CLIENT : M/s.

ONGC
Contractor : M/s. LTHE
Sub-Contractor : M/s DOEPL
PROJECT : Balance work for Pipeline Replacement Project - 4

CA : M/S. ABSIV (India) Pvt.Ltd. PRODUCTION DATE: 14.03.2018


TPI : M/S. DNV-GL REPORTING DATE : 15.03.2018
Location : WN1 Platform
Barge: Ocean303
Achieved Cumulative Balance Achieved % Cumulative
Sr. no Description UOM Scope Alloted % Balance % Remarks
Qty.Today Qty. Qty. Today %
Over all Progress ( A+B+C) 100.00% 32.95% 75.33% 25.67%

A) Piping

1 Erection of Piping spools Nos 11 20.00% 7 11 0 12.73% 20.00% 0.00%

Fit up of Field Joints Nos 16 13.00% 4 15 1 3.25% 12.19% 0.81%


2
Fit up of(Modification joints) Nos 1 0.00% 1 2 -1 0.00% 0 0

3 Fit up Adiitional work Nos N/A N/A N/A N/A N/A N/A N/A N/A

Welding Scope = 52" ( 6"= 7 Joints, 2" = 2 Joints,


Inch Dia 52 29.00% 16 40 12 8.92% 22.31% 6.69%
4 3/4" = 8 Joints)

Welding (Modification Inch Dia) Inch Dia 8 0.00% 2 8 0 0.00% 0.00% 0.00%

5 Welding Additional work Inch Dia N/A N/A N/A N/A N/A N/A N/A N/A

6 Installation of Piping Supports Nos. 7 7.00% 2 4 3 2.00% 4.00% 3.00%

7 NDT( No. of Field Joints) Nos 17 12.00% 4 15 2 2.82% 10.59% 1.41%

8 Hydrotesting of Piping Loops Nos. 1 4.00% 0 0 1 0.00% 0.00% 4.00%

10 Hook up/Tie in point Nos. 2 4.00% 0 0 2 0.00% 0.00% 4.00%

11 Painting Touch-up work lot 1 1.00% 0 0 1 0.00% 0.00% 1.00%

12 Insulation lot N/A N/A N/A N/A N/A NA N/A N/A

TOTAL-A 90.00% 29.72% 69.08% 20.92%

B) DEMOLITION

Demolition of existing 10" WI WN2-WN1 Segment


1 lot 1 1.50% 0.25 1 0 0.38% 1.50% 0.00%
associated piping

TOTAL-B 1 1.50% 0 0 1 0.38% 1.50% 0.00%

C) ELECTRICAL & INSTRUMENTATION

1 Instrument Installation No 2 3.50% 1 1 1 1.75% 1.75% 1.75%

2 Impulse Tubing Mtr 10 0.50% 10 10 0 0.50% 0.50% 0.50%

3 Cable Tray Mtr 8 0.50% 8 8 0 0.50% 0.50% 0.50%

4 Cable laying Mtr 20 1.00% 2 20 0 0.10% 1.00% 0.00%

5 Cable termination and glanding No 2 1.00% 0 0 2 0.00% 0.00% 1.00%

6 Calibration No 2 1.00% 0 2 0 0.00% 1.00% 0.00%

7 Loop checking No 1 1.00% 0 0 1 0.00% 0.00% 1.00%

8 Logic checking No N/A N/A N/A N/A N/A N/A N/A N/A

TOTAL-C 8.50% 0 0 2.85% 4.75% 4.75%

Distribution and Contact List


ABSIV sekumaran@eagle.org, pramanathan@absconsulting.com, dbhujbal@absconsulting.com
ONGC pandey_ak5@ongc.co.in, khanra_Rajat@ongc.co.in, Thakur_Ashish@ongc.co.in
DNV-GL birju.jaiswal@dnvgl.com, mani.choudhary@dnvgl.com, merlyn.menezes@dnvgl.com

Activities performed
1 Scoffolding erection is in progress below cellar Deck

2 Erection, Fit up & Welding of Spool Joints 6" - 2 Joints, 2" - 2 Joints completed.

3 Fit up & Welding of 2" modification - 1 joint completed

4 2" & 6" Ball Valve Installed

5 RT taken for Piping Joints

6 Demolition of existing line 12" x 10" Receiver at below Cellar deck is completed

7 Stanchion and supports erection for PT & PG and followed cable tray & cable installation completed.

8 Installation of PT with impulse tubing completed

9 Shifting of demolition material from platform to barge deck

Planned activities(Next Day) :-

1 Scaffolding below cellar deck for support installation

2 Fit-up and welding of 6" piping spools bellow celler deck

3 Radiography of joints will be continued

4 Piping support fitup and welding

5 Fitup and welding of temperary hyrotesting flange

6 Preparation for hydrotesting

Area of Concern if any :

Nil

Bhabesh Porel Vipin James EL.Krishnan


DNV -Mech. ( ONGC-TPI) DNV-E&I (ONGC-TPI) ABSIV-Mech. (ONGC-CA) ABSIV-E & I (ONGC-CA) (ONGC REP.)