 240v, in NEMA 3R enclosure set 2.00 1,200.00 2,400.00
30at, 50af, 2p, 240v, in NEMA 3R enclosure set 1.00 1,200.00 1,200.00
20at, 50af, 2p, 240v, in NEMA 3R enclosure set 1.00 1,200.00 1,200.00

Sub - Total for F 342,510.80


G. Direct Unit Cost (E + F) 347,794.23
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 41,735.31
I. Contractor's Profit (CP) 8% of G 27,823.54
J. Value Added Tax (VAT) 5% of (G + H + I) 20,867.65
K. Total Unit Cost (G + H + I + J) 438,220.73
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1103(1) Lighting Fixtures (12CL)


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 55.00 94.05 5,172.75


b. Skilled Laborer 1 55.00 67.95 3,737.25
c. Unskilled Laborer 2 55.00 52.42 5,766.20

Sub - Total for A 14,676.20

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 1,467.62

Sub - Total for B 1,467.62


C. Total (A + B) 16,143.82
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 16,143.82

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 2 x 36 watts FL fixture box type w/ canopy base


and stem 1.5 ft. (450mm) length similar to amco set 48.00 1,173.00 56,304.00
AP-113-1.5 or aproved equal.
b. 2 x 36 watts FL fixture. set 24.00 650.00 15,600.00
c. 1 x 36 watts FL fixture box type. set 62.00 355.00 22,010.00
d. 1 - 18 watts CFL w/ medium base keyless type set 7.00 320.00 2,240.00
porcelain
e. Wall Fanreceptacle.
with control Switch set 24.00 1,200.00 28,800.00

Sub - Total for F 124,954.00


G. Direct Unit Cost (E + F) 141,097.82
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 16,931.74
I. Contractor's Profit (CP) 8% of G 11,287.83
J. Value Added Tax (VAT) 5% of (G + H + I) 8,465.87
K. Total Unit Cost (G + H + I + J) 177,783.25
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1208(1) Fire Alarm System (12CL)


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Skilled Laborer 1 31.00 67.95 2,106.45


b. Unskilled Laborer 1 31.00 52.42 1,625.02

Sub - Total for A 3,731.47

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 373.15

Sub - Total for B 373.15


C. Total (A + B) 4,104.62
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 4,104.62

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Fire Alarm Control Panel set 1.00 13,890.00 13,890.00


b. Fire Alarm Bell set 4.00 1,350.00 5,400.00
c. Manual Pull Station Switch set 4.00 1,600.00 6,400.00

Sub - Total for F 25,690.00


G. Direct Unit Cost (E + F) 29,794.62
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 3,575.35
I. Contractor's Profit (CP) 8% of G 2,383.57
J. Value Added Tax (VAT) 5% of (G + H + I) 1,787.68
K. Total Unit Cost (G + H + I + J) 37,541.22
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(26) Cistern


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 100.00 94.05 9,405.00


b. Skilled Laborer 2 100.00 67.95 13,590.00
c. Unskilled Laborer 4 100.00 52.42 20,968.00

Sub - Total for A 43,963.00

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 4,396.30

Sub - Total for B 4,396.30


C. Total (A + B) 48,359.30
D. Output = 1
E. Direct Unit Cost (C ÷ D) 48,359.30

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Reinforcing Bars Grade 40 kgs 4350.95 44.00 191,441.80


b. Concrete m3 58.83 5,065.00 297,993.80
c. Phenolic Board (0.019 x 1.2 x 2.4) - 4 uses pc 89.00 1,450.00 129,050.00
d. Good Lumber - 3 uses bd ft 1,809.37 42.00 75,993.54
d. 0.60 x 0.60 Manhole Cover pc 2.00 5,000.00 10,000.00
e. Waterproofing bags 588.30 46.00 27,061.80
f. Gravel Fill cu.m 12.84 614.75 7,893.39
g. G.I. Tie Wires kgs 87.02 75.00 6,526.50
h. 25mm Stainless Steel (Ladder) m. 20.00 2,000.00 40,000.00

Sub - Total for F 785,960.83


G. Direct Unit Cost (E + F) 834,320.13
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 100,118.42
I. Contractor's Profit (CP) 8% of G 66,745.61
J. Value Added Tax (VAT) 5% of (G + H + I) 50,059.21
K. Total Unit Cost (G + H + I + J) 1,051,243.37
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL-3 Septic Vault Type E (8CL)


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 34.75 94.05 3,268.24


b. Skilled Laborer 2 34.75 67.95 4,722.53
c. Unskilled Laborer 4 34.75 52.42 7,286.38

Sub - Total for A 15,277.14

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 1,527.71

Sub - Total for B 1,527.71


C. Total (A + B) 16,804.86
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) 16,804.86

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Reinforcing Bars Grade 40 kgs 655.79 44.00 28,854.76


b. Concrete m3 8.27 5,065.00 41,887.55
c. Plaster Finish m2 82.44 84.25 6,945.57
d. Cement Based Waterproofing, SaharaSahara bag 200.00 45.00 9,000.00
e. 6" thk. CHB m2 5.00 187.50 937.50
f. 4" thk. CHB m2 2.50 162.50 406.25

