Professional Documents
Culture Documents
The Handbook For Hospital Planning and Designing
The Handbook For Hospital Planning and Designing
DESIGNING
hospaccxconsulting.com/the-handbook-for-hospital-planning-and-designing-india/
INTRODUCTION
Planning and designing hospital is a complex and multifaceted process that requires
careful consideration of various factors to ensure the delivery of high-quality patient care
while optimizing operational efficiency. Hospitals and other healthcare facilities are
designed with the help of healthcare architects, who have a crucial and varied role to play.
Due to the special and complex requirements of healthcare facilities, their participation is
essential. Task of the architects before construction of a hospital are to determine the
broad requirement for the hospital system. The system should be able to provide
reasonably effective services to patients. Further, workloads and the required activities of
any healthcare institution are never predictable in detail. Architects, therefore, must
recognize the two main problems, expansion and flexibility to keep pace with the rapidly
developing technology in medical sciences. Physical planning must allow for future
expansions in all major functional areas of the hospital and for internal adjustments in the
use of space to desired degree of changes must be feasible. Functionally a hospital has
six major facility zones:
1/24
2. Ambulatory Care (outpatients department).
3. Diagnostic and Therapeutic Facility
4. In-Patient (Nursing Care) Units.
5. Administration Department and Business.
6. Hospital Engineering Services.
However, for reasons of overall control and security, entries and exits are to be kept to a
minimum.
The outpatient department in a hospital has a very important role in health care delivery.
A well-organized and well-equipped outpatient department can play a key role in reducing
the load on the inpatient beds and saving a lot of time and expenditure. The emphasis is
now more on outpatient facilities, which are likely to increase substantially, thereby
reducing the load of inpatients and the cost of hospital projects as a whole.
These facilities should be placed at different levels accordingly, taking into account their
functional use and the degree of necessity for dependent departments. Diagnostic and
imaging units generally deal with radiography and fluoroscopy, ultrasound, nuclear
2/24
medicine, CAT scans, etc.
This technique is rapidly developing and should be designed with the future scope of
expansion in mind. Laboratories are concerned with the analysis of diseased tissue,
fluids, and other elements in the body. This department may comprise activities like
biochemistry, microbiology, clinical pathology, hematology, histology, cytology, and
serology.
Other activities connected with the department are mortuary and autopsy. Radiography
involves the treatment of different types of radiation, from superficial therapy to
megavoltage therapy.
The size of the department depends on the load, scope of work, and type of equipment
employed. High levels of radiation, protective measures, and air conditioning for the
efficient functioning of the electronic equipment are the essential design requirements for
the department.
In-patient nursing care units (wards) occupy the maximum share of hospital space.
Concept of providing this facility is fast changing due to policy of early ambulation
and in fact only a few patients really need to be on bed.
3/24
Nursing care is broadly classified into general wards, specialty-wise wards and
intensive care units. Basic consideration in placing wards is to ensure sufficient
nursing care, segregating patients according to three categories, locating them
according to the needs of the treatment in respective medical discipline and
controlling cross infection.
Specialty-wise wards, however, should be located closer to their respective
outpatient clinics to act as self-contained centers. In planning a ward, the aim
should be to minimize the work of the nursing staff and provide basic amenities to
the patients within the unit.
Ward pattern has undergone a radical change from Nightingale ward to Riggs ward.
Many variations and modifications of the concept are meeting specific socio-medical
requirements while attempting to enhance the efficiency of nurse-patients interaction,
observability, lighting and other physical requirements, replenishment system for
supply of diet medical and surgical supplies, linen and other materials at the
doorstep of nursing activity have further relieved the nursing staff on non-nursing
functions to attend patient centered activities.
In-patient care is not only for admitting patients who cannot be treated outside the
hospital, but also for training doctors and paramedical staff.
In-patients are likely to fall into one of five broad cares grouping in the proportions shown.
Intensive Medical Care Where continuous medical and nursing observation and
mechanical assistance is necessary to maintain life one percent.
