Eiul BBP PS Overview V3.0
Eiul BBP PS Overview V3.0
BUSINESS BLUEPRINT
Project “SANKALP”
PROJECT SYSTEM MODULE
ON SAP ERP
AT
EAST INDIA UDYOG LIMITED
Submitted By
Intellect Bizware Services Pvt. LTD
Scenario – PS.01
SAP PS Overview
Page 1 of 29
Business Blueprint Document
Process code : PS.01
Consultant : Mr. Prapanna Ray
Version : 1.0
DOCUMENT CONTROL
Title Project System
Process SAP PS Overview
Project Phase Business Blueprint Phase
Author Prapanna Ray
File Name EIUL-BBP-PS-OVERVIEW
Path Project Repository
Created on 24.03.2021
Last Edited on 14.04.2021
SIGN-OFF
Role Name Signature
BU Head Mr. Surendra Babu
Commercial Head Mr. Darshan Dhiman
Execution Head Mr. Pushpendra Saini
Execution (State Head) Mr. G. Kameshwar Rao
Page 2 of 29
Business Blueprint Document
Process code : PS.01
Consultant : Mr. Prapanna Ray
Version : 1.0
REVISION HISTORY
Contents
1. OVERVIEW OF SAP PROJECT SYSTEM.......................................................................................................................................................................................5
Page 3 of 29
Business Blueprint Document
Process code : PS.01
Consultant : Mr. Prapanna Ray
Version : 1.0
1.1 INTRODUCTION...........................................................................................................................................................................................................................5
1.2 PROJECT SYSTEM ORGANIZATION STRUCTURE................................................................................................................................................................7
1.3 MASTER DATA.............................................................................................................................................................................................................................8
1.4 PROJECT STRUCTURING...........................................................................................................................................................................................................9
1.5 OPERATIVE PROJECTS.............................................................................................................................................................................................................10
1.6 WORK BREAKDOWN STRUCTURE.......................................................................................................................................................................................10
1.7 PROJECT PROFILE.....................................................................................................................................................................................................................11
1.8 PROJECT TYPE................................................................................................................................................................................................................................12
1.9 PROJECT CODING MASK.........................................................................................................................................................................................................13
1.10 PROJECT / WBS STATUS..........................................................................................................................................................................................................14
1.11 PERSON RESPONSIBLE............................................................................................................................................................................................................15
1.12 APPLICANT NUMBER...............................................................................................................................................................................................................15
1.13 BUSINESS PROCESS FOR CREATION OF PROJECT............................................................................................................................................................15
1.14 PLANNING...................................................................................................................................................................................................................................17
1.15 PLANNING OF BUDGET...........................................................................................................................................................................................................18
1.16 COST PLAN AND BUDGET PROCESS EXPLAINATION......................................................................................................................................................21
1.17 PROJECT EXECUTION AND MONITORING:.........................................................................................................................................................................22
1.18 PROJECT CONTROL..................................................................................................................................................................................................................23
1.19 BUDGET CHECK........................................................................................................................................................................................................................23
1.20 PS TEXT.......................................................................................................................................................................................................................................23
1.21 PERIODIC SETTELEMENT.......................................................................................................................................................................................................23
1.22 PROJECT CLOSURE...................................................................................................................................................................................................................24