Sub - Total for F 88,031.63


G. Direct Unit Cost (E + F) 104,836.49
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 12,580.38
I. Contractor's Profit (CP) 8% of G 8,386.92
J. Value Added Tax (VAT) 5% of (G + H + I) 6,290.19
K. Total Unit Cost (G + H + I + J) 132,093.97
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(5) Sanitary/Plumbing Fixtures (8CL)


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 182.00 94.05 17,117.10


b. Skilled Laborer 1 182.00 67.95 12,366.90
c. Unskilled Laborer 1 182.00 52.42 9,540.44

SEPTIC VAULT
a. Construction Foreman 1 34.75 94.05 3,268.24
b. Skilled Laborer 2 34.75 67.95 4,722.53
c. Unskilled Laborer 4 34.75 52.42 7,286.38

Sub - Total for A 54,301.58

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 5,430.16

Sub - Total for B 5,430.16


C. Total (A + B) 59,731.74
D. Output = 1
E. Direct Unit Cost (C ÷ D) 59,731.74

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Water Closet complete w/ fittings & accs. sets 12.00 5,500.00 66,000.00
b. Wall Hung Lavatory, complete w/ fittings & accs. sets 1.00 6,500.00 6,500.00
c. Floor Drain pcs 48.00 280.00 13,440.00
d. Faucet pcs 24.00 195.00 4,680.00
e. Gate Valve 32mm sets 4.00 627.00 2,508.00
f. Mirror m2 24.00 500.00 12,000.00
g. Consumables 5,256.40
h. Urinal (trough) set 4.00 9,500.00 38,000.00
i. Concrete Sink 3 faucet set 3.00 6,028.00 18,084.00
j. Concrete Sink 1 faucet set 5.00 2,895.00 14,475.00
k. Gate Valve 50mm pcs 2.00 980.00 1,960.00
l. Gate Valve 20mm pcs 4.00 450.00 1,800.00
m. Check Valve 50mm pcs 1.00 954.00 954.00
n. PWD handrail set 1.00 4,500.00 4,500.00
o. Sink Drain pcs 4.00 280.00 1,120.00

SEPTIC VAULT
a. Reinforcing Bars Grade 40 kgs 655.79 44.00 28,854.76
b. Concrete m3 8.27 5,065.00 41,887.55
c. Plaster Finish m2 82.44 84.25 6,945.57
d. Cement Based Waterproofing, SaharaSahara bag 200.00 45.00 9,000.00
e. 6" thk. CHB m2 5.00 187.50 937.50
f. 4" thk. CHB m2 2.50 162.50 406.25

CISTERN TANK
a. Reinforcing Bars Grade 40 kgs 655.79 44.00 28,854.76
b. Concrete m3 8.27 5,065.00 41,887.55
c. Plaster Finish m2 82.44 84.25 6,945.57
d. Cement Based Waterproofing, SaharaSahara bag 200.00 45.00 9,000.00

Sub - Total for F 365,996.91


G. Direct Unit Cost (E + F) 425,728.65
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 51,087.44
I. Contractor's Profit (CP) 8% of G 34,058.29
J. Value Added Tax (VAT) 5% of (G + H + I) 25,543.72
K. Total Unit Cost (G + H + I + J) 536,418.10
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(10) Conduit, Boxes, and Fittings (8CL)


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 30.00 94.05 2,821.50


b. Skilled Laborer 1 58.00 67.95 3,941.10
c. Unskilled Laborer 1 58.00 52.42 3,040.36

Sub - Total for A 9,802.96

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 980.30

Sub - Total for B 980.30


C. Total (A + B) 10,783.26
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 10,783.26

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 32mmØ PVC pipe length 2.00 120.00 240.00


b. 32mmØ PVC Adapter pc 2.00 16.00 32.00
c. 32mmØ L&B pc 2.00 16.00 32.00
d. 25mmØ PVC pipe length 10.00 92.00 920.00
e. 25mmØ PVC Adapter pc 6.00 14.00 84.00
g. 20mmØ PVC conduit length 284.00 69.00 19,596.00
h. 20mmØ PVC adapter pc 500.00 8.00 4,000.00
i. 20mmØ L&B pc 500.00 8.00 4,000.00
j. utility box, deep type pc 85.00 50.00 4,250.00
k. junction box, deep type pc 115.00 50.00 5,750.00
l. 40mmØ entrance cap pc 1.00 304.00 304.00
m. 16mmØX2.4m ground rod w/ connector pc 2.00 1,200.00 2,400.00
n. 20mmØ Flexible metal Conduit length 6.00 20.00 120.00
o. 20mmØ Connector pc 2.00 10.00 20.00
p. 25mmØ L&B pc 2.00 14.00 28.00
q. 40mmØ RSC pipe length 4.00 1,069.50 4,278.00
r. 40mmØ RSC Elbow pc 2.00 289.80 579.60

Sub - Total for F 46,633.60


G. Direct Unit Cost (E + F) 57,416.86
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 6,890.02
I. Contractor's Profit (CP) 8% of G 4,593.35
J. Value Added Tax (VAT) 5% of (G + H + I) 3,445.01
K. Total Unit Cost (G + H + I + J) 72,345.24
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(33) Wires and Wiring Devices (8CL)


