Medium Density Fiberboard (MDF) Project

Level I Master Schedule


Activity Name Start Finish 2020 2021 2022
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun JulAug
-7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
MEDIUM DENSITY FIBERBOARD SCHEDULE01-Jan-20
Level I 07-Jun-22 MEDIUM DENSITY FIBERBOARD SCHEDULE Level I
Milestones 01-Jan-20 07-Jun-22 Milestones
General 01-Jan-20 07-Jun-22 General
Point A (Down Payment to SK) 16-Feb-20* Point A (Down Payment to SK)
Point B (L/C + 30D MAX) 07-Jun-20* Point B (L/C + 30D MAX)
MDF MOU 15-Apr-20* MDF MOU
PDMI MOU 23-Apr-20* PDMI MOU
FeedStock MOU 16-Jun-20* FeedStock MOU
Effective Date 07-Jul-20* Effective Date
WORK & Site Early Work Start 01-Jan-20 WORK & Site Early Work Start
Land Agreement 01-Oct-20* Land Agreement
TCF Finished 07-Dec-20* TCF Finished
Project Tie-ins 07-Oct-21* Project Tie-ins
Figure Garantee of Primary PTJ Mechnanical Completion 07-Dec-21* Figure Garantee of Primary PTJ Mechnanical Com

Feed Stock Available and Row Materials 07-Jan-22* Feed Stock Available and Row Materials
Ready For Start Up & 1st Board 21-Feb-22* Ready For Start Up & 1st Board
Start of 3 Shift Operation 09-May-22* Start of 3 Shift Operation
Provisional Acceptance Certificate(Siemplkamp) 07-Jun-22* Provisional Accepta
Provisional Acceptance Certificate (Petrojet) 07-Jun-22* Provisional Accepta
Permits 16-Feb-20 08-May-22 Permits
Main Permits Obtained 07-Dec-20 Main Permits Obtained
Other Permits 16-Feb-20* 08-May-22
Tie-Ins 07-Sep-21 07-Sep-21 Tie-Ins
Interconnecing Piping - OSBL for Water Sources 07-Sep-21* Interconnecing Piping - OSBL for Water Sources
Interconnecing Piping - OSBL for Waste Collection Points 07-Sep-21* Interconnecing Piping - OSBL for Waste Collection Points

Interconnecing Cables (Power & Telecomm.) to Governmental 07-Sep-21* Interconnecing Cables (Power & Telecomm.) to Governmental M
MV Transformer
Professional Services 01-Sep-20 27-Jul-21 Professional Services
Engineering 01-Sep-20 27-Jul-21 Engineering
(S.K.) 3D-Model (completed 90%) 07-May-21* (S.K.) 3D-Model (completed 90%)
Governmental Industrial Water Source Engineering Inputs (by 01-Sep-20* Governmental Industrial Water Source Engineering Inputs (by WOTECH)
WOTECH)
Governmental Potable Water Source Engineering Inputs (by 01-Sep-20* Governmental Potable Water Source Engineering Inputs (by WOTECH)
WOTECH)
Governmental Power Source Engineering Inputs (by 07-Oct-20* Governmental Power Source Engineering Inputs (by WOTECH)
WOTECH)
Governmental Telecome. Source Engineering Inputs (by WOTECH) 01-Oct-20* Governmental Telecome. Source Engineering Inputs (by WOTECH)

Governmental Waste Collection Point (Sewage) Engineering 09-Dec-20* Governmental Waste Collection Point (Sewage) Engineering Inputs (by WOTECH)
Inputs (by WOTECH)
End of Siemplkamp Engineering 07-Jun-21* End of Siemplkamp Engineering

Actual Work Critical Remaining Work Summary Date Revision Checked Approved
Planning & Project Control Team 07-Jul-2020 Rev.A Eng Samir Refaat
Remaining Work Milestone
Medium Density Fiberboard (MDF) Project
Level I Master Schedule
Activity Name Start Finish 2020 2021 2022
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun JulAug
-7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
End of Petrojet Engineering 27-Jul-21 End of Petrojet Engineering
Material Supply 07-Mar-21 07-Mar-22 Material Supply
Start of ISBL (SK SOW) Delivery 07-Mar-21* Start of ISBL (SK SOW) Delivery
End of of ISBL (SK SOW) Delivery 06-Jun-21* End of of ISBL (SK SOW) Delivery
End of Petrojet Supply Scope 07-Mar-22 End of Petrojet Supply Scope
Construction 21-May-21 07-Jun-22 Construction
Start of SK SOW Supervision 21-May-21* Start of SK SOW Supervision
Utilities Available 07-Nov-21* Utilities Available
Primary PTJ Mechanical Completion related to S.K. 07-Nov-21* Primary PTJ Mechanical Completion related to S.K.
Mechanical Completion (SK SOW) & Start of pre-commission 07-Dec-21* Mechanical Completion (SK SOW) & Start of pre
without FeedStock
Ready for Commissioning (with Feedstock) 21-Jan-22* Ready for Commissioning (with Feedstock
Finish for commssioning (With FeedStock) 21-Mar-22* Finish for commssioning (With F
Mechanical Completion OSBL (Petrojet SOW) 07-May-22* Mechanical Completion O
Finish of OSBL Commissioning (Petrojet SOW) 07-Jun-22* Finish of OSBL Com
CONSTRUCTION, COMMISSIONING & START UP 07-Jul-20 07-Jun-22 CONSTRUCTION, COMMISSIONING & START UP
Construction Works related to SK SOW (OSBL) 07-Jul-20 07-Nov-21
Commissioning for Figures Garantee of PTJ Primary Scope 08-Nov-21 07-Dec-21
related to S.K.
ISBL Precommissioning Without feedstock 08-Dec-21 20-Jan-22
Commissioning With feedstock 22-Jan-22 21-Mar-22
Construction and commsioning work (OSBL) not related to SK 07-Jul-20 07-May-22
SOW
Start-up, Performance Tuning & Test 21-Feb-22 07-Jun-22

Actual Work Critical Remaining Work Summary Date Revision Checked Approved
Planning & Project Control Team 07-Jul-2020 Rev.A Eng Samir Refaat
Remaining Work Milestone