Project: INSTALL WATER SEPARATOR PIPING FOR PHE 23/17/24,4&7 Location: HVBL-HMP ID Task Outline Task Name Duration Start Finish Mode Number March 2024 April 2024 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 1 1 1 INSTALL WATER SEPARATOR PIPING FOR PHE 34 days? 3/8/24 4/12/24 2&3, 4&7 2 1.1 1.1 Contract And Purchase 12 days 3/8/24 3/20/24 12 days
3 1.1.1 1.1.1 Letter of award 1 day 3/8/24 3/8/24
3/8 3/8 4 1.1.2 1.1.2 Contract and Advance payment,PO 1 day 3/8/24 3/9/24 3/8 3/9 5 1.1.3 1.1.3 Prepare and purchase material 10 days 3/9/24 3/20/24 10 days 3/9 3/20 6 1.1.3.1 1.1.3.1 Method statement and JSA 1 day 3/9/24 3/11/24 3/9 3/11 7 1.1.3.2 1.1.3.2 Submit for Owner approval 2 days 3/11/24 3/13/24 3/11 3/13 8 1.1.3.3 1.1.3.3 Purchase all material 7 days 3/13/24 3/20/24 3/13 3/20 9 1.2 1.2 Construction work 12 days? 3/20/24 4/2/24 12 days? 3/20 4/2 10 1.2.1 1.2.1 Site temporary work-Handover layout area 2 days? 3/20/24 3/22/24 2 days? by Heineken 3/20 3/22 11 1.2.1.1 1.2.1.1 Handover layout area by Heineken 1 day? 3/20/24 3/21/24 3/20 3/21 12 1.2.1.2 1.2.1.2 Set up site 1 day 3/20/24 3/21/24 3/20 3/21 13 1.2.1.3 1.2.1.3 Import materials into the factory 1 day? 3/20/24 3/21/24 3/20 3/21 14 1.2.1.4 1.2.1.4 Primer and coasting seamless steel pipe 1 day? 3/21/24 3/22/24 and fitting 3/21 3/22 15 1.2.2 1.2.2 Install pipings from GAD 150 E to PHEs 10 days 3/22/24 4/2/24 10 days 2&3 16 1.2.2.1 1.2.2.1 Mark the support position 1 day 3/22/24 3/23/24 3/22 3/23 17 1.2.2.2 1.2.2.2 Construction of pipe support 3 days 3/23/24 3/26/24 3/23 3/26 18 1.2.2.3 1.2.2.3 Installation the seperator pipe DN20 3 days 3/27/24 3/29/24 Amonia supply/Return 3/27 3/29 19 1.2.2.4 1.2.2.4 Pipe Welding 3 days 3/29/24 4/2/24 3/29 4/2 20 1.2.3 1.2.3 3. Install pipings from GAD 150 E to PHEs 10 days 3/22/24 4/2/24 10 days 4&7 21 1.2.3.1 1.2.3.1 Mark the support position 1 day 3/22/24 3/23/24 3/22 3/23 22 1.2.3.2 1.2.3.2 Construction of pipe support 3 days 3/23/24 3/26/24 3/23 3/26 23 1.2.3.3 1.2.3.3 Installation the seperator pipe DN20 3 days 3/27/24 3/29/24 Amonia supply/Return 3/27 3/29 24 1.2.3.4 1.2.3.4 Pipe Welding 3 days 3/29/24 4/2/24 3/29 4/2 25 1.3 1.3 Project testing. 2 days? 4/2/24 4/4/24 2 days?
26 1.3.1 1.3.1 Pressure Test 1 day? 4/2/24 4/3/24
4/2 4/3 27 1.3.2 1.3.2 Radiography test 10% 1 day? 4/3/24 4/4/24 4/3 4/4 28 1.4 1.4 Pipe Insulation – foam PU and Tie - In 5 days? 4/4/24 4/9/24
29 1.4.1 1.4.1 Tie - In 1 day? 4/4/24 4/4/24
4/4 4/4 30 1.4.2 1.4.2 pipings from GAD 150 E to PHEs 2&3 5 days 4/4/24 4/9/24 insulation 4/4 4/9 31 1.4.3 1.4.3 pipings from GAD 150 E to PHEs 4&7 5 days 4/4/24 4/9/24 insulation 4/4 4/9 32 1.5 1.5 Testing,Defect and Handover acceptance 3 days? 4/9/24 4/12/24 3 days? 4/9 4/12 33 1.5.1 1.5.1 Remove scaffolding and cleaning area 1 day 4/9/24 4/10/24 4/9 4/10 34 1.5.2 1.5.2 Commissioning 1 day? 4/10/24 4/11/24 4/10 4/11 35 1.5.3 1.5.3 Acceptance & Project handover 1 day? 4/11/24 4/12/24 4/11 4/12