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 41.00 94.05 3,856.05


b. Skilled Laborer 1 58.00 67.95 3,941.10
c. Unskilled Laborer 1 58.00 52.42 3,040.36

Sub - Total for A 10,837.51

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 1,083.75

Sub - Total for B 1,083.75


C. Total (A + B) 11,921.26
D. Output = 1 l.s. .
E. Direct Unit Cost (C ÷ D) 11,921.26

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 2.0mm2 TW wire,stranded m 84.00 24.00 2,016.00


b. 3.5mm2 THWN wire,stranded m 1,835.00 23.00 42,205.00
c. 3.5mm2 TW wire,stranded m 920.00 23.00 21,160.00
d. 5.5mm2 THWN wire,stranded m 54.00 24.00 1,296.00
e. 5.5mm2 TW wire,stranded m 30.00 24.00 720.00
f. 14.0mm2 TW wire,stranded m 12.00 86.00 1,032.00
g. 8.0mm2 TW wire,stranded m 12.00 65.00 780.00
h. 14mm2 THWN wire,stranded m 6.00 86.00 516.00
i. 38mm2 THWN wire,stranded m 24.00 292.60 7,022.40
j. one gang switch set 14.00 150.00 2,100.00
k. two gang switch set 16.00 230.00 3,680.00
l. one gang 3 way switch set 14.00 145.00 2,030.00
m. duplex C.O. grounding type, 15A, 250V set 16.00 138.00 2,208.00
n. duplex C.O. grounding type, 15A, 250V, WP set 4.00 420.00 1,680.00
o. KWHR meter round with base set 1.00 2,200.00 2,200.00
p. n. Tape, bolt&nut, mica tube, terminal lugs, JB
lot 1.00 4,431.47 4,431.47
cover clamps, screw and anchors

Sub - Total for F 95,076.87


G. Direct Unit Cost (E + F) 106,998.13
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 12,839.78
I. Contractor's Profit (CP) 8% of G 8,559.85
J. Value Added Tax (VAT) 5% of (G + H + I) 6,419.89
K. Total Unit Cost (G + H + I + J) 134,817.65
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1102(1) Panelboard with Main & Branch Breakers 8CL
Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 13.00 94.05 1,222.65


b. Skilled Laborer 1 13.00 67.95 883.35
c. Unskilled Laborer 2 13.00 52.42 1,362.92

Sub - Total for A 3,468.92

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 346.89

Sub - Total for B 346.89


C. Total (A + B) 3,815.81
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 3,815.81

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

MDP - Flush Mounted, NEMA 1 Enclosure w/ Ground Te set 1.00 18,135.00 18,135.00
Main: 150at, 225af, 2p, 240v, 22KAIC
Branches: 1 - 60at, 50af, 2p, 230v
2 - 40at, 50af, 2p, 230v

LPA - Flush Mounted, NEMA 1 Enclosure w/ Ground Ter set 1.00 5,185.00 5,185.00
Main: 60at, 2p, 240v (lugs only)
Branches: 4 - 15at, 50af, 2p, 230v
6 - 20at, 50af, 2p, 240v
2- 30at, 50af, 2p, 240v

LPB - Flush Mounted, NEMA 1 Enclosure w/ Ground Ter set 1.00 14,346.80 14,346.80
Main: 40at, 50af, 2p, 240v
Branches: 4 - 15at, 50af, 2p, 230v
6 - 20at, 50af, 2p, 240v

30at, 50af, 2p, 240v, in NEMA 3R enclosure set 2.00 1,200.00 2,400.00
20at, 50af, 2p, 240v, in NEMA 3R enclosure set 1.00 1,200.00 1,200.00
40at, 50af, 2p, 240v, in NEMA 3R enclosure set 1.00 1,200.00 1,200.00

Sub - Total for F 42,466.80


G. Direct Unit Cost (E + F) 46,282.61
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 5,553.91
I. Contractor's Profit (CP) 8% of G 3,702.61
J. Value Added Tax (VAT) 5% of (G + H + I) 2,776.96
K. Total Unit Cost (G + H + I + J) 58,316.09
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1200(5)b Exhaust Fan


Unit of Measurement : set
Output per hour : 0.50

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 94.05 94.05


b. Skilled Laborer 1 1.00 67.95 67.95
c. Unskilled Laborer 2 1.00 52.42 104.84

Sub - Total for A 266.84

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 26.68

Sub - Total for B 26.68


C. Total (A + B) 293.52
D. Output = 0.5 set
E. Direct Unit Cost (C ÷ D) 587.05

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Wall mounted Exhaust Fan set 1.00 1,419.00 1,419.00

Sub - Total for F 1,419.00


G. Direct Unit Cost (E + F) 2,006.05
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 240.73
I. Contractor's Profit (CP) 8% of G 160.48
J. Value Added Tax (VAT) 5% of (G + H + I) 120.36
K. Total Unit Cost (G + H + I + J) 2,527.62
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1208(1) Fire Alarm System (8CL)


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

FIRE ALARM SYSTEM


a. Skilled Laborer 1 31.00 67.95 2,106.45
b. Unskilled Laborer 1 31.00 52.42 1,625.02

