Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 46

Page 1 of 46

Payment Advice Annexure -I


Name of the Project: PARK HOSPITAL

Summary of Bill ( 14th RA Bill)


Name Of Contractor
M/S S.M. Nirman Infrastructure& Development Pvt.Ltd.
PAN No. AAMCS 5931M
WBST/CST/VAT No.
P.F No.
WB/CA/54477
GST No.
19AAMCS5931M1ZM
Bill To
PARK HOSPITALS-2, RAWDON STREET, KOLKTATA -700017.

Work Order No. & Date PH/NT/EXT/WO/007/2022-23 DATED-11.02.2023


Particulars of Work CIVIL WORK-Sub & Super structural work for proposed extention
building at New town, Kolktata :- 700156.
Actual Value of Work Order Rs. 10,62,59,094.00
Variation,If any (Ref No….) Rs.
Total Value of Work Order Rs.
Schedule of Completion
Actual Date of Completion
Liquidated Damages to be Deducted (Give reason for non-deduction) No
MEMORANDUM OF PAYMENT

Gross Total Bill Value Rs. #NAME?


Rebate, If Any Rs. N.A.
Amount after Rebate Rs. #NAME?
Less:Bill Value upto previous R/A Rs. #NAME?
Gross Value of Present Bill Rs. #NAME?
Add: GST @ 18% Rs. #NAME?
Gross Bill value of Present Bill including GST Rs. #NAME?
Less : Advance to be deducted (Against steel PI, SMN/PI/23-24/073)
dated 3rd January-24 Rs. -2,100,000.00
Less : Advanced payment Rs. 0.00
Less : Retaintion Mony 2.5 % Amount if Any Rs. #NAME?
Less : Other Amount if Any (Please Specify) Rs. 0.00
Less:Deduction towards supply of Material (refer reconciliation statement) Rs. 0.00
Less: Deduction for Electrical Charges (Unit 690…….rate…8.5…………) Rs. -5,865.00
Less: Deduction or Hold Amount (please specify) Rs. 0.00
R/O Rs. 0.00
Net Payable against Present Bill Rs. #NAME?
* (All deductions/payments - statutory & others as per/ against Work Order will be made by Accounts Department)

________________________ ;

(Signature of Contarctor with date & seal) Date : 19/02/2024


____________________________
__________________________ _

(Signature EIC) (Signature of Site EIC) Approved By Project - in - charge


Date : Date : Date:
PROJECT -:PARK HOSPITAL
2,Rawdon street, kolkata -700017 ABSTRACT SHEET
Project : Work Order no. Date : Name of the Contractor Bill Date
NBW&CCC
PH/NT/EXT/WO/007/2022-2023 11.02.2023

Item As per BOQ Cummulative Total


SL No. Description of work UOM Rate
Code QTY Amt. Rs. QTY Amt. Rs. Balance Quantity Upto GF Slab
A 2 SITE DEVELOPMENT AND EARTH WORK
3.1 9 Depth upto 1.5 m. CUM 150 2,175 326,250 1,644.153 246,623.00 230.847

3.2 10 For additional depth beyond 1.5 m. and upto 3.00 m. CUM 165 1,800 297,000 1,311.288 216,362.48 388.7123
3.3 11 For additional depth beyond 3.00 m. CUM 190 2,900 551,000 967.986 183,917.38 1,732.014
12 0
5.0 16 Supply, fitting & fixing of Sheet pile work with profile sheet having size 12m MT 60,500 225 13,612,500 88.796 5,372,161.02 133.20395
(+/-200mm) long 0.60m wide U shape & ISMB 300-12m long for weller,
bracing etc. along with ISA75x75x6mm, 65x65x6mm including King post
@6.0M C/C, weller etc. including cost of transportation, loading, unloading,
necessary welding, removing of materials after completion of RCC retaining
wall etc. all complete as per drawing design & direction of EIC. (Note:
Necessary shop drawing is required to be submited for prior approval of
employer before starting of shoring work). SHEET PILE WORKS

6.0 17 Back filling with approved good quality excavated earth beyond retaining CUM 110 1,300 143,000 1,177.171 129,488.85 0
wall/side wall, area development etc. wherever specified in layers not
exceeding 500 mm thick including breaking clods, watering, compacting each
layer with vibratory compactor and at unaccessible places with wooden/steel
rammers to achieve 90 to 95% proctor density at optimum moisture content,
with all leads and lifts, bailing/ pumping out of water to keep site dry while
backfilling; Cost shall include conveyance of all materials, labour, machinery
etc. complete as directed. Note : Rate Quoted is for compacted soil and no
bulkage will be considered for payment.

7.0 18 Supplying & filling silver sand inside basement with specified in layer not CUM 1,750 850 1,487,500 178.219 311,882.58 Silver sand will use further road work and
exceeding 200mm thick including watering, compating with mechanical etc.
devices etc. all complete as per direction of EIC.
PROJECT -:PARK HOSPITAL
2,Rawdon street, kolkata -700017 ABSTRACT SHEET
Project : Work Order no. Date : Name of the Contractor Bill Date
NBW&CCC
PH/NT/EXT/WO/007/2022-2023 11.02.2023

Item As per BOQ Cummulative Total


SL No. Description of work UOM Rate
Code QTY Amt. Rs. QTY Amt. Rs. Balance Quantity Upto GF Slab
8.0 19 Providing and laying in position single layer 75mm thick Brick Flat soling by SQM 470 100 47,000 53.821 25,295.99 0
picked Jhama brick with sand cushion of 50mm thick including the cost of sand
cushion, base preparation by compaction, filling the joints with sand etc.

9.0 20 SHORING WORK 0

21 Hire and labour charges for shoring work(including necessary close plank 0
walling.Farming piling. strutting etc.) complete as per direction of the Engineer
-in-charge for foundation excavation .(Vertical surface area in contact with
supported earth is to be measured .) (This item should be executed on specific
direction of the Engineer-in-charge.)

9.1 22 Depth upto 1.5 m. SQM 6,500 40 260,000 38.670 251,355.00 1.33

10.0 23 DISMANTLING OF PILE HEAD 0

24 Dismantling of pile head upto cut-off level (50mm above cut-off level) 0
including proper positioning of pile reinforcement, necessary built up if extra
pile length dismantled beyond cut-off level, cost of Lifting, shifting & removing
of concrete bolder /rubbish from site etc. all complete as per direction of EIC
(Note: location for dumping of boulder/ rubbish anywhere i.e. out side our
premises, will be decided by the contractor at thier own risk & cost).

10.1 25 PILE:450 MM DIA RM 725 50 36,250 50.000 36,250.00 0.000


10.2 26 PILE:500 MM DIA RM 875 200 175,000 301.750 264,031.25 -101.750
0
B 28 CONCRETE WORK (PLAIN AND RCC) 0
11.0 30 Providing and laying P.C.C. 1:4:8 of specified thickness as per drawing CUM 6,450 41 264,450 0.00 41.000
wherever specified using medium coarse river sand, 40mm and down size
metal including sub grade preparation,leveling, all leads and lifts,rough
finishing at the top surface,proper curing and shuttering if necessary etc. all
complete as per drawing & instruction of EIC.

12.0 32 Providing and laying P.C.C. 1:3:6 / RMC M-10 of specified thickness wherever CUM 6,650 117 778,050 117.646 782,346.94 -0.646
specified using medium coarse river sand, 20mm and downsize metal
including base preperation, Compaction, levelling, all leads and lifts, proper
curing and shuttering if necessary etc., Complete in all respect as per the
instruction EIC.

13.0 34 READY MIX CONCRETE 0


35 NOTE: 0
13.1 39 M35 Up to & including deck slab (Ground floor slab) CUM 7,871 1,040 8,185,840 662.478 5,214,368.27 292.5215
13.2 40 M30 FOR U.G.W.R. CUM 7,766 150 1,164,900 82.782 642,885.01 52.218
13.3 41 M35 above deck to 3rd floor lev. CUM 7,871 430 3,384,530 0.00
13.4 42 M30 deck up to 3rd floor lev. CUM 7,816 250 1,954,000 187.354 1,464,357.01
13.5 43 M30 above 3rd to 6th floor lev. CUM 7,866 586 4,609,476 0.000 0.00
13.6 44 M30 above 6th to Roof lev.+Above roof CUM 7,916 710 5,620,360 0.000 0.00
13.7 45 M25 for lintel & chajja CUM 7,910 105 830,550 20.232 160,035.12
13.8 46 M25 for Footing, base of Column, Plinth Beam (for boundary wall) CUM 8,110 112 908,320 112.000 908,322.94
13.9 47 M25 for Column (for boundary wall) CUM 8,110 15 121,650 10.204 82,755.29
PROJECT -:PARK HOSPITAL
2,Rawdon street, kolkata -700017 ABSTRACT SHEET
Project : Work Order no. Date : Name of the Contractor Bill Date
NBW&CCC
PH/NT/EXT/WO/007/2022-2023 11.02.2023

Item As per BOQ Cummulative Total


SL No. Description of work UOM Rate
Code QTY Amt. Rs. QTY Amt. Rs. Balance Quantity Upto GF Slab
14.0 49 Centering and shuttering 0
14.1 52 Up to & including deck slab + U.G.W.R. SQM 525 5,000 2,625,000 3,184.061 1,671,632.04 1,515.939
14.2 53 Above Deck to 3rd floor lev. SQM 550 4,710 2,590,500 580.223 319,122.43
14.3 54 Above 3rd to 6th floor lev. SQM 560 4,015 2,248,400 0.000 0.00
14.4 55 Above 6th to Roof lev.+Above roof SQM 575 5,020 2,886,500 0.000 0.00
14.5 56 For Lintel & Chajja SQM 650 1,500 975,000 0.000 0.00
14.6 57 Footing, Plinth Beam (for boundary wall) SQM 550 250 137,500 414.862 228,174.37
14.7 58 Column (for boundary wall) SQM 575 100 57,500 0.000 0.00
59 0 0.000
15.0 60 Reinforcement Steel 0 0.000
15.1 64 Up to & including deck slab + U.G.W.R. (Fe 500) MT 69,983 135 9,447,705 108.581 7,598,853.65 22.419
15.2 65 Above Deck to 3rd floor lev. (Fe 500) MT 69,983 90 6,298,470 30.021 2,100,959.64
15.3 66 Above 3rd to 6th floor lev. (Fe 500) MT 70,983 83 5,891,589 0.000 0.00
15.4 67 Above 6th to Roof lev.+Above roof. (Fe 500) MT 71,483 100 7,148,300 0.000 0.00
15.5 68 For Lintel & Chajja. (Fe 500) MT 73,983 12 887,796 0.000 0.00
15.6 69 For Boundary Wall (Fe 500) MT 73,983 1 73,983 0.000 0.00
70 0 0.000 0.00
Total Amount 86,025,869.00 28,211,180.28
PROJECT -:PARK HOSPITAL
2,Rawdon street, kolkata -700017
Project : Work Order no. Date : Name of the Contractor Bill No. Bill Date
NBW&CCC
M/S S.M. Nirman Infrastructure
PH/NT/EXT/WO/007/2022-2023 11.02.2023 RA-14 08.03.2024
& Development Pvt.Ltd.
Item As per BOQ Infrastructure Work Admin Block Main Building Cummulative Total
SL No. Description of work UOM Rate
Code QTY QTY QTY QTY QTY
A 2 SITE DEVELOPMENT AND EARTH WORK
1.0 3 Surface dressing of the ground including SQM 55 1,410 1410.000 1,410.000
removing vegetation and inequalities not
exceeding 15 cm deep and disposal of
rubbish, lead upto 50 m and lift upto 1.5 m
for all kinds of soil

2.0 4 Removal of specific coloured, chamfered SQM 65 520 356.040 356.040


edge Cement Concrete paver blocks over
sand bed and stacking of paver blocks as per
size/shape and pattern, in the designated
area restoring from footpath, parks, lawns,
drive ways or light traffic parking etc.
complete as per direction of Engineer in
3.1 9 Charge.
Depth upto 1.5 m. CUM 150 2,175 169.140 338.916 1136.097 1,644.153

3.2 10 For additional depth beyond 1.5 m. and upto CUM 165 1,800 198.496 1112.792 1,311.288
3.00 m.
3.3 11 For additional depth beyond 3.00 m. CUM 190 2,900 967.986 967.986

4.1 13 Supply & Fixing of color coated galvalum SQM 950 240 239.867 239.867
sheet .5 mm thick (Make TATA/ JSW) over
Fencing including all labour, machineries
tools tackles screws etc. Complete as
required for fixing.
4.2 14 Supply, transportation, fabrication, Painting, KG 125 65 52.990 52.990
Erection, alignment & welding of 6mm thick
MS Plate.
4.3 15 Supply, transportation, fabrication, Painting, KG 125 560 1773.979 1,773.979
Erection, alignment & welding of SHS-
50X50X2.9 mm Main Vertical Post. (Spacing
3.5 M) (Unit Wt 4.12Kg/m)

5.0 16 SHEET PILE WORKS MT 60,500 225 88.796 88.796

6.0 17 Earth Back filling with approved CUM 110 1,300 107.668 209.30875 860.194 1,177.171
good quality
7.0 18 Supplying & filling silver sand CUM 1,750 850 12.201 166.018 178.219
8.0 19 Providing and laying in position single layer SQM 470 100 53.821 53.821
75mm thick Brick Flat soling by picked Jhama
brick with sand cushion of 50mm thick
including the cost of sand cushion, base
preparation by compaction, filling the joints
with sand etc.

9.0 20 SHORING WORK


9.1 22 Depth upto 1.5 m. SQM 6,500 40 38.670 38.670
10.0 23 DISMANTLING OF PILE HEAD 0.000
10.1 25 PILE:450 MM DIA RM 725 50 50.000 50.000
10.2 26 PILE:500 MM DIA RM 875 200 58.7 243.050 301.750
B 28 CONCRETE WORK (PLAIN AND RCC) 0.000
11.0 30 Providing and laying P.C.C. 1:4:8 of specified CUM 6,450 41 0.000
thickness as per drawing wherever specified
using medium coarse river sand, 40mm and
down size metal including sub grade
preparation,leveling, all leads and lifts,rough
finishing at the top surface,proper curing and
shuttering if necessary etc. all complete as
per drawing & instruction of EIC.

12.0 32 Providing and laying P.C.C. 1:3:6 / RMC M-10 CUM 6,650 117 15.187 27.834 74.625 117.646
of specified thickness wherever specified
using medium coarse river sand, 20mm and
downsize metal including base preperation,
Compaction, levelling, all leads and lifts,
proper curing and shuttering if necessary etc.,
Complete in all respect as per the instruction
EIC.

13.0 34 READY MIX CONCRETE


13.1 39 M35 Up to & including deck slab (Ground CUM 7,871 1,040 425.795 425.795
floor slab)
13.2 40 M30 FOR U.G.W.R. CUM 7,766 150 0.000 0.000
13.3 41 M35 above deck to 3rd floor lev. CUM 7,871 430 236.683 236.683
13.4 42 M30 deck up to 3rd floor lev. CUM 7,816 250 270.136 270.136
13.5 43 M30 above 3rd to 6th floor lev. CUM 7,866 586 0.000
13.6 44 M30 above 6th to Roof lev.+Above roof CUM 7,916 710 0.000
13.7 45 M25 for lintel & chajja CUM 7,910 105 0.000
13.8 46 M25 for Footing, base of Column, Plinth CUM 8,110 112 59.765 52.235 112.000
Beam (for boundary wall)
13.9 47 M25 for Column (for boundary wall) CUM 8,110 15 0.000
0.000
14.0 49 Centering and shuttering 0.000
14.1 52 Up to & including deck slab + U.G.W.R. SQM 525 5,000 1610.6178 2529.154 4,139.772
14.2 53 Above Deck to 3rd floor lev. SQM 550 4,710 580.2226 580.223
14.3 54 Above 3rd to 6th floor lev. SQM 560 4,015 0.000
14.4 55 Above 6th to Roof lev.+Above roof SQM 575 5,020 0.000
14.5 56 For Lintel & Chajja SQM 650 1,500 0.000
14.6 57 Footing, Plinth Beam (for boundary wall) SQM 550 250 414.862 414.862

14.7 58 Column (for boundary wall) SQM 575 100 0.000


59 0.000
15.0 60 Reinforcement Steel 0.000
15.1 64 Up to & including deck slab + U.G.W.R. (Fe MT 69,983 135 4.571 40.077 84.119 128.767
500)
15.2 65 Above Deck to 3rd floor lev. (Fe 500) MT 69,983 90 9.835 9.835
15.3 66 Above 3rd to 6th floor lev. (Fe 500) MT 70,983 83 0.000
15.4 67 Above 6th to Roof lev.+Above roof. (Fe 500) MT 71,483 100 0.000

15.5 68 For Lintel & Chajja. (Fe 500) MT 73,983 12 0.000


15.6 69 For Boundary Wall (Fe 500) MT 73,983 1 0.000
70 0.000
16.0 71 Re-bar Grouting 0.000
16.1 73 8 T Bar NOS 125 2,700 26.000 122.000 148.000
16.2 74 10 T Bar NOS 150 1,300 86.000 12.000 98.000
16.3 75 12 T Bar NOS 210 2,000 204.000 204.000
16.4 76 16 T Bar NOS 300 2,000 184.000 184.000
16.5 77 20 T Bar NOS 400 60 23.000 23.000
16.6 78 25 T Bar NOS 525 20 10.000 10.000
C 80 MASONRY WORK 0.000
17.0 82 Brick work in foundation
17.1 83 To cost of Brick masonry work in foundation
to plinth CUM 7,000 34 18.072 3.056 14.768 35.896

18.0 84 Brick work in superstructure


18.1 86 200/ 250mm thick Brick work with 1:6 Cum 7,300 133 0.000
cement sand Mortar (1cement : 6 Medium
coarse sand)

18.2 87 125mm thick Brick work with 1:4 cement SQM 1,050 RO #NAME? #NAME?
sand Mortar (1cement : 4 Medium coarse
sand)

19.0 88 AAC Block work with specified Adhesive 0.000

19.1 90 100 mm/ 150mm thick CUM 6,880 660 0.000


19.2 91 200 mm thick CUM 6,680 300 0.000
19.3 92 250 mm thick CUM 6,680 200 0.000
19.4 93 100mm thick for external elevation work CUM 7,080 182 0.000

D 97 PLASTERING & POINTING WORK:- 0.000


20.0 99 Internal Wall plaster 0.000
20.1 100 Providing and applying 12-15 mm thick SQM 265 3,500 57.620 158.0725 215.693

21.0 101 External Wall plaster


21.1 102 Providing and applying 20 mm thick plaster in SQM 320 4,100 114.385 114.385
two layers (1st layer 12mm thick 1:4

22.0 103 Ceiling plaster


22.1 104 Providing and applying 6-8mm thick plaster to SQM 250 400 18.860 18.860
RCC slab in cement mortar 1:4 (1 cement : 4
medium coarse sand ) finished smooth
including hacking the surfaces, scaffolding,
curing, making grooves at desired location
etc. complete as per drawing.

