Professional Documents
Culture Documents
Construction Contracts Liability
Construction Contracts Liability
Abstract: This paper explores the importance of limitation of liability in construction contracts and associated legal framework in the United
Arab Emirates (UAE) with an objective of assessing its adequacy in comparison to its economic counterparts. It points out that since there is
no independent statute dealing with the unfair contract terms, there is no equilibrium in contract provisions. This can cause several challenges
for the industry and contracting entities. Despite the fact that the UAE law does not mandate reasonableness in limitation of liability contract
Downloaded from ascelibrary.org by Zhejiang University on 04/11/24. Copyright ASCE. For personal use only; all rights reserved.
clauses, client organizations must adopt best practices from industries around the world and they should be driven by the numerous ad-
vantages they offer. The paper lists the importance of limiting liability in a construction contract and accompanying benefits. It also enlists
the measures and recommended approach that shall be adopted by contracting parties and the state in order to achieve equipoise in the
contracting setup. This study focuses on the law of the United Arab Emirates. DOI: 10.1061/JLADAH.LADR-829. © 2023 American
Society of Civil Engineers.
can be established between the breach and harm or loss. Decennial Liability
It seems liability under tort cannot be limited as made clear by
Article 296 of the UAE Civil Transactions Code, which states that As per Article 880 of the UAE Civil Code, contractors and engi-
any agreement purporting to provide exemption from liability for a neers are jointly liable for structural defects or collapse of the work
harmful act shall be void. While limitation of liability in tort is that happens within 10 years from the time the works are taken over
invalid under UAE law, it would be helpful to have such provisions by the employer. This liability, which has its roots in French law,
in contract law. This is a highly contentious issue and it can be argued is known as decennial liability. It is a strict liability under the
that without express limitation of liability provision in construction UAE Law.
contracts, Article 878 of the same code makes the contractor re- Main contractors and engineers are liable for cost of remedying
sponsible for all damages (Mohamed 2014). Consequential damages structural defects that surface within the time period of 10 years
may be foreseeable and besides this, the code under the muqawala from the day of handing over the project. When structural integrity
provisions does not differentiate between direct and consequential of a building is uncertain within 10 years of handover, it is deemed
damages. that both the contractor and engineer are in default; the only excep-
For example, the FIDIC Red Book 1999, which is the most tion to this rule is when the life of the building was meant to be for
common form of contract under use in the UAE, provides under less than 10 years (Mohamed 2014).
Clause 17.6 that the total liability of the contractor to the employer If the contractor did not perform the contract according to the
(with a few exceptions under some other subclauses) shall not ex- conditions and specifications, the liability for any resultant damage
ceed the sum stated in the particular conditions. Or if such sum is or loss will lie with the contractor, despite the fact that there was no
not stated or agreed, the limit shall be the accepted contract amount. shortcoming. Article 878 provides that “The contractor shall be li-
This subclause goes on to provide that it does not limit liability able for any loss or damage resulting from his act or work whether
in any case of fraud, deliberate default, or reckless misconduct by arising through his wrongful act or default or not, but he shall not
the defaulting party. Thus, under the FIDIC Redbook 1999, the be liable if it arises out of an event which could not have been
overall liability of the contractor, including tort, is limited subject prevented.” Consequently, default or negligence by a contractor
to a few exclusions. It is unclear how far this agreement would be or architect need not exist. The only way the contractor or engineer
upheld in UAE courts if contested by one of the contracting parties can escape this liability is proof of force majeure or extraneous
(Mohamed 2014). If the breach of contract constitutes also a breach circumstances.
of law (tort liability), any limitation of such a liability may not It was held in another UAE case that “one of the effects of such a
apply. contract is that the contractor guarantees any harm or loss arising
The following sections will explain some rules of law that are out of his act or the thing he has made, whether or not arising
directly related to limitation of liability such as liquidated damages, through his infringement or shortcoming. There will also be a
decennial liability, exclusion of liability for consequential losses, liability if a defect appears in the building.”
validity of exclusive remedy clauses, indemnification in the UAE, Article 880(2) further provides that such decennial liability can-
and proportionate liability. not be excluded by contract. The obligation to compensate will
remain even if it is proved that the cause for defect or failure of
the building was due to defective land or despite the fact that the
Liquidated Damages employer had consented to the construction of a faulty building or
installation. Thus, Article 880(2) makes the contractor liable for
Article 390 allows the contracting parties to fix the amount of com- all types of unforeseeable physical and ground conditions. In sum-
pensation in advance by agreeing on predetermined sum specified mary, for liability to arise no fault is necessary. The contractor and
in the contract, for a loss sustained due to a breach. However, the the engineer may be jointly and severally liable.
same article also grants the courts a discretionary power to scruti- Article 882 states that agreement the purport of which is to
nize and vary the limits agreed in the contract. It provides that if one exempt the contractor or the architect from liability or to limit such
of the parties makes a claim, the judges may vary such pre-agreed liability shall be void (Mohamed 2014). Thus, it seems in contracts
amount in order to make the damages and loss equal. Article 390 is in the UAE, the exposure of engineers or contractors for decennial
a mandatory rule and any contract excluding this right shall be void liability cannot be capped or excluded.
and this has been upheld by courts. This is reflecting the Shari’ah As per Article 881, if the role of the architect/engineer was only
(Islamic law) principles according to which remedies or compen- in making the designs or plans, he shall only be liable for any defects
sation shall be equal to the actual loss suffered. Thus, agreement on in the plans. If the engineer also took the role of the resident engi-
liquidated damages also has no certainty under the existing system. neer or supervisory consultant and supervised the construction ac-
However, including a liquidated damages clause is an effective tivities, he will be jointly and severally liable with the contractor,