2. MODULE INTEGRATION................................................................................................................................................................................................................25
2.1 MATERIAL MANAGEMENT..............................................................................................................................................................................................................25
2.2 FINANCIAL ACCOUNTING...............................................................................................................................................................................................................26
2.3 CONTROLLING................................................................................................................................................................................................................................27
2.4 SALES AND DISTRIBUTION.............................................................................................................................................................................................................27
3. INFORMATION STRUCTURES......................................................................................................................................................................................................27
Page 4 of 29
Business Blueprint Document
Process code : PS.01
Consultant : Mr. Prapanna Ray
Version : 1.0
Project Systems provides a central point through which the procurement of materials and services, the planning and scheduling of services and
reporting of milestone dates can be coordinated and tracked. SAP PS is the component of both my SAP Enterprise Resource Planning (my SAP ERP)
and my SAP Product lifecycle Management (my SAP PLM)
Depending on the project type and requirement of project monitoring, one can structure the project. SAP Project System provided two type of
structures for mapping of a projects which are work breakdown structures called WBS and network and activity. One uses a work break down
Page 5 of 29
Business Blueprint Document
Process code : PS.01
Consultant : Mr. Prapanna Ray
Version : 1.0
structure to organize a project in form of a hierarchy, and so map the structure of project. Network on other hands is used to represent the individual
project activities together with their logical relationships in other words, the flow of the project. One can map a project using just one work break
down or one network. However one can also illustrate a project using a work break down structure and one or more networks in order to use the
characteristics of both structure together. Work break down structure consists of work break down elements (WBS elements) that are arranged at
various levels to produce a hierarchy model of project activities to be carried out. Each individual WBS elements can act as controlling objects in which
one can plan and monitor costs, revenues, payments, budgets, and dates. A network represents the flow of work .the individual tasks in project are
mapped as activities in a network. Activities form the operative basis for planning and controlling dates costs and resources. When activities are
assigned to WBS elements the dates and cost defined in the individual activities are totaled up at WBS level and can be evaluated. One can analyze
order costs for the WBS element and check them against the WBS budget. With the help of progress analysis one can view progress values that reflect
the status of project relative to the individual WBS element or aggregate them according to the project hierarchy.
Page 6 of 29
Business Blueprint Document
Process code : PS.01
Consultant : Mr. Prapanna Ray
Version : 1.0
assignments to the organizational units in other modules like Financial, Controlling, Material Management, Sales and Distribution, Production Planning
etc.
Page 7 of 29
Business Blueprint Document
Process code : PS.01
Consultant : Mr. Prapanna Ray
Version : 1.0
modules of SAP. For example, Material Masters are created in MM module. BOMs are created in PP module. Standard WBS, Standard Network, Work
Center are created in PS module G/L account, Cost Centers, Cost Elements, Profit Centers are created in FI/CO module.
We will be using PS, MM, SD, FI, CO, QM, PP modules of SAP S/4 HANA.
Some important master data are given below:
o Material master
o Purchasing masters:
Vendor master.
Purchasing info-records
Vendor master
o Sales masters:
Customer master.
o Production masters:
BOM.
Work Center.
Resources.
o Finance & Controlling:
G/L account.
Cost Centers.
Cost Elements.
Costing Sheets.
Profit Centers
The work breakdown structure (WBS) is a model of the project that organizes project tasks into a hierarchy. The main objectives of the WBS are
to split the project into manageable units, define basic dates, and determine its costs.
The WBS divides the project step-by-step into structure elements. The elements are called work breakdown structure elements (WBS elements)
in the project system. WBS elements are the only structural element in work breakdown structures.
The project definition is the binding framework for all organizational elements within a project.
Page 9 of 29
Business Blueprint Document
Process code : PS.01
Consultant : Mr. Prapanna Ray
Version : 1.0
o Define overall project start and finish dates (start and finish may change / vary depends upon the project status).
o Determine the project objectives (responsible person, text, etc.).
Page 10 of 29
Business Blueprint Document
Process code : PS.01
Consultant : Mr. Prapanna Ray
Version : 1.0
o Control Data: – These are various default profile set for control purpose.
Page 11 of 29
Business Blueprint Document
Process code : PS.01
Consultant : Mr. Prapanna Ray
Version : 1.0
Z2 Supply.
Z3 Erection.
Z4 Other
Page 12 of 29
Business Blueprint Document
Process code : PS.01
Consultant : Mr. Prapanna Ray
Version : 1.0
SYSTEM STATUS:
System status is a status of a project definition or WBS element that are predefined in the system.