23.0 105 Providing and fixing Nylon mesh of size 12mm SQM 125 270 0.000
x22 at the junction of disimilar surfaces of
brick masonry wall, Corner of Walls and R C C
column by beams and the like including
necessary nails for fixing etc, complete all as
per specification and direction of Engineer -in
-charge for all floor at all heights.

E 108 STEEL WORKS


109 (Quoted Rates are for all heights, depths,
levels, leads and lifts)
24.0 110 Steel work
24.1 112 With Mild steel KG 153 3,700 0.000

F 116 MISCELLANEOUS WORKS


25.0 117 RCC Flooring
25.1 118 Reinforced cement concrete flooring CUM 7,723 25 0.000
(thickness 50mm to 150mm) using M25
grade concrete including the cost of side
shuttering with MS channels, vibrating,
curing, Cutting of VDF floor 100-150mm thick
with Diamond Saw System and filling the
same but reinforcement steel includes
straightening, cutting, bending, fabricating,
and placing in position, at all levels including
lead and lift, according to drawings,
specifications etc. complete. (RMC & Steel of
standard specification, duly approved by
EIC,PM, consulant shall be Supplied by the
vendor ) Reinforcement Steel will be paid
seperately.

26.0 119 Vaccum dewatering 0.000


26.1 120 Extra for vaccum de-watered flooring SQM 150 350 0.000
operation consisting of providing side
shuttering with MS channels, angles to the
required levels, vibrating the concrete by
using screed vibrator, de-watering using
vacuum pumps by suction method and
finishing the top surface to required level and
grade using skim floaters / discs / power
trowels. Covering the finished concrete
surface with 200 micron thick polythene
sheet and curing, etc., complete

27.0 121 8mm wide 20 mm deep groove in flooring RM 125 100 0.000
surface and fill with silicon complete as per
design & drawing.

28.1 123 40 mm thick (average) SQM 425 1,650 0.000


124 0.000
29.0 125 Puddle flanges 0.000
29.1 127 75mm dia NOS 2,125 14 3 2.000 5.000
29.2 128 100 mm dia NOS 3,645 9 0.000 0.000
29.3 129 150 mm dia NOS 8,200 1 1.000 1.000
29.4 130 200 mm dia NOS 10,600 2 3.000 3.000
30.0 132 Conduits 0.000
30.1 134 25 mm RM 140 0 0.000
30.2 135 32 mm RM 170 0 0.000
30.3 136 40 mm RM 207 0 0.000
30.4 137 50 mm RM 250 0 0.000
31.0 138 Core Cutting 0.000
31.1 140 RCC Slabs 0.000
31.1.1 141 100mm dia & upto 200mm depth NOS 500 25 0.000
31.1.2 142 150mm dia & upto 200mm depth NOS 650 35 0.000
31.1.3 143 200mm dia upto 200mm depth NOS 750 30 0.000
31.2 144 RCC Beams 0.000
31.2.1 145 65mm dia & depth upto 350mm NOS 750 10 0.000
31.2.2 146 160mm dia & deoth upto 350mm NOS 950 10 0.000
31.2.3 147 180mm dia & depth upto 350mm NOS 1,150 10 0.000
31.3 148 RCC Walls 0 0.000
31.3.1 149 65mm dia. & depth upto 350mm NOS 700 20 11.000 11.000
31.3.2 150 160mm dia & depth upto 350mm NOS 900 10 10.000 10.000
31.3.3 151 180mm dia & depth upto 350mm NOS 1,100 10 7.000 7.000
32.0 152 Scaffolding 0.000
32.1 153 Providing and fixing steel scaffolding including PER SQM 6,300 0.000
working platform on exclusive demand by the PER DAY
client to be used by other agency. However
vender to allow other agency to use
scaffolding already erected for their own
work without any charge.

33 155 Providing & packing with Polyurithine Foam 0.000


between top layer of AAC block and RCC
beam in any height & any level as per the
instruction & direction of EIC

33.1 156 a) 100mm th. Wall RM 55 710 0.000


33.2 157 b) 200mm th. Wall RM 95 2,050 0.000
33.3 158 c) 250mm. Th. Wall RM 115 255 0.000
34.0 159 Supply & fixing of Reinforce pvc foot rest NOS 325 140 0.000
(180mm.x260mm) as per drawing with
proper line & level
35.0 160 Providing and filling sunken portion of Toilet CUM 6,040 76 0.000
Slabs etc. with AAC Block with Cement
mortar of 1:6 (1 Cement : 6 sand ) Including
cleaning the surface and laid to proper
Gradient.

36.0 161 Dismantling of AAC block work along with CUM 1,850 50 0.000
Plaster & RCC band of all thickness &
including shifting of Rubbish any level to
ground floor & disposal of rabish from site
within 5km distance including necessary
permission to be taken from local authority &
no extra payment to be made for the same.

37.0 162 Dismantling of brick work of all thickness CUM 1,850 18 5.155 40.507 45.662
along with plaster & including shifting,
disposal of Rubbish within 5km distance.

38.0 163 Supply & fixing of Green of Green shade Net SQM 85 21 0.000 0.000
including necessary supporting system, at any
level ec. All complete as per site requirement
& direction of EIC

39.0 164 Fitting & Fixing of DI drain Gratings & grating NOS 1,050 107 0.000
channel having of capacity 12MT including
necessary two coats of synthetic paint of
approved shade & make over one coat of
suitable Primer all complete as per drawing &
direction of EIC.

40.0 165 Supply, Fitting & fixing of Fixing of DI Tank 0.000


man hole Cover at proper line & level
including necessary two coats of synthetic
anemel paint of approved shade & make over
one coat of suitable primer all complete as
per drawing & direction of EIC.

40.1 166 Cover size 600x 600 capacity 35MT for UGR NOS 8,500 8 0.000

40.2 167 Cover size 600x 600 capacity 5MT for OHT NOS 7,550 6 0.000

41.0 168 Providing & making 75-100mm wide & 10mm R/MT 120 1,133 0.000
thick Plaster band on window sill, jamb &
soffit with cement mortar of proportion 1:6 in
proper line & level including 7days curing etc.
in any floor & any level all cpmplete as per
direction of EIC. (Cement of specific standard
required for the job will be prpovided by
vendor)

42.0 169 Providing & making 30x10mm thick drip R/MT 95 320 0.000
course with cement sand mortar of
proportion 1:6 in proper line & level on
window soffit including necesary stagging
7days curing etc. all cpmplete for any floor &
any level as per direction of EIC. (Cement of
specific standard required for the job will be
prpovided by vendor)

43.0 170 Supply & fixing of MS Insert Plate with proper KG 150 200 0.000
line & level on wall Beam, slab wherever
required at any level as per drawing, design &
instructgion of EIC.

44.0 171 Providing & making of RCC 1:2:4 for Vertial CUM 7,450 70 0.000
& Horizontal RCC Band in AAC block work at
any level incljuding cost of all materials,
labour tools tackle all complete as per
drawing and instruction of EIC.

45.0 172 Supply, cutting, bending binding of MT. 72,850 6 0.000


Reinforcement work for Vertial & Horizontal
Band in AAC block work at any level all
complete as per drawing & direction of EIC.
46.0 173 Providing & making shuttering work for SQM 550 875 0.000
Vertial & Horizontal Band in AAC block work
at any level all complete as per drawing &
direction of EIC.

47.0 174 Supply & fixing of MS Pipe sleeve in floor 0.000


beams for taking fire/ other pipes in beams at
any level including one coat of red oxide
primer etc. all complete as per drawing &
direction of PIC.

47.1 175 200mm dia 300mm long NOS 1,650 50 0.000


47.2 176 100mm dia 300mm long NOS 800 50 0.000
47.3 177 50mm dia 300mm long NOS 350 100 0.000
48.1 179 Dismantling of RCC wall, Slab, Beam etc. by CUM 5,500 150 7.227 140.860 148.087
core cutting method of any thickness
including necessary scafolding, stagging,
lifting, shifting & desposal of rabis from site
by mechanical devices at a distance within
5Km after necessary permision for competent
authority & no extra cost to be paid for the
same etc. all complete a as per direction of
EIC.
Measurement Sheet
Name Of Client: - PROJECT -: NBWCCC HOSPITAL EXTENSION AT NEW TOWN
Name Of Contractor: - M/S S M Nirman Infrastructure& Development Pvt.Ltd.
Name of Project: - NBWCCC KOLKATA
RA Bill No. TILL RA-14 Date
Sl. No. Breadth
Height
Description Unit No Length(M) Total QTY Released % Bill Qty REMARKS.
(M)
(M)

3.10 Earth Excavation


Depth upto 1.5 m.
Main Building EGL +300

Cum 19.8 16.3 1.800 580.932


Tank -1 road side to grid 3 upto sheet pile 1
Sheet pile to grid1 upto balla pile Cum 1 11.3 10.575 1.800 215.096
11 th RA Bill
Back filling SW1 & Admin Block cu m 1 10.5 5.7 1.800
side cu m 1 2 2.5 1.800
Assanya side cu m 1 11.5 2.2 1.800
Above Bolla cu m 1 11.5 4.5 1.800
Existing and new building wll backfiling cu m 1 25 3.1 1.800
Existing and new building wll backfiling cu m 1 9.676 3.1 1.800
12 thRA JMR no-38 cu m 1 7 1.5 1.200 12.600
13 th RA Bill
UP basement portion cu m 1 14.25 13.525 0.900 173.458
,, cu m 1 15.45 11.076 0.900 154.012

Total Quantity Cum 1136.097 100.00% 1136.097


Previous Quantity Cum
This Bill Quantity Cum
For additional depth beyond 1.5 m. and
3.20 upto 3.00 m.
Cum 484.110
Tank -1 road side to grid 3 upto sheet pile 1 19.8 16.3 1.500
Sheet pile to grid1 upto balla pile Cum 1 11.3 10.575 1.500 179.246
11 th RA Bill
SW1 & Admin Block cu m 1 10.5 5.7 0.750
side cu m 1 2 2.5 0.750
Assanya side cu m 1 11.5 2.2 1.500
Above Bolla cu m 1 11.5 4.5 1.500
Existing and new building wll backfiling cu m 1 25 3.1 0.600
Existing and new building wll backfiling cu m 1 9.676 3.1 0.900
13 th RA Bill
UP basement portion cu m 1 14.25 13.525 1.000 192.731
,, cu m 1 15.88 11.076 1.000 175.887
5 pile cap cu m 4 3.6 2.5 0.500 18.000
4 pile cap cu m 2 2.5 2.5 0.500 6.250
3 pile cap cu m 2 2.3 2.5 0.500 5.750
Deducton cu m -2 1.3 0.65 0.500 -0.845
4 pilecap cu m 2 3.815 2.625 0.500 10.014
Deduction cu m -4 1.407 0.712 0.500 -2.004
Sump cu m 1 4.35 3.15 0.500 6.851
14 TH RA
FBD C1-C4 cu m 1 2.951 0.75 0.550 1.217
FDB C4-C9 cu m 1 1.877 0.75 0.550 0.774
FDB C9-C13 cu m 1 2.352 0.75 0.550 0.970
FDB C13-C17 cu m 1 2.693 0.75 0.550 1.111
FDB C2-C5 cu m 1 3.239 0.75 0.550 1.336
FDB C5-C10 cu m 1 1.877 0.75 0.550 0.774
FDB C10-C14 cu m 1 2.901 0.75 0.550 1.197
FDB C14-C18 cu m 1 2.859 0.75 0.550 1.179
FDB C4-RW cu m 1 1.55 0.75 0.550 0.639
FDB C9-RW cu m 1 1.55 0.75 0.550 0.639
FDB C13-RW cu m 1 1.786 0.75 0.550 0.737
FDB1 C6-C5 cu m 1 5.125 0.75 0.700 2.691
FBD1 C5-C4 cu m 1 4.175 0.75 0.700 2.192
FDB1 C11-C10 cu m 1 3.925 0.75 0.700 2.061
FDB1 C10-C9 cu m 1 4.175 0.75 0.700 2.192
FDB1 C15-C14 cu m 1 3.925 0.75 0.700 2.061
FDB1 C14-C13 cu m 1 4.175 0.75 0.700 2.192
RAFT DOWN PORTION cu m 1 64.193 0.200 12.839
Total Quantity Cum 1112.792 100.00% 1112.792
Previous Quantity Cum -663.356
This Bill Quantity Cum 449.436
3.30 For additional depth beyond 3.00 m.
Cum 613.206
Tank -1 road side to grid 3 upto sheet pile 1 19.8 16.3 1.900
Sheet pile to grid1 upto balla pile Cum 1 11.3 10.575 1.900 227.045

3 pile Pile Cap Cum 6 0.8 1.3 0.800 4.992


Cum 6 0.9 1.45 0.800 6.264
Cum 6 2.6 0.925 0.800 11.544
Sump Cum 1 1.9 1.9 0.900 3.249
Beam FD1 Cum 2 4.525 0.85 0.600 4.616
Beam FD Cum 1 2.9 0.85 0.450 1.109
Beam FD Cum 2 2.8 0.85 0.450 2.142
Beam Cum 1 9.125 0.85 0.450 3.490 9888.03%
5p Pile Cap Cum 2 3.9 2.8 0.900 19.656
8 Pile Cap Cum 1 4.3 3.9 0.900 15.093
6 Pile Cap Cum 1 4.3 2.8 0.900 10.836
Beam FD1 c15 to c16 Cum 1 4.5 0.75 0.500 1.688
Beam FD1 c11 to c12 Cum 1 4.5 0.75 0.500 1.688
11 th RA Bill 0.000
Back filling SW1 & Admin Block cu m 1 10.5 5.7 0.000 0.000
side cu m 1 2 2.5 0.000 0.000
Assanya side cu m 1 11.5 2.2 1.500 0.000
Above Bolla cu m 1 11.5 4.5 1.000 0.000
Existing and new building wll backfiling cu m 1 25 3.1 0.000 0.000
Existing and new building wll backfiling cu m 1 9.676 3.1 1.800 0.000
13 th RA Bill (-2.1 m)
5 pile cap cu m 4 3.6 2.5 0.500 18.000
4 pile cap cu m 2 2.5 2.5 0.400 5.000
3 pile cap cu m 2 2.3 2.5 0.300 3.450
Deducton cu m -2 1.3 0.65 0.300 -0.507
4 pilecap cu m 2 3.815 2.625 0.300 6.009
Deduction cu m -4 1.407 0.712 0.300 -1.202
Sump cu m 1 4.35 3.15 0.775 10.619
Total Quantity Cum 967.986 100.00% 967.986
Previous Quantity Cum -926.617
This Bill Quantity Cum 41.369
6.00 Back Filling
Cum 1 16.3 1.4 4.800 109.536
Cum 1 12.7 1.8 4.800 109.728
Less Raft Projection Cum -1 16.3 0.5 0.300 -2.445
Cum -1 12.7 0.5 0.300 -1.905
11 th RA
Back filling SW1 & Admin Block cu m 1 10.5 5.7 1.950 116.708
side cu m 1 2 2.5 1.950 9.750
Assanya side cu m 1 11.5 2.2 3.700 93.610
Above Bolla cu m 1 11.5 4.5 1.500 77.625
Existing and new building wll backfiling cu m 1 25 3.1 2.000 155.000
12 th RA JMR no-38 cu m 1 7 1.5 1.200 12.600
Existing tank back filling 110.010
14 TH RA
FBD C1-C4 cu m 1 2.951 0.5 0.450 0.664
FDB C4-C9 cu m 1 1.877 0.5 0.450 0.422
FDB C9-C13 cu m 1 2.352 0.5 0.450 0.529
FDB C13-C17 cu m 1 2.693 0.5 0.450 0.606
FDB C2-C5 cu m 1 3.239 0.5 0.450 0.729
FDB C5-C10 cu m 1 1.877 0.5 0.450 0.422
FDB C10-C14 cu m 1 2.901 0.5 0.450 0.653
FDB C14-C18 cu m 1 2.859 0.5 0.450 0.643
FDB C4-RW cu m 1 1.55 0.5 0.450 0.349
FDB C9-RW cu m 1 1.55 0.5 0.450 0.349
FDB C13-RW cu m 1 1.786 0.5 0.450 0.402
FDB1 C6-C5 cu m 1 5.125 0.5 0.600 1.538
FBD1 C5-C4 cu m 1 4.175 0.5 0.600 1.253
FDB1 C11-C10 cu m 1 3.925 0.5 0.600 1.178
FDB1 C10-C9 cu m 1 4.175 0.5 0.600 1.253
FDB1 C15-C14 cu m 1 3.925 0.5 0.600 1.178
FDB1 C14-C13 cu m 1 4.175 0.5 0.600 1.253
5 pile cap cu m 4 13.4 0.5 1.000 26.800
4 pile cap cu m 2 11.2 0.5 0.900 10.080
3 pile cap cu m 2 10.9 0.5 0.800 8.720
4 PA pilecap(C21 & C2) cu m 1 14 0.5 0.800 5.600
4 P pile cap (C13) cu m 1 13.4 0.5 0.800 5.360
Total Quantity Cum 860.194 100.00% 860.194
Previous Quantity Cum
This Bill Quantity Cum