1. Intensive nursing care is where patients are unable to leave their beds and where
continuous nursing, observation, and physical assistance are needed, with a 20-25
percent increase in the number of patients.
2. Medium Nursing Care allows patients to leave their beds for short periods (up to
four hours) each day with assistance from 20-25 percent.
3. Low nursing care where patients are able to leave their beds for more than four
hours per day, requiring minimal assistance of 20-30 percent.
4. Self-care patients leading an apparently normal life while in hospital for observation
represent 5-10 percent.
4/24
The extent of these functions established by the individual hospital will vary depending on
the hospital’s aim, expectations of the community, and political will. The scope and form
are undergoing dramatic change.
If it functions well, it can reduce pressure on inpatient care, which can be achieved by
increasing diagnostic and treatment services.
Planning is a dynamic process and necessary for orderly development. It can be carried
out at many levels of detail and in many timeframes.
To assure a smooth, orderly project the first step in the planning process is to establish a
schedule for the entire project:
Preplanning schedule.
Determination of community need for healthcare.
Evolution of existing conditions.
Demographic survey of the community.
Statement of goals and objectives related to community needs.
Capital financing plan.
Operational programme to meet goals and objectives.
Master development plan as a framework, including gross departmental area
allocation.
Schematic plans, and construction staging.
Cost analysis.
Detailed space programme of first stage for construction.
Equipment list.
Design of first stage.
Construction of first stage.
Evaluation of operation and feedback.
The departments responsible for each group’s successful interaction are the foundation of
the hospital’s work.
Each separate department needs its own identity and within it, its own map, its own
private and public space as well as own front door.
The design must allow the identity of many families which form its work force to be
identifiable, physically, from inside the complex.
0 beds -10 acres, 100 beds 15-20 acres, 200 beds 20-25 acres, 500 beds 55-
70acres, 700 beds 80-90 acres, 1000 beds 90-100 acres. Hospital design must
have flexibility, to adopt change and its concern should be the quality of medical
care and the improvement of its standards.
It is accepted that planning and proper programming is essential to strengthen the
health care facilities.
Every country should accept it as its responsibility to design and implement
changes that enhance the performance of the total health service delivery system in
a balanced and integrated manner, because hospital is a complex organization.
5/24
The idea of planning is to prevent the haphazard mushrooming up of structure, to
prevent fragmentation of function and to promote logical flow of patient, staff and
equipment and to attain a fair degree of uniformity and standardization.
The implementation of a health care facility project could be regarded as a
sequence of phases.
Formulation consists in establishing the need for a facility; in making sure that its
erection would be in accordance with stated policies and priorities, in ascertaining
that the resources (money and manpower) necessary for its realization and
operation are available or will be available when needed.
At the end, formation of planning team should be made.
SITE SELECTION
When selecting the site, one must keep in mind that any further expansion in the size of
land required will be as follows:
Single storey
Double storey
3-5 stories
4-6 stories
6-9 stories.
Basement is possible if the sub-soil water is below 25 feet in mid monsoon time
The need for a good hospital design not only indicates impeccable infrastructure, but also
a step towards healing and wellbeing. Hence, hospital design is an extremely crucial
aspect. Here are the things to be taken into consideration while designing a hospital:
Design Plan
6/24
Circulation area such as corridors, entrance halls, staircase, etc. in the hospital building
should not be less than 30 percent of the total area of the building.
Radial-linear
Tree-shaped or dendritic-grid.
Water Supply
About 300-500 liters of water per bed per day (excluding water for gardening) is to be
catered for Water supply should be preferably from two sources. Reserve water for 7
days if from a single source and 2 days if from two sources.
Electricity
Electricity supply should be from 2 grid/3 grid (source). In addition, generator supply for
certain essential areas should be catered for even for more essential equipment there
should be provision for uninterrupted electric supply. Requirement for the hospital is 1
kWh per bed per day.
Sanitary Requirements
Toilet for an individual room (single or two beds) in a ward unit shall be 3.5m2 comprising
a bath, a wash and WC.
Toilet common to serve two such rooms shall be 5.25m to comprise a bath, a WC in a
separate cubicle and a wash basin.