Page 13 of 29
Business Blueprint Document
Process code : PS.01
Consultant : Mr. Prapanna Ray
Version : 1.0
System status are either automatically set by the system based on different business processes (such as budgeting or entering actual dates)
or manually assigned by the user.
Following are some important system statuses that can be set manually: -
o Released (REL): In this status, cost and revenue can be assigned to WBS element. This status is automatically passed on to
subordinate WBS element and cannot be reset.
o Technically Completed (TECO): The status for project or WBS element that are completed from a technical point of view but where it
still expects costs to accrue. This status does not allow any planning activities but allows the account assignment of committed costs
and revenues. However, costs through FI module can be booked even after this status. This status is automatically passed on to
subordinate WBS element and can be reset.
o Closed (CLSD): The status for a project definition or WBS element that has been completed from both a logistic and an accounting
point of view. This status not only prohibits planning activities, but also posting of actual cost and revenues. This status is
automatically passed on to subordinate WBS element and can be reset (resetting this status leads to TECO status).
o Deletion Flag (DLFL): The deletion flag status designates work breakdown structures or WBS elements that have been flagged for
deletion. This means that the objects are deleted logically, but not physically. This status prohibits all business transactions. This
status is automatically passed on to subordinate WBS element and can be reset.
o Locked: The use of this status to either lock individual business transactions or all the data in a work breakdown structure or WBS
element, this can be set the following statuses:
o
Account assignment locked (AALK)
Master data locked (MDLK)
We can set these statuses in addition to every other status except deletion flag. The statuses are not passed on to subordinate WBS elements
and can be reset.
Following are some important system statuses that is set automatically by system: -
o Created (CRTD): This is the initial system status for a new project or WBS element. In this status you structure the project and plan
dates, costs, and revenues. The system sets this status automatically when you create a new project or WBS element.
Page 14 of 29
Business Blueprint Document
Process code : PS.01
Consultant : Mr. Prapanna Ray
Version : 1.0
o Budgeted (BUDG): This status is automatically set by the system when budgeting for a WBS element is done.
o Availability Control Active (AVAC): This status is automatically set by the system when availability control is activated.
If there is any change (add or delete) in WBS structure, add or delete the WBS
element and save the project.
Once the final structure is ready, original budgeting will be done.
Page 15 of 29
Business Blueprint Document
Process code : PS.01
Consultant : Mr. Prapanna Ray
Version : 1.0
If you want to delete a WBS element, then first check whether it is budgeted or not.
If the WBS element does not contain any budget, then you can delete the WBS Element. But if it contains budget, then you must first remove
the budget from.
That WBS element and then you have to set deletion flag. You cannot delete a WBS
element if contains a budget.
After the releasing the WBS element, if you want to add any WBS element then you can add the WBS element.
After releasing a WBS element, you can only delete those WBS elements which do not have budget.
Those WBS elements which have budget, cannot be deleted, instead can be set to deletion flag after making the budget value to zero through
budget update process.
To delete those WBS elements which have commitments, remove the commitments, and make the budget value to zero and then set deletion
flag.
1.14 PLANNING
PLANNING OF COST:
Cost planning deals with the cost that is expected to incur in connection with the project. Cost plan has different aims at
different stages of the project. At the design and rough planning stage, cost planning acts as the base for initial cost
estimate.
At the approval stage, it forms the basis for the budget allocation. During the execution stage, cost planning is used to
compare plan cost and actual cost and analyse variance.
Page 16 of 29
Business Blueprint Document
Process code : PS.01
Consultant : Mr. Prapanna Ray
Version : 1.0
PLANNING PROFILE:
The planning profiles are needed to be configured to plan the cost at overall level.
The system considers the settings that you make in the planning profile during manual planning and during VSR
optimization (interactive and in the background, see VSR Optimization).
CO VERSION
During the planning and execution phase, plan cost for a WBS element keeps on changing. CO versions enables you to plan
several different costs for a single WBS element. Plan cost is always done with reference to a CO version.
Planning of cost should to be done in version “1” When there is a change in the plan cost, the existing plan cost of Version
“0” needs to be changed in version 0 itself.