8.00 75 mm Brick Flat soling


10 th RA bill
C11 raft projection side sq m 1 3.5 0.5 1.750
,, sq m 1 2.5 1.4 3.500
Lift Looby portion sq m 1 3.9 2 7.800
C15, C11 sq m 2 3.4 2.3 15.640
C6,C7 sq m 1 3.8 3.4 12.920
C3 sq m 1 2.65 0.95 2.517
,, sq m 1 1.45 1.1 1.595
,, sq m 1 1.45 0.775 1.124
12 th RA JMR no-34 sq m 1 3.1 2.25 6.975
53.821 100.00% 53.821

12.00 All charges for laying Concreate PCC (1:3:6)


For Tank-1, Portion Cum 1 5.280 13.900 0.100 7.339
Grid 5 to 4 Cum 1 7.500 14.250 0.100 10.688
Grid 4 to 3 Cum 1 4.600 14.250 0.100 6.555
Grid 3 to 2 Cum 1 8.770 7.750 0.100 6.797
Below Bricks work Cum 0.000
FDB1 19 to 20 Cum 1 4.525 0.300 0.100 0.136
FDB1 11 to 12 & 15 to 16 Cum 2 4.475 0.500 0.100 0.448

FDB Cum 2 2.900 0.250 0.100 0.145


FDB Cum 2.05 0.25 0.1 0.000
Sump Bottom Cum 4 1.200 0.200 0.100 0.096

Total Quantity Cum 32.203 100.00% 32.203


Previous Quantity Cum -25.847
This Bill Quantity Cum 6.356

9 th RA
6 pilacap bottom cu m 1 3.8 2.3 0.100 0.874 100.00% 0.874

10 th RA
3 Pilecap cu m 1 2.65 0.95 0.100 0.252
,, cu m 1 1.1 1.45 0.100 0.160
,, cu m 1 1.45 0.775 0.100 0.112
Raft Bottom cu m 1 8.959 4.701 0.100 4.212
Deduction 6 pile cap cu m -1 3.8 2.3 0.100 -0.874
Deduction 3 pile cap cu m -1 2.65 0.95 0.100 -0.252
cu m -1 1.1 1.45 0.100 -0.160
cu m -1 1.45 0.775 0.100 -0.112
13 th RA Bill
5 pile cap cu m 4 3.6 2.5 0.075 2.700
4 pile cap cu m 2 2.5 2.5 0.075 0.938
3 pile cap cu m 2 2.3 2.5 0.075 0.862
Deducton cu m -2 1.3 0.65 0.075 -0.127
4 pilecap cu m 2 3.815 2.625 0.075 1.502
Deduction cu m -4 1.407 0.712 0.075 -0.301
Sump cu m 1 4.35 3.15 0.075 1.028
14 th RA
FBD C1-C4 cu m 1 2.951 0.75 0.100 0.221
FDB C4-C9 cu m 1 1.877 0.75 0.100 0.141
FDB C9-C13 cu m 1 2.352 0.75 0.100 0.176
FDB C13-C17 cu m 1 2.693 0.75 0.100 0.202
FDB C2-C5 cu m 1 3.239 0.75 0.100 0.243
FDB C5-C10 cu m 1 1.877 0.75 0.100 0.141
FDB C10-C14 cu m 1 2.901 0.75 0.100 0.218
FDB C14-C18 cu m 1 2.859 0.75 0.100 0.214
FDB C4-RW cu m 1 1.55 0.75 0.100 0.116
FDB C9-RW cu m 1 1.55 0.75 0.100 0.116
FDB C13-RW cu m 1 1.786 0.75 0.100 0.134
FDB1 C6-C5 cu m 1 5.125 0.75 0.100 0.384
FBD1 C5-C4 cu m 1 4.175 0.75 0.100 0.313
FDB1 C11-C10 cu m 1 3.925 0.75 0.100 0.294
FDB1 C10-C9 cu m 1 4.175 0.75 0.100 0.313
FDB1 C15-C14 cu m 1 3.925 0.75 0.100 0.294
FDB1 C14-C13 cu m 1 4.175 0.75 0.100 0.313
RAFT portion cu m 1 25.05 15.45 0.100 38.702
RAFT portion cu m 1 0.5 0.45 0.100 0.023
Deduction
FBD C1-C4 cu m -1 2.951 0.5 0.100 -0.148
FDB C4-C9 cu m -1 1.877 0.5 0.100 -0.094
FDB C9-C13 cu m -1 2.352 0.5 0.100 -0.118
FDB C13-C17 cu m -1 2.693 0.5 0.100 -0.135
FDB C2-C5 cu m -1 3.239 0.5 0.100 -0.162
FDB C5-C10 cu m -1 1.877 0.5 0.100 -0.094
FDB C10-C14 cu m -1 2.901 0.5 0.100 -0.145
FDB C14-C18 cu m -1 2.859 0.5 0.100 -0.143
FDB C4-RW cu m -1 1.55 0.5 0.100 -0.078
FDB C9-RW cu m -1 1.55 0.5 0.100 -0.078
FDB C13-RW cu m -1 1.786 0.5 0.100 -0.089
FDB1 C6-C5 cu m -1 5.125 0.5 0.100 -0.256
FBD1 C5-C4 cu m -1 4.175 0.5 0.100 -0.209
FDB1 C11-C10 cu m -1 3.925 0.5 0.100 -0.196
FDB1 C10-C9 cu m -1 4.175 0.5 0.100 -0.209
FDB1 C15-C14 cu m -1 3.925 0.5 0.100 -0.196
FDB1 C14-C13 cu m -1 4.175 0.5 0.100 -0.209
5 pile cap cu m -4 3.4 2.3 0.100 -3.128
4 pile cap cu m -1 2.3 2.3 0.100 -0.529
4 pile cap cu m -1 1.9 2.3 0.100 -0.437
3pile cap cum -1 3.853 0.100 -0.385
3pile cap cu m -1 3.509 0.100 -0.351
4 pile cap PA cu m -1 5.815 0.100 -0.582
5 pile cap PA2 cu m -1 5.867 0.100 -0.587
sump cu m -1 3.6 2.4 0.100 -0.864
wall side cu m -1 12.774 1.2 0.100 -1.533

Total = 41.548 100.00% 41.548


13.80 M-35 Raft Casting
Raft tank-1 Cum 1 13.700 5.180 0.300 21.290
Raft grid 5 to 4 Cum 1 14.055 7.500 0.300 31.624
Raft grid 4 to 3 Cum 1 14.055 4.500 0.300 18.974
Raft C-11 corner part Cum 1 1.200 1.700 0.300 0.612
Raft grid 3 to 8 pile cap end Cum 1 7.050 8.570 0.300 18.126
8 Pile Cap Cum 1 3.800 3.400 0.900 11.628
Cum 4 0.800 2.300 0.800 5.888
3 Pile Cap
Cum 4 1.550 1.300 0.800 6.448
5 Pile Cap Cum 2 3.400 2.300 1.000 15.640
Beam FBD1 Cum 3 4.500 0.500 0.600 4.050
Beam FBD Cum 3 2.400 0.500 0.450 1.620
Cum 3 1.350 0.250 0.900 0.911
Sump Wall
Cum 1 1.350 0.250 0.150 0.051
Wall Tank-01 Cum 1 12.700 0.275 3.700 12.922
Cum 1 12.700 0.250 3.700 11.748
Cum 2 3.230 0.275 3.700 6.573
Wall Tank-02 Cum 1 12.400 0.275 3.700 12.617
Cum 1 12.400 0.250 3.700 11.470
Cum 1 3.230 0.275 3.700 3.287
Wall Column 11 to 19 Cum 1 13.055 0.250 2.100 6.854
wall column C08 to C-16 Cum 1 9.850 0.250 2.400 5.910
column 16 Cum 1 0.400 0.750 2.400 0.720
Column 12 & 8 Cum 2 0.350 0.750 2.400 1.260
C-15 to 16 & 11 to 12 wall Cum 2 6.100 0.250 1.200 3.660
C-11 & C-15 Cum 2 0.400 0.750 1.200 0.720
SC column Cum 2 0.250 0.750 1.200 0.450
Column C-06 Cum 1 0.250 1.200 1.900 0.570
Column C-19 Cum 1 0.400 0.650 2.100 0.546
Column C-20 Cum 1 0.350 0.750 2.400 0.630
Tank Slab Cum 1 12.600 3.730 0.200 9.400
Tank Slab Cum 1 12.350 3.730 0.200 9.213
Tank Slab Cum 1 12.350 0.300 0.200 0.741
Tank Slab Cum 1 8.870 0.300 0.200 0.532
Cum
Total Quantity Cum 236.683 100.00% 236.683
Previous Quantity Cum -140.155 Previous Bill less

Cum This qty claim at


This Bill Quantity 96.528 item no 39

39.00 9th RA Bill


M-35 concrete cu m

wall C8 to C16 cu m 1 9.55 0.28 2.000 5.348


C16 to C12 level(-1.3m to 1.05m) cu m 1 5.00 0.25 2.350 2.938
C16 to C20 level (avr. -.575m to 1.05m) cu m 1 4.45 0.25 1.625 1.808
C15 to C16/ C11 to C12 cu m 2 5.00 0.25 1.200 3.000
C11 to C6 upto ramp slab cu m 1 3 0.25 1.200 0.900
Ramp slab cu m 1 9.9 4.1 0.150 6.088
,, cu m 1 5.00 4.1 0.150 3.075
,, cu m 1 3.675 5.0 0.150 2.756
B2 cu m 1 4.45 0.25 0.500 0.556
B2A cu m 1 6.375 0.25 0.600 0.956
B1 cu m 2 1.8 0.25 0.400 0.360
B2/1 cu m 1 4.95 0.25 0.600 0.743
B2/2 cu m 1 5.000 0.25 0.600 0.750
wall C15 to C16 out side wall cu m 1 5.000 0.25 0.150 0.188
C19 cu m 1 0.65 0.4 1.500 0.390
C20 cu m 1 0.75 0.35 1.500 0.394
C16 cu m 1 0.75 0.4 1.500 0.450
C12 cu m 1 0.75 0.35 1.500 0.394
C8 cu m 1 0.75 0.35 1.500 0.394
SC cu m 2 0.75 0.25 0.800 0.300
C6,C7 cu m 2 1.2 0.25 1.200 0.720
C11,C15 cum 2 0.75 0.4 1.200 0.720
Slab -2.1 m level (Lift side) cu m 1 6.2 2.25 0.150 2.093
B2 cum 1 6.2 0.25 0.500 0.775
B1 cu m 2 2.25 0.25 0.500 0.563
Tank slab 1 cu m 1 12.35 0.7 0.200 1.729
Tank slab 2 cu m 1 8.87 0.7 0.200 1.242

Total = 39.628 100.00% 39.628


10 th RA bill
Stair from basenent to ramp top cu m 1 1 0.3 0.330 0.099
1st Flight cu m 1 2.075 1.00 0.150 0.311
Riser cu m 3.5 1 0.25 0.160 0.140
1st landing cu m 1 2 1 0.150 0.300
2nd flight cu m 1 1.692 1 0.150 0.254
Riser cu m 3.5 1 0.25 0.160 0.140
2nd landing cu m 1 1.75 1 0.200 0.350
3 rd Flight cu m 1 3.673 1 0.150 0.551
Riser cu m 6.5 1 0.25 0.160 0.260
3rd landing cu m 1 1.2 1 0.150 0.180
6 pile cap cu m 1 3.8 2.3 0.900 7.866
C12 column cu m 1 0.75 0.35 2.800 0.735
C16 column cu m 1 0.75 0.4 2.800 0.840
C20 column cu m 1 0.75 0.35 1.650 0.433
wall C12 to C16 cu m 1 5 0.275 2.800 3.850
wall C16 to C20 cu m 1 4.45 0.25 1.650 1.836
Stair side wall cu m 1 2.8 0.25 1.725 1.208
,, cu m 1 3.15 0.25 0.525 0.413
3 pile cap cu m 1 2.65 0.9 0.800 1.908
,, cu m 1 1.45 1.1 0.800 1.276
,, cu m 1 1.45 0.775 0.800 0.899
Balance portion Raft cu m 1 8.959 4.701 0.300 12.635
C3 cu m 1 0.75 0.35 2.400 0.630
SW1 cu m 1 2.75 0.3 2.400 1.980
Lift wall cu m 1 8.85 0.25 2.400 5.310
C6 to Lift wall cu m 1 1.2 0.25 2.400 0.720
SW1 to C3 cu m 1 4 0.325 2.400 3.120
C3 to C8 cu m 1 4.95 0.325 2.400 3.861
Lift connecting beam cu m 1 1.2 0.5 0.250 0.150
Lift connecting slab cu m 1 2.25 1.2 0.150 0.405
Ramp 2 nd part cu m 1 4.1 5.684 0.150 3.496
B1 cu m 1 4.4 0.25 0.400 0.440
B2 cu m 1 5 0.25 0.600 0.750
C8 to C12 wall cu m 1 5.45 0.3 0.500 0.818
Manhole cu m 1 3.2 0.2 0.600 0.384
,, cu m 1 3.2 0.2 0.400 0.256
C7 column cu m 1 1.2 0.25 1.500 0.450
cu m Total = 59.253 100.00% 59.253
11 th RA cu m

SW1 to C8 3rd lift cu m 1 12.8 0.31 1.200 4.762


C3 column 3rd lift cu m 1 0.5 0.1 2.200 0.110
SW1 to C3 4th lift cu m 1 7.1 0.3 1.000 2.130
C3 to C8 4th lift cu m 1 5.7 0.3 1.950 3.335
Ramp last part cu m 1 5.503 4.1 0.150 3.384
Beam B2/4 cu m 1 5.503 0.25 0.600 0.825
Column C7 cu m 1 1.2 0.25 1.500 0.450
SW1 to C7 wall cu m 1 5.503 0.25 0.550 0.757
C11 to SC & C15 to SC cu m 2 2.1 0.25 0.500 0.525
SC column 2 nos. cu m 2 0.75 0.25 0.200 0.075
C11 & C15 cu m 2 0.75 0.4 0.800 0.480
Manhol fixing cu m 2 3.4 0.2 0.450 0.612
12 th RA cu m