Biomedical waste (soiled, semi-soiled and liquid) amounts to 2 kg per bed per day.
The hospital drainage should be connected to the main town drainage system.
The Hospital Space Module is taken as 3.5 sq.m. This space is enough to accommodate
a toilet comprising a WC, wash basin and a shower. 7 sq.m is enough for the routine
hospital bed, and 14 sq.m will be required for each bed in the Intensive care unit.
1. Hospital Engineering Grid is taken as 1.6 m one and a half grid i.e. 2.4 m is the
desired width of a corridor. Width of door, window etc. can also be expressed in the
form of a grid.
7/24
2. Plinth area
With all constraints the recommended area per bed is 75 sq.m. Whereas in developed
countries it is 150 sq.m.
Floor height
The height of all the room in the hospital should not be less than 3 m and not more than
3.65m.
1. Head room
The minimum height under the beams, fans, lights and other fixture on the ceiling should
not be less than 2.6m. measured vertically from the floor.
2. Dado
3. Door
The minimum width of doors should not be less than 1.6 m. and height 2.1 m.
1. The traction system of the hospital may be divided into two parts extramural and
intramural. The extramural system is the ambulance service. The intramural system
includes ramps, lifts, conveyor belts, and dumb waiters and trolleys etc.
2. Lifts (automatic control) with speed of 0.36 m and 0.75 per second for hospitals of
two or more stories.
Design Competition
8/24
If the hospital is big, a tender can be introduced to invite the architects for a design
competition and a rate. A group of users and experts can choose the best design and
rates, etc. Construction by Contractor A project like a hospital has to be contracted only at
a reasonable price with a reputed contractor.
A tender has to be issued by the engineering department with full and complete
specifications stating type of work, the accepting cost, period of completion, etc. The
planning team should take a decision regarding allotment of work. Proper control of
construction must be exercised by management.
Control
The success of a project depends largely on getting everything set up correctly: choosing
an appropriate process, selecting appropriate team members, and doing the groundwork,
so a team will know what the project is all about.
9/24
Maintain communication
Fix obvious problems
Look upstream
Document progress and problems
Monitor changes. Teams must spend time in the early stages of their project
planning how the project will unfold. Planning is the heart of using a scientific
approach to quality improvement.
Healthcare in India is in a developing stage and requires a radical policy shift at the
government level to implement changes and address the challenges of the future. Under
the umbrella of health care providers are outpatient set-ups, nursing homes, hospitals,
medical colleges, health spas, diagnostic centers, ayurvedic and naturopathy centers,
hospices, old age homes and more. Most of these institutions will have varied needs,
which will differ vastly in terms of their planning needs.
Health care provision in India is different in rural and semi urban settings where it is more
unorganized to today’s super specialty centers where it more institutionalized. The
mechanisms for funding are fast changing to the private sector involvement thereby
pushing up the cost of both setting up hospitals as well as availing health care in these
hospitals. The lowering of interest rates over the years has no doubt helped the cause of
the private sector wherein more entrepreneurs are coming forward to set up hospitals as
it has become affordable to take loans and repay them. The rapid growth of the insurance
sector is equally helping the community to face the problem of spiralling health care
costs.
