Legend: P 1 4 A Proposed Two-Storey Commercial Building Sps. John and Geesnell Yap

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

GENERAL PLUMBING NOTES

LEGEND
1. ALL PLUMBING WORKS HEREIN SHALL BE EXECUTED
ACCORDING TO THE REQUIREMENTS OF THE PHILIPPINE SANITARY WATER PIPE LINE
NATIONAL PLUMBING CODE
AND THE RULES AND REGULATIONS OF THE EXISTING FRESH WATER PIPE LINE
LOCAL CODES AND ORDINANCES. NOTHING CONTAINED
ON THE DRAWING SHALL BE CONSTRUED AS TO RAIN WATER PIPE LINE
CONFLICT WITH THE NATIONAL AND LOCAL
ORDINANCES OR LAWS GOVERNING THE GUTTER LINE
IMPLEMENTATION OF THE PLUMBING WORKS. M WATER METER
2. REFER TO ALL ARCHITECTURAL, STRUCTURAL,
ELECTRICAL, MECHANICAL PLANS AND SPECIFICATIONS
CB CATCH BASIN
AND INVESTIGATE ALL POSSIBLE INTERFERENCE AND VTR VENT THRU ROOF
CONDITIONS AFFECTING THE PLUMBING WORKS.
DS DOWN SPOUT
3. IT IS NOT INTENDED THAT DRAWINGS SHALL SHOW
EVERY PIPE FITTING, VALVE AND APPLIANCES. FURNISH
F.D. FLOOR DRAIN
AND INSTALL, IF NECESSARY ALL ITEMS WHETHER W.C. WATER CLOSET
SPECIFICALLY MENTIONED OR NOT, OR INDICATED ON
THE DRAWINGS, TO COMPLETE THE SYSTEM IN LAV. LAVATORY
ACCORDANCE WITH THE BEST PRACTICE OF THE
PLUMBING TRADE AND TO THE SATISFACTION OF THE SHO SHOWER
ARCHITECT. UR URINAL
4. PERFORM ALL LABOR IN A FIRST-CLASS, NEAT,
WORKMANLIKE MANNER BY SPECIALISTS SKILLED IN
THEIR TRADES, AND SUCH SPECIALISTS AND THEIR
WORKS SHALL BE SATISFACTORY TO THE ARCHITECT.
21.35 21.35
BASIC MATERIALS

1. PROVIDE MATERIALS THAT ARE NEW AND THAT C.O.


CONFORM C.O. W.C. W.C.
WITH THE STANDARDS OF THE UNDERWRITERS SINK SINK
LABORATORIES, INC. W.C. W.C.
2. FOR OTHER MISCELLANEOUS REQUIRED MATERIALS
NOT SPECIFICALLY MENTIONED, PROVIDE THE BEST
OF THE RESPECTIVE KIND.
F.D. F.D.
3. SUBMIT SAMPLES OF THE MATERIALS FOR APPROVAL
AS REQUIRED BY THE ARCHITECT. LAV LAV
C.O. C.O.
4. CONFORM ALL APPLICABLE PIPES AND MATERIALS
FOR VARIOUS SERVICES TO THE STANDARDS STATED LAV LAV
HEREUNDER. S.S. S.S.
PLUMBING FIXTURES F.D. F.D.
URI W.C. URI W.C.
1. INSTALL ALL PLUMBING FIXTURES FREE AND OPEN IN
A MANNER TO ACCESS FOR CLEANING, FURNISHING
WITH BRACKETS, CLEATS, PLATES AND ANCHORS C.O.
REQUIRED TO SUPPORT THE FIXTURES RIGIDLY IN
PLACE.

2. KEEP AWAY AT A SUFFICIENT DISTANCE BUT NOT LESS


THAN 1 2 INCH (12.7mm) ALL SERVICE PIPES, VALVES
AND FITTINGS FROM SURFACES AND LOCATION WHICH
MAY REQUIRE FINISH COATS OR COVERING.

3. EXTEND THE PIPING TO ALL FIXTURES, OUTLETS AND


EQUIPMENT FROM REQUIRED GATE VALVES
INSTALLED IN EACH BRANCH NEAR RISERS.

SOIL, WASTE, DRAIN & VENT PIPING

1. INSTALL ALL PIPING WORKS IN CONFORMITY WITH ALL


PROVISIONS REQUIRED OF THE LATEST EDITION OF
THE PHILIPPINES AND APPLICABLE REQUIREMENTS OF
EXISTING LOCAL CODES.

2. EXCAVATE TO REQUIRED DEPTHS AND GRADES ALL


EXCAVATIONS REQUIRED FOR THE INSTALLATION OF
PLUMBING AND DRAINAGE SYSTEM. WHEN ROCK IS
ENCOUNTERED, EXTEND EXCAVATION TO A DEPTH
150mm. BELOW THE PIPE BOTTOM AND BEFORE PIPE IS
LAID, FILL SAND AND OTHER APPROVED MATERIALS.
23.97

23.97
3. LAY WATER SUPPLY PIPES AND SEWERS IN SEPARATE
TRENCHES.