SW1 column cu m 1 2.75 0.3 0.950 0.784


C6,C7 column cu m 2 1.2 0.25 3.150 1.890
SC1,2 column cu m 2 0.75 0.25 3.150 1.181
C12 column cu m 1 0.75 0.35 0.600 0.158
C16 column cu m 1 0.75 0.4 0.600 0.180
C11 column cu m 1 0.75 0.4 3.600 1.080
C15 column cu m 1 0.75 0.4 3.600 1.080
C19 column cu m 1 0.65 0.4 1.350 0.351
GBY-7-3/4 cu m 1 9.5 0.25 0.600 1.425
GBY-7/2 cu m 1 5 0.625 0.300 0.938
GBY-7/1 cu m 1 4.55 0.3 0.600 0.819
GBX-4A cu m 2 4 0.25 0.600 1.200
GBY8-2/3 cu m 1 9.5 0.25 0.800 1.900
GBX-1 cu m 1 2.25 0.25 0.450 0.253
GBX-2/3 cu m 1 2.25 0.3 0.600 0.405
GBX-4/4 cu m 1 2.25 0.25 0.600 0.337
GBX-6 cu m 1 2.25 0.25 0.625 0.352
GBX-5/4 cu m 1 2.25 0.25 0.625 0.352
SLAB A cu m 1 2.4 2.25 0.125 0.675
SLAB-B cu m 1 2.25 5 0.125 1.406
SLAB-C cu m 1 6.55 6 0.200 7.860
SLAB-E cu m 1 4.95 2.2 0.125 1.361
DEDUCTION cu m -1 3.15 1.05 0.125 -0.413
Deduction stair cu m -1 2.1 0.5 0.200 -0.210
STAIR SIDE WALL cu m 1 1.1 0.33 1.400 0.508
,, cu m 1 2 0.25 0.500 0.250
STEP PORTION cu m 1 2.1 0.75 0.150 0.236
STEPS cu m 1.50 2.1 0.25 0.150 0.118
13 th RA Bill (upper raft)
5 pile cap cu m 4 3.4 2.3 1.000 31.280
4 pile cap cu m 2 2.3 2.3 0.900 9.522
3 pile cap cu m 2 2.3 2.1 0.800 7.728
Deducton cu m -2 1.3 0.75 0.800 -1.560
4 PA pilecap(C21 & C2) cu m 1 3.615 2.425 0.800 7.013
Deduction cu m -2 1.407 0.808 0.800 -1.819
4 P pile cap (C13) cu m 1 3.4 2.3 0.750 5.865
Deduction cu m -2 1.299 0.75 0.750 -1.461
SW1 column cu m 1 2.75 0.3 2.400 1.980
C3 column cu m 1 0.75 0.35 2.400 0.630
C6,C7 column cu m 2 1.2 0.25 2.400 1.440
C8 column cu m 1 0.75 0.35 2.400 0.630
C11 column cu m 1 0.75 0.4 2.400 0.720
C12 column cu m 1 0.75 0.35 2.400 0.630
C15 column cu m 1 0.75 0.4 2.400 0.720
C16 column cu m 1 0.75 0.4 2.400 0.720
C19 column cu m 1 0.65 0.4 2.400 0.624
C20 column cu m 1 0.75 0.35 2.400 0.630
Sump cu m 1 4.2 3 0.300 3.780
14 th RA
FBD C1-C4 cu m 1 2.951 0.5 0.400 0.590
FDB C4-C9 cu m 1 1.877 0.5 0.400 0.375
FDB C9-C13 cu m 1 2.352 0.5 0.400 0.470
FDB C13-C17 cu m 1 2.693 0.5 0.400 0.539
FDB C2-C5 cu m 1 3.239 0.5 0.400 0.648
FDB C5-C10 cu m 1 1.877 0.5 0.400 0.375
FDB C10-C14 cu m 1 2.901 0.5 0.400 0.580
FDB C14-C18 cu m 1 2.859 0.5 0.400 0.572
FDB C4-RW cu m 1 1.55 0.5 0.400 0.310
FDB C9-RW cu m 1 1.55 0.5 0.400 0.310
FDB C13-RW cu m 1 1.786 0.5 0.400 0.357
FDB1 C6-C5 cu m 1 5.125 0.5 0.600 1.537
FBD1 C5-C4 cu m 1 4.175 0.5 0.600 1.253
FDB1 C11-C10 cu m 1 3.925 0.5 0.600 1.178
FDB1 C10-C9 cu m 1 4.175 0.5 0.600 1.253
FDB1 C15-C14 cu m 1 3.925 0.5 0.600 1.178
FDB1 C14-C13 cu m 1 4.175 0.5 0.600 1.253
RAFT portion cu m 1 23.7 15.45 0.300 109.849
RAFT portion cu m 1 0.75 0.45 0.300 0.101
RAFT portion cu m 1 5.1 0.2 0.300 0.306
RAFT portion cu m 1 1.3 1.05 0.300 0.410
4 pile cap cu m 1 2.3 0.4 0.300 0.276
3pile cap cum 1 2.342 0.419 0.300 0.294
4 pile cap PA cu m 1 0.663 0.300 0.199
sump deduction cu m -1 3.6 2.4 0.300 -2.592
wall side deduction cu m -1 12.774 0.95 0.300 -3.641
RW wall both side cu m 2 15.45 0.25 3.100 23.947
Deduction stair portion cu m -1 4.1 0.25 0.850 -0.871
Column C1(-2.1 to 1.0m) cu m 1 0.4 0.4 3.100 0.496
Column C2(-2.1 to 1.0m) cu m 1 0.4 0.4 3.100 0.496
Column C21(-2.1 to 1.0m) cu m 1 0.4 0.4 3.100 0.496
Column C4(-2.1 to 1.0m) cu m 1 0.8 0.4 3.100 0.992
Column C5(-2.1 to 1.0m) cu m 1 0.85 0.4 3.100 1.054
Column C9(-2.1 to 1.0m) cu m 1 0.75 0.4 3.100 0.930
Column C10(-2.1 to 1.0m) cu m 1 0.75 0.4 3.100 0.930
Column C13(-2.1 to 1.0m) cu m 1 0.75 0.4 3.100 0.930
Column C14(-2.1 to 1.0m) cu m 1 0.75 0.4 3.100 0.930
Column C17(-2.1 to 1.0m) cu m 1 0.4 0.4 3.100 0.496
Column C18(-2.1 to 1.0m) cu m 1 0.4 0.4 3.100 0.496
1ST FLOOR UPPER PORTION GF BEAM cu m 0.000
GBX 2/1 (300X600) cu m 1 8.075 0.3 0.600 1.453
GBX 2/2 (300X600) cu m 1 6.075 0.3 0.600 1.094
GBX 3/1 (250X450) cu m 1 6.275 0.25 0.450 0.706
GBX 3/2(250X450) cu m 1 6.075 0.25 0.450 0.683
GBX 4/1, 4/2 (300X600) cu m 1 8.085 0.3 0.600 1.455
GBX 4/4 (300X600) cu m 1 6.075 0.3 0.600 1.094
GBX 5/1,5/2 (300X600) cu m 1 8.075 0.3 0.600 1.453
GBX 5/3(300X600) cu m 1 6.075 0.3 0.600 1.094
GBY 1/1,1/2,1/3,1/4 (400X400) cu m 1 21.275 0.4 0.400 3.404
GBY 2/1,2/2,2/3,2/4(300X600) cu m 1 19.075 0.3 0.600 3.433
GBY-3(250X450) cu m 1 5.45 0.25 0.450 0.613
GBY3A (250X450) cu m 1 4.95 0.25 0.450 0.557
GBY 4/1,4/2,4/3,4/4(300X600) cu m 1 19.05 0.3 0.600 3.429
GBY 5 (250X600) cu m 1 7.275 0.25 0.600 1.091
GBY-6 (250X450) cu m 1 5.9 0.25 0.450 0.664
GBX 2A(250X450) cu m 1 4.1 0.25 0.450 0.461
GBY 6A(250X450) cu m 2 0.4 0.25 0.450 0.090
SLAB A cu m 1 22.2 0.5 0.125 1.388
SLAB B cu m 1 5.45 1.6 0.125 1.090
SLAB C cu m 1 5.45 2.175 0.125 1.482
SLAB D cu m 1 5.45 3.85 0.135 2.833
SLAB E cu m 1 5.45 1.725 0.125 1.175
SLAB F cu m 1 5 1.6 0.125 1.000
SLAB G cu m 1 6.275 2.225 0.125 1.745
SLAB H cu m 1 6.275 2.525 0.125 1.981
SLAB I cu m 1 6.075 2.525 0.125 1.917
SLAB J cu m 1 2.225 1.725 0.125 0.480
SLAB K cu m 1 5.9 1.6 0.125 1.180
SLAB L cu m 1 6.275 5.9 0.175 6.479
SLAB M cu m 1 5.875 3.45 0.125 2.534
SLAB N cu m 1 5.9 2.375 0.125 1.752
SLAB P cu m 1 4.95 1.61 0.125 0.996
SLAB Q cu m 1 4.95 3.1 0.125 1.918
SLAB R cu m 1 4.95 2.925 0.125 1.810
SLAB S cu m 1 6.075 4.95 0.150 4.511
SLAB T cu m 1 4.1 1.575 0.125 0.807
STAIR BASEMENT TO GF bottom beam cu m 1 2.075 0.3 0.300 0.187
1st waist slab cu m 1 4.225 2.075 0.150 1.315
1st landing cu m 1 4.1 2.075 0.150 1.276
2nd waist slab cu m 1 1.85 2.075 0.150 0.576
2nd landing cu m 1 2 2.075 0.150 0.623
Steps cu m 8.5 2.075 0.3 0.150 0.794
326.915 100.00% 326.915

14.60 Shuttering Work Shuttering work

Sqm 2 13.700 0.300 8.220


Sqm 2 5.180 0.300 3.108
Sqm 2 12.900 0.300 7.740
Sqm 2 4.280 0.300 2.568
Tank Portion Raft Side
Sqm 2 12.900 0.300 7.740
Sqm 2 3.100 0.300 1.860
Sqm 2 6.675 0.300 4.005
Sqm 2 7.500 0.300 4.500
1 8.750 0.300 2.625
1 1.200 0.300 0.360
Raft Side 1 1.750 0.300 0.525
1 4.500 0.300 1.350
11.250 0.300 0.000

Sump shuttering Sqm 4 1.200 0.900 4.320


Tank-01 Wall Out side Sqm 1 12.700 3.600 45.720
Tank-01 Wall Out side Sqm 2 3.730 3.600 26.856
Tank-01 Wall Out side Sqm 1 16.080 3.600 57.888
Tank-01 Wall Out side Sqm 1 12.350 3.600 44.460
Tank-01 Wall Out side Sqm 1 8.870 3.600 31.932
In side Sqm 4 12.100 3.600 174.240
Sqm 4 3.230 3.600 46.512
Slab Sqm 2 12.100 3.230 78.166
Sqm 1 12.350 0.300 3.705
Sqm 1 8.870 0.300 2.661
Slab Outer Sqm 1 12.700 0.200 2.540
Sqm 2 4.730 0.200 1.892
Sqm 1 16.080 0.200 3.216
Sqm 1 12.350 0.200 2.470
Sqm 1 8.870 0.200 1.774
Column & Wall C11 to C19 Sqm 2 13.055 2.100 54.831
Column & Wall C8 to C16 Wall Sqm 2 9.850 2.400 47.280

C-15 - 16 & C11 -12 Sqm 2 12.200 1.200 29.280


Column C-8 & C12 Sqm 2 2.200 2.400 10.560
Column C-11 & C15 Sqm 2 2.300 1.200 5.520
Column C-20 Sqm 1 2.200 2.400 5.280
Column C-19 Sqm 1 2.100 2.100 4.410
Column C-07 Sqm 1 2.900 1.900 5.510
SC Sqm 2 2.000 1.200 4.800
Column -16 Sqm 1 2.300 2.400 5.520

Total Quantity Sqm 745.944 100.00% 745.944


Previous Quantity Sqm -431.639
This Bill Quantity Sqm 314.305

9th RA Bill
Shuttering work Sqm
wall C8 to C16 Sqm 2 9.55 2.400 45.840
C16 to C12 level(-1.3m to 1.05m) Sqm 2 5.00 2.350 23.500
C16 to C20 level (avr. -.550m to 1.05m) Sqm 2 4.45 1.600 14.240
C15 to C6/ C11 to C12 Sqm 4 5.00 1.200 24.000
C11 to C6 upto ramp slab Sqm 2 3.0 1.200 7.200
Ramp slab Sqm 1 4.1 9.900 40.590
Ramp slab Sqm 1 5.00 4.100 20.500
Ramp slab Sqm 1 3.675 5.000 18.375
Ramp Beam B2 Sqm 1 4.45 0.900 4.005
Ramp Beam B2A Sqm 1 6.375 1.100 7.013
Ramp Beam B1 Sqm 2 1.8 0.750 2.700
Ramp Beam B2/1 Sqm 1 4.95 1.300 6.435
Ramp Beam B2/2 Sqm 1 5.000 1.150 5.750
wall C15 to C16 out side wall Sqm 2 5.000 0.450 4.500
C19 Sqm 1 2.1 1.500 3.150
C20 Sqm 1 2.2 1.500 3.300
C16 Sqm 1 2.3 1.500 3.450
C12 Sqm 1 2.2 1.500 3.300
C8 Sqm 1 2.2 1.500 3.300
SC Sqm 2 2 0.800 3.200
C6,C7 Sqm 2 2.9 1.200 6.960
C11,C15 Sqm 2 2.3 1.200 5.520
Slab -2.1 m level (Lift side) Sqm 1 6.2 2.250 13.950
B2 Sqm 1 6.2 1.100 6.820
B1 Sqm 2 2.25 0.950 4.275
Tank slab 1 Sqm 1 12.35 0.700 8.645
Tank slab 2 Sqm 1 8.87 0.700 6.209
Total = 296.726 100.00% 296.726