Note: When Controlling area is created, the system automatically creates the CO version “Plan/Actual (Version 0)”.
Page 17 of 29
Business Blueprint Document
Process code : PS.01
Consultant : Mr. Prapanna Ray
Version : 1.0
Page 18 of 29
Business Blueprint Document
Process code : PS.01
Consultant : Mr. Prapanna Ray
Version : 1.0
Within Projects: Returns within projects follow the bottom-up principle, from a lower-level WBS element
to a higher-level one. Only budget, which is still distributable or available, can be returned. The system
calculates the budget available/distributable in controlling area currency and includes budget line items
entered in other currencies.
From Projects: With a return from a project, budget that is still available or distributable in a WBS element.
The effect of the return is recorded within the project - meaning that the overall budget is reduced.
Budget Transfers: Within a responsibility area, it may happen that one project is running short of funds
while another still has plenty. Transfer is a tool, which enables the available budget in one project at the
disposal of another. Additionally, the WBS elements involved may belong to the same project or to
different ones.
o Budget Release: In many businesses, budget distribution is not the same as releasing the funds. For this reason,
the project system includes a separate funds release facility, which can be used to make successive budget
releases. The release is based on the current budget. For example in the organization for a particular project if
“X” amount is the sanctioned budget but whereas allocated budget can be only some percentage of “X” then the
budget release facility is adopted.
o Current Budget: The current budget is shown in the information system as budget values. The current budget is
calculated as follows:
The current distributable budget forms the basis for availability control as per the released budget (the system checks automatically the
availability of budget while creating PR / PO as per the tolerances {80 % budget reaches the system will give warning message and after
reaching 100 % the system gives error message} and automatically stops generating the PR / PO).
Budgeting Methods:
The project system supports top-down budget planning. In top-down planning, the budget plan values are distributed from the upper to
the lower WBS planning elements. For budgeting the top-down planning is required to have better control over the distribution of the
Page 19 of 29
Business Blueprint Document
Process code : PS.01
Consultant : Mr. Prapanna Ray
Version : 1.0
funds available. Within the project structure, the system ensures that the funds in lower-level WBS elements (distributed values) do not
exceed those in the higher-level elements. The project system also supports bottom-up budget planning. In bottom-up planning, the
budget plan values are distributed from the lower WBS planning elements. Since the system doesn’t support to total up the top WBS
planning element automatically, hence the total up at top WBS planning element has to be done by clicking Edit Total up or F9.
Based on the project stage and the details available and required, the budgeting can be done across the time frame of the project
duration. The budget can be planned for Overall values or annual values or Both.
Page 20 of 29
Business Blueprint Document
Process code : PS.01
Consultant : Mr. Prapanna Ray
Version : 1.0
If there is an increase in the budget, then it will be done by supplementing the additional budget to the WBS element at Current
Year (supplement to the project).
If there is a decrease in the budget, then it will be done by returning the additional budget from the WBS element (return from
the project). If there is a transfer in the budget, then it will be done by transferring the additional budget from sender WBS
element to receiver WBS element from one year to another.
After any update in the budget (supplements, returns & transfers), plan cost also need to be updated. This will have to be done
manually.
During the project execution phase, the project should have control over the planned budget values and the actual values. Any
actual values exceeding the planned budget value should be controlled and proper approvals need to be taken and then the work
needs to be carried out.
Project is controlled by status (system & user) and availability control.
Page 22 of 29
Business Blueprint Document
Process code : PS.01
Consultant : Mr. Prapanna Ray
Version : 1.0
Availability control enables you to control costs actively by issuing warning, warning with mail to person responsible and error
messages when costs are incurred. Availability control checks the current distributable budget (or release) against the assigned
value.
1.20 PS TEXT
PS texts are text created and managed in the project system. During project processing, you can enter information, such as
requirements definitions, work package definitions, or logs, directly into the project system, in the form of PS texts.
