Professional Documents
Culture Documents
Michelin Time On Tools Results 2018 Q1
Michelin Time On Tools Results 2018 Q1
Michelin Time On Tools Results 2018 Q1
2018 Q1
Agenda
Background (5 minutes)
Background
Scope
Results
Recommendations
Time on Tools®: Defined
Background
Scope
Results
Recommendations
2 REPORTING PARAMETERS
LOCATION TRADE
Mechanical
TC West TC East
Warehouse Electrical
Soft Trades
Time on Tools®: Overall Results
Background
Scope
Results
Recommendations
External
Historical
This Program
CAP Programs
Background
Scope
Results
Recommendations
• Possible fatigue
consideration with lower
percentage Working Time
after Lunch
Time on Tools®: Stand-By Time
Comparisons
Background
Scope
Results
Recommendations
Best Practice
PRIORITY 1
PRIORITY 2
Time on Tools®: Priority 1 – Waiting
on Equipment
Background
Scope
Results
Recommendations
Historical Comparisons
Comparisons are made with Capital Project Work Program results only.
• Pipe fitting crew had consistent issues with an-lifts not being charged, 150 minutes lost to
equipment breakdown in a single shift.
• HVAC fitting crew had to utilize ladders as sequencing of work prevented the use of man-lifts,
110 minutes of material travel & collection in a single shift.
• Several crews expressed opinions that the issues highlighted above were not isolated
incidents.
• Slightly elevated levels of material travel and collection to be expected because the work required
significant working at height on man-lifts.
Time on Tools®: Priority 1 – Waiting
on Equipment
Background
Scope
Results
Recommendations Recommendation #1: Recommendation #2:
Establish clear responsibility and Increase the focus on sequencing
accountability with each sub-contractor to discussions, to enable crews to utilize the
ensure charging of equipment. most appropriate equipment for their task.
Charging Sequencing
• Communicate clear expectations to
• Ensure equipment access requirements are
workforce that equipment is always fully
considered in work sequencing.
available for use during shift time.
• Assign a team to review the remaining
• Make a person responsible within each
sequence of activities on the project.
sub-contractor for ensuring suitable
arrangements are made each day to
• Consider re-sequencing activities where
charge equipment.
there are potential obstacles to the use of
appropriate equipment (and tools).
• Require reporting on all instances of
insufficient charging.
• Encourage sub-contractors to work with
safety personnel investigating alternate
• Analyze the root causes of all events.
equipment options, where it is not possible
to optimize sequence of work.
• Take action to increase provision of access
to electrical power where necessary.
Time on Tools®: Priority 2 – Waiting
on Materials
Background
Scope
Results
Recommendations
Historical Comparisons
Comparisons are made with Capital Project Work Program results only.
GAP FROM INDUSTRY STANDARD: Category results for this Study Program were:
18 mins / 60 mins x 1300 FTEs x $5 / Hour: 27 mins MORE than Best Practice (at 10 mins)
• Material supply issues were responsible for two significant Coordination Delays.
• Also concern raised regarding out-of-sequence work because of sprinkler heads no being supplied on time.
• Some positive examples of strong 5S behavior, but also areas for improvement:
• Set-in-order – Opportunity – small parts often not well organized and many parts not stored close to
point of work.
• Standardize – Opportunity – minimize in-field preparation by utilizing support staff and non-busy
periods to prepare necessary materials.
• Sustain – Opportunity – build on good start in this area to reduce material travel and collection times.
Time on Tools®: Priority 2 – Waiting
on Materials
Background
Scope
Results
Recommendations Recommendation:
Encourage the use of indoor laydown areas to efficiently store materials close
to the point of work.
5S Incentive Scheme
• We have previously seen a 30% reduction in material collection and travel time as a result
of a 5S incentive scheme at a comparable major manufacturing construction project.
• Actively reward and recognize efficient practices to encourage other contractors to adopt
similar practices.
• Challenge sub-optimal practices (regular long trips for basic materials, poorly arranged
supplies etc.) then follow-up to reward any positive improvements noted.
• Work with sub-contractors to agree the assignment of suitable indoor lay down areas and
best practices for laying out materials.
• Build a culture of ‘no excuses for standing idle’, as if the crew cannot do their current scope
they could be preparing their material needs for future tasks.
Time on Tools®: Priority 3 –
Coordination Delays
Background
Scope
Results
Recommendations
Program Results
Historical Comparisons
Comparisons are made with CAP Work Program results only.
• Major Coordination Delay (>30 minutes) observed in each of the three buildings studied.
• Most significant impacts were in TC720 and Warehouse – least congested areas of
the site.
• Each of these shifts lost over 130 minutes to avoidable Coordination Delays.
• There was limited evidence of crews having contingency plans in place when
their planned scope could not be executed.
Time on Tools®: Priority 3 –
Coordination Delays
Background
Scope
Results
Recommendations Recommendation:
Provide visualization tools to assist coordination planning between crews.
Zone Planning
• Sub-divide management of building into smaller areas (e.g. TC720) and develop a daily plan for
space allocation for crews in that zone.
• Use whiteboard with outline of building, then move counters and mark-up board to represent crew
movements and hand-over points.
• Flag open items that interface with crews working in other zones (e.g. working at height on east
side of wall, will prevent people working underneath on west side of wall).
• Utilize the permitting process as a tool for driving discussion in this area.
• Make priority calls in advance to provide crews with opportunity to change plans.
Time on Tools®: Priority 3 –
Coordination: Example Zone Plan
Background
Scope
Results
Recommendations Outdoor Laydowns
Inspection
10-11am
TC620 TC720 TC820
Potential Clash
Civils need area
Crew from 620
need this space
by 3pm
after 1pm
TC720 Services
Time on Tools®: Room for
Improvement
Background
Scope
Results
Recommendations
• Major factor in above average planning and method work instruction events on those shifts.
Recommendation: Investigate opportunities for pre-fabrication of large diameter metal piping to reduce
installation schedules.
Permit Preparation
• Permitting time was observed to be 9 minutes more thank industry averages (including sites with live
process systems)
• Crews typically had to wait for supervision to arrive with permits before signing on, then often faced
long lines as many were covered on one permit.
Recommendation: Ensure permits are fully ready for execution at the start of shift.
Time on Tools®: Room for
Improvement
Background
Scope
Results
Recommendations
• Travel time significantly reduced effective rest time provided to workers in their break.
Recommendation: Provide access to additional food vendors close to the point of work.
Inspections
• Radiography inspection in UT125 building prevented several crews from working because of 15m
exclusion zone.
• Crews did not appear to be aware that inspection would occur in that area at that time, so had bo
alternate plans.
Recommendation: Schedule major inspections at times when they will not disrupt other work in the
immediate vicinity, or plan around those inspections.
Time on Tools®: Key Recommendations
Background
Scope
Results
Recommendations
Rec Mitigation
Area Recommendation Mitigation Opportunity
# Category
Reduce Waiting on Equipment by 9 min / shift for all
Establish clear responsibility and Sub-contractors must report all instances of Procedural /
crews
1 Equipment accountability with each sub-contractor to electric charge not being available and the Managerial
=
ensure charging of equipment. underlying root cause, to mitigate future issues. Enhancement
$273k / year additional Working Time
Reduce Waiting on Equipment by 5 min / shift for all
Increase the focus on sequencing
Review remaining schedule for sequencing crews
2 Equipment discussions, to enable crews to utilize the Focused Study
conflicts and identify specific mitigations =
most appropriate equipment for their task.
$152k / year additional Working Time
Reduce Waiting on Materials by 11 min / shift for all
Encourage the use of indoor laydown areas to Implement a 5S incentive scheme to reward crews (Previous experience has resulted in 30%
Knowledge
3 Materials efficiently store materials close to the point of positive behavior and flag up strong examples to
Transfer
reduction in events)
work. follow for efficient material storage. =
$334k / year additional Working Time
Coordination
Utilize 'Zone Planning' on a daily basis to agree Procedural / Reduce Coordination time by 23 min / shift for all crews
(Plus Materials Provide visualization tools to assist
4 priority calls and hand-offs between crews working Managerial =
and coordination planning between crews
in each zone of the plant. Enhancement $698k / year additional Working Time
Inspection)
Investigate opportunities for pre-fabrication of Facilitate the set up of well supplied pre- Procedural /
Other
5 Stoppages
large diameter metal piping to reduce fabrication stations, or pre-order large sections of Managerial Reducing schedule duration for installation times.
installation schedules piping as per the BIM designs for the plant. Enhancement
Bring in supervision early, or use their time during
the previous shift, to arrange all permit Reduce Permitting delays by 9 min / shift for all MEP
Procedural /
Ensure permits are fully ready for execution at requirements prior to the arrival of crews on site. crews.
6 Permitting Managerial
the start of shift. Keep size of the group covered by permit =
Enhancement
manageable to facilitate Toolbox talks to promptly $273k / year additional Working Time
brief them on permit details.
Reduce travel at breaks by 6 mins per shift for half the
Provide access to additional food vendors Provide food trucks by the lunch tents for the Logistical workforce
7 Travel
close to the point of work. Utilities and TC buildings. Enhancement =
$105k / year additional Working Time.
Reduce Inspection delays by 3 mins per shift for Utilities
Schedule radiography (and similarly disruptive) Procedural /
Review arrangements for scheduling major workforce (congested areas)
8 Inspections inspections out of hours, or pre-plan other scopes Managerial
inspections =
for crews working in the effect area. Enhancement
$28k / year additional Working Time.
Time on Tools®: Next Steps
Background
Scope
Results
Recommendations
Target
working time
REQUIRED INCREASE IN
WORKING TIME
=
61% 61 MINUTES PER SHIFT
Background
Scope
Results
Recommendations
@fgouldconnect
Faithful+Gould