126 - Hes-001-2023 - Greatwall Gardens 6 - Works Report - 11TH February 2024

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 20

126 - HES-001-2023–GREAT WALL GARDENS 6

WORKS REPORT

13th February 2024.

HES-001-2023

PROPOSED RESIDENTIAL APARTMENTS

ATHI RIVER, MACHAKOS COUNTY

FOR

ERDEMANN PROPERTY LIMITED


TYPICAL BLOCK A
Backfilling of the ground beams was done.

Backfilling of the ground beams in progress.

Challenges
None
TYPICAL BLOCK B
Shuttering of the ground beams was done.

Ground beam shuttering ongoing.

Challenges
None
TYPICAL BLOCK C
No activity was done, awaiting steel fixing of the shear walls.

No activity ongoing.
Challenges
None
TYPICAL BLOCK D
No activity was done, awaiting shuttering of the bases and rafts.

No activity ongoing.

Challenges
None
TYPICAL BLOCK E
Setting out of shear wall positions on the bases and rafts was done.

Setting out of shear wall positions on the bases


and rafts in progress.
Challenges
None
TYPICAL BLOCK F
No activity was done, awaiting shuttering of the bases and rafts.

No activity ongoing.
Challenges
None
TYPICAL BLOCK G
No activity was done, awaiting shuttering of the bases and raft.

No activity ongoing.
Challenges
None
TYPICAL BLOCK H
No activity was done, awaiting shuttering of the bases and rafts.

No activity ongoing.
Challenges
None
TYPICAL BLOCK J
No activity was done, awaiting shuttering of the shear walls.

No activity ongoing.
Challenges
None
SHOP BLOCK K
No activity ongoing, awaiting backfilling of the foundation.

No activity ongoing.
Challenges
None
SHOP BLOCK L
De-shuttering of the shear walls in progress.

De-shuttering of the shear walls in progress.

Challenges
None
SHOP BLOCK M
Preparation of the bases and rafts for blinding was done.

Preparation of the bases and rafts for


blinding in progress.

Challenges
None
SHOP BLOCK N
No activity was done.

No activity ongoing.
Challenges
None
SHOP BLOCK P
No activity ongoing, awaiting debris clearance.

No activity ongoing.
Challenges
None
SHOP BLOCK Q
No activity was done.

No activity in progress.

Challenges
None
SHOP BLOCK R
No activity was done, awaiting steel fixing of the bases and rafts.

No activity ongoing.
Challenges
None
SHOP BLOCK S
No activity was done, awaiting casting of the bases and rafts.

No activity ongoing.
Challenges
None
WASTEWATER TANK
Hard rock breaking of the foundation was done.

Hard rock breaking of the foundation in progress.


Challenges
None
WEATHER
It was calm and sunny throughout the day. Construction activities continued smoothly
throughout the day.

SITE SAFETY.
Site safety measures were observed.
The organization of the site was OK.

ACCIDENTS AND INCIDENCES


No accident was reported.