Stakeholders
There are innumerable stakeholders in the health care delivery domain including the
government, philanthropic trusts, educational institutions, corporate sector, insurance
companies, bio-medical vendors, architects, construction companies, patients, relatives,
the pharmaceutical industry, professionals like doctors and other para-medical staff, and
the funding agencies The industry’s growth will be beneficial to many in the population
due to its wide range of stakeholders. The hospital ownership pattern can be basically
three types:
1. Government owned - central / state / district / autonomous like army, railways etc
2. Not for Profit – Managed by Trusts / Societies
3. For Profit – Corporate Sector
PROJECT CONCEPTUALIZATION
The first step in hospital planning is to freeze the project concept in terms of:
Identification of the market needs and deriving the appropriate size of the project
Determining the possibility of getting skilled manpower
10/24
All the above factors have a bearing on the project cost and its viability in the future. This
process helps understand the need of the community that will be served by the hospital in
the given location. For doing this, one needs to undertake a detailed Market Survey by
collecting secondary data from various sources like the internet, libraries, media
publications, newspaper archives, ministry of health and district health departments
records etc. Unfortunately, India does not have a reliable mechanism for capturing health
related data especially in the private sector. One also needs to undertake primary data
search by conducting interviews with households, practicing doctors and visiting existing
institutions. There can be three types of surveys required:
Household Survey
This is essentially done to understand the health care seeking behavior pattern of the
community as a whole. Sampling techniques are used to map the statistically significant
number of households. The basic information which should be collected and analyzed is
as follows:
Doctor’s Survey
Medical professionals are usually the best judge of deficiencies in the medical market and
should be carefully interviewed to determine a successful project approach in the
geographic services field. The sample of physicians surveyed should include specialists
in all medical and surgical departments, including specialists in diagnostic departments
such as laboratory, imaging, and physical therapy. Basic information Laboratory, image
processing, physical therapy, etc. Collected and analyzed when:
Institutional Survey
Getting basic feedback on the competitors in the primary service area, which is within a 5-
10 km radius, would be important to assess the strengths and weaknesses of major
players. For national centers of excellence, however, the catchment area could be much
11/24
larger, maybe the whole country, like Tata Memorial Hospital in Mumbai. One would also
need to know the productivity, tariffs, salary structure etc, which will help with preparation
of the feasibility report. The important information to be collected would be as:
DATA ANALYSIS
The data collected through secondary and primary sources is then analyzed to arrive at a
facility mix for the proposed project. It will also determine the scale of the project in terms
of its bed size. In case it identifies some atypical need like cancer treatment, it would
perhaps need more research to understand the profitability of such a capital-intensive
specialty. The end result should give definitive information on the following:
After finalizing the project concept in terms of its facilities and size, the next important
step is to analyse its financial viability. This will also help the promoter in planning the
means of financing the project based on its profitability and capability of servicing the debt
proportion.
The first step of the feasibility process is to identify the cost of the project in a realistic
manner. This is done by way of producing a detailed project report (DPR). Many projects
have failed midway through the construction process because it was identified that the
cost overrun would be more than 50% of the estimated budget.
12/24
Hospital buildings are very complex in terms of their engineering needs and hence
specialized agencies are required to plan these and identify the cost. The cost of the
project should be broken down under the following heads:
1. Civil Works including RCC, masonry, doors, windows, interior, and facade treatment
2. Electrical Work
3. Plumbing & Fire Fighting
4. Air Conditioning
5. Landscape & Site Development
6. Elevators
7. Medical Equipment Broken Down Under Departmental Heads
8. Non-Medical Equipment Like Kitchen, Laundry, Computer Hardware & Software Etc
9. Hospital Furniture and Fixtures
10. Professional Fees
11. Pre-Operative Expenses
12. Municipal Taxes & Deposit
13. Interest During Construction
14. Contingency
The estimates for all the above should be compiled meticulously after detailed
discussions with experts and undertaking adequate research. Financial institutions also
require sufficient back up data to accept the costs before accepting the project for
funding.
INCOME ASSUMPTIONS
After compiling the project cost, the next important step is to ascertain the income from
the project from various heads. Whilst doing this, one would rely heavily on institutional
market research to understand the industry benchmarks for making assumptions. Income
assumptions will need to be made for the following income heads:
1. Room rents for all categories of beds like general ward, twin/single rooms, ICU,
NICU etc.
2. Departmental income for diagnostic services
3. OPD & IPD Consultations
4. Surgical Operations (Major and Day Care Interventions)
5. Health Check Schemes
6. Pharmacy
7. Emergency
8. Deliveries
9. Blood Bank
10. Emergency
11. Any specialty service like LINAEC, IVF, Angioplasty, Minimal Invasive Surgery,
Organ Transplant etc. will need to be separately assessed
EXPENSE ASSUMPTIONS
13/24
The next important step is to compute all the important expenditure heads for the project
operations. These heads would include the following:
1. Salaries and wages – these should be computed on a cost to company basis and
should take into a staffing pattern inclusive of those for leaves, contract labours etc.
