DAILY PROGRESS REPORT

PIPE REPLACEMENT PROJECT - 4 (SEASON-I)

CLIENT M/s Oil and Natural Gas Corporation Limited. DPR No. ONGC/ST/PRP-4/35
C.A M/s ABS Industrial Verification Pvt.Ltd. DPR Date 02-Feb-16
TPI M/s DNV-GL Report Date 03-Feb-16
Contractor M/s Swiber Offshore Construction PTE LTD.(SOC) Country: INDIA
Sub-contractor M/s Das offshore engg.pvt.ltd.
Barge Saujana Tiga
Location: HRD PLATFORM FIELD HEERA SEGMENT HQ-HRD

ACTIVITY DESCRIPTION ALLOTTED ACHIEVED TODAY BALANCE CUMULATIVE


SR. NO. SCOPE ACHIEVED TODAY CUMULATIVE
(%) (%) (%) (%)
A) Deck Strengthening - 0%
1 Deck Strengthening MT 0.15 86.00% 0.00% 0.00% 86.00% 0.00 0.15
2 NDT for Deck Strengthening Lot 1 14.00% 0.00% 0.00% 14.00% 0.00 1
TotaL Progress Achieved (%) 100.00% 0.00% 0.00% 100.00%
B) PIPING - 95 %
1 Erection of Piping Spools Nos. 65 18.75% 0.00% 0.00% 18.75% 0 65
Fit up of Field Joints Nos. 115 12.50% 0.00% 0.00% 12.50% 0 115
2
Fit up (Site Modification Joints) Nos. 0 0 2
Welding Inch-Dia 327 21.25% 0.00% 0.00% 21.25% 0 327
3
Welding (Site Modification Inch.dia.) Inch-Dia 0 0 19
4 Installation of Piping Supports Nos. 43 12.50% 0.00% 0.00% 12.50% 0 43
RT 59 17.50% 0.00% 0.00% 17.50% 0.00 59
SR 0 0 0
5 NDT (No. of Field Joints) RT (Site MOD.) 0 0 0
SR (Site MOD.) 0 0 0
DPT 56 2.50% 0.00% 0.00% 2.50% 0 56
6 Hydrotesting of Piping Loops Nos. 5 8.75% 1.75% 0.00% 8.75% 1 5
7 Hook up/ Tie in point Nos. 5 2.50% 1.00% 0.00% 2.50% 2 5
8 Painting Touch-up work Lot 1 2.50% 2.50% 0.00% 2.50% 1 1
9 Insulation Lot 1 1.25% 0.00% 0.25% 1.00% 0 0.8
TotaL Progress Achieved (%) 100.00% 5.25% 0.25% 99.75%
C) ELECTRICAL & INSTRUMENTATION - 5 %
1 Calibration of Instruments Nos. 18 10.00% 0.00% 4.44% 5.56% 0.00 10
2 Installation of Instruments Nos. 18 15.00% 0.00% 7.50% 7.50% 0.00 9
3 Cable laying Mtrs. 3675 30.00% 0.00% 0.00% 30.00% 0.00 3675
4 Cable Glanding & Termination Nos. 52 10.00% 0.00% 1.54% 8.46% 0.00 44
5 Fusible Plug Installation Nos. 6 10.00% 0.00% 0.00% 10.00% 0.00 6
6 Tube Laying Mtrs. 50 10.00% 0.00% 0.00% 10.00% 0.00 50
7 Installation of stanchion Nos. 4 5.00% 0.00% 0.00% 5.00% 0.00 4
8 Tube Testing Lot 1 5.00% 5.00% 0.00% 5.00% 1.00 1
9 SDP Panel installation Nos. 0 0.00% 0.00% 0.00% 0.00% 0.00 0
10 F&G Panel & installation Nos. 0 0.00% 0.00% 0.00% 0.00% 0.00 0
11 Control Room Modification Lot 1 5.00% 0.00% 1.25% 3.75% 0.00 0.75

TotaL Progress Achieved (%) 100.00% 5.00% 14.73% 85.27%


SCOPE ALLOTTED ACHIEVED TODAY BALANCE CUMULATIVE
Overall Progress Acieved (%) % % % % %
100% 100% 13% 10% 90%
D)Demolition

1 NO Scope Lot 0 0.0% 0.00% 0.00% 0.00% 0 0

E) WEATHER CONDITIONS:
Wind Direction Wind Speed (in knots) Sea Swell Direction Swell Height (in mtrs) Remarks
NNE'ly 12-15 1-1.5

F) DETAILED ACTIVITIES OF THE DAY :


1. RT o production mnaifold spool completed.
2. Hydrotest completed for new manifold spool and production manifold line at 1750 hrs
3. Pigging of HQ- HRD segment before hydrotesting.
4. Scaffolding removel and material shifting to barge deck in progress.

G) ACTIVITIES PLANNED FOR NEXT 24 hrs :


1. Hydrotesting of NEW HQ-HRD line from HQ-XSDV
2.Scaffolding removel.
3. gangway removel.

H) MANPOWER DETAILS ONBOARD FALCON CHIEF :


Marine Crew
ONGC DNV-Gl ABS SWIBER DAS CSS OER Other Universal TOTAL
ONBOARD (CHO)
0 3 1 4 177 10 22 16 2 13 248

I) AREA OF CONCERN:
1]IMIR and Release note for received Pipe spools and valves not available on barge.
2) Only one Computer is available at Client office which is resulted in Piling of project Documentation to be done by CA & TPI
3) Telephone not available for communication at Client office
4) Shutdown valve not opening fully by manually / hydraulically of HRD celler deck..
5) FD, HCD & H2S detectors yet to received at barge.
6) PSH, PSL & 1/2'' ball valve yet to received at barge.
7) Shutdown valve opening 95% by hydraulically of HQ celler deck..
J) REMARKS:

Mr. R. Rajnarayanan Mr. Lalan Kumar (E&I)


TPI (DNVGL) CA (ABSIV) ONGC