10 th RA bill
Stair from basenent to ramp top (bottom) Sq m 2 1 0.33 0.660
1st Flight Sq m 1 1 2.07 2.070
Flight side Sq m 1 2.07 0.15 0.310
Riser Sq m 7 1 0.16 1.120
1st landing Sq m 1 2 1 2.000
Landing side Sq m 2 1 0.15 0.300
2 nd flight Sq m 1 1.692 1 1.692
Flight side Sq m 2 1.692 0.15 0.508
Riser Sq m 7 1 0.16 1.120
2 nd landing Sq m 1 1.75 1 1.750
Landing side Sq m 1 2.5 0.2 0.500
3 rd Flight Sq m 1 3.673 1 3.673
Flight side Sq m 2 3.673 0.15 1.102
Riser Sq m 13 1 0.16 2.080
3 rd landing Sq m 1 1.2 1 1.200
3rd Landing side Sq m 1 2.2 0.15 0.330
Riser side Sq m 23.5 0.25 0.16 0.940
C12 column Sq m 1 1.6 2.8 4.480
C16 column Sq m 1 1.6 2.8 4.480
C20 column Sq m 1 1.6 1.65 2.640
wall C12 to C16 Sq m 2 5 2.8 28.000
wall C16 to C20 Sq m 2 4.45 1.65 14.685
Stair side wall Sq m 2 2.8 1.75 9.800
,, Sq m 2 3.15 0.525 3.308
,, Sq m 1 0.525 0.25 0.131
,, Sq m 1 2 0.25 0.500
C3 Sq m 1 1.6 2.4 3.840
SW1 Sq m 1 5.8 2.4 13.920
Lift wall Sq m 1 9.35 2.4 22.440
,, Sq m 1 8.35 2.4 20.040
C6 to Lift wall Sq m 2 1.2 2.4 5.760
SW1 to C3 Sq m 2 4 2.4 19.200
C3 to C8 Sq m 2 4.95 2.4 23.760
Lift connecting beam Sq m 1 1.2 1.1 1.320
Lift connecting slab Sq m 1 2.25 1.2 2.700
Ramp 2 nd part Sq m 1 4.1 5.684 23.304
B1 Sq m 1 4.4 0.9 3.960
B2 Sq m 1 5 1.3 6.500
C8 to C12 wall Sq m 2 5.45 0.5 5.450
Manhole Sq m 1 5.6 0.6 3.360
,, Sq m 1 5.6 0.4 2.240
C7 column Sq m 1 2.9 1.5 4.350
Total = 251.523 100.00% 251.523
11 th RA
SW1 to C8 3rd lift sq m 2 12.8 1.200 30.720
C3 column 3rd lift sq m 1 0.6 2.200 1.320
SW1 to C3 4th lift sq m 2 7.1 1.000 14.200
C3 to C8 4th lift sq m 2 5.7 1.950 22.230
Ramp last part sq m 1 5.503 4.100 22.562
Beam B2/4 sq m 1 5.503 1.300 7.154
Column C7 sq m 1 2.9 1.500 4.350
SW1 to C7 wall sq m 2 5.503 0.550 6.053
C11 to SC & C15 to SC sq m 4 2.1 0.500 4.200
SC column 2 nos. sq m 2 2 0.200 0.800
C11 & C15 sq m 2 2.3 0.800 3.680
Manhole fixing sq m 2 6.8 0.450 6.120
12 th RA
SW1 column Sq m 1 6.1 0.950 5.795
C6,C7 column Sq m 2 2.9 3.150 18.270
SC1,2 column Sq m 2 2 3.150 12.600
C12 column Sq m 1 2.2 0.600 1.320
C16 column Sq m 1 2.3 0.600 1.380
C11 column Sq m 1 2.3 3.600 8.280
C15 column Sq m 1 2.3 3.600 8.280
C19 column Sq m 1 2.1 1.350 2.835
GBY-7-3/4 Sq m 1 9.5 1.325 12.588
GBY-7/2 Sq m 1 5 1.350 6.750
GBY-7/1 Sq m 1 4.55 1.375 6.256
GBX-4A Sq m 2 4 1.250 10.000
GBY8-2/3 Sq m 1 9.5 1.725 16.388
GBX-1 Sq m 1 2.25 1.025 2.306
GBX-2/3 Sq m 1 2.25 1.250 2.813
GBX-4/4 Sq m 1 2.25 1.325 2.981
GBX-6 Sq m 1 2.25 1.175 2.644
GBX-5/4 Sq m 1 2.25 1.125 2.531
SLAB A Sq m 1 2.4 2.250 5.400
SLAB-B Sq m 1 2.25 5.000 11.250
SLAB-C Sq m 1 6.55 6.000 39.300
SLAB-E Sq m 1 4.95 2.200 10.890
DEDUCTION Sq m -1 3.15 1.050 -3.308
DEDUCTION Sq m -1 2.1 0.500 -1.050
Slab side Sq m 1 4.2 0.125 0.525
STAIR SIDE WALL Sq m 1 2.53 1.400 3.542
,, Sq m 2 2 0.500 2.000
STEP PORTION Sq m 1 2.1 0.750 1.575
STEPS Sq m 3 2.1 0.150 0.945
13 th RA Bill
5 pile cap Sq m 4 11.4 1.000 45.600
4 pile cap Sq m 2 9.2 0.900 16.560
3 pile cap Sq m 2 7.7 0.800 12.320
4 pilecap C2 Sq m 1 9.7 0.800 7.760
4 pilecap C13 Sq m 1 9.2 0.750 6.900
SW1 column Sq m 1 6.1 2.400 14.640
C3 column Sq m 1 2.2 2.400 5.280
C6,C7 column Sq m 2 2.9 2.400 13.920
C8 column Sq m 1 2.2 2.400 5.280
C11 column Sq m 1 2.3 2.400 5.520
C12 column Sq m 1 2.2 2.400 5.280
C15 column Sq m 1 2.3 2.400 5.520
C16 column Sq m 1 2.3 2.400 5.520
C19 column Sq m 1 2.1 2.400 5.040
C20 column Sq m 1 2.2 2.400 5.280
Sump inside Sq m 1 12 0.700 8.400
Sump outside Sq m 1 14.4 0.700 10.080
14 th RA
RAFT portion Sq m 2 15.45 0.300 9.270
RAFT portion Sq m 1 1.05 0.300 0.315
RAFT portion Sq m 1 7.17 1.500 10.755
sump Sq m 1 12 0.300 3.600
down portion raft Sq m 1 38.136 0.200 7.627
RW wall out side Sq m 2 15.45 3.100 95.790
RW wall inside Sq m 2 15.45 2.975 91.928
Deduction stair portion Sq m -2 4.1 0.850 -6.970
Column C1(-2.1 to 1.0m) Sq m 2 0.4 3.100 2.480
Column C2(-2.1 to 1.0m) Sq m 2 0.4 3.100 2.480
Column C21(-2.1 to 1.0m) Sq m 1 0.4 3.100 1.240
Column C4(-2.1 to 1.0m) Sq m 1 2.4 3.100 7.440
Column C5(-2.1 to 1.0m) Sq m 1 2.5 3.100 7.750
Column C9(-2.1 to 1.0m) Sq m 1 2.3 3.100 7.130
Column C10(-2.1 to 1.0m) Sq m 1 2.3 3.100 7.130
Column C13(-2.1 to 1.0m) Sq m 1 2.3 3.100 7.130
Column C14(-2.1 to 1.0m) Sq m 1 2.3 3.100 7.130
Column C17(-2.1 to 1.0m) Sq m 2 0.4 3.100 2.480
Column C18(-2.1 to 1.0m) Sq m 2 0.4 3.100 2.480
1ST FLOOR UPPER PORTION GF BEAM Sq m 0.000
GBX 2/1 (300X600) Sq m 1 8.075 1.250 10.094
GBX 2/2 (300X600) Sq m 1 6.075 1.250 7.594
GBX 3/1 (250X450) Sq m 1 6.275 0.900 5.648
GBX 3/2(250X450) Sq m 1 6.075 1.025 6.227
GBX 4/1, 4/2 (300X600) Sq m 1 8.085 1.250 10.106
deduction Sq m -2 6.075 0.050 -0.608
GBX 4/3 (300X600) Sq m 1 6.075 1.250 7.594
GBX 5/1,5/2 (300X600) Sq m 1 8.075 1.250 10.094
GBX 5/3(300X600) Sq m 1 6.075 1.250 7.594
deduction sq m -1 6.075 0.025 -0.152
GBY 1/1,1/2,1/3,1/4 (400X400) Sq m 1 21.275 0.950 20.211
GBY 2/1,2/2,2/3,2/4(300X600) Sq m 1 19.075 1.250 23.844
deduction sq m -1 5.9 0.050 -0.295
GBY-3(250X450) Sq m 1 5.45 0.890 4.850
GBY3A (250X450) Sq m 1 4.95 0.900 4.455
GBY 4/1,4/2,4/3,4/4(300X600) Sq m 1 19.05 1.250 23.813
deduction sq m 1 4.95 0.025 0.124
GBY 5 (250X600) Sq m 1 7.275 1.325 9.639
deduction sq m -1 1.575 0.125 -0.197
GBY-6 (250X450) Sq m 1 5.9 0.900 5.310
GBX 2A(250X450) Sq m 1 4.1 1.025 4.203
GBY 6A(250X450) Sq m 2 0.4 1.150 0.920
SLAB A Sq m 1 22.2 0.5 11.100
SLAB B Sq m 1 5.45 1.6 8.720
SLAB C Sq m 1 5.45 2.175 11.854
SLAB D Sq m 1 5.45 3.85 20.983
SLAB E Sq m 1 5.45 1.725 9.401
SLAB F Sq m 1 5 1.6 8.000
SLAB G Sq m 1 6.275 2.225 13.962
SLAB H Sq m 1 6.275 2.525 15.844
SLAB I Sq m 1 6.075 2.525 15.339
SLAB J Sq m 1 2.225 1.725 3.838
SLAB K Sq m 1 5.9 1.6 9.440
SLAB L Sq m 1 6.275 5.9 37.023
SLAB M Sq m 1 5.875 3.45 20.269
SLAB N Sq m 1 5.9 2.375 14.013
SLAB P Sq m 1 4.95 1.61 7.970
SLAB Q Sq m 1 4.95 3.1 15.345
SLAB R Sq m 1 4.95 2.925 14.479
SLAB S Sq m 1 6.075 4.95 30.071
SLAB T Sq m 1 4.1 1.575 6.458
STAIR BASEMENT TO GF bottom beam Sq m 2 2.075 0.3 1.245
1st waist slab Sq m 1 4.225 2.075 8.767
2nd waist slab side sq m 2 4.225 0.15 1.267
1st landing Sq m 1 4.1 2.075 8.508
2nd landing side sq m 1 2 0.15 0.300
2nd waist slab Sq m 1 1.85 2.075 3.839
3rd waist slab side sq m 2 1.85 0.15 0.555
2nd landing Sq m 1 2 2.075 4.150
3rd landing Sq m 1 2 0.15 0.300
Riser Sq m 19 2.075 0.15 5.914
Riser side sq m 8.5 0.3 0.15 0.383
0.000
0.000
Total = 1234.961 100.00% 1234.961

### #NAME?
Sump Bricks Work Cum 4 1.450 0.250 0.900 1.305
5p Pile Caps Cum 2 3.900 0.250 1.000 1.950
5p Pile Caps Cum 2 2.300 0.250 1.000 1.150
3 P Pile Cap Cum 1 8.800 0.250 0.800 1.760

Total Quantity Sqm 6.165 100.00% 6.165


Previous Quantity Sqm -1.305
This Bill Quantity Sqm 4.860

9 th RA bill
Brick work 6 pipe cap Cu m 2 4.3 0.25 0.900 1.935
2 2.3 0.25 0.900 1.035
1 4.3 0.25 0.600 0.645
Total = 3.615 100.00% 3.615
10 th RA bill
3 pile cap cu m 1 8.938 0.25 0.800 1.788
Raft side cu m 1 18.861 0.25 0.300 1.415
12 th RA
JMR NO-32 CU M 1 2.5 0.125 0.900 0.281
,, CU M 2 2.4 0.125 0.250 0.150
,, CU M 2 2.1 0.125 0.100 0.053
JMR NO-44 CU M 1 1.5 0.125 0.800 0.150
,, CU M 5 2.4 0.125 0.250 0.375
,, CU M 3 2.1 0.125 0.150 0.118
JMR NO-52 CU M 1 6.2 0.125 0.850 0.659
Total = 4.988 100.00% 4.988
### #NAME?
3pile cap Sqm 2 1.050 0.800 1.680
Sqm 2 2.550 0.800 4.080
Sqm 4 0.800 0.800 2.560
Sqm 4 1.500 0.800 4.800
Beam Sqm 2 3.000 0.450 2.700
Beam Sqm 4 3.000 0.600 7.200

Total Quantity Sqm 23.020 0.00% 0.000


Previous Quantity Sqm #NAME?
This Bill Quantity Sqm #NAME?

### Pile Breaking 450 mm dia


RM 50.000 50.000

Total Quantity RM 50.000 100.00% 50.000


Previous Quantity RM -50.000
This Bill Quantity RM 0.000

### Pile Breaking 500 mm dia


RM 57.350 57.350
JMR page no 70 RM 2.500 2.500
JMR page no 72 RM 49.350 49.350
JMR page no 73 RM 8.600 8.600
13 th RA JMR no 70A RM 45.950
14 TH RA RM 55.800
Total Quantity RM 219.550 100.00% 219.550
Previous Quantity RM -57.350
This Bill Quantity RM 162.200
9 th RA bill
Pile head bracking JMR no-86 RM 13.500 100.00% 13.500

10 th RA bill RM 10.000 100.00% 10.000

7.00 Silver Sand Filling


Silver Sand Filling at Tank-1 Cum 1 12.100 3.230 0.700 27.358
Silver Sand Filling at Tank-2 Cum 1 12.100 3.230 0.700 27.358
12 th RA 0.003
2nd existing tank filling 100.000
cu m 1 5.000 4.700 0.000 0.000
Total Quantity RM 154.719 100.00% 154.719
Previous Quantity RM -54.716
This Bill Quantity RM 100.003

10 th RA bill
Sand filling pile cap side cu m 11.299 100.00% 11.299

### Bollah Pilling


Assana side RM 1 12.400
RM 1 11.000
admin Side RM 1 12.750
RM 1 4.600
Hospital Side RM 1 23.700
64.450
Total Quantity RM 64.450 60.00% 38.670
Previous Quantity RM -38.670
This Bill Quantity RM 0.000

### Reinforcement Steel

1st Lot (17.06.2023) 13.742


2nd Lot (25.06.2023) 17.071
3rd Lot 2.327
4th Lot 18.000

Total Quantity MT 51.140 80.00% 40.912


Previous Quantity MT -26.450
This Bill Quantity MT 14.462

11 TH ra bill BBS SUBMITED 43.356 100.00% 43.356


12 th RA BBS 7.559 7.559
13 th Ra BBS MT 11.504 11.504
14 TH RA BBS MT 21.700 21.700
Total = 84.119

48.10 RCC Dismantling work


JMR page no 44 Cum 0.066
JMR page no 51 Cum 14.509
JMR page no 55 Cum 17.601
JMR page no 63 Cum 2.975
JMR page no 68 Cum 12.345
JMR page no 70 Cum 2.396
JMR page no 73 Cum 0.756
JMR page no 47 Cum 0.220
JMR page no 51 Cum 0.918
JMR page no 69 Cum 4.120
cu m
Total Quantity Cum 55.906 100.00% 55.906
Previous Quantity MT -55.972
This Bill Quantity Cum -0.066

9 th RA bill
R.C.C dismantling JMR no-84 cu m 1.900 100.00% 1.900
11 th RA
JMR page no-44 Cum 0.066
JMR page no-36 (Paid RA-6) 0.000
JMR page no-37 (Paid RA-6) 0.000
JMR page no-39 (Paid RA-6) 0.000
JMR page no-69 Cum 0.000
JMR page no-77 1.250
JMR page no-82 12.970
JMR page no-3A 0.875
JMR page no-15A 1.125
16.286
Tank Dismantling work ext-Fire tank
Tank Slab Cum 1 5 5.6 0.2 5.600
wall 1 10.9 0.3 3.45 11.2815
Middle slab 1 5 5.6 0.25 7.000
Bottom slab 1 5 5.6 0.4 11.200
Manhole cover wall 2 3.2 0.2 0.6 0.768
12 th ra jmr no-33 0.27
12 th RA for tank dismantling work Cum 28.10
for 3 pile cap Cum Total= 64.220
13 RA BILL Cu m 0.903
14 TH RA 1.645
Cum Grand total 83.054 100.00% 83.054
37.00 Brick work Dismantling
JMR page no 47 Cum 0.168
JMR page no 51 Cum 2.435
JMR page no 56 Cum 13.990
JMR page no 63 Cum 2.677
JMR page no 69 Cum 18.645

Total Quantity Cum 37.915 100.00% 37.915


Previous Quantity MT -37.915
This Bill Quantity Cum 0.000
9 th RA bill
Brickwork dismantling JMR no-84 Cum 1.350 100.00% 1.350
12 th RA JMR no-27 cu m 1.242 100.00% 1.242

25.10 SHEET PILE WORKS


U Type Sheet MT 27.562 Work done 100%
U Type Sheet
U Type Sheet 33 MT 26.752 Work done 100%
ISMB 400 MT 4.630 Supporting Work done 100%
ISMB 400 MT 2.315 Supporting WIP
ISMB 400 MT 28.000 ISMB WIP
Total Quantity (Up to 9th RA) MT 89.259 95.00% 84.796

MT 4.000 4.000
10th RA (Oxygen room to SW1 pile cap side)
Total quantity up to 10th RA MT 88.796

16 Re-bar Grouting
Providing & doing Mechanical rebar grouting with
approved make chemical & authorized agencies of Hilti
or Fisher etc. including cost of all materials, tools &
tackle complete as per drawing & direction of EIC.

73 8 T Bar 19.000 100.00% 19.000


74 10 T Bar 12.000 100.00% 12.000
75 12 T Bar 33.000 100.00% 33.000
BAR BENDING SCHEDULE
Project : NBWCCC HOSPITAL EXTENSION AT NEW TOWN
Contractor : M/S S M Nirman Infrastructure& Development Pvt.Ltd.
Length Total length Remarks
M To-
SL. Cutting
Description Shape Dia. e No. tal
NO Length
m. No. A B C D E 8 10 12 16 20 25 32

Footing (1200 x 900) :-

1 bottom bar 10 2 7 14 0.100 1.150 0.100 1.310 - 18.340 - - - - -

2 bottom bar 10 2 9 18 0.100 0.850 0.100 1.010 - 18.180 - - - - -

Footing (900 x 900) :-

1 bottom bar 10 2 7 14 0.100 0.850 0.100 1.010 - 14.140 - - - - -

2 bottom bar 10 2 7 14 0.100 0.850 0.100 1.010 - 14.140 - - - - -

Column (300x200) :- (0.040) - - - - - - -

Vertical Bar 16 4 4 16 0.3 5.6 0.1 5.936 - - - 94.976 - - -

Stirrup 8 4 24 96 0.15 0.25 0.08 0.880 84.480 - - - - - -

Tie Beam (200x400) :- - - - - - - -

Top & Bottom 8 5.486 - - - 43.888 - - -


16 2 4 0.3 4.95 0.3
bar

Stirrup 8 2 34 68 0.15 0.35 0.08 1.080 73.440 - - - - - -

Top & Bottom 8 4.986 - - - 39.888 - - -


16 2 4 0.3 4.45 0.3
bar

Stirrup 8 2 31 62 0.15 0.35 0.08 1.080 66.960 - - - - - -

Roof Beam (200x400) :- - - - - - - -

Top & Bottom 8 5.486 - - - 43.888 - - -


16 2 4 0.3 4.95 0.3
bar

Stirrup 8 2 34 68 0.15 0.35 0.08 1.080 73.440 - - - - - -

Top & Bottom 8 4.986 - - - 39.888 - - -


16 2 4 0.3 4.45 0.3
bar
Stirrup 8 2 31 62 0.15 0.35 0.08 1.080 66.960 - - - - - -

Lintel :- - - - - - - -

Top & Bottom 4 2.736 - - - 10.944 - - -


16 1 4 0.2 2.4 0.2
bar

middle bottom 2.760 - 2.760 - - - - -


10 1 1 1 0.2 2.4 0.2
bar

Stirrup 8 1 17 17 0.15 0.25 0.08 0.880 14.960 - - - - - -

Chajja :- - - - - - - -

Main bar 10 1 16 16 0.225 0.475 0.05 0.35 1.052 - 16.832 - - - - -

Binder 8 1 6 6 0.1 2.4 0.1 0.35 2.560 15.360 - - - - - -

Slab :- - - - - - - -

main bar 8 2 41 82 0.05 4.45 0.05 0.35 4.510 369.820 - - - - - -

LAP 8 1 20 20 0.4 0.400 8.000 - - - - - -

Binder 8 2 37 74 0.05 4.95 0.05 5.050 373.700 - - - - - -

Chair 10 1 20 20 0.4 0.6 0.043 1.486 - 29.720 - - - - -

DG Foundation :- - - - - - - -

binder 10 4 13 52 0.2 5.35 0.2 5.710 - 296.920 - - - - -

Mainbar 10 4 37 148 0.2 1.95 0.2 2.310 - 341.880 - - - - -

Chair 10 1 17 17 0.4 0.6 0.21 1.820 - 30.940 - - - - -

LAP 10 1 20 20 0.5 0.500 - 10.000 - - - - -

Tranceformar Top Foundation :- 100.000

Mainbar 10 2 22 44 0.2 1.55 0.2 1.910 - 84.040 - - - - -

binder 10 2 11 22 0.2 3.15 0.2 3.510 - 77.220 - - - - -

Chair 10 1 6 6 0.4 0.6 0.21 1.820 - 10.920 - - - - -


Mainbar 10 2 61 122 0.1 0.60 0.1 0.800 - 97.600 - - - - -

binder 8 2 4 8 0.1 9.0 0.1 9.200 73.600 - - - - - -

Electric Trench Foundation :- 37 0 15.075 4.95 1.075 0.35 21.060 - - - - - - -

Mainbar 10 2 88 176 0.1 1.15 0.1 1.350 - 237.600 - - - - -

binder 8 2 7 14 0.1 13.5 0.1 13.700 191.800 - - - - - -

Electric Trench Wall :- - - - - - - -

Vertical Bar 10 4 88 352 0.15 1.15 0.1 1.360 - 478.720 - - - - -

binder 8 4 7 28 13.5 13.500 378.000 - - - - - -

U- bar 10 2 26 52 0.4 0.6 0.4 1.400 - 72.800 - - - - -

RCC
PARAPIT 8 4 2 8 5 5.000 40.000 (8.060)
WALL

RCC
PARAPIT 8 15 4 60 0.2 0.1 0.2 0.500 30.000
WALL
Total Length in MTR : 1,860.52 1,944.69 - 273.47
Total Length in M.T : 0.735 1.202 - 0.432