2. Departmental expenses in terms of consumables. This could be arrived as
percentage expense to the departmental income by taking industry benchmarks
3. Professional fee payable to doctors for rendering clinical services. This would differ
from assuming a flat salary to incentive-based remuneration. Again, industry
benchmarks will have to be followed for same. Some hospitals have a mix of both
the options
4. Energy costs in terms of electricity, water, medical gases, generator
5. Food expenses for patients and staff
6. Laundry & linen expenses for patients and staff
7. Housekeeping expenses can be calculated on a per sq. ft basis for the building
8. Stationery expense
9. Telecommunication
10. Conveyance and car maintenance
11. Marketing expenses
12. Repairs and maintenance
13. Insurance, Legal and Audit charges
14. Miscellaneous expenses
15. Depreciation
16. Interest cost for loans taken
17. Taxes for corporate hospital
FINANCIAL STATEMENTS
After computing the income and expense statements as mentioned above, one arrives at
the various financials, such as the Profit & Loss statement, Balance Sheet, Cash Flow,
and Break-Even Analysis. After computing these statements, once we can undertake
sensitivity analysis by subjecting the project assumptions to certain changes and
evaluating the impact on profitability, like:
Once you have agreement on a capital investment strategy and a facility mix (derived
from the detailed project report), it is time to undertake programming. The detailed project
report (DPR) may have been done for a long-range planning strategy, a short-term need
or maybe both. The functional program and the space program are to be prepared for the
short-term project or for phases of a longer-term project for which planning has already
14/24
been done in totality, like a teaching hospital. It serves as a common policy document
which outlines the parameters and vision of the project for all the members of the
planning and design team. It should also contain all the necessary information for the
architectural design team to commence conceptual and schematic design. The
components of the functional and space program for each department of the proposed
healthcare facility can read as follows:
The space program consists of a list of the various spaces in the department in square
feet and meters.
The space program provides a list of all rooms or areas required for each function and the
total area required for the function. The above approach flows from the functional
requirements. This document defines the functional requirements of the project in keeping
with the facility & service mix brief provided by the clients. These functional requirements
are defined in terms of the following parameters:
The room data sheets are an extension of the space program. Usually confined to an A3
sheet, it can contain a plan of the room, minimum dimension of the space, a list of major
items of medical or other equipment to be housed within that space, and any unique
temperature, humidity, lighting etc. conditions.
Without the plan, the same information can be given could an Excel sheet, and the plan
can be added after schematic design is done to complete the sheet. At this stage, the
room data sheets could only be generic to help the non-healthcare architect plan the
furniture, fixture and equipment plan (FFE).
For the room data sheets to be of optimal use, they would need to be prepared after the
FFE is in place.
ZONING
15/24
Zoning of a site is a concept every architect is familiar with, so I will just give a brief
description for the benefit of my healthcare professional readers. On a site that has
multiple usages by which I mean buildings housing differing kinds of functions it is useful
at the onset of design to block out appropriate areas that each usage will occupy. This is
done by considering the following factors:
16/24
Enumerated below are the agencies who would be collectively involved in the
construction of the hospital:
1. Excavation contractor
2. Civil contractor
3. Plumbing
4. Firefighting
5. Electrical
6. HVAC
7. Elevator
8. MGPS
9. Pneumatic Tubes
10. Nurse Call
11. IBMS
12. Hard Flooring & Dado
13. Casework, millwork
14. False Ceiling
15. Painting
16. Wall coverings
17. Crash guards / corner guards
18. Doors
19. Windows
20. Loose furniture
21. Artworks
22. Façade works
23. Landscape
24. Signage
25. IV tracks, curtains
26. Steel storage
27. Medical furniture
28. Display screens
29. Equipment – medical, non-medical
30. Low voltage applications – access control, CCTV, RFID
This act was enacted by the central government and is being adopted by the states of
India. It needs a one-time registration for a premise to be operated as a hospital. The
registration must be done by the respective state government that has adopted this act.
