18” WF Rigid Pipe Line – HSA to HRG (KP 0.000 to KP 15.

030)
12th March 2016

Pipe line is installed from 09th November to 21st November 2015.

Swiber is performing the Pigging activities from 11th March Midnight onwards.

Pipe line Installation Punch Points dated on 21st November are given below.

S.No Punch Point Description Status


01 Subject to approval of dwg. No. PRP4-S1-PPD-HSA-HRG-PLR- Closed on 24th November
7002 Rev.C0 and to be submitted 2015.Submitted onboard
02 As Per temporary crossing Support Installation Report Open
PRP4/SWIBER/ONGC/PH-1/CONQUEST/0005, temporary
supports are provided over soft crossings, however the
temporary supports ( 18” x 6M bare Pipes) are not approved by
ONGC. No temporary supports are Provided over rigid crossings
/ hard crossing.Permanent Supports to be Provided in all the
crossings mentioned in the Site Memo PRP4-SWIBER-ONGC-
PH1-CONQUEST-0005 & Drawing No.PRP4-S1-PPD-H’SA-HRG-
PLR-7002 Rev.C0.
03 ABS IRN is to be submitted for the 18” H’SA-HRG CWC Pipes Open

04 DNV GL Comments are not closed in Procedure No. PRP4-S1- Open


SOC-GNPL-PLR-PRC-0202 Rigid Pipeline Installation Procedure
Rev_C0
05 Anode type Mentioned in drawing No. PRP4-S1-PPD-HSA-HRG- Open
PLR-DRW-7002 Rev.C0 is A3, But in Annexure No.UC-001 Rev.0
fromf Jindal Saw Ltd stated A16 & A17
06 ABS IV marked DCI drawings (critical drawings) to be submitted Open
for Review and approval

DLB Swiber Resolute completed the work related to the 18” Riser stalk on with Pipeline and Installation of
18” Riser in to the preinstalled subsea Riser clamps on 05th January 2016 at HSA Platform, West Face in Heera
field for 18” WF HSA-HRG Rigid line

Punch Point of 18”WF Riser for 18”WF HSA-HRG Rigid line at HSA Platform dated on 05 th January

S.No Punch Point Description Status


01 Subjected to Satisfactory Results of dry density, Saturated Open
density and compressive strength of HDPUF Sample

02 Complete Painting of Riser section above the Hang off sleeve Open
and Hanger Clamp doubler Plate with Platform jacket member
and Hanger clamp Stub with doubler Plate to be carried out as
per ONGC Specification No.2005 Rev.04,after removing the
18” WF Rigid Pipe Line – HSA to HRG (KP 0.000 to KP 15.030)
12th March 2016

temporary Paint.

AWB Swiber Chateau completed the work related to the 18” Riser stalk on with Pipeline and Installation of
18” Riser in to the preinstalled subsea Riser clamps on 20th February 2016 at HRG Platform, South Face in
Heera field for 10” WF HSA-HRG Rigid line

Punch Point of 18”WF Riser for 18”WF HSA-HRG Rigid line at HRG Platform dated on 20 th February

S.No Punch Point Description Status


01 Subjected to Satisfactory Results of dry density, Saturated Open
density and compressive strength of HDPUF Sample

02 Complete Painting of Riser section above the Hang off sleeve Open
and Hanger Clamp doubler Plate with Platform jacket member
and Hanger clamp Stub with doubler Plate to be carried out as
per ONGC Specification No.2005 Rev.04,after removing the
temporary Paint.

03 Torque Tightening and final Inspection of Hanger Clamp Open

04 Temporary Sand bag support to be replaced by Permanent Open


grout bag as per ONGC Specification

05 As-Built drawing to be approved Open

06 HSS at Joint No.OFW-03 is observed minor damaged during Closed on 23rd February 2016
installation, needs to be re wrapped and holiday tested

07 ABS Comment : ABSIV Marked DCI drawings ( critical drawings) Open


not submitted for Review and approval

08 ABS Comment : Subject to clearance of IMIR comments Open

09 ABS Comment : Revised Installation Procedure Rev.C1 to be Open


submitted for Review from ONGC TPI / CA

10 ABS Comment : Torque Test witness balance for HRG-HC-A1 Open

11 Subject to availability of Release Note & Report of Activity by Open


Third Party Inspector and Certified Agency for welding of
Hanger Clamp.

12 NDT and Painting is balance for Hanger Clamp Open