Total Quantity in MT:- 2.369


BAR BENDING SCHEDULE
Project : NBWCCC HOSPITAL EXTENSION AT NEW TOWN
Contractor : M/S S M Nirman Infrastructure& Development Pvt.Ltd. RA-04
Length Total length Remarks
M To-
SL. Cutting
Description Shape Dia. e No. tal
NO Length
m. No. A B C D E 8 10 12 16 20 25 32

TRANCH RAFT

bottom bar &


1 Top bar 10 2 23 46 0.100 1.350 0.100 1.510 - 69.460 - - - - -

bottom bar &


2 Top bar
10 2 80 160 0.100 1.350 0.100 1.510 - 241.600 - - - - -

bottom bar &


3 Top bar
10 2 205 410 0.100 1.350 0.100 1.510 - 619.100 - - - - -

bottom bar &


4 Top bar
10 2 10 20 0.100 1.350 0.100 1.510 - 30.200 - - - - -

Chair 10 1 56 56 1.55 3.100 - 173.600 - - - - -

Vertical Bar 10 2 629 1258 0.15 0.8 0.930 - 1,169.940 - - - - -

U Bar 10 2 47 94 0.7 0.700 - 65.800 - - - - -

1 Raft Binder 8 2 7 14 3.350 3.350 46.900 - - - - - -

1 Raft Binder 8 2 8 16 11.900 11.900 190.400 - - - - - -

1 Raft Binder 8 2 8 16 30.650 30.650 490.400 - - - - - -

1 Raft Binder 8 2 8 16 1.350 1.350 21.600 - - - - - -

1 Lap 8 2 48 96 0.400 0.400 38.400 - - - - - -

Binder 8 2 5 10 94.25 94.250 942.500 - - - - - -

1 Lap 8 2 40 80 0.400 0.400 32.000 - - - - - -


Electrical Room
Floor 8 1 16 16 4.2 4.200 67.200 - - - - - -

Electrical Room
Floor 8 1 15 15 4.7 4.700 70.500 - - - - - -

Less 8 1 3 3 -2.1 (2.100) (6.300) - -

Less 8 1 13 13 -0.6 (0.600) (7.800) - -

Less 8 1 3 3 -4.7 (4.700) (14.100) - -

Less 8 1 5 5 -0.6 (0.600) (3.000) - -

Total Length in MTR : 1,868.70 2,369.70 - -


Total Length in M.T : 0.738 1.464 - -

Total Quantity in MT:- 2.203


Measurement Sheet
Name Of Client: - PROJECT -: NBWCCC HOSPITAL EXTENSION AT NEW TOWN
Name Of Contractor: - M/S S M Nirman Infrastructure& Development Pvt.Ltd.
Name of Project: - NBWCCC KOLKATA
RA Bill No. TILL RA-12 Date
Sl. Breadth
Height
No. Description Unit No Length(M) Total QTY Released % Bill Qty REMARKS.
(M)
(M)
3.10 Earth Excavation
Depth upto 1.5 m.
Boundary Wall & Electrical Treance Cum 7 0.95 0.8 1.000 5.320
Beam Cum 1 21.4 0.4 0.700 5.992
RA-06
Cum
Cum

Total Quantity Cum 169.140 100.00% 169.140


Previous Quantity Cum -157.828
This Bill Quantity Cum 11.312
6.00 Back Filling
Total Quantity Cum 107.668 100.00% 107.668
Previous Quantity Cum #NAME?
This Bill Quantity Cum #NAME?

11.00 All charges for laying Concreate


Measurement Sheet
Name Of Client: - PROJECT -: NBWCCC HOSPITAL EXTENSION AT NEW TOWN
Name Of Contractor: - M/S S M Nirman Infrastructure& Development Pvt.Ltd.
Name of Project: - NBWCCC KOLKATA
RA Bill No. TILL RA-12 Date
Sl. Breadth
Height
No. Description Unit No Length(M) Total QTY Released % Bill Qty REMARKS.
(M)
(M)
Boundary Wall cum 7 0.950 0.800 0.100 0.532
cum 1 21.100 0.400 0.100 0.844
Electrical Trench cum 1 7.500 1.100 0.100 0.825
cum

Total Quantity Cum 15.187 100.00% 15.187


Previous Quantity Cum -12.986
This Bill Quantity Cum 2.201
Measurement Sheet
Name Of Client: - PROJECT -: NBWCCC HOSPITAL EXTENSION AT NEW TOWN
Name Of Contractor: - M/S S M Nirman Infrastructure& Development Pvt.Ltd.
Name of Project: - NBWCCC KOLKATA
RA Bill No. TILL RA-12 Date
Sl. Breadth
Height
No. Description Unit No Length(M) Total QTY Released % Bill Qty REMARKS.
(M)
(M)

13.80 M25 for Footing, base of Column, Plinth Beam (for boundary wall)
Boundary Wall Cum 7 0.750 0.600 0.150 0.473
Cum 7 0.350 0.150 0.368
Column Cum 7 0.250 0.250 1.050 0.459
Tie Beam Cum 1 21.100 0.250 0.350 1.846
Coping Cum 1 21.100 0.250 0.125 0.659
Electrical Trench Cum 1 7.500 1.400 0.200 2.100
Wall Cum 2 7.500 0.150 1.050 2.363
Cable trench slab Cum 1 7.500 1.100 0.150 1.238
Cable trench slab Cum 1 31.655 1.100 0.125 4.353

Total Quantity Cum 59.765 100.00% 59.765


Previous Quantity Cum -45.907
This Bill Quantity Cum 13.858
14.60 Footing, Plinth Beam (for boundary wall) Shuttering work
Boundary Wall footing Sqm 7 2.700 0.150 2.835
Column Sqm 7 1.000 1.050 7.350
Tie Beam Sqm 2 21.100 0.350 14.770
Coping Sqm 2 21.100 0.125 5.275
Electrical Trench slab Sqm 2 7.500 0.200 3.000 RA-06
Wall Sqm 4 7.500 1.050 31.500
Slab Sqm 1 7.500 0.800 6.000
Slab Sqm 2 7.500 0.125 1.875
Slab Sqm 1 31.650 0.800 25.320
Side Sqm 2 31.650 0.125 7.913
Front Side Sqm 26 1.100 0.125 3.575

Total Quantity Sqm 414.862 100.00% 414.862


Previous Quantity Sqm -305.450
This Bill Quantity Sqm 109.412
### #NAME?

Boundary Wall Cum 1 20.000 0.250 0.650 3.250 RA-06

Total Quantity Sqm 18.072 100.00% 18.072


Previous Quantity Sqm -14.822
This Bill Quantity Sqm 3.250
### #NAME?
Boundary Wall Sqm 2 21.400 0.875 37.450

Total Quantity Sqm 114.385 100.00% 114.385


Previous Quantity Sqm -76.935
This Bill Quantity Sqm 37.450
Fine yelloe Sand Filling (Zone-IV)
Cable trench transforma to smn office Cum 10.05 0.8 0.550 4.422
DO Cum 2.3 0.6 0.550 0.759 Difference
DO Cum 2.8 0.8 0.250 0.560 Amount will be
claim.
Smn office to meter room Cum 30.8 0.8 0.250 6.160 Silversand vs
DO Cum 1.5 0.8 0.250 0.300 red sand

Total Quantity Cum 12.201 100.00% 12.201


Previous Quantity Cum 0.000
This Bill Quantity Cum 12.201

Green net fixing


193.000

Total Quantity Cum 193.000 0.00% 0.000


Measurement Sheet
Name Of Client: - PROJECT -: NBWCCC HOSPITAL EXTENSION AT NEW TOWN
Name Of Contractor: - M/S S M Nirman Infrastructure& Development Pvt.Ltd.
Name of Project: - NBWCCC KOLKATA
RA Bill No. TILL RA-12 Date
Sl. Breadth
Height
No. Description Unit No Length(M) Total QTY Released % Bill Qty REMARKS.
(M)
(M)
Previous Quantity Cum 0.000
This Bill Quantity Cum 0.000
Measurement Sheet
Name Of Client: - PROJECT -: NBWCCC HOSPITAL EXTENSION AT NEW TOWN
Name Of Contractor: - M/S S M Nirman Infrastructure& Development Pvt.Ltd.
Name of Project: - NBWCCC KOLKATA
RA Bill No. TILL RA-14 Date
Sl. No. Breadth
Height
Description Unit No Length(M) Total QTY Released % Bill Qty REMARKS.
(M)
(M)

3.10 Earth Excavation


Depth upto 1.5 m.
Adim Bock EGL +450
11 th RA

Cum 18.65 5 1.500 139.875


Water reservoir tank Portion (3 nos taken) 1
C1, C2 column pile cap cu m 2 2.45 1.05 1.500 7.718
C5, C12 column pile cap cu m 2 3.55 2.45 1.500 26.078
C8 column pile cap cu m 1 3.95 2.45 1.500 14.516
C4 column pile cap cu m 1 2.45 2.25 1.500 8.269
Deduction cu m -1 1.3 0.75 1.500 -1.463
C7, C10 column lift area cu m 1 3.548 2.45 1.500 13.039
Lift area cu m 1 1.617 2.95 1.500 7.155
12TH RA 0.000
Water reservoir tank 4th part cu m 1 5.2 5 1.500 39.000
C11, C14, C15, C16, C3 column pile cap cu m 5 2.45 1.05 1.500 19.294
C6, C9, C13 column pile cap cu m 3 2.45 2.25 1.500 24.806
Deduction cu m -3 1.3 0.75 1.500 -4.388
Tie beam C1-C14 cu m 1 18.75 0.4 1.025 7.687
Tie beam C2-C15 cu m 1 18.8 0.4 1.025 7.708
Tie beam C3-c16 cu m 1 19.85 0.4 1.025 8.138
Tie beam C4-C6 cu m 1 9.15 0.4 1.025 3.751
Tie Beam C11-C13 cu m 1 9.15 0.4 1.025 3.751
Tie beam C14-C6 cu m 1 8.05 0.35 1.625 4.578
Tie beam C1-C3 cu m 1 8.55 0.35 1.025 3.067
Tie beam C8-C9 cu m 1 5.5 0.4 1.025 2.255
Tie beam Lift- TB-2 cu m 2 2.3 0.4 1.025 1.886
Tie beam stair cu m 1 4.8 0.4 1.025 1.968
13 th RA 0.000
Stair bottom cu m 1 2 0.5 0.225 0.225

Total Quantity Cum 338.916 100.00% 338.916


Previous Quantity Cum
This Bill Quantity Cum
For additional depth beyond 1.5 m. and
3.20 upto 3.00 m.
Tank Portion Cum 1 18.65 5 1.275 118.894
C1, C2 area cu m 2 2.45 1.05 0.450 2.315
C5, C12 area cu m 2 3.55 2.45 0.450 7.823
C8 area cu m 1 3.95 2.45 0.450 4.355
C4 area cu m 1 2.45 2.25 0.450 2.481
Deduction cu m -1 1.3 0.75 0.450 -0.439
C7, C10 area cu m 1 3.548 2.45 1.475 12.822
Lift area cu m 1 1.617 2.95 0.625 2.981
12 th RA 0.000
Water reservoir tank 4th part cu m 1 5.2 5 1.275 33.150
sumu portion cu m 1 2 2 0.550 2.200
C11, C14, C15, C16, C3 column pile cap cu m 5 2.45 1.05 0.450 5.788
C6, C9, C13 column pile cap cu m 3 2.45 2.25 0.450 7.442
Deduction cu m -3 1.3 0.75 0.450 -1.316
Total Quantity Cum 198.496 100.00% 198.496
Previous Quantity Cum
This Bill Quantity Cum
3.30 For additional depth beyond 3.00 m.
0.000

Total Quantity Cum 0.000 100.00% 0.000


Previous Quantity Cum
This Bill Quantity Cum
6.00 Back Filling
12 th RA
Tank portion cu m 5 5.8 0.5 2.075 30.088
,, cu m 2 24.85 0.5 2.325 57.776
sumu portion cu m 1 8 0.5 0.550 2.200
2 pile cap cu m 7 8.4 0.5 1.700 49.980
3 pile cap cu m 4 9.7 0.5 1.700 32.980
5 pile cap cu m 2 13.4 0.5 1.700 22.780
5PC cu m 1 17 0.5 1.700 14.450
6 pile cap cu m 1 14.2 0.5 1.700 12.070
Tie beam C1-C14 cu m 2 18.75 0.5 0.500 9.375
Tie beam C2-C15 cu m 2 19.3 0.5 0.500 9.650
Tie beam C3-c16 cu m 2 20.85 0.5 0.500 10.425
Tie beam C4-C6 cu m 2 10.65 0.5 0.500 5.325
Tie Beam C11-C13 cu m 2 10.15 0.5 0.500 5.075
Tie beam C14-C6 cu m 2 9.05 0.5 1.200 10.860
Tie beam C1-C3 cu m 2 9.05 0.5 0.500 4.525
Tie beam C8-C9 cu m 2 4.1 0.5 0.500 2.050
Tie beam Lift- TB-2 cu m 4 2.3 0.5 0.500 2.300
Tie beam stair cu m 2 4.8 0.5 0.500 2.400
Hold due to not completed work L/S Cum -75.000
Total Quantity Cum 209.309 100.00% 209.309
Previous Quantity Cum
This Bill Quantity Cum

8.00 75 mm Brick Flat soling

0.000 100.00% 0.000

12.00 All charges for laying Concreate PCC (1:3:6)


11 th RA 0.000
Tank Portion Cum 1 18.65 5 0.100 9.325
C1, C2 area cu m 2 2.45 1.05 0.075 0.386
C5, C12 area cu m 2 3.55 2.45 0.075 1.304
C8 area cu m 1 3.95 2.45 0.075 0.726
C4 area cu m 1 2.45 2.25 0.075 0.413
Deduction cu m -1 1.3 0.75 0.075 -0.073
C7, C10 area cu m 1 3.548 2.45 0.075 0.652
Lift area cu m 1 1.617 2.95 0.075 0.358
12TH RA 0.000
Water reservoir tank 4th part cu m 1 5.2 5 0.100 2.600
sump cu m 1 2 2 0.075 0.300
C11, C14, C15, C16, C3 column pile cap cu m 5 2.45 1.05 0.075 0.965
C6, C9, C13 column pile cap cu m 3 2.45 2.25 0.075 1.240
Deduction cu m -3 1.3 0.75 0.075 -0.219
Tie beam C1-C14 cu m 1 21.25 0.4 0.075 0.638
Tie beam C2-C15 cu m 1 21.3 0.4 0.075 0.639
Tie beam C3-c16 cu m 1 22.35 0.4 0.075 0.670
Tie beam C4-C6 cu m 1 11.65 0.4 0.075 0.350
Tie Beam C11-C13 cu m 1 11.65 0.4 0.075 0.350
Tie beam C14-C6 cu m 1 10.55 0.35 0.075 0.277
Tie beam C1-C3 cu m 1 10.55 0.35 0.075 0.277
Tie beam C8-C9 cu m 1 7 0.4 0.075 0.210
Tie beam Lift- TB-2 cu m 2 2.3 0.4 0.075 0.138
Tie beam stair cu m 1 4.8 0.4 0.075 0.144
JMR NO-40 cu m 6 0.580 0.350 0.250 0.305
Tank inside cu m 2 4.300 3.700 0.080 2.546
Tank inside cu m 2 5.475 3.700 0.080 3.241
13 th RA
stair bottom cu m 1 2.000 0.500 0.075 0.075

Total Quantity Cum 27.834 100.00% 27.834


Cum
46.00 M-25 concreting
11 th RA
Tank Raft Cum 1 18.55 4.8 0.250 22.260
1 st tank wall cu m 1 17 0.25 1.875 7.969
1st tank slab cu m 1 4.8 4.2 0.200 4.032
2nd & 3rd tank wall cu m 2 19.35 0.25 1.875 18.141
3rd & 3rd tank slab cu m 2 5.975 4.2 0.200 10.038
Deduction -10.204
Total Quantity Cum 52.235 100.00% 52.235

45.00 M-25 concreting (Lintel & Chajja)


12 th RA
4 th tank raft cu m 1 5.1 4.8 0.250 6.120
tank wall cu m 1 18 1.875 0.250 8.438
tank slab cu m 1 4.8 4.2 0.200 4.032
sump raft cu m 1 1.7 1.7 0.250 0.722
sump wall cu m 1 4.6 0.25 0.800 0.920
Total Quantity Cum 20.232 100.00% 20.232

