Professional Documents
Culture Documents
2.2 PM - Activity Based Costing - 250622
2.2 PM - Activity Based Costing - 250622
2.2 PM - Activity Based Costing - 250622
A cost pool is an activity that consumes resources and for which overhead costs are identified and
allocated. For each cost pool there should be a cost driver.
Cost Driver
A cost driver is a unit of activity that consumes resources. An alternative definition of a cost driver
is the factor influencing the level of cost.
A cost driver is a factor that influences (or drives) the level of cost.
a cost driver
A simpler approach
Suppose we are talking of a Dominos outlet. Let us check what all overhead costs are incurred
- Maintenance costs
- Depreciation on machine
Now, it makes perfect sense to absorb these costs basis the machine hours used
- Say there are 4 types of pizzas that are made.
But there are other overheads as well - Like rent of premises, salary of security guy etc
- In absorption costing, even this would be absorbed using machine hour basis
- And that is wrong because machine hours are not directly responsible or connected with rent
ABC overcomes this problem by not using a generic item like machine hours for absorption
Instead it uses cost pools to group the costs which are driven by an activity
- The cost of order processing might be related to the number of orders dispatched or to the
weight of items dispatched
- the cost of purchasing might be related to the number of purchase orders made
- the cost of setting up machinery for a production run might be driven by the number of set-ups
Traditional systems measure accurately volume-related resources that are consumed in proportion to the number
of units produced of the individual products. Such resources include direct materials, direct labour, energy, and
machine-related costs
However, many organisational resources exist for activities that are unrelated to physical volume. Non-volume relate
consist of support activities such as materials handling, material procurement, set-ups, production scheduling
and first item inspection activities.
Traditional product-cost systems, which assume that products consume all activities in proportion to their production
thus report distorted product costs.
So, although both traditional absorption costing and activity-based costing systems adopt a two-stage allocation proc
the differences can be listed as follows:
For overhead allocation, ABC establishes separate cost pools for support activities such as material handling
As the costs of these activities are assigned directly to products through cost driver rates, reapportionment
of service department costs is avoided.
Overhead absorption into products is where the main difference lies between ABC and traditional costing.
Traditional absorption costing uses two absorption bases, (labour hours or machine hours) to charge
overhead to products, whereas ABC uses many cost drivers as absorption bases (e.g. the number of orders,
or the number of dispatches)
The use of cost drivers is the main idea behind ABC as they highlight what causes costs to increase
for example, the number of orders to suppliers each product incurs. Overheads that do not vary with
volume/output, but with some other activity, should be traced to products using ABC cost drivers.
Traditional absorption costing, on the other hand, allows overheads to be related to products
in more arbitrary ways – therefore producing less accurate product costs.
Say total maintenance cost is 100000
We now absorb this cost in each pizza type in proportion to number of hours
ditional costing.
umber of orders,
Step 1
Group production overheads into activities, according to how they are driven.
Step 2
Identify cost drivers for each activity, i.e. what causes these activity costs to be incurred.
Step 3
Calculate a cost driver rate for each activity.
The cost driver rate is calculated in the same way as the absorption costing OAR.
However, a separate cost driver rate will be calculated for each activity, by
taking the activity cost and dividing by the total cost driver volume.
Step 4
Absorb the activity costs into the product.
The activity costs should be absorbed back into the individual products.
Step 5
Calculate the full production cost and/ or the profit or loss.
Question
Breakup of OH
Machining Costs 5,000
Component Costs 15,000
Set-up Cost 30,000
Packing cost 30,000
Solution
Step 1 : Identify the activities - Machining, Putting together the components, Set-ups done, Packing of orders
Step 2
Identify cost drivers for each activity, i.e. what causes these activity costs to be incurred.
Step 4
Absorb the activity costs into the product.
Number of Components 4 6 20
Per component cost 500 500 500
B Total component cost 2,000 3,000 10,000
Number of setups 3 1 26
Set up cost per set up done 1,000 1,000 1,000
C Total set up cost 3,000 1,000 26,000
Comments
- Under absorption costing technique, all OH were absorbed using machine hours
- Now that we know the break up of costs, we can scientifically apportion costs and then better estimate the
cost per unit
- Under traditional absorption costing method, cost per unit and profit are cal;culated and it might lead us to
conclude that Moon egg is not worth producing
- But, after using ABC which is a more appropriate method, we can conclude that Sun Bar might have to be discont
Using ABC, calculate the full production cost per unit and the profit per unit for each product.
Comment on the implications of the figures calculated.
Cabal makes and sells two products, Plus and Doubleplus. The direct costs of production are $12 for one unit
of Plus and $24 per unit of Doubleplus.
Other overhead costs do not have an identifiable cost driver, and in an ABC system, these overheads
would be recovered on a direct labour hours basis.
Required
Calculate the production cost per unit of Plus and of Doubleplus if the company uses traditional
absorption costing and the overheads are recovered on a direct labour hours basis.
Calculate the production cost per unit of Plus and of Doubleplus if the company uses ABC.
Comment on the reasons for the differences in the production cost per unit between the two methods.
What are the implications for management of using an ABC system instead of an absorption costing system?
Solution
ABC Approach
Plus Doubleplus
Using traditional absorption costing 19.20 34.80
Using ABC 16.33 37.67
Assume the selling prices are 25.00 40.00
Using absorption costing sales margins 23.2% 13.0%
ABC sales margins are 34.7% 5.8%
c) The reasons
driven by labourfor hours
the difference
and, as a in the production
result, cost per unit between the two methods
the Double Plus
i received
By taking1.5
thistimes
into the production
account we endoverhead
up with aofmuch
the Plus.
more
ii accurate
are production
4 special parts foroverhead costPlus
the Double per unit.
compared to only one
iii for the Plus.
As a accurate
This result of allocation
this complexity, the Double
is important Plusthe
because has received more than three times the overhead of the Plus.
production
iv overhead is a large proportion of the overall cost.
uses traditional
It provides a more accurate cost per unit. As a result, pricing, sales strategy, performance management
and decision making should be improved.
ABC recognises that overhead costs are not all related to production and sales volume.
ABC can be applied to all overhead costs, not just production overheads.
In many businesses, overhead costs are a significant proportion of total costs, and management needs to
understand the drivers of overhead costs in order to manage the business properly. Overhead costs
can be controlled by managing cost drivers.
Disadvantages
ABC will be of limited benefit if the overhead costs are primarily volume related or if the overhead
is a small proportion of the overall cost.
ABC can be more complex to explain to the stakeholders of the costing exercise.
The benefits obtained from ABC might not justify the costs. In some situations, ABC does not provide very
different information from traditional absorption costing.
ce management
gement needs to
he overhead
When government introduces austerity measures, there is an increased pressure on the government
- Pressure to deliver more, with lesser resources at disposal
Austerity, a word that characterizes severity or sternness, is used in economics to refer to austerity measures.
These are economic policies implemented by a government to reduce public-sector debt, by significantly curtailing
government spending, particularly when a nation is in jeopardy of defaulting on its bonds.
Public Sector organizations therefore have to be more accurate in identification, allocation and absorption of OH
Public responsibility
Public accountability