Minutes of Meeting dated 28/06/2022, with BDPO

—Action taken reports (ATRs) to be submitted by the concerned BDPO on the relevant dates mentioned in
the last column.
—ATRs to be specific along with particular dates
—Information regarding Finances of Panchayats to be submitted in the following Performa by all Blocks
Name of Panchayat/Pan- Total Funds received in Works sanctioned in year Total Funds lying unspent
chayat Samiti year 2021-22 2021-22, 22-23 in the Panchayat/Block
(Sub divided into differ- Samiti Accounts
ent sources)
1. 15th FC 1. Name of Work 1. FC Account
a. Tied 2. Status of work (Ongo- A. Tied
b. Untied ing/Not started/Com- B. Untied
2. Panchayat Own pleted) 2. Panchayat Own
Funds 3. Total Budget Funds
3. Punjab Nirman 4. Source from obtained 3. Punjab Nirman Funds
4. Other Funds 5. Total Budget 4. Other Funds (Received
from Zila Parishad/
BLock Samiti etc. )
BLOCK BARNALA
Issues (BLOCK BAR- Status Proposed Action Date by which Action to
NALA) be taken

Auction 46 acres unauctioned. To be utilised for Planta-


tion.

—included in the list of


Sites identified for Planta-
tion.
Carrying out of new By Thursday, Muster Roll
works under MGNREGA —As Stated by the APO to be issued in at least 65
Scheme following is the status of villages.
works
Resolution for Plantation in By 07/06/2022
— MGNREGA 37 new 70 Acres to be prepared by
works have been identified Thursday.
and estimate made.
-10 Amrit Sarovars to be
—45 Micro Irrigation identified and uploaded on —07/06/2022
Works identified out of the APP sharing the infor-
which 20 already Sanc- mation with HQ.
tioned.

—Work sanctioned but yet


Pending Works not started to be reviewed —15/06/2022
—194 work sanctioned ear- anew. The works which can
lier but pending to be be started to be identified
started. and work started on
ground.

—Work to be started as
soon as possible in the
—10 Pond works have monsoon season. —15/06/2022
been sanctioned for dewa-
tering and desolation in the
current year. 6 Amrit
Sarovar have been identi-
fied as in the following vil- —Works must be identified
lages: and admin sanction taken to
• Thikriwal engage maximum work-
• Aspal Kalan force. This must be clearly
communicated to the con-
• Pandher cerned GRS.
• Kalike
• Badbar
• Kattu
• Dhurkot —By 15/02/2022

—Engagement of at least
40 workers in every Gram
Panchayat
Issues (BLOCK BAR- Status Proposed Action Date by which Action to
NALA) be taken
Completion of Process re- As per the APOs Payment
garding the Pending Pay- —PPTs of Payment for
ments of MGNREGA Rs. 1.35 Cr. are ready at the —PPTs to be sent to HQ -07/06/2022
Works level of APO. for payment at the earliest

—Payment PPTs/Excels to —DDPO Checking Pend-


be readied for all Cattle ing.
Shed for whom Bills have
been raised on the system. —Skilled Labour Payment
(Approx 50 in Number) Pending. —Different Pro-
cedure to be adopted for
payment of Skill Labour.

—42 Cattle Shed—By to-


morrow.

Rejected cases for pay- Total cases whose PPT for To resolve the issue either 05.07.20222
ments payment rejected are 9 through modification in
-4 cases are related to re- PPT in consultation with
construction of street and HQ.
drains which is non-permis-
sible.

-5 relates to width of streets


being more than 10 feet -Payment recommendation
to be revised as per the per-
missible limit and rest of
the payment to be done
through other funds of Pan-
chayat

Issuance of New Job —Grievance raised by Vil- —Problem to be identified —15/02/2022


Cards lage Hamidi that new Job by the DPO, NGREGA
Cards are not being pro-
cessed
—Proposed Action to be
—Steps to be taken to issue devised by the APOs to
New Job Cards in every maximise the new registra-
village tion.

Creation of Wetlands Directions by Deputy Com- To identify the feasibility 07/02/2022


missioner, to identify suit- of sites from the angle of
able land approx 20-40 wetlands.
acres for conversion to wet-
land. Two possible sites
have been identified.
—Badbar
—Sanghera.
Issues (BLOCK BAR- Status Proposed Action Date by which Action to
NALA) be taken
Resolutions for construc- 6 villages identified so far. -Suitable sites to be identi- 01.07.2022
tion of MNREGA —badbar fied and resolutions passed
Bhawan in 10 villages —karamgarh at the latest by 01.07.2022
—Nangal

Contingency for ZIla Pending Rs. 3 lakh to be transferred 30.07.2022


Parishad From Block Funds

Works identified in the Village Thulewal —Resolution for the work 05.07.2022
previous visits —Estimate for light and to be passed and work to be
fencing for the stadium is started
prepared by the SDO.
-Estimate for Sprinkler sys- —Estimate for sprinkler
tem to be prepared. system to be prepared by
-Pond work to be started SDO
under MGNREGA
—MGNREGA work on
Pond to be started
-Solar water pump to be
purchased and installed. —Solar water pump to be
installed

Village Nangal
-Pond near the Gurughar to 05.07.2022
be converted into Amrit —Design and estimateto be
Sarovar prepared by the SDO.

—Solar Motor operational.


But Electricity connection
required.

—Street to be made. -Estimate to be prepared for


the stadium and work
started.
Village Karamgarh
-Stadium Work

05.07..2022
Issues (BLOCK BAR- Status Proposed Action Date by which Action to
NALA) be taken
PLANTATION IN THE -SUITABLE LANDS AND The information to be sup- 15.02.2022
COMING SEASON SPACES ARE TO BE plied by 15.02.2022 in the
IDENTIFIED FOR THE following COLUMS:
PLANTATION.
1. Village Name
2. Land Area identified.
3. Type of Land (School,
Panchayati Land etc.)
4. Water Source Avail-
able? What kind
5. Whether there is
Boundary on the Land
6. Number of trees which
can be planted
7. Kind of trees required?
(Fruit, shade, specific
species)

JAL JEEWAN MISSION Aspal Kalan—Resolution To be resolved and work 30.07.2022


and Transfer of Funds 12 started by Friday
lakh
Jhaloor—Resolution and
Transfer of Funds 12 lakh
Rureken Kalan—SDO Res-
olution Pending 40 lakh.