47.00 M-25 concreting ( boundery wall)


3rd & 3rd tank slab cu m 2 5.975 4.2695 0.200 10.204

10.204 100.00% 10.204


42.00 M-30 concreting
11 th RA
C1, C2 Pilecap cu m 2 2.3 0.9 0.900 3.726
C5, C12 Pilecap cu m 2 3.398 2.30 1.050 16.412
C8 Pilecap cu m 1 3.8 2.3 1.100 9.614
C4 Pilecap cu m 1 2.4 2.1 0.950 4.788
Deduction cu m -1 1.3 0.75 0.950 -0.926
C7, C10 Pilecap cu m 1 3.398 2.3 1.100 8.597
Lift raft cu m 1 1.542 2.8 0.250 1.079
Lift wall cu m 1 8.900 0.250 1.800 4.005
12 th RA 0.000
C11, C14, C15, C16, C3 column pile cap cu m 5 2.3 0.9 0.900 9.315
C6, C9, C13 column pile cap cu m 3 2.3 2.1 0.950 13.766
Deduction cu m -3 1.3 0.75 0.950 -2.779
Tie beam C1-C14 cu m 1 21.25 0.25 0.500 2.656
Tie beam C2-C15 cu m 1 21.3 0.25 0.500 2.662
Tie beam C3-c16 cu m 1 22.35 0.25 0.500 2.794
Tie beam C4-C6 cu m 1 11.65 0.25 0.500 1.456
Tie Beam C11-C13 cu m 1 11.65 0.25 0.500 1.456
Tie beam C14-C6 cu m 1 10.55 0.2 0.500 1.055
Tie beam C1-C3 cu m 1 10.55 0.2 0.500 1.055
Tie beam C8-C9 cu m 1 7 0.25 0.500 0.875
Tie beam Lift- TB-2 cu m 2 2.3 0.25 0.500 0.575
Tie beam stair cu m 1 4.8 0.25 0.500 0.600
Column C1,C2,C3,C11,C14.C5,C16 (pile cap to
cu m 7 0.750 0.200 3.600 3.780
1st floor top)
C4,C6,C9,C13 column (cap to 1st floor) cu m 4 0.500 0.300 3.550 2.130
C7,C10 column (same) cu m 2 0.750 0.250 3.000 1.125
C5,C12 column (same) cu m 2 0.600 0.350 3.450 1.449
C8 column (Same) cu m 1 0.750 0.350 3.400 0.893
13 th RA Bill
Manhole cu m 4 3.200 0.200 0.210 0.538
2nd floor Column C1,C2,C3,C11,C14.C5,C16 1st
cu m 7 0.750 0.200 3.450 3.623
to 2nd floor
C4,C6,C9,C13 column (Same) cu m 4 0.500 0.300 3.450 2.070
C7,C10 column cu m 2 0.750 0.250 3.450 1.294
C5,C12 column cu m 2 0.600 0.350 3.450 1.449
C8 column cu m 1 0.750 0.350 3.450 0.906
1st floor slab soffit A cu m 1 2.400 1.800 0.110 0.475
Deduction column projection 5 nos Cum -4 0.400 0.100 0.110 -0.018
Slab soffit B cu m 1 4.800 4.650 0.150 3.348
Slab soffit C cu m 1 5.000 4.800 0.150 3.600
Slab soffit D cu m 1 6.175 2.250 0.110 1.528
Slab soffit E cu m 1 6.175 2.250 0.110 1.528
Beam 1BX-1/1 (200x600) cu m 1 3.800 0.200 0.600 0.456
1BX-1/2 - (200x600) cu m 1 6.750 0.200 0.600 0.810
1BX-2/1 -(250x500) cu m 1 4.650 0.250 0.550 0.639
1BX -2/2 (300x600) cu m 1 7.000 0.300 0.600 1.260
1BX-3 (250x550) cu m 1 4.550 0.250 0.550 0.626
1BX-5 (250X600) cu m 1 4.550 0.250 0.600 0.683
1BX-4(300x600) cu m 1 7.000 0.300 0.600 1.260
1BX 6/1( .25X550) cu m 1 4.650 0.250 0.550 0.639
1BX 6/2 (300x600) cu m 1 7.000 0.300 0.600 1.260
1BX 7/1 (200x600) cu m 1 3.800 0.200 0.600 0.456
1BX 7/2 (200x600) cu m 1 6.750 0.200 0.600 0.810
1BY-1A(250x550) cu m 1 5.000 0.250 0.550 0.688
1BY-1/3 (250x550) cu m 1 1.300 0.250 0.550 0.179
1BY-1/2 (250X550) cu m 1 4.400 0.250 0.550 0.605
1BY-1/1 (250x550) cu m 1 5.000 0.250 0.550 0.688
1by 3/4 (250x550) cu m 1 5.000 0.250 0.550 0.688
1BY 3/3 (250X550) Ccu m 1 5.450 0.250 0.550 0.749
1BY 3/2 (.25X.55) cu m 1 5.850 0.250 0.550 0.804
1BY-3/1 (250X5550) cu m 1 5.000 0.250 0.550 0.688
1BY-2(250X400) cu m 1 1.800 0.250 0.400 0.180
1BY 3A/2/1 (250X5550) cu m 2 6.175 0.250 0.550 1.698
1BY -4/4 (250x550) cu m 1 5.000 0.250 0.550 0.688
1BY-4/3(250x550) cu m 1 6.175 0.250 0.550 0.849
1BY-4/2 (250X550) cu m 1 6.175 0.250 0.550 0.849
1BY-4/1 (250x550) cu m 1 5.000 0.250 0.550 0.688
2nd floor slab 0.000
Slab soffit A cu m 1 2.400 1.800 0.110 0.475
Slab soffit B cu m 1 4.800 2.050 0.110 1.082
Slab soffit C cu m 1 4.800 2.350 0.110 1.241
Slab soffit D cu m 1 4.800 2.300 0.110 1.214
Slab soffit E cu m 1 4.800 2.450 0.110 1.294
Slab soffit F cu m 1 7.250 5.000 0.200 7.250
Slab soffit G cu m 1 7.250 6.175 0.200 8.954
Slab Soffit H cu m 1 7.250 6.175 0.200 8.954
Slab Soffit I cu m 1 7.250 5.000 0.200 7.250
Slab soffit J cu m 1 5.000 4.800 0.150 3.600
Beam 2BX-1/1 (200x600) cu m 1 3.800 0.200 0.600 0.456
2BX-1/2 - (200x600) cu m 1 6.750 0.200 0.600 0.810
2BX-2/1 -(250x550) cu m 1 4.650 0.250 0.550 0.639
2BX -2/2 (300x600) cu m 1 7.000 0.300 0.600 1.260
2BX-3 (250x625) cu m 1 4.550 0.250 0.625 0.711
2BX-5 (250X550) cu m 1 4.550 0.250 0.550 0.626
2BX-4(300x600) cu m 1 7.000 0.300 0.600 1.260
2BX-5A (250x400) cu m 1 4.800 0.250 0.400 0.480
2BX 6/1( .25X550) cu m 1 4.800 0.250 0.550 0.660
2BX 6/2 (300x600) cu m 1 7.000 0.300 0.600 1.260
2BX 7/1 (200x600) cu m 1 3.800 0.200 0.600 0.456
2BX 7/2 (200x600) cu m 1 6.750 0.200 0.600 0.810
2BX-5A (250x400) cu m 1 4.800 0.250 0.400 0.480
2BY-1A(250x550) cu m 1 5.000 0.250 0.550 0.688
2BY-1/3 (250x550) cu m 1 1.300 0.250 0.550 0.179
2BY-1/2 (250X550) cu m 1 4.400 0.250 0.550 0.605
2BY-1/1 (250x550) cu m 1 5.000 0.250 0.550 0.688
2BY 3/4 (250x550) cu m 1 5.000 0.250 0.550 0.688

2BY 3/3 (250X550) Ccu m 1 5.450 0.250 0.550 0.749

2BY 3/2 (.25X.55) cu m 1 5.850 0.250 0.550 0.804


2BY-3/1 (250X5550) cu m 1 5.000 0.250 0.550 0.688
2BY-2(250X400) cu m 1 1.800 0.250 0.400 0.180
2BY -4/4 (250x550) cu m 1 5.000 0.250 0.550 0.688
2BY-4/3(250x550) cu m 1 6.175 0.250 0.550 0.849
2BY-4/2 (250X550) cu m 1 6.175 0.250 0.550 0.849
2BY-4/1 (250x550) cu m 1 5.000 0.250 0.550 0.688
Projection cu m 1 12.800 0.375 0.150 0.720
Stair bottom wall cu m 1 2.000 0.600 0.200 0.240
Stair bottom raft cu m 1 2.100 0.400 0.150 0.126
Stair 1 st Flight (GF to 1st floor) cu m 1 2.083 2.000 0.150 0.625
1st Landing cu m 1 2.000 2.000 0.150 0.600
2nd Flight cu m 1 2.000 0.750 0.150 0.225
2nd Landing cu m 1 2.100 2.000 0.150 0.630
3 rd flight cu m 1 2.083 2.000 0.150 0.625
3rd Landing cu m 1 2.400 2.000 0.150 0.720
4 th Flight cu m 1 2.000 0.400 0.150 0.120
4 th Landing cu m 1 2.100 2.000 0.150 0.630
HLB (.25x.625) cu m 1 4.700 0.250 0.600 0.705
Racker Beam cu m 1 6.073 0.250 0.550 0.835
Steps cu m 7.5 2.000 0.300 0.150 0.675
1st floor to 2nd floor 0.000
Stair 1 st Flight cu m 1 2.083 2.050 0.150 0.641
1st Landing cu m 1 2.100 2.000 0.150 0.630
2nd Flight cu m 1 2.000 0.750 0.150 0.225
2nd Landing cu m 1 2.100 2.000 0.150 0.630
3 rd flight cu m 1 2.830 2.000 0.150 0.849
3rd Landing cu m 1 2.100 2.000 0.150 0.630
4 th Flight cu m 1 2.000 0.750 0.150 0.225
4 th Landing cu m 1 2.100 2.000 0.150 0.630
HLB (.25x.625) cu m 1 4.700 0.250 0.625 0.734
Racker Beam cu m 1 6.073 0.250 0.550 0.835
Steps cu m 8 2.050 0.300 0.150 0.738

Total Quantity Cum 205.242 100.00% 205.242


Previous Quantity Cum
This Bill Quantity Cum

14 TH RA
13.40 M-30 CONCRETE CU M

3RD FLOOR SLAB NO 1 CU M 1 4.8 2.45 0.110 1.294


4th FLOOR SLAB NO 2 CU M 1 4.8 2.3 0.110 1.214
5th FLOOR SLAB NO 3 CU M 1 4.8 2.35 0.110 1.241
6th FLOOR SLAB NO 4 CU M 1 4.8 2.05 0.110 1.082
7th FLOOR SLAB NO 5 CU M 1 2.4 1.8 0.110 0.475
8th FLOOR SLAB NO 6 CU M 1 4.8 2.6 0.110 1.373
9th FLOOR SLAB NO 7 CU M 1 4.8 2.15 0.110 1.135
10th FLOOR SLAB NO 8 CU M 1 5 1.5 0.110 0.825
11th FLOOR SLAB NO 9 CU M 1 6.175 1.5 0.110 1.019
12th FLOOR SLAB NO 9A CU M 1 6.175 1.5 0.110 1.019
13th FLOOR SLAB NO 8A CU M 1 5 1.5 0.110 0.825
14th FLOOR SLAB NO 10 CU M 1 5 2.65 0.110 1.458
15th FLOOR SLAB NO 11 CU M 1 6.175 2.65 0.110 1.800
16th FLOOR SLAB NO 11A CU M 1 6.175 2.65 0.110 1.800
17th FLOOR SLAB NO 10A CU M 1 5 2.65 0.110 1.458
18th FLOOR SLAB NO 12 CU M 1 5 2.6 0.110 1.430
19th FLOOR SLAB NO 13 CU M 1 6.175 2.6 0.110 1.766
20th FLOOR SLAB NO 13A CU M 1 6.175 2.6 0.110 1.766
21st FLOOR SLAB NO 12A CU M 1 5 2.6 0.110 1.430
0.000
Beam 3BX-1/1 (200x600) cu m 1 3.800 0.200 0.600 0.456
3BX-1/2 - (200x600) cu m 1 6.750 0.200 0.600 0.810
3BX-2/1 -(250x550) cu m 1 4.650 0.250 0.550 0.639
3BX -2/2 (300x600) cu m 1 7.000 0.300 0.600 1.260
3BX-3 (250x625) cu m 1 4.550 0.250 0.625 0.711
3BX-5 (250X550) cu m 1 4.550 0.250 0.550 0.626
3BX-4(300x600) cu m 1 7.000 0.300 0.600 1.260
3BX-5A (250x400) cu m 2 4.800 0.250 0.400 0.960
3BX 6/1( .25X550) cu m 1 4.800 0.250 0.550 0.660
3BX 6/2 (300x600) cu m 1 7.000 0.300 0.600 1.260
3BX 7/1 (200x600) cu m 1 3.800 0.200 0.600 0.456
3BX 7/2 (200x600) cu m 1 6.750 0.200 0.600 0.810
3BX-1A(250x400) cu m 1 4.800 0.250 0.400 0.480
3BY-1A(2500X550) cu m 1 5.000 0.250 0.550 0.688
3BY-1/3 (250x550) cu m 1 1.300 0.250 0.550 0.179
3BY-1/2 (250X550) cu m 1 4.400 0.250 0.550 0.605
3BY-1/1 (250x550) cu m 1 5.000 0.250 0.550 0.688
3BY 3/4 (250x550) cu m 1 5.000 0.250 0.550 0.688

3BY 3/3 (250X550) Ccu m 1 5.450 0.250 0.550


0.749
3BY 3/2 (.25X.55) cu m 1 5.850 0.250 0.550 0.804
3BY-3/1 (250X5550) cu m 1 5.000 0.250 0.550 0.688
3BY-2(250X400) cu m 1 1.800 0.250 0.400 0.180
3BY -4/4 (250x550) cu m 1 5.000 0.250 0.550 0.688
3BY-4/3(250x550) cu m 1 6.175 0.250 0.550 0.849
3BY-4/2 (250X550) cu m 1 6.175 0.250 0.550 0.849
3BY-4/1 (250x550) cu m 1 5.000 0.250 0.550 0.688
3BY-3A/1,3A/4 (250x550) cu m 4 5.000 0.250 0.550 2.750
3BY-3A/3,3A/4 9250X550) cu m 4 6.175 0.250 0.550 3.396
Projection cu m 1 12.800 0.375 0.150 0.720

2nd floor Column C1,C2,C3,C11,C14.C5,C16


cu m 7 0.750 0.200 3.000
2nd floor to 3rd floor
3.150
C4,C6,C9,C13 column (Same) cu m 4 0.500 0.300 3.000 1.800
C7,C10 column cu m 2 0.750 0.250 3.000 1.125
C5,C12 column cu m 2 0.600 0.350 3.000 1.260
C8 column cu m 1 0.750 0.350 3.000 0.787
2nd floor to 3rd floor 0.000
Stair 1 st Flight cu m 1 2.083 2.050 0.150 0.641
1st Landing cu m 1 2.100 2.000 0.150 0.630
2nd Flight cu m 1 2.000 0.750 0.150 0.225
2nd Landing cu m 1 2.100 2.000 0.150 0.630
3 rd flight cu m 1 2.830 2.000 0.150 0.849
3rd Landing cu m 1 2.100 2.000 0.150 0.630
4 th Flight cu m 1 2.000 0.750 0.150 0.225
4 th Landing cu m 1 2.100 2.000 0.150 0.630
HLB (.25x.625) cu m 1 4.700 0.250 0.625 0.734
Racker Beam cu m 1 6.073 0.250 0.550 0.835
Steps cu m 8 2.050 0.300 0.150 0.738
Total Quantity Cum 270.136 100.00% 270.136
Previous Quantity Cum

