PROJECT MASTER SCHEDULE


Project: INSTALL WATER SEPARATOR PIPING FOR PHE 23/17/24,4&7
Location: HVBL-HMP
ID Task Outline Task Name Duration Start Finish
Mode Number
March 2024 April 2024
5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22
1 1 1 INSTALL WATER SEPARATOR PIPING FOR PHE 34 days? 3/8/24 4/12/24
2&3, 4&7
2 1.1 1.1 Contract And Purchase 12 days 3/8/24 3/20/24 12 days

3 1.1.1 1.1.1 Letter of award 1 day 3/8/24 3/8/24


3/8 3/8
4 1.1.2 1.1.2 Contract and Advance payment,PO 1 day 3/8/24 3/9/24
3/8 3/9
5 1.1.3 1.1.3 Prepare and purchase material 10 days 3/9/24 3/20/24 10 days
3/9 3/20
6 1.1.3.1 1.1.3.1 Method statement and JSA 1 day 3/9/24 3/11/24
3/9 3/11
7 1.1.3.2 1.1.3.2 Submit for Owner approval 2 days 3/11/24 3/13/24
3/11 3/13
8 1.1.3.3 1.1.3.3 Purchase all material 7 days 3/13/24 3/20/24
3/13 3/20
9 1.2 1.2 Construction work 12 days? 3/20/24 4/2/24 12 days?
3/20 4/2
10 1.2.1 1.2.1 Site temporary work-Handover layout area 2 days? 3/20/24 3/22/24 2 days?
by Heineken 3/20 3/22
11 1.2.1.1 1.2.1.1 Handover layout area by Heineken 1 day? 3/20/24 3/21/24
3/20 3/21
12 1.2.1.2 1.2.1.2 Set up site 1 day 3/20/24 3/21/24
3/20 3/21
13 1.2.1.3 1.2.1.3 Import materials into the factory 1 day? 3/20/24 3/21/24
3/20 3/21
14 1.2.1.4 1.2.1.4 Primer and coasting seamless steel pipe 1 day? 3/21/24 3/22/24
and fitting 3/21 3/22
15 1.2.2 1.2.2 Install pipings from GAD 150 E to PHEs 10 days 3/22/24 4/2/24 10 days
2&3
16 1.2.2.1 1.2.2.1 Mark the support position 1 day 3/22/24 3/23/24
3/22 3/23
17 1.2.2.2 1.2.2.2 Construction of pipe support 3 days 3/23/24 3/26/24
3/23 3/26
18 1.2.2.3 1.2.2.3 Installation the seperator pipe DN20 3 days 3/27/24 3/29/24
Amonia supply/Return 3/27 3/29
19 1.2.2.4 1.2.2.4 Pipe Welding 3 days 3/29/24 4/2/24
3/29 4/2
20 1.2.3 1.2.3 3. Install pipings from GAD 150 E to PHEs 10 days 3/22/24 4/2/24 10 days
4&7
21 1.2.3.1 1.2.3.1 Mark the support position 1 day 3/22/24 3/23/24
3/22 3/23
22 1.2.3.2 1.2.3.2 Construction of pipe support 3 days 3/23/24 3/26/24
3/23 3/26
23 1.2.3.3 1.2.3.3 Installation the seperator pipe DN20 3 days 3/27/24 3/29/24
Amonia supply/Return 3/27 3/29
24 1.2.3.4 1.2.3.4 Pipe Welding 3 days 3/29/24 4/2/24
3/29 4/2
25 1.3 1.3 Project testing. 2 days? 4/2/24 4/4/24 2 days?

26 1.3.1 1.3.1 Pressure Test 1 day? 4/2/24 4/3/24


4/2 4/3
27 1.3.2 1.3.2 Radiography test 10% 1 day? 4/3/24 4/4/24
4/3 4/4
28 1.4 1.4 Pipe Insulation – foam PU and Tie - In 5 days? 4/4/24 4/9/24

29 1.4.1 1.4.1 Tie - In 1 day? 4/4/24 4/4/24


4/4 4/4
30 1.4.2 1.4.2 pipings from GAD 150 E to PHEs 2&3 5 days 4/4/24 4/9/24
insulation 4/4 4/9
31 1.4.3 1.4.3 pipings from GAD 150 E to PHEs 4&7 5 days 4/4/24 4/9/24
insulation 4/4 4/9
32 1.5 1.5 Testing,Defect and Handover acceptance 3 days? 4/9/24 4/12/24 3 days?
4/9 4/12
33 1.5.1 1.5.1 Remove scaffolding and cleaning area 1 day 4/9/24 4/10/24
4/9 4/10
34 1.5.2 1.5.2 Commissioning 1 day? 4/10/24 4/11/24
4/10 4/11
35 1.5.3 1.5.3 Acceptance & Project handover 1 day? 4/11/24 4/12/24
4/11 4/12

Task Inactive Summary External Tasks


Split Manual Task External Milestone
Milestone Duration-only Deadline
Owner: Heineken Vietnam Brewery
BOQ: Q24-077 Summary Manual Summary Rollup Progress
Issued date: 3/16/24 - R0 Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only

Remarks: Page 1 of 1
- Not including public holidays, New year holidays in 2024.