Professional Documents
Culture Documents
1689 Report
1689 Report
Harvey Rodgers
Department of Communities
PO Box 160
MIRRABOOKA WA 6061
Dear Harvey
As instructed by Tracy Hewitt of the Department of Communities, Integrity Engineering has undertaken
a structural condition assessment of the retaining walls on the northern and western boundaries of this
site where they lie within the rear yards of Units 8, 9, 10 and 11.
1. General Description
The boundary retaining walls are of masonry construction and have maximum height 1.32m.
Retained soil height measures a maximum of 1.2m and is generally around 100mm lower than
the top of the wall itself. Your site is located on the low side of the walls.
The western wall features steel post and panel fencing with timber sleepers beneath to fill any
voids between the top of the retaining wall and the bottom rail of the fencing panels. The fence
posts are spaced at 2.4m centres and fence height is 1.8m.
The northern wall features a corrugated fibre cement sheet fence on the upper side. Fence
height varies from 1.5m at the western end to 2.3m at the eastern end.
A site layout plan, retaining wall elevation views and indicative retaining wall section views are
provided in Drawing Set 1689 attached for your reference. Digital photographs showing the
condition of the wall at the time of inspection accompany this report via electronic transmissal.
2. Site Investigation
Investigation of the retaining walls via probing and potholing indicated that they comprise three
masonry leafs. The front two leafs extend to full height of the wall and are covered by a brick-
on-edge header course, while the third leaf at the rear extends from footing level to a height of 5
brick courses (430mm) below the header course. See Drawing 1689-2 for a section view.
Scanning of the walls using a Protovale Imp metal detector revealed no internal steel
reinforcement. The walls must therefore be acting as mass gravity walls that rely entirely on
their own self-weight to resist rotation. They are not cantilever walls that transfer loads down to
the footing via a reinforced concrete core.
Compaction testing in various locations along the base of the walls using a Perth Sand
Penetrometer returned satisfactory results of greater than 5 blows per 300mm penetration from
depth 150mm to 1050mm at all test locations.
3. Condition Assessment
Both retaining walls have rotated towards the low side (i.e. towards your property). Rotation was
measured at a maximum of 7.5° from vertical for the western wall and 2.6° from vertical for the
northern wall. Detailed rotational measurements along the walls are shown marked on Drawing
1689-2 for your reference.
Significant cracking and lateral displacement of the masonry has occurred near the junction of
the northern and western walls, where the 90° corner acts as a buttress support to both walls.
The cracking has occurred where the stabilising effect of the buttress dissipates and there is a
transition between rotated and non-rotated sections of wall.
Reverse analysis of the retaining wall construction detailing revealed that they are inadequate to
resist design loadings. At maximum retained height of 1.2m, the existing wall has just half the
base thickness required to resist design surcharge loadings. The use of post and panel fencing
with walls of this type is also problematic as wind loads are concentrated at post locations rather
than distributed evenly along the length of the wall.
Both boundary retaining walls are distressed and structural intervention is required to stabilise
them against further rotation.
4. Cause of Distress
Retaining walls can fail via any of the following failure modes:
1. Overturning failure:
The wall has inadequate resistance to overturning and rotates about the toe of the wall
towards the low side.
2. Sliding failure:
The wall has inadequate embedment depth and/or friction with the soil beneath and
slides laterally under load.
3. Bearing failure:
The soil beneath the wall does not have adequate bearing strength to withstand the
loads imposed by the footing and compacts causing rotational settlement.
5. Structural failure:
The wall has inadequate strength to resist design loads resulting in cracking,
deformation or partial collapse of the structure.
Cracking near the corner junction of the northern and western walls does constitute localised
structural failure, however this is a direct result of overturning failure. The cracking would not
have occurred but for overturning failure (rotation) of the sections of wall that are not stabilised
by the corner buttress.
5. Responsible Party
Adjoining sites appear to be at or close to natural level which indicates the retaining walls may
have been constructed to retain cut at your site only. Fence locations relative to adjoining
properties also indicate that the walls may be located entirely within your site.
6. Recommendations
The existing walls require either complete replacement or structural intervention to stabilise
them against further rotation. Remedial options are as follows:
Grout stabilisation can only be used where the existing masonry has rotated by not more than
3.5° from vertical as grouting cannot effectively stabilise the masonry beyond that point. The
section of severely rotated western wall extending from the control joint in Unit 9 yard to the
northern boundary will therefore need to be demolished and reconstructed per Options 2 - 4.
The author was awarded a Bachelor’s Degree of Civil Engineering with First Class Honours by
the University of Adelaide in 2003, is a current member of the Institute of Engineers Australia
(Membership No. 2657436), and has more than fifteen years of specialist experience in the field
of structural failure diagnostics and remediation in Western Australia and elsewhere.
I trust that the preceding comments have addressed your present requirements. If I can be of any
further assistance, or if you have any queries regarding this report, please contact me on 9258 9261.
Yours faithfully
Tim Wilson
Director
BE(Hons) MIEAust
Encl.
- Drawing Set 1689 (x5 A3 sheets)
The work carried out in the preparation of this report has been performed in accordance with the requirements of Integrity
Engineering’s Quality Management System.
This document is and shall remain the property of Integrity Engineering. The document is specific to the client and site detailed
in the report. Use of the document must be in accordance with the Terms of Engagement for the commission and any
unauthorised use of this document in any form whatsoever is prohibited. No part of this report including the whole of same shall
be used for any other purpose or by any third party without prior written consent of Integrity Engineering.
Document Status