For registration, hospitals should fulfill the minimum requirement under the category in
which they fall. Each state has described the procedure of registration of the hospitals
that fall within their territory.
17/24
This act is applicable when the hospital established it under the ownership of a
corporation. The act needs the corporation to be registered and fulfils the requirements of
incorporation like memorandum of association, articles of association, capital structure
formation, securities allotment, account audits, etc.
In case the hospital is being established under the ownership of society, the society
registration act is required.
This is required to be chosen well, because if there are already some hospitals in the
locality, then it would be difficult to get in patients. Also, the hospital must be set up in an
area that has a good transportation facility or is close to a railway station. One must look
for non-agricultural land particularly designed for hospitals. All the electricity supply, as
well as the water supply, should be easily available and that is required to be checked
before purchasing any land for the hospital set up.
Facilities Offered
The facilities offered by the hospital should be decided by the management depending on
the locality of the hospital. It might be generalized into pathology, ICU treatment;
orthopedic, as well as other specialized services should be specified. Also, the facilities
linked to electricity, AC rooms, water, hygiene maintenance, etc, should be checked
before providing any specialized services.
Permits
A hospital could be set up only on no- agricultural land that could be used. The numerous
approvals, as well as permissions required from the local authority and the government
should be obtained before starting any hospital.
A hospital needs approximately 100 liters of water per bed each day. The water
requirement for the various hospitals would be different from project to project based on
whether the hospital is a primary, specialized hospital, etc. The concerned municipal
authority’s permission should be obtained to make the water and electricity facilities
available.
18/24
Sewage
Well planned sanitary measures for disposal of waste as well as a drainage system which
includes tanks, pipelines, etc. and permission from the local authorities should be
obtained.
Biomedical Waste
The large hospitals must have an incinerator for disposal of bio-disposal waste, for
instance, body parts or tissues. A smaller hospital is not able to afford such a cost and it
needs minimal space and additional machinery installations, which are expensive for a
small hospital set up. The Municipal corporation’s permission would also be required for
such disposal of waste and it must not be harmful to the people living in a nearby
location.
Approval of the Fire Department is required for a large hospital as well as a Health
certificate from the local authority after installation of all the beds and equipment within
the hospital. A NOC from the Fire department should also be required for small hospitals
and it would be the responsibility of the hospital management to prove that the hospital
would not cause any harm or loss of life and needs to be procured from the local
municipal council.
SIGN BOARDS
Rules for the size, contents as well as the correct place for signboards (IMC Regulations
2002)
19/24
The FSSAI license comes from the Food Safety and Standards Authority of India under
the Ministry of Health and Family Welfare, Government of India. The license is necessary
if the hospital runs an in-house kitchen for the patients as well as attendants.
If the hospital store has an LPG cylinder in large quantities for use in the hospital’s
kitchen or hospital purposes, the hospital must have a permit from the Controller of
Explosives under the Petroleum act, 1934.
This comes under the Office of the Drug Controller. There are different licenses for
medical shops attached to hospitals (IP) and standalone medical shops. There are
minimum requirements for the registration like the minimum size of the shop (250 – 300
ft) as well as requirements of Air conditioner and Refrigerator. This license is valid for 5
years.
Trademark registration
The Indian Trademarks Act 1999 is not a mandatory activity and is essential only if the
hospital wants to trademark its logo or name.
The ambulance bought by the hospital must be registered with the RTO, the Transport
Department, and the state government.
If arms are possessed by the hospital or its employees (for example by security guards),
a license for the same should be available.