4. ALL HORIZONTAL PIPING SHALL BE RUN IN PRACTICAL


ALIGNMENT AND AT A UNIFORM GRADE OF NOT LESS
THAN TWO PERCENT (2%) OR 2cm PER METER
TOWARD THE POINT OF DISPOSAL.

PLUMBING PIPES & FITTINGS

1. FOR WATER LINES USE, POLYPROPYLENE (PPR) PIPES


C.O. DS DS DS DS DS
AND FITTINGS CONFORMING TO STANDARD
DIMENSIONS, USING MANUFACTURER SPECIFIED
METHOD OF INSTALLATION & CONNECTION. MATERIAL
BRAND IS POLYMUTAN OR APPROVED EQUAL..

2. SEWER PIPES, VENT FITTINGS AND TRAPS TO USE PVC


PIPES AND FITTING MATERIAL OF NELTEX, EMERALD
OR ATLANTA BRAND.

3. PVC JOINT CEMENT. MATERIAL BRAND, NELTEX,


EMERALD OR ATLANTA.

4. FLOOR DRAIN SIZE IS 100mm x 100mm STAINLESS


STEEL.
MATERIAL BRAND, METMA MODEL NO. M210 OR
APPROVED EQUAL.

SEPTIC TANK
POTABLE
5. WATER METER PROVIDED BY RLC. RAINWATER RAINWATER
TANK TANK
6. AIR CHAMBER TO BE PROVIDED FOR ALL WATER LINES
OUTLETS ALL NECESSARY FITTING SHALL BE
PROVIDED.

7. TEFLON TAPE FOR ALL WATER LINES CONNECTIONS


APPLIED TO MALE THREADS ONLY.

8. STAINLESS STEEL SINK STRAINER MATERIAL BRAND,


BIG BOY USA OR APPROVED EQUAL.
HOLDING
9. APPLY PIONEER EPOXY FOR JOINT. TANK
10. MAKE ALL JOINTS WATER TIGHT. FOR JOINING PIPES,
USE THE FOLLOWING:
A. GALVANIZED IRON AND COPPER PIPES: CAREFULLY
REAMED THREADED JOINTS. APPLY TEFLON TAPE
OR PAINT WITH RED LEAD AT ALL LENGTHS.
B. CEMENT PIPES: GROUT WITH CEMENT MIX ALL
AROUND THE JOINTS IN A CONSISTENT MANNER. DO
NOT ALLOW GROUT TO BULGE INSIDE PIPE
INTERIORS
C. PVC PIPES: USE APPROPRIATE COUPLERS AND
GLUE AT JOINTS.
SHUT-OFFS
11. THE THREADS OF DRAINAGE FITTINGS SHALL BE
TAPPED
PROVIDE TO ALLOW
THE ENTIRE
GRADE
TWO WITH
SYSTEM (2) PERCENT
VALVESOR
SO21mm/M
LOCATED THAT THE SYSTEM OR PORTIONS OF IT 1 GROUND FLOOR SANITARY LAYOUT 2 SECOND FLOOR SANITARY LAYOUT
CAN BE OPERATED, REPLACED AND REPAIRED, AS
WELL AS AFFORDING COMPLETE CONTROL OF P 1 SCALE 1:100 METERS
P 1 SCALE 1:100 METERS
THE WATER SUPPLY TO EACH GROUP OF THE
FIXTURES. WHEN REQUIRED, PROVIDE ALSO
PRESSURE REDUCING VALVES.

OTHERS

1. PIPES SHALL BE INSTALLED AS INDICATED.


ANY RELOCATION REQUIRED FOR PROPER
EXECUTION OF OTHER TRADES SHALL BE
PRIOR APPROVAL OF ARCHITECT AND THE
DESIGNING PLUMBING ENGINEER.

2. PROPOSED SANITARY UTILITIES SHALL


CONFORM TO THE ACTUAL LOCATION,
DEPTH , AND INVERT ELEVATIONS.

3. ALL FIXTURES SHALL BE VENTED, UNLESS


OTHERWISE INDICATED.

MASTER PLUMBER PROJECT TITLE/ LOCATION: OWNER: SHEET CONTENTS: DRAWING NO.:

1. GROUND FLOOR SANITARY LAYOUT


Sps. JOHN AND GEESNELL YAP 2. SECOND FLOOR SANITARY LAYOUT P 1
A PROPOSED TWO-STOREY COMMERCIAL BUILDING 4
OWNER
TAGBILARAN CITY SHEET NO.:

THESE DRAWINGS AS INSTRUMENTS OF SERVICE ARE THE PROPERTY AND DOCUMENT OF THE ARCHITECT. ADDRESS: TAGBILARAN CITY
IT SHALL BE UNLAWFULL FOR ANY PERSON, WITHOUT THE WRITTEN CONSENT OF THE ARCHITECT
OR AUTHORS OF THE SAID DOCUMENT TO DUPLICATE OR COPY SAID INSTRUMENTS
11 18
SIGNATURE TIN: CTC NO. DRAWN: CHECKED: GWORKS