CLIENT : M/s.

ONGC
Contractor : M/s. LTHE
Sub‐Contractor : M/s DOEPL
PROJECT : Balance work for Pipeline Replacement Project ‐ 4

CA : M/S. ABSIV (India) Pvt.Ltd. PRODUCTION DATE: 27.03.2018

TPI : M/S. DNV‐GL REPORTING DATE : 28.03.2018


Location : NLM10 Platform
Barge: Ocean303
Achieved Cumulative Balance Achieved % Cumulative
Sr. no Description UOM Scope Alloted % Balance % Remarks
Qty.Today Qty. Qty. Today %
Over all Progress ( A+B+C) 100.00% 21.47% 79.91% 20.09%

A) Piping

1 Erection of piping spools Nos 14 20.00% 1 13 1 1.43% 18.57% 1.43%

Fit up of Field Joints Nos 27 13.00% 3 25 2 1.44% 12.04% 0.96%


2
Fit up of(Modification joints) Nos 7 0.00% 2 7 0 0.00% 0.00% 0.00%

3 Fit up Adiitional work Nos N/A N/A N/A N/A N/A NA N/A N/A

Welding Inch Dia 83.5 29.00% 12.75 67.5 16 4.43% 23.44% 5.56%
4
Welding (Modification Inch Dia) Inch Dia 42 0.00% 30 42 0 0.00% 0.00% 0.00%

5 Welding Additional work Inch Dia N/A N/A N/A N/A N/A NA N/A N/A

6 Installation of Piping Supports Nos. 6 7.00% 6 6 0 7.00% 7.00% 0.00%


NDT( No. of Field Joints)
7 Nos 27 12.00% 5 25 2 2.22% 11.11% 0.89%

8 NDT(Modification Joints) Nos 7 0.00% 0 7 0 0.00% 0.00% 0.00%

9 Hydrotesting of Piping Loops Nos. 2 4.00% 1 1 1 2.00% 2.00% 2.00%

10 Hook up/Tie in point Nos. 2 4.00% 0 0 2 0.00% 0.00% 4.00%

11 Painting Touch-up work lot 1 1.00% 0 0 1 0.00% 0.00% 1.00%

12 Insulation lot N/A N/A N/A N/A N/A NA N/A N/A


TOTAL-A 90.00% 18.52% 74.16% 15.84%

B) DEMOLITION

1 NIL lot 0 0.00% 0 0 0 0.00% 0.00% 0.00%

TOTAL-B 0 0.00% 0.00% 0.00% 0.00%

C) ELECTRICAL & INSTRUMENTATION

1 Instrument Installation No 4 3.50% 2 2 2 1.75% 1.75% 1.75%

2 Impulse Tubing mtr 20 1.00% 0 0 20 0.00% 0.00% 1.00%

3 Cable Tray mtr 50 1.00% 20 50 0 0.40% 1.00% 0.00%

4 Cable laying mtr 300 1.50% 60 300 0 0.30% 1.50% 0.00%

5 Cable termination and glanding No 8 1.00% 4 4 4 0.50% 0.50% 0.50%

6 Calibration No 4 1.00% 0 4 0 0.00% 1.00% 0.00%

7 Loop checking No 4 1.00% 0 0 4 0.00% 0.00% 1.00%

TOTAL-C 10.00% 0 0 2.95% 5.75% 4.25%

Distribution and Contact List


ABSIV sekumaran@eagle.org, pramanathan@absconsulting.com, dbhujbal@absconsulting.com
ONGC pandey_ak5@ongc.co.in, khanra_Rajat@ongc.co.in, Thakur_Ashish@ongc.co.in
DNV‐GL birju.jaiswal@dnvgl.com, mani.choudhary@dnvgl.com, merlyn.menezes@dnvgl.com

Activities performed
1 Scaffolding on cellar deck and below cellar deck is in progress.

2 Erection, Fit‐up and welding of 6" piping spool is completed at Cellar deck

3 Fitup & welding of piping supports completed.

4 Cable laying & cable tray completed.

5 Cable termination at JB

6 NDT of weld joints completed.

7 Preperation of hydrotesting of main loop.

Planned activities(Next Day) :‐

1 Hydrotesting of main loop.

2 Cable termination at JB.

3 Instrument installation.

4 Instrumentation JB installation.

5 Scaffolding removal on cellar deck and below cellar deck

6 Material Shifting from Platform to Barge deck

Area of Concern if any :

Nil

Bhabesh Porel Vipin James EL.Krishnan


DNV ‐Mech. ( ONGC‐TPI) DNV‐E&I (ONGC‐TPI) ABSIV‐Mech. (ONGC‐CA) ABSIV‐E & I (ONGC‐CA) (ONGC REP.)