BUSINESS BLUEPRINT
Project “SANKALP”
PROJECT SYSTEM MODULE
ON SAP ERP
AT
EAST INDIA UDYOG LIMITED
Submitted By
Intellect Bizware Services Pvt. LTD
Scenario – PS.03
Electrical Projects (Erection)
Page 1 of 12
Business Blueprint Document
Process code : PS.03
Consultant : Mr. Prapanna Ray
Version : 1.0
DOCUMENT CONTROL
Title Project System
Process SAP PS Erection Process.
Project Phase Business Blueprint Phase
Author Prapanna Ray
File Name EIUL-BBP-PS-Erection
Path Project Repository
Created on
Last Edited on 09.07.2021
SIGN-OFF
Role Name Signature
BU Head Mr. Chandra Mohan
Commercial Head
Execution Head
Execution (State Head)
Page 2 of 12
Business Blueprint Document
Process code : PS.03
Consultant : Mr. Prapanna Ray
Version : 1.0
REVISION HISTORY
Page 3 of 12
Business Blueprint Document
Process code : PS.03
Consultant : Mr. Prapanna Ray
Version : 1.0
Contents
1. SAP BEST PRACTICE.........................................................................................................................................................................................................................5
2. TO BE PROCESS FLOWCHART (ERECTION):............................................................................................................................................................................6
3. PROCESS BLUEPRINT (ERECTION):.............................................................................................................................................................................................7
4. IMPLEMENTATION CONSIDERATIONS....................................................................................................................................................................................10
5. PROCESS STEP MAPPING..............................................................................................................................................................................................................11
Page 4 of 12
Business Blueprint Document
Process code : PS.03
Consultant : Mr. Prapanna Ray
Version : 1.0
Page 5 of 12
Business Blueprint Document
Process code : PS.03
Consultant : Mr. Prapanna Ray
Version : 1.0
Page 6 of 12
Business Blueprint Document
Process code : PS.03
Consultant : Mr. Prapanna Ray
Version : 1.0
Step TO BE Process
AS IS Process, Requirements & Expectations Gap / Comment
No. (R-Required, O-Optional)
1 Project key points are now mentioning in Excel for Project Structure will create using the T-
reporting purpose. code “CJ20N” from Project template.
o Project Definition.
o WBS Element.
o Network and activity.
o Material Component.
Page 7 of 12
Business Blueprint Document
Process code : PS.03
Consultant : Mr. Prapanna Ray
Version : 1.0
Step TO BE Process
AS IS Process, Requirements & Expectations Gap / Comment
No. (R-Required, O-Optional)
Page 8 of 12
Business Blueprint Document
Process code : PS.03
Consultant : Mr. Prapanna Ray
Version : 1.0
Step TO BE Process
AS IS Process, Requirements & Expectations Gap / Comment
No. (R-Required, O-Optional)
Budgeted cost against WBS elements for
which the cost planning is done.
5 There is no existing as-is process Related to budget release Assigned budget need to be released for
consumption of budget.
Budget release functionality is useful for
the better control over the budget.
It is done through the transaction code
“CJ32”.
Budget can be released as a of
percentage of allocated budget.
Work-Order Creation Subcontracting Purchase Requisition will
be created automatically from project.
6 Remaining purchase process will cover in
MM BBP
Page 9 of 12
Business Blueprint Document
Process code : PS.03
Consultant : Mr. Prapanna Ray
Version : 1.0
4. Implementation Considerations
Prerequisites Material Master, Vendor Master, Customer Master, Project, WBS,
Outputs
Reports All Standard SAP Reports, DPR, Contractor Stock Report
KPIs
Changes
Authorizations
Improvements
Page 10 of 12
Business Blueprint Document
Process code : PS.03
Consultant : Mr. Prapanna Ray
Version : 1.0
Activity Step Transacti Fitness Responsibility/ Remarks Processing system (SAP, non-
on Code Authorization SAP etc.)
in SAP
S/C/D/M
Project – Create 1 CJ20N S Execution Team - SAP
Page 11 of 12
Business Blueprint Document
Process code : PS.03
Consultant : Mr. Prapanna Ray
Version : 1.0
Page 12 of 12