FIRE PROTECTION SYSTEM


a. Construction Foreman 1 34.75 94.05 3,268.24
b. Skilled Laborer 2 34.75 67.95 4,722.53
c. Unskilled Laborer 4 34.75 52.42 7,286.38

Sub - Total for A 19,008.61

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 1,900.86

Sub - Total for B 1,900.86


C. Total (A + B) 20,909.47
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 20,909.47

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

FIRE ALARM SYSTEM


a. Fire Alarm Control Panel set 1.00 13,890.00 13,890.00
b. Fire Alarm Bell set 4.00 1,350.00 5,400.00
c. Manual Pull Station Switch set 4.00 1,600.00 6,400.00
d. Smoke / Heat Detector set 8.00 5,891.83 47,134.64
e. Close Circuit Television (CCTV ) set 2.00 14,202.80 28,405.60

FIRE PROTECTION SYSTEM


a
b.Fire
FireHose Cabinet with
Extinguisher, Fire
10 lbs Extinguisher
Capacity, Wall set 4.00 24,000.00 96,000.00
Mounted, HCFC 123 set 12.00 6,825.00 81,900.00
c. FDC Siamese Twin: Two-Way unit 1.00 6,500.00 6,500.00
d. Overhead Water Tank 2000 US Gal unit 1.00 167,000.00 167,000.00
e. End-Suction Centrifugal Water Pump, TDH 22m,
2.0HP, 60GPM unit 2.00 36,780.00 73,560.00

f. Booster Pump, TDH 25m, 3HP, 80GPM unit 1.00 39,300.00 39,300.00

Sub - Total for F 565,490.24


G. Direct Unit Cost (E + F) 586,399.71
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 70,367.97
I. Contractor's Profit (CP) 8% of G 46,911.98
J. Value Added Tax (VAT) 5% of (G + H + I) 35,183.98
K. Total Unit Cost (G + H + I + J) 738,863.64
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL-3 Fire Protection System (8CL)


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 134.75 94.05 12,673.24


b. Skilled Laborer 2 134.75 67.95 18,312.53
c. Unskilled Laborer 4 134.75 52.42 28,254.38

Sub - Total for A -

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) -

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. B.I. Pipe 75mm dia lm 20.00 984.00 19,680.00


b. B.I. Pipe 65mm dia lm 30.00 708.00 21,240.00
c. Fittings (Elbow, Tee, Reducer, etc) 4,092.00
d. Fire Hose Cabinet with Fire Extinguisher set 4.00 24,000.00 96,000.00
e. Fire Extinguisher, 10 lbs Capacity, Wall set 12.00 6,825.00 81,900.00
Mounted, HCFC 123
f. FDC Siamese Twin: Two-Way unit 1.00 6,500.00 6,500.00
g. Overhead Water Tank 2000 US Gal unit 1.00 167,000.00 167,000.00
h. Concrete m³ 5,065.00 -
i. Rebar kg 44.00 -
j. Plaster Finish m² 84.25 -
k. Cement Based Waterproofing bag 45.00 -
l. .60 x .60 Manhole ea 2.00 21,000.00 42,000.00
m. End-Suction Centrifugal Water Pump, TDH
22m, 2.0HP, 60GPM unit 2.00 36,780.00 73,560.00

n. Booster Pump, TDH 25m, 3HP, 80GPM unit 1.00 39,300.00 39,300.00

Sub - Total for F -


G. Direct Unit Cost (E + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G -
I. Contractor's Profit (CP) 8% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -

* Please Check the Summation for Sub-Total A, B,


and F
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1106 (1) CCTV System


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 48.00 94.05 4,514.40


b. Skilled Laborer 1 48.00 67.95 3,261.60
c. Unskilled Laborer 2 48.00 52.42 5,032.32

Sub - Total for A 12,808.32

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B 0.00


C. Total (A + B) 12,808.32
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 12,808.32

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Bullet Camera pc. 2.00 1,280.00 2,560.00


Turbo HD720P IR, 1.0 Megapixel high
Performance CMOS, Analog HD Output, up to
720P resolution, True day/night, Digital Noise
reduction (DNR), Smart Infrared (IR)

b. Dome Camera pc. 2.00 1,359.50 2,719.00


Turbo HD720P IR, 1.0 Megapixel high
Performance CMOS, Analog HD Output, up to
720P resolution, True day/night, Digital Noise
reduction (DNR), Smart Infrared (IR)
c. Power Supply , 12V, 1.5Amp pc. 4.00 200.00 800.00
d. Turbo HD Digital Video Recorder (DVR) pc. 1.00 8,000.00 8,000.00
e. Hard Drive Disc (4TB) pc. 1.00 9,500.00 9,500.00
f. LED Monitor (19.5 Screen Size) pc. 1.00 9,923.20 9,923.20
g. Other Work Materials (Cables, cable ties, plastic 6,700.44
moulding, silicone glue etc.)