LICENSE REQUIRED
20/24
3. No objection certificate under Pollution Control Act.
4. Narcotics and Psychotropic substances Act, 1985
5. Vehicle Registration Certificates (For all hospital vehicles.)
6. Atomic energy regulatory body approvals (For the structural facility of radiology
dept, TLD badges, etc)
7. Boilers Act, 1923(If applicable)
8. MTP Act, 1971 (MTP stands for Medical termination of pregnancy. To be displayed
in the Gynaec and Obs department)
9. License for the Blood Bank (To be displayed in the Blood Bank)
10. Transplantation of Human Organs Act 1994(If applicable)
11. PNDT Act, 1996 (PNDT stands for Prenatal diagnostics test. To be displayed in the
Radiology department that this is followed
12. Dentist Regulations, 1976
13. Drugs & Cosmetics Act, 1940
14. Electricity Act, 1998
15. ESI Act, 1948 (For contract employees)
16. Environment Protection Act, 1986
17. Fatal Accidents Act 1855
18. Guardians and Wards Act, 1890
19. Indian Lunacy Act, 1912 (Applicable only if a Psychiatry dept is there in the hospital)
20. Indian Nursing Council Act 1947 (Whether nurses are registered with NCI).
21. Pharmacists registered with Pharmacy Council of India.
22. Insecticides Act, 1968
23. Lepers Act Maternity Benefit Act, 1961
24. Minimum wages act, 1948 (For contract employees)
25. Pharmacy Act, 1948
26. SC and ST Act, 1989
27. Protection of Human Rights Act, 1993
28. Registration of Births and Deaths Act, 1969
29. Urban Land Act, 1976
30. Right to Information Act 2005
The registration for transplantation of human organ Act, 1994 (in case the hospital varies
out human organ transplantation or organ harvesting, it shall be registered under this Act)
Excise permit to store spirit (to store spirit beyond a certain quantity, the hospital must
obtain a permit from state excise department). Multiple medical laws along with ethics are
required to be followed at every step. A set of rules and eligibility criteria were put forth by
our government for hospitals, which offer services for central government health scheme
beneficiaries.
Unlike most other buildings, health facilities are complex buildings incorporating multiple
clinical disciplines. They need to be planned and designed to accommodate various
functions that have to strictly follow laid down operational policies. It is not just the
21/24
building but other asset classes such as MEP and HVAC services that follow strict design
norms, not to mention the medical devices that can often cost as much as or more than
the building itself. Establishing the facilities under these circumstances is just half the
task. Hospitals, by and large are complex, expensive to operate and maintain. It is
therefore essential to synchronize the commissioning and hand over in a seamless
manner so as to minimize any problems in future.
The commissioning team would prepare a project implementation plan / program based
on the objectives of the project promoters, the nature of the hospital, timelines for
commissioning the facility, the various assets and services that need to be incorporated,
the building plans, etc.
1. Building envelope
2. Safety systems
3. MEP systems
4. HVAC systems
5. Medical Gas Pipeline Systems (MGPS)
6. Nurse Call Systems (NCS)
7. Pneumatic Tube Systems (PTS)
8. Fire protection and alarm systems
9. Information technology
10. Vertical transports
11. Material handling
12. Interiors including lighting, furniture and finishes
13. Landscapes
14. Exterior lighting
It is important to write and execute policies and protocols and SOPs to ensure that the
skill sets for clinical and managerial areas are maintained to achieve complete patient
care. Some more aspects covered under commissioning assistance are:
Human Resource
Manpower Planning
Training Modules
Induction Program
22/24
Basic etiquette for Housekeeping, Nurses & Ward boys
Communication etiquette for front office staffs
Code of conduct
Grooming
Basic Etiquette for Housekeeping, Nurses & Ward boys
Evaluation Program
IT Integration & Planning
Module Selection
Technology Evaluation And Finalization
Selection of It Hardware
Implementation of IT
Assistance of Data Masters
Website Framework
Integration With HIS
Mobile App Framework
Security Guidelines For IT
BMS (Building Management System)
Public Address System
EPBX
CCTV
Queue System
Nurse Call Integration With His
E- ICU Management
Integration of Various Medical Equipment’s With His
Operations Management:
Induction Program
Workflow Management
Departmental Flow chart
SOP’s of Every Department As Per NABH
Tariff Design
Marketing Management:
Branding Activities
23/24
Brochure Design
Signage Program
Stationary Program
Finalization of Linen
Ambulance Design
Hoarding Design
Marketing and Branding are the final steps when it comes to planning any hospital which
is important for two main things-
CONCLUSION
24/24