This Bill Quantity Cum

14.60 Shuttering Work Shuttering work

11 th RA
Tank Raft Sq m 1 46.7 0.250 11.675
1 st tank wall inside Sq m 1 16 1.875 30.000
1st tank wall outside Sq m 1 18 2.075 37.350
1st tank slab Sq m 1 3.7 4.300 15.910
2nd & 3rd tank wall inside Sq m 2 18.35 1.875 68.813
3rd & 3rd tank wall outside Sq m 2 20.35 2.075 84.453
3rd & 3rd tank slab Sq m 2 5.475 3.700 40.515
C1, C2 Pilecap Sq m 2 6.4 0.900 11.520
C5, C12 Pilecap Sq m 2 11.396 1.050 23.932
C8 Pilecap Sq m 1 12.2 1.100 13.420
C4 Pilecap Sq m 1 7.7 0.950 7.315
C7, C10 Pilecap Sq m 1 8.598 0.300 2.579
Lift raft Sq m 1 5.884 0.250 1.471
Lift wall inside Sq m 1 7.900 1.800 14.220
Lift wall outside Sq m 1 9.900 1.800 17.820
12 th RA Sq m 0.000
4 th tank raft Sq m 1 15 0.250 3.750
tank wall Sq m 1 34 2.075 70.550
,, Sq m -1 16 0.200 -3.200
tank slab Sq m 1 4.3 3.700 15.910
sump raft Sq m 1 6.8 0.250 1.700
sump wall Sq m 1 3.6 0.800 2.880
,, Sq m 1 5.6 1.050 5.880
C11, C14, C15, C16, C3 column pile cap Sq m 5 6.4 0.900 28.800
C6, C9, C13 column pile cap Sq m 3 7.7 0.950 21.945
Tie beam C1-C14 Sq m 2 21.25 0.500 21.250
Tie beam C2-C15 Sq m 2 21.3 0.500 21.300
Tie beam C3-c16 Sq m 2 22.35 0.500 22.350
Tie beam C4-C6 Sq m 2 11.65 0.500 11.650
Tie Beam C11-C13 Sq m 2 11.65 0.500 11.650
Tie beam C14-C6 Sq m 2 10.55 0.500 10.550
Tie beam C1-C3 Sq m 2 10.55 0.500 10.550
Tie beam C8-C9 Sq m 2 7 0.500 7.000
Tie beam Lift- TB-2 Sq m 4 2.3 0.500 4.600
Tie beam stair Sq m 2 4.8 0.500 4.800
Column C1,C2,C3,C11,C14.C5,C16 Sq m 7 1.900 3.600 47.880
C4,C6,C9,C13 column Sq m 4 1.600 3.550 22.720
C7,C10 column Sq m 2 2.000 3.000 12.000
C5,C12 column Sq m 2 1.900 3.450 13.110
C8 column Sq m 1 2.200 3.400 7.480
13 th RA Bill Sq m
Manhole Sq m 4 6.400 0.210 5.376
1st to 2nd floor Column
Sq m 7 1.900 3.450 45.885
C1,C2,C3,C11,C14.C5,C16
C4,C6,C9,C13 column Sq m 4 1.600 3.450 22.080
C7,C10 column Sq m 2 2.000 3.450 13.800
C5,C12 column Sq m 2 1.900 3.450 13.110
C8 column Sq m 1 2.200 3.450 7.590
1st floor slab soffit A Sq m 1 2.400 1.800 4.320
Slab soffit B Sq m 1 4.800 4.650 22.320
Slab soffit C Sq m 1 5.000 4.800 24.000
Slab soffit D Sq m 1 6.175 2.250 13.894
Slab soffit E Sq m 1 6.175 2.250 13.894
Beam 1BX-1/1 (200x600) Sq m 1 3.800 1.400 5.320
1BX-1/2 - (200x600) Sq m 1 6.750 1.400 9.450
1BX-2/1 -(250x500) Sq m 1 4.650 1.200 5.580
1BX -2/2 (300x600) Sq m 1 7.000 1.500 10.500
Deduction Sq m -1 2.250 0.110 -0.248
1BX-3 (250x550) Sq m 1 4.550 1.200 5.460
1BX-5 (250X600) Sq m 1 4.550 1.300 5.915
Deduction Sq m -2 2.400 0.110 -0.528
1BX-4(300x600) Sq m 1 7.000 1.500 10.500
Deduction Sq m -2 2.250 0.110 -0.495
1BX 6/1( .25X550) Sq m 1 4.800 1.050 5.040
1BX 6/2 (300x600) Sq m 1 7.000 1.500 10.500
Deduction Sq m -1 2.250 0.110 -0.248
1BX 7/1 (200x600) Sq m 1 3.800 1.250 4.750
1BX 7/2 (200x600) Sq m 1 6.750 1.400 9.450
1BY-1A(250x550) Sq m 1 5.000 1.350 6.750
1BY-1/3 (250x550) Sq m 1 1.300 1.350 1.755
1BY-1/2 (250X550) Sq m 1 4.400 1.200 5.280
1BY-1/1 (250x550) Sq m 1 5.000 1.200 6.000
1by 3/4 (250x550) Sq m 1 5.000 1.350 6.750
1BY 3/3 (250X550) Sq m 1 5.450 1.240 6.758
deduction Sqm -1 2.000 0.150 -0.300
1BY 3/2 (.25X.55) Sq m 1 5.850 1.090 6.377
1BY-3/1 (250X5550) Sq m 1 5.000 1.200 6.000
1BY-2(250X400) Sq m 1 1.800 0.940 1.692
1BY 3A/2/1 (250X5550) Sq m 2 6.175 1.240 15.314
1BY -4/4 (250x550) Sq m 1 5.000 1.350 6.750
1BY-4/3(250x550) Sq m 1 6.175 1.350 8.336
1BY-4/2 (250X550) Sq m 1 6.175 1.350 8.336
1BY-4/1 (250x550) Sq m 1 5.000 1.350 6.750
2nd floor slab Sq m
Slab soffit A Sq m 1 2.400 1.800 4.320
Slab soffit B Sq m 1 4.800 2.050 9.840
Slab soffit C Sq m 1 4.800 2.350 11.280
Slab soffit D Sq m 1 4.800 2.300 11.040
Slab soffit E Sq m 1 4.800 2.450 11.760
Slab soffit F Sq m 1 7.250 5.000 36.250
Slab soffit G Sq m 1 7.250 6.175 44.769
Slab Soffit H Sq m 1 7.250 6.175 44.769
Slab Soffit I Sq m 1 7.250 5.000 36.250
Slab soffit J Sq m 1 5.000 4.800 24.000
Beam 2BX-1/1 (200x600) Sq m 1 3.800 1.250 4.750
2BX-1/2 - (200x600) Sq m 1 6.750 1.200 8.100
2BX-2/1 -(250x550) Sq m 1 4.650 1.050 4.883
2BX -2/2 (300x600) Sq m 1 7.250 1.100 7.975
2BX-3 (250x625) Sq m 1 4.550 1.350 6.143
2BX-5 (250X550) Sq m 1 4.550 1.240 5.642
2BX-4(300x600) Sq m 1 7.000 1.100 7.700
2BX-5A (250x400) Sq m 1 4.800 0.830 3.984
2BX 6/1( .25X550) Sq m 1 4.800 1.130 5.424
2BX 6/2 (300x600) Sq m 1 7.000 1.100 7.700
2BX 7/1 (200x600) Sq m 1 4.800 1.290 6.192
2BX 7/2 (200x600) Sq m 1 6.750 1.200 8.100
2BX-5A (250x400) Sq m 1 4.800 0.830 3.984
2BY-1A(250x550) Sq m 1 5.000 1.200 6.000
2BY-1/3 (250x550) Sq m 1 1.300 1.300 1.690
2BY-1/2 (250X550) Sq m 1 4.400 1.240 5.456
2BY-1/1 (250x550) Sq m 1 5.000 1.240 6.200
2BY 3/4 (250x550) Sq m 1 5.000 1.000 5.000
2BY 3/3 (250X550) Sq m 1 5.450 1.000 5.450
2BY 3/2 (.25X.55) Sq m 1 5.850 1.040 6.084
2BY-3/1 (250X5550) Sq m 1 5.000 1.040 5.200
2BY-2(250X400) Sq m 1 1.800 0.940 1.692
2BY -4/4 (250x550) Sq m 1 5.000 1.150 5.750
2BY-4/3(250x550) Sq m 1 6.175 1.150 7.101
2BY-4/2 (250X550) Sq m 1 6.175 1.150 7.101
2BY-4/1 (250x550) Sq m 1 5.000 1.150 5.750
Projection bottom Sq m 1 12.800 0.375 4.800
side Sqm 1 12.800 0.150 1.920
Projection side Sq m 1 0.750 0.150 0.112
Stair bottom wall Sq m 1 4.500 0.600 2.700
Stair bottom raft Sq m 1 2.900 0.150 0.435
Stair 1 st Flight (GF to 1st floor) soffit Sq m 1 2.083 2.000 4.166
Flght side Sq m 2 2.083 0.150 0.625
1st Landing soffit Sq m 1 2.100 2.000 4.200
Landing side Sq m 1 2.000 0.150 0.300
2nd Flight Sq m 1 2.000 0.750 1.500
Side Sq m 1 0.750 0.150 0.112
2nd Landing Sq m 1 2.100 2.000 4.200
3 rd flight Sq m 1 2.083 2.000 4.166
side Sq m 1 2.083 0.150 0.312
3rd Landing Sq m 1 2.400 2.000 4.800
4 th Flight Sq m 1 2.000 0.400 0.800
side Sq m 1 0.400 0.150 0.060
4 th Landing Sq m 1 2.100 2.000 4.200
HLB (.25x.625) Sq m 1 4.700 1.350 6.345
Racker Beam Sq m 1 6.073 1.200 7.288
riser Sq m 19 2.000 0.150 5.700
Riser side Sq m 15.5 0.300 0.150 0.698
1st floor to 2nd floor Stair Sq m 0.000
Stair 1 st Flight Sq m 1 2.083 2.000 4.166
side Sq m 2 2.226 0.150 0.668
1st Landing Sq m 1 2.100 2.000 4.200
side Sq m 1 2.000 0.150 0.300
2nd Flight Sq m 1 2.000 0.750 1.500
side Sq m 1 0.750 0.150 0.112
2nd Landing Sq m 1 2.100 2.000 4.200
3 rd flight Sq m 1 2.083 2.000 4.166
side Sq m 1 2.083 0.150 0.312
3rd Landing Sq m 1 2.100 2.000 4.200
4 th Flight Sq m 1 2.000 0.750 1.500
side Sq m 1 0.750 0.150 0.112
4 th Landing Sq m 1 2.100 2.000 4.200
HLB (.25x.625) Sq m 1 4.700 1.350 6.345
Racker Beam Sq m 1 6.073 1.200 7.288
riser Sq m 20 2.000 0.150 6.000
Riser side Sq m 16 0.300 0.150 0.720
Total Quantity Sq m 1610.618 100.00% 1610.618
Previous Quantity Sq m
This Bill Quantity Sq m

14.70 14 TH RA
SHUTTERING CU M
3RD FLOOR SLAB NO 1 CU M 1 4.8 2.45 11.760
4th FLOOR SLAB NO 2 CU M 1 4.8 2.3 11.040
5th FLOOR SLAB NO 3 CU M 1 4.8 2.35 11.280
6th FLOOR SLAB NO 4 CU M 1 4.8 2.05 9.840
7th FLOOR SLAB NO 5 CU M 1 2.4 1.8 4.320
8th FLOOR SLAB NO 6 CU M 1 4.8 2.6 12.480
9th FLOOR SLAB NO 7 CU M 1 4.8 2.15 10.320
10th FLOOR SLAB NO 8 CU M 1 5 1.5 7.500
11th FLOOR SLAB NO 9 CU M 1 6.175 1.5 9.263
12th FLOOR SLAB NO 9A CU M 1 6.175 1.5 9.263
13th FLOOR SLAB NO 8A CU M 1 5 1.5 7.500
14th FLOOR SLAB NO 10 CU M 1 5 2.65 13.250
15th FLOOR SLAB NO 11 CU M 1 6.175 2.65 16.364
16th FLOOR SLAB NO 11A CU M 1 6.175 2.65 16.364
17th FLOOR SLAB NO 10A CU M 1 5 2.65 13.250
18th FLOOR SLAB NO 12 CU M 1 5 2.6 13.000
19th FLOOR SLAB NO 13 CU M 1 6.175 2.6 16.055
20th FLOOR SLAB NO 13A CU M 1 6.175 2.6 16.055
21st FLOOR SLAB NO 12A CU M 1 5 2.6 13.000
0.000
Beam 3BX-1/1 (200x600) cu m 1 3.800 1.290 4.902
3BX-1/2 - (200x600) cu m 1 6.750 1.290 8.708
3BX-2/1 -(250x550) cu m 1 4.650 1.240 5.766
3BX -2/2 (300x600) cu m 1 7.000 1.280 8.960
3BX-3 (250x625) cu m 1 4.550 1.350 6.143
3BX-5 (250X550) cu m 1 4.550 1.240 5.642
3BX-4(300x600) cu m 1 7.000 1.280 8.960
3BX-5A (250x400) cu m 2 4.800 0.830 7.968
3BX 6/1( .25X550) cu m 1 4.800 1.130 5.424
3BX 6/2 (300x600) cu m 1 7.000 1.280 8.960
3BX 7/1 (200x600) cu m 1 3.800 1.290 4.902
3BX 7/2 (200x600) cu m 1 6.750 1.290 8.708
3BX-1A(250x400) cu m 1 4.800 0.780 3.744
3BY-1A(2500X550) cu m 1 5.000 1.240 6.200
3BY-1/3 (250x550) cu m 1 1.300 1.350 1.755
3BY-1/2 (250X550) cu m 1 4.400 1.240 5.456
3BY-1/1 (250x550) cu m 1 5.000 1.240 6.200
3BY 3/4 (250x550) cu m 1 5.000 1.130 5.650
3BY 3/3 (250X550) Ccu m 1 5.450 1.240
6.758
3BY 3/2 (.25X.55) cu m 1 5.850 1.130 6.611
3BY-3/1 (250X5550) cu m 1 5.000 1.130 5.650
3BY-2(250X400) cu m 1 1.800 0.940 1.692
Deduction cu m -2 2.400 0.110 -0.528
3BY -4/4 (250x550) cu m 1 5.000 1.240 6.200
3BY-4/3(250x550) cu m 1 6.175 1.240 7.657
3BY-4/2 (250X550) cu m 1 6.175 1.240 7.657
3BY-4/1 (250x550) cu m 1 5.000 1.240 6.200
3BY-3A/1,3A/4 (250x550) cu m 4 5.000 1.130 22.600
3BY-3A/3,3A/4 9250X550) cu m 4 6.175 1.130 27.911
Projection cu m 1 12.800 0.525 6.720
Projection side cu m 1 0.375 0.150 0.056
2nd TO 3RD floor Column
Sq m 7 1.900 3.000
C1,C2,C3,C11,C14.C5,C16 39.900
C4,C6,C9,C13 column Sq m 4 1.600 3.000 19.200
C7,C10 column Sq m 2 2.000 3.000 12.000
C5,C12 column Sq m 2 1.900 3.000 11.400
C8 column Sq m 1 2.200 3.000 6.600
2nd floor to 3rd floor 0.000
Stair 1 st Flight Sq m 1 2.083 2.000 4.166
side Sq m 2 2.226 0.150 0.668
1st Landing Sq m 1 2.100 2.000 4.200
side Sq m 1 2.000 0.150 0.300
2nd Flight Sq m 1 2.000 0.750 1.500
side Sq m 1 0.750 0.150 0.112
2nd Landing Sq m 1 2.100 2.000 4.200
3 rd flight Sq m 1 2.083 2.000 4.166
side Sq m 1 2.083 0.150 0.312
3rd Landing Sq m 1 2.100 2.000 4.200
4 th Flight Sq m 1 2.000 0.750 1.500
side Sq m 1 0.750 0.150 0.112
4 th Landing Sq m 1 2.100 2.000 4.200
HLB (.25x.625) Sq m 1 4.700 1.350 6.345
Racker Beam Sq m 1 6.073 1.200 7.288
riser Sq m 20 2.000 0.150 6.000
Riser side Sq m 16 0.300 0.150 0.720

Total Quantity Cum 580.223 100.00% 580.223


Previous Quantity Cum
This Bill Quantity Cum

### #NAME?
C7 & C10 pilecap Cum 1 12.396 0.125 0.900 1.395
C5, C12 pile cap side cu m 2 3.900 0.125 0.500 0.488
C8 pilecap cu m 1 4.300 0.125 0.500 0.269
12 th RA
JMR NO-55 cu m 2 1.700 0.125 1.150 0.489
,, cu m 2 1.450 0.125 1.150 0.417

Total Quantity Sqm 3.056 100.00% 3.056


Previous Quantity Sqm
This Bill Quantity Sqm
### #NAME?

Total Quantity Sqm 0.000 0.00% 0.000


Previous Quantity Sqm #NAME?
This Bill Quantity Sqm #NAME?

### Pile Breaking 450 mm dia


RM 0.000

Total Quantity RM 0.000 100.00% 0.000


Previous Quantity RM
This Bill Quantity RM

### Pile Breaking 500 mm dia


0.000
JMR page no 13 A RM 25.900 25.900
JMR page no 14A RM 10.600 10.600
JMR page no 21A RM 5.150 5.150
JMR 30,37,39 RM 17.050 17.050
Total Quantity RM 58.700 100.00% 58.700
Previous Quantity RM
This Bill Quantity RM
7.00 Silver Sand Filling

Total Quantity RM 0.000 100.00% 0.000


Previous Quantity RM -54.716
This Bill Quantity RM -54.716
### Bollah Pilling

0.000
Total Quantity RM 0.000 60.00% 0.000
Previous Quantity RM
This Bill Quantity RM

### Reinforcement Steel MT


11 th RA bill MT 17.959 100.00% 17.959
MT
12 th RA MT 5.618 5.618
13 th RA MT 16.500 16.500
This Bill Quantity MT 40.077

13.20 Reinforcement
14 th RA Bill MT 9.835

Total Quantity MT 9.835 100.00% 9.835


Previous Quantity MT
This Bill Quantity MT
48.10 RCC Dismantling work

Total Quantity Cum 0.000 100.00% 0.000


Previous Quantity MT
This Bill Quantity Cum
37.00 Brick work Dismantling

Total Quantity Cum 0.000 100.00% 0.000


Previous Quantity MT
This Bill Quantity Cum

25.10 SHEET PILE WORKS


16 Re-bar Grouting
Providing & doing Mechanical rebar grouting with
approved make chemical & authorized agencies of Hilti
or Fisher etc. including cost of all materials, tools &
tackle complete as per drawing & direction of EIC.

73 8 T Bar 100.00% 0.000


74 10 T Bar 100.00% 0.000
75 12 T Bar 100.00% 0.000
12 th RA
20.10 Plastering 12-15 mm thick Tank inside sq m 2 16 1.875 60.000
Tank inside sq m 2 18.35 1.875 68.813
Tank out side JMR no-41 sq m 2 18 0.400 14.400
,, 2 18.575 0.400 14.860
158.073 100.00% 158.073

You might also like