Provision of EPCC for

Surveillance Record Phase 1- 100KBOPD Field


Surface Facility Project
Iraq-Branch B9

No:HSE-001

Inspected Dept. HSSE Date 2023-02-13

Location Outside FH-3HY Responsible person Zhao Dianjun

When do coating & painting, workers were


left ignited. Sometimes, workers without
attention were exposed to this fire
Inspection

Inspector:Hussein Hisham Date: 2023-02-13


- Close or reduce the fire with the availability of a fire extinguisher.
preventive measures
suggestions and

- At least three workers must be available when making coating & painting.
Handling

Inspector:Hussein Hisham Responsible person:Zhao Dianjun 23 2 13


Correction

Person in charge of correction: Y M D


Review conclusion

Reviewer: Y M D