Sub - Total for F 40,202.64


G. Direct Unit Cost (E + F) 53,010.96
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 6,361.32
I. Contractor's Profit (CP) 8% of G 4,240.88
J. Value Added Tax (VAT) 5% of (G + H + I) 3,180.66
K. Total Unit Cost (G + H + I + J) 66,793.81
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1711(1) Stone Masonry


Unit of Measurement : cu.m.
Output per hour : 1.60

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 94.05 94.05


b. Skilled Laborer 2 1.00 67.95 135.90
c. Unskilled Laborer 8 1.00 52.42 419.36

Sub - Total for A 649.31

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. One Bagger Mixer 1 1.00 172.00 172.00


a. Water Truck/Pump (16000 L) 1 0.05 2,450.00 122.50
b. Backhoe (Wheel Type, 0.28 cu.m.) 1 0.10 922.00 92.20
Minor Tools (10% of Labor Cost) 64.93

Sub - Total for B 451.63


C. Total (A + B) 1,100.94
D. Output per Hour = 1.60 m3
E. Direct Unit Cost (C ÷ D) 688.09

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Cement bag 5.50 240.00 1,320.00


b. Sand m 3
0.30 868.30 260.49
c. Gravel Fill m3 0.02 753.30 15.07
d. Weep holes (PVC) m 0.30 145.00 43.50
e. Filter Cloth m2 0.015 280.00 4.20
f. Stones m 3
1.05 903.30 948.47
Miscellaneous (1% of Materials Cost) 25.92

Sub - Total for F 2,617.64


G. Direct Unit Cost (E + F) 3,305.73
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 396.69
I. Contractor's Profit (CP) 8% of G 264.46
J. Value Added Tax (VAT) 5% of (G + H + I) 198.34
K. Total Unit Cost (G + H + I + J) 4,165.22
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(8) Sewer Line Works (4CL)


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 27.50 94.05 2,586.38


b. Skilled Laborer 1 27.50 67.95 1,868.63
c. Unskilled Laborer 2 27.50 52.42 2,883.10

Sub - Total for A 7,338.10

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment
Minor Tools (10% of labor cost) 733.81
Sub - Total for B 733.81
C. Total (A + B) 8,071.91
D. Output = 1
E. Direct Unit Cost (C ÷ D) 8,071.91

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials
a. PVC Pipe, 50mm Ø x 3m, S-1000 lgths. 16.00 300.00 4,800.00
b. PVC Pipe, 50mm Ø x 3m, S-1000 VENT 24.00 300.00 7,200.00
c. PVC Pipe, 75mm Ø x 3m, S-1000 lgths. 4.00 435.00 1,740.00
d. PVC Pipe, 101mm Ø x 3m, S1000 lgths. 20.00 652.00 13,040.00
e. Elbow, 50mm dia. x 90 deg. Bend pc 16.00 26.00 416.00
f. Elbow, 100mm dia. x 90 deg. bend pc 8.00 81.00 648.00
g. WYE, 50mm Ø pc 8.00 82.00 656.00
h. WYE, 100mm Ø pc 12.00 165.00 1,980.00
i.WYE Reducer, 100mm Ø x 75mm Ǿ pc 3.00 120.00 360.00
j.WYE Reducer, 100mm Ø x 50mm Ǿ pc 13.00 100.00 1,300.00
k. Tee, 100mm dia pc 4.00 180.00 720.00
l. Tee REDUCER 75 X 50mm dia pc 4.00 89.00 356.00
m. Single Branch Sweep Tee, 50mm dia pc 28.00 60.00 1,680.00
n. Clean Out w/ Cover, 100mm dia. pc 8.00 110.00 880.00
o. P-trap, 50mm dia. pc 34.00 120.00 4,080.00
p. PVC Solvent, 400cc cans 7.00 245.00 1,715.00
q. Consumables (5% of Material Cost) 1,339.00

Sub - Total for F 42,910.00


G. Direct Unit Cost (E + F) 50,981.91
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 6,117.83
I. Contractor's Profit (CP) 8% of G 4,078.55
J. Value Added Tax (VAT) 5% of (G + H + I) 3,058.91
K. Total Unit Cost (G + H + I + J) 64,237.21
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(6) Waterline Works (4CL)


Unit of Measurement : pc
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 6.00 94.05 564.30


b. Skilled Laborer 1 6.00 67.95 407.70
c. Unskilled Laborer 2 6.00 52.42 629.04

Sub - Total for A 1,601.04

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 160.10

Sub - Total for B 160.10


C. Total (A + B) 1,761.14
D. Output = 1
E. Direct Unit Cost (C ÷ D) 1,761.14

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. PPRC Pipe, 20mm dia. X 4m, PN 16 lgths 7.00 275.50 1,928.50


b. PPRC Pipe, 25mm dia. X 4m, PN 16 lgths 10.00 425.92 4,259.20
c. PPRC Pipe, 32mm dia. X 4m, PN 16 lgths 4.00 736.28 2,945.12
d. PPRC Elbow, 20mm Ǿ pc 20.00 12.64 252.80
e. PPRC Elbow, 25mm Ǿ pc 3.00 20.54 61.62
f. PPRC Elbow, 32mm Ǿ pc 2.00 31.60 63.20
g. PPRC Tee, 20mm Ǿ pc 16.00 14.80 236.80
h. PPRC Reducer, 25mm Ǿ x 20mm Ǿ pc 3.00 14.00 42.00
i. PPRC Reducer, 32mm Ǿ x 25mm Ǿ pc 2.00 15.80 31.60
j. Consumables (5% of Material Cost) 456.64
Sub - Total for F 10,277.48
G. Direct Unit Cost (E + F) 12,038.63
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 1,444.64
I. Contractor's Profit (CP) 8% of G 963.09
J. Value Added Tax (VAT) 5% of (G + H + I) 722.32
K. Total Unit Cost (G + H + I + J) 15,168.67
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(9) Storm Drainage and Downspout (4CL)


