DPR BWPRP4 Ocean303 27.03.18
DPR BWPRP4 Ocean303 27.03.18
ONGC
Contractor : M/s. LTHE
Sub‐Contractor : M/s DOEPL
PROJECT : Balance work for Pipeline Replacement Project ‐ 4
A) Piping
3 Fit up Adiitional work Nos N/A N/A N/A N/A N/A NA N/A N/A
Welding Inch Dia 83.5 29.00% 12.75 67.5 16 4.43% 23.44% 5.56%
4
Welding (Modification Inch Dia) Inch Dia 42 0.00% 30 42 0 0.00% 0.00% 0.00%
5 Welding Additional work Inch Dia N/A N/A N/A N/A N/A NA N/A N/A
B) DEMOLITION
Activities performed
1 Scaffolding on cellar deck and below cellar deck is in progress.
2 Erection, Fit‐up and welding of 6" piping spool is completed at Cellar deck
5 Cable termination at JB
3 Instrument installation.
4 Instrumentation JB installation.
Nil