Professional Documents
Culture Documents
18" WF Rigid Pipe Line - HSA To HRG
18" WF Rigid Pipe Line - HSA To HRG
18" WF Rigid Pipe Line - HSA To HRG
030)
12th March 2016
Swiber is performing the Pigging activities from 11th March Midnight onwards.
Pipe line Installation Punch Points dated on 21st November are given below.
DLB Swiber Resolute completed the work related to the 18” Riser stalk on with Pipeline and Installation of
18” Riser in to the preinstalled subsea Riser clamps on 05th January 2016 at HSA Platform, West Face in Heera
field for 18” WF HSA-HRG Rigid line
Punch Point of 18”WF Riser for 18”WF HSA-HRG Rigid line at HSA Platform dated on 05 th January
02 Complete Painting of Riser section above the Hang off sleeve Open
and Hanger Clamp doubler Plate with Platform jacket member
and Hanger clamp Stub with doubler Plate to be carried out as
per ONGC Specification No.2005 Rev.04,after removing the
18” WF Rigid Pipe Line – HSA to HRG (KP 0.000 to KP 15.030)
12th March 2016
temporary Paint.
AWB Swiber Chateau completed the work related to the 18” Riser stalk on with Pipeline and Installation of
18” Riser in to the preinstalled subsea Riser clamps on 20th February 2016 at HRG Platform, South Face in
Heera field for 10” WF HSA-HRG Rigid line
Punch Point of 18”WF Riser for 18”WF HSA-HRG Rigid line at HRG Platform dated on 20 th February
02 Complete Painting of Riser section above the Hang off sleeve Open
and Hanger Clamp doubler Plate with Platform jacket member
and Hanger clamp Stub with doubler Plate to be carried out as
per ONGC Specification No.2005 Rev.04,after removing the
temporary Paint.
06 HSS at Joint No.OFW-03 is observed minor damaged during Closed on 23rd February 2016
installation, needs to be re wrapped and holiday tested