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 20.50 94.05 1,928.02


b. Skilled Laborer 2 20.50 67.95 2,785.95
c. Unskilled Laborer 4 20.50 52.42 4,298.44

Sub - Total for A 9,012.42

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Minor Tools (10% of labor cost) 901.24


b. Plate Compactor (5hp) 1 3.07 123.00 378.22

Sub - Total for B 1,279.47


C. Total (A + B) 10,291.88
D. Output = 1
E. Direct Unit Cost (C ÷ D) 10,291.88

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a.PVC Pipe 150mm dia x 3m lgths. 13.00 1,975.29 25,678.77


c. PVC Pipe, 100mm Ø x 3m, S-1000 lgths. 33.00 652.00 21,516.00
d. Elbow, 100mm dia. x 45 deg. Bend pcs. 18.00 60.00 1,080.00
e. PVC Solvent, 400cc cans 4.00 245.00 980.00
f. Consumables (5% of Material Cost) 1,075.80
g. Roof Drain Dome Type pcs. 8.00 1,500.00 12,000.00

Sub - Total for F 62,330.57


G. Direct Unit Cost (E + F) 72,622.45
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 8,714.69
I. Contractor's Profit (CP) 8% of G 5,809.80
J. Value Added Tax (VAT) 5% of (G + H + I) 4,357.35
K. Total Unit Cost (G + H + I + J) 91,504.29
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(5) Sanitary/Plumbing Fixtures (4CL)


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 161.75 94.05 15,212.59


b. Skilled Laborer 1 161.75 67.95 10,990.91
c. Unskilled Laborer 1 161.75 52.42 8,478.94

Sub - Total for A 34,682.44

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 3,468.24

Sub - Total for B 3,468.24


C. Total (A + B) 38,150.68
D. Output = 1
E. Direct Unit Cost (C ÷ D) 38,150.68

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Water Closet complete w/ fittings & accs. sets 12.00 5,500.00 66,000.00
b. Wall Hung Lavatory, complete w/ fittings & accs. sets 1.00 6,500.00 6,500.00
c. Floor Drain pcs 34.00 280.00 9,520.00
d. Faucet pcs 14.00 195.00 2,730.00
e. Gate Valve 32mm sets 4.00 627.00 2,508.00
f. Mirror m2 24.00 500.00 12,000.00
g. Consumables 4,962.90
h. Urinal (trough) set 4.00 9,500.00 38,000.00
i. Concrete Sink 3 faucet set 3.00 6,028.00 18,084.00
j. Concrete Sink 1 faucet set 5.00 2,895.00 14,475.00
k. Gate Valve 50mm pcs 2.00 980.00 1,960.00
l. Gate Valve 20mm pcs 4.00 450.00 1,800.00
m. Check Valve 50mm pcs 1.00 954.00 954.00
n. PWD handrail set 1.00 4,500.00 4,500.00

Sub - Total for F 183,993.90


G. Direct Unit Cost (E + F) 222,144.58
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 26,657.35
I. Contractor's Profit (CP) 8% of G 17,771.57
J. Value Added Tax (VAT) 5% of (G + H + I) 13,328.67
K. Total Unit Cost (G + H + I + J) 279,902.17
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL-3 Fire Protection System (4CL)


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 130.25 94.05 12,250.01


b. Skilled Laborer 2 130.25 67.95 17,700.98
c. Unskilled Laborer 4 130.25 52.42 27,310.82

Sub - Total for A 57,261.81

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 5,726.18

Sub - Total for B 5,726.18


C. Total (A + B) 62,987.99
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) 62,987.99

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. B.I. Pipe 75mm dia lm 20.00 984.00 19,680.00


b. B.I. Pipe 65mm dia lm 30.00 708.00 21,240.00
c. Fittings (Elbow, Tee, Reducer, etc) l.s. 1.00 4,092.00 4,092.00
d.
e. Fire
Fire Hose Cabinet10
Extinguisher, with
lbsFire Extinguisher
Capacity, Wall set 4.00 24,000.00 96,000.00
Mounted, HCFC 123 set 4.00 6,825.00 27,300.00
f. FDC Siamese Twin: Two-Way unit 1.00 6,500.00 6,500.00
g. Overhead Water Tank 2000 US Gal unit 1.00 167,000.00 167,000.00
h. Concrete m³ 18.75 5,065.00 94,968.75
i. Rebar kg 787.50 44.00 34,650.00
j. Plaster Finish m² 78.00 84.25 6,571.50
k. Cement Based Waterproofing bag 188.00 45.00 8,460.00
l. .60 x .60 Manhole ea 2.00 21,000.00 42,000.00
m. End-Suction Centrifugal Water Pump, TDH
22m, 2.0HP, 60GPM unit 2.00 36,780.00 73,560.00
n. Booster Pump, TDH 25m, 3HP, 80GPM unit 1.00 39,300.00 39,300.00

