Tentative Schedule
Tentative Schedule
Orig
% Early Early 2012 2013 2014
S OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Description Dur Start Finish
PROGRAMME OF WORK
020 Preparation and Submission of Detailed 08OCT12 24OCT12 Preparation and Submission of Detailed Programme
Programme
030 Client Review and Approval 25OCT12 07NOV12 Client Review and Approval
090 Urban Design Principles, Development 08DEC12 15JAN13 Urban Design Principles, Development Rationale
Rationale
100 Inquiry by Design Documentation for Workshop 01JAN13 22JAN13 Inquiry by Design Documentation for Workshop
120 Complete Project Inception Report 23JAN13 31JAN13 Complete Project Inception Report
130 Submission of Project Inception Report 01FEB13 15FEB13 Submission of Project Inception Report
TOPOGRAPHICAL SURVEY
150 3D Topographical Survey 23OCT12 15JAN13 3D Topographical Survey
160 Verify and confirm existing Topographical 16DEC12 24JAN13 Verify and confirm existing Topographical Report
Report
170 Clients Submission 26JAN13 31JAN13 Clients Submission
GEOTECHNICAL INVESTIGATION
180 Site Investigation 08DEC12 31JAN13 Site Investigation
URBAN DESIGN
210 Transportation Engineering, analysis & 01JAN13 31MAY13 Transportation Engineering, analysis & mapping
mapping
220 Civil Engineering analysis & mapping 01JAN13 31MAY13 Civil Engineering analysis & mapping
230 Landscape Analysis and Mapping 01JAN13 31MAY13 Landscape Analysis and Mapping
240 Planning and Policy Analysis 01JAN13 31MAY13 Planning and Policy Analysis
250 Urban Plan Concept Design 01JAN13 31MAY13 Urban Plan Concept Design
URBAN DESIGN
280 Client Review & Approval of Urban Plan 16JUN13 30JUN13 Client Review & Approval of Urban Plan
LANDSCAPE PLAN
290 Preparation of Draft Concept Landscape Plan 02FEB13 15APR13 Preparation of Draft Concept Landscape Plan
300 Preparation of Concept Landscape Strategy 16FEB13 15APR13 Preparation of Concept Landscape Strategy
320 Client Review & Approval 01MAY13 15MAY13 Client Review & Approval
430 Preparation & Submission Primary utilities 24AUG13 15SEP13 Preparation & Submission Primary utilities dwgs
dwgs
440 Client Review & Approval 16SEP13 30SEP