Settlement is the process where the actual costs incurred for a WBS element are allocated, in whole or in part, to one or more
receivers. The debit postings remain in the receivers (WBS elements / Cost centre / WIP), where they can display them.
Settlement rule need to be created for WBS – which contains settlement profile, source structure, distribution structure. Within
settlement rule, distribution rules are created, which defines the percentage / amount to be allocated to receiving WBS.
Maximum number of distribution rules that can be made for any WBS is 999.
A prerequisite for settlement is that:
o The relevant objects should have system status "Released" at WBS element.
o The settlement rule must have been defined in the WBS as account assignment element (WBS element/ sales order/cost
centre / fixed asset.
o Settlement can be done to another WBS.
o Common costs can be settled from common WBS to individual WBS / asset by defining appropriate settlement /
distribution rule.
o The sender (WBS element) object should have actual cost incurred in the WBS account assignment element.
o As the project is executed, project person will make sure, at the end of each period that all the cost data belonging to the
project are settled, the fewer WBS elements in the project, the better the performance of the project functions.
Page 23 of 29
Business Blueprint Document
Process code : PS.01
Consultant : Mr. Prapanna Ray
Version : 1.0
o Costs can be transferred to capital work in progress (WIP) periodically without waiting for the entire project completion
or can be transferred to cost centre for non-capitalized costs. The settled costs are recorded in the relevant receiver, and
it can be evaluated in reporting.
Following are the two-settlement type: -
o DIRECT SETTLEMENT:
Each WBS element is settled directly to the external cost object. Examples: cost centre / GL.
o MULTI-LEVEL SETTLEMENT:
Individual WBS element in the project can be settled to other WBS elements within the same project.
Closed (CLSD):
Set this status for a work breakdown structure or WBS element that has been completed from both a logistic and an
accounting point of view.
LOCKED (LKD):
Page 24 of 29
Business Blueprint Document
Process code : PS.01
Consultant : Mr. Prapanna Ray
Version : 1.0
You can use this status to either lock individual business transactions or all the data in a work breakdown structure or WBS
element. You can set the following statuses: -
Account assignment locked (AALK)
Master data locked (MDLK)
2. MODULE INTEGRATION
Considering the specific requirements of the organization, the integration takes place between modules. The continuous exchange of
information with other application areas. System ensures a real time database. Fully integrated processing helps us to optimize the
project execution within the company.
Purchase requisition
Material purchase order
Service requisition
Service purchase order
Good receipt
Invoice receipt
Material issue
Page 25 of 29
Business Blueprint Document
Process code : PS.01
Consultant : Mr. Prapanna Ray
Version : 1.0
Page 26 of 29
Business Blueprint Document
Process code : PS.01
Consultant : Mr. Prapanna Ray
Version : 1.0
2.3 Controlling
Cost center accounting
Re-postings
Settlements
Cost elements
For example, the costing of the operation - both external and internal - is done automatically with data maintained in activity type prices and the price
maintained in material / service master.
For example, when sale order is created, WBS Element is captured in Sales order with billing element activated at WBS Element level.
3. INFORMATION STRUCTURES
The project information system is required to analyse and control your project.
There are various standard reports available in the project information system. The standard also includes reports offering different degrees of
detail, summarizations, and views of current data, version data, and archive data for:
o Structures
o Controlling.
o Progress
o Resources
Cost Reports:
Page 27 of 29
Business Blueprint Document
Process code : PS.01
Consultant : Mr. Prapanna Ray
Version : 1.0
Budget Reports:
o S_ALR_87013557 - Budget/Actual/Variance
o S_ALR_87013558 - Budget/Actual/Commitment/Rem Plan/Assigned
o S_ALR_87013559 - Budget/Distributed/Plan/Distributed
o S_ALR_87013560 - Budget updates
Material/Service Reports:
Page 28 of 29
Business Blueprint Document
Process code : PS.01
Consultant : Mr. Prapanna Ray
Version : 1.0
Confirmation Reports:
Page 29 of 29