Sub - Total for F 641,322.25


G. Direct Unit Cost (E + F) 704,310.24
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 84,517.23
I. Contractor's Profit (CP) 8% of G 56,344.82
J. Value Added Tax (VAT) 5% of (G + H + I) 42,258.61
K. Total Unit Cost (G + H + I + J) 887,430.90

* Please Check the Summation for Sub-Total A, B,


and F
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL-3 Septic Vault Type E (4CL)


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 25.00 94.05 2,351.25


b. Skilled Laborer 2 25.00 67.95 3,397.50
c. Unskilled Laborer 4 25.00 52.42 5,242.00

Sub - Total for A 10,990.75

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 1,099.08

Sub - Total for B 1,099.08


C. Total (A + B) 12,089.83
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) 12,089.83

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Reinforcing Bars Grade 40 kgs 528.98 44.00 23,275.12


b. Concrete m3 5.28 5,065.00 26,743.20
c. Plaster Finish m2 53.96 84.25 4,546.13
d. Cement Based Waterproofing, Sahara bag 131.00 45.00 5,895.00
e. 6" thk. CHB m2 5.00 187.50 937.50
f. 4" thk. CHB m2 2.50 162.50 406.25

Sub - Total for F 61,803.20


G. Direct Unit Cost (E + F) 73,893.03
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 8,867.16
I. Contractor's Profit (CP) 8% of G 5,911.44
J. Value Added Tax (VAT) 5% of (G + H + I) 4,433.58
K. Total Unit Cost (G + H + I + J) 93,105.21
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(6)b1 Catch Basin -1 (4CL)


Unit of Measurement : ea
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 94.05 94.05


b. Skilled Laborer 1 1.00 67.95 67.95
c. Unskilled Laborer 1 1.00 52.42 52.42

Sub - Total for A 214.42

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 21.44

Sub - Total for B 21.44


C. Total (A + B) 235.86
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) 235.86

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 10 mm dia x 6.0 Reinforcing Steel Bars kg 8.63 44.00 379.72


b. Concrete m3 0.07 5,065.00 354.55
c. Masonry m2 0.80 162.50 130.00
d. Plaster Finish m2 1.76 84.25 148.28

Sub - Total for F 1,012.55


G. Direct Unit Cost (E + F) 1,248.41
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 149.81
I. Contractor's Profit (CP) 8% of G 99.87
J. Value Added Tax (VAT) 5% of (G + H + I) 74.90
K. Total Unit Cost (G + H + I + J) 1,573.00
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(19) Conduit, Boxes, and Fittings (4CL)


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 23.00 94.05 2,163.15


b. Skilled Laborer 1 43.00 67.95 2,921.85
c. Unskilled Laborer 1 43.00 52.42 2,254.06

Sub - Total for A 7,339.06

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 733.91

Sub - Total for B 733.91


C. Total (A + B) 8,072.97
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 8,072.97

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 32mmØ RSC pipe length 4.00 883.75 3,535.00


b. 32mmØ RSC Elbow pc 2.00 320.00 640.00
c. 25mmØ RSC L&B pc 2.00 14.00 28.00
d. 25mmØ PVC pipe length 17.00 92.00 1,564.00
e. 25mmØ PVC Adapter pc 10.00 14.00 140.00
f. 20mmØ PVC conduit length 195.00 69.00 13,455.00
g. 20mmØ PVC adapter pc 350.00 8.00 2,800.00
h. utility box, deep type pc 65.00 50.00 3,250.00
i. junction box, deep type pc 75.00 50.00 3,750.00
j. 32mmØ entrance cap pc 1.00 243.20 243.20
k. 20mmØX2.4m ground rod w/ connector pc 2.00 1,200.00 2,400.00
l. 20mmØ locknut and bushing pc 350.00 8.00 2,800.00
m. 20mmØ Flexible metal Conduit length 6.00 20.00 120.00
n. 20mmØ Connector pc 2.00 10.00 20.00

Sub - Total for F 34,745.20


G. Direct Unit Cost (E + F) 42,818.17
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 5,138.18
I. Contractor's Profit (CP) 8% of G 3,425.45
J. Value Added Tax (VAT) 5% of (G + H + I) 2,569.09
K. Total Unit Cost (G + H + I + J) 53,950.89
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(18) Wires and Wiring Devices (4CL)


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 29.00 94.05 2,727.45


b. Skilled Laborer 1 43.00 67.95 2,921.85
c. Unskilled Laborer 1 43.00 52.42 2,254.06

Sub - Total for A 7,903.36

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 790.34

Sub - Total for B 790.34


C. Total (A + B) 8,693.70
D. Output = 1 l.s. .
E. Direct Unit Cost (C ÷ D) 8,693.70

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 2.0mm2 TW wire,stranded m 72.00 24.00 1,728.00


b. 3.5mm2 THWN wire,stranded m 1,242.00 23.00 28,566.00
c. 3.5mm2 TW wire,stranded m 621.00 23.00 14,283.00
d. 5.5mm2 THWN wire,stranded m 54.00 24.00 1,296.00
e. 5.5mm2 TW wire,stranded m 27.00 24.00 648.00
f. 8.0mm2 THWN wire,stranded m 6.00 65.00 390.00
g. 8.0mm2 TW wire,stranded m 24.00 65.00 1,560.00
h. 30mm2 THWN wire,stranded m 24.00 210.00 5,040.00
i. one gang switch set 11.00 150.00 1,650.00
j. two gang switch set 11.00 230.00 2,530.00
j. one gang 3 way switch set 14.00 145.00 2,030.00
k. duplex C.O. grounding type, 15A, 250V set 8.00 138.00 1,104.00
l. duplex C.O. grounding type, 15A, 250V, WP set 4.00 420.00 1,680.00
m. KWHR meter round with base set 1.00 2,200.00 2,200.00
n. Consumables (5% of Materials Cost) lot 1.00 3,235.25 3,235.25

Sub - Total for F 67,940.25


G. Direct Unit Cost (E + F) 76,633.95
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 9,196.07
I. Contractor's Profit (CP) 8% of G 6,130.72
J. Value Added Tax (VAT) 5% of (G + H + I) 4,598.04
K. Total Unit Cost (G + H + I + J) 96,558.77
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1102(21) Power Load Center, Switchgear, and Panel Boards (4CL)
Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 13.00 94.05 1,222.65


b. Skilled Laborer 1 13.00 67.95 883.35
c. Unskilled Laborer 2 13.00 52.42 1,362.92

Sub - Total for A 3,468.92

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 346.89

Sub - Total for B 346.89


C. Total (A + B) 3,815.81
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 3,815.81

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

MDP - Flush Mounted, NEMA 1 Enclosure w/ Ground Te set 1.00 11,134.50 11,134.50
Main:100at, 100af, 2p, 240v
Branches: 2 - 40at, 50af, 2p, 230v
1 - 50at, 50af, 2p, 230v

LPA - Flush Mounted, NEMA 1 Enclosure w/ Ground Ter set 1.00 11,674.00 11,674.00
Main: 50at, 2p, 240v (lugs only)
Branches: 3 - 15at, 50af, 2p, 230v
5 - 20at, 50af, 2p, 240v
2 - 30at, 50af, 2p, 240v

LPB - Flush Mounted, NEMA 1 Enclosure w/ Ground Ter set 1.00 12,012.00 12,012.00
Main: 40at, 50af, 2p, 240v
Branches: 3 - 15at, 50af, 2p, 230v
5 - 20at, 50af, 2p, 240v

30at, 50af, 2p, 240v, in NEMA 3R enclosure 2.00 1,200.00 2,400.00


40at, 50af, 2p, 240v, in NEMA 3R enclosure set 1.00 1,200.00 1,200.00
20at, 50af, 2p, 240v, in NEMA 3R enclosure 1.00 1,200.00 1,200.00

Sub - Total for F 39,620.50


G. Direct Unit Cost (E + F) 43,436.31
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 5,212.36
I. Contractor's Profit (CP) 8% of G 3,474.90
J. Value Added Tax (VAT) 5% of (G + H + I) 2,606.18
K. Total Unit Cost (G + H + I + J) 54,729.75
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1103(1) Lighting Fixtures (4CL)


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 20.00 94.05 1,881.00


b. Skilled Laborer 1 23.00 67.95 1,562.85
c. Unskilled Laborer 2 23.00 52.42 2,411.32

Sub - Total for A 5,855.17

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 585.52

Sub - Total for B 585.52


C. Total (A + B) 6,440.69
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 6,440.69

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 2 x 36 watts FL fixture box type w/ canopy base


and stem 1.5 ft. (450mm) length similar to amco set 16.00 1,173.00 18,768.00
AP-113-1.5 or aproved equal.
b. 2 x 36 watts FL fixture. set 8.00 650.00 5,200.00
c. 1 x 36 watts FL fixture box type. set 19.00 355.00 6,745.00
d. 1 - 18 watts CFL w/ medium base keyless type set 17.00 320.00 5,440.00
porcelain
e. Wall fanreceptacle.
with controlswitch set 8.00 1,200.00 9,600.00

Sub - Total for F 45,753.00


G. Direct Unit Cost (E + F) 52,193.69
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 6,263.24
I. Contractor's Profit (CP) 8% of G 4,175.49
J. Value Added Tax (VAT) 5% of (G + H + I) 3,131.62
K. Total Unit Cost (G + H + I + J) 65,764.05
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1208(1) Fire Alarm System (4CL)


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Skilled Laborer 1 31.0 67.95 2,106.45


b. Unskilled Laborer 1 31.0 52.42 1,625.02

Sub - Total for A 3,731.47

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 373.15

Sub - Total for B 373.15


C. Total (A + B) 4,104.62
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 4,104.62

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Fire Alarm Control Panel set 1.00 13,890.00 13,890.00


b. Fire Alarm Bell set 4.00 1,350.00 5,400.00
c. Manual Pull Station Switch set 4.00 1,600.00 6,400.00

Sub - Total for F 25,690.00


G. Direct Unit Cost (E + F) 29,794.62
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 3,575.35
I. Contractor's Profit (CP) 8% of G 2,383.57
J. Value Added Tax (VAT) 5% of (G + H + I) 1,787.68
K. Total Unit Cost (G + H + I + J) 37,541.22

You might also like