JSA 06-Rev.01 - Dismantling of Scaffolding
JSA 06-Rev.01 - Dismantling of Scaffolding
Obstruction to movement in work area Do not use scaffolding braces for climbing up,
use ladders
Gloves with good grip must be used while
climbing.
Use PPE'S required.
Standard lifting procedure to be used for
lifting objects.
No person to be allowed to stand under the
1 Removal of scaffolding Struck (injury) by falling objects
weight which is to be lifted
If scaffolding erecting is above normal
walkways, use safety net
Injury due to Fall (Slip/trip) from the work
Use Full body Harness
location
Ensure proper tightening of bolts and nuts
and follow sequence of erection and
dismantling.
Nobody should be allowed to work in
Injury due to sudden collapse of incomplete scaffold.
incomplete scaffolding
All scaffolds should be checked and certified
by the competent authorities.
All scaffolds should carry status boards
Use trolley for shifting the Scaffolding
material. Do not use bare hands For shifting
scaffolding material to height
Use rope and pulley arrangement with
Injury due to improper handling
Shifting of scaffolding sufficient manning and barricading; tie rods
2 properly to avoid slips.
material
Materials to be kept at one location away from
walking area. Area to be barricaded.
Injury due to improper stacking of Scaffolding erected should not block identified
scaffolding materials. Escape routes of the Plant/Work location.
Use correct tools.
3 All sub activities ( 1 ) Physical Injury while working
Use mandatory PPEs.
Note:
JSA to be done by issuer and accepter of work permit, in case required, representative from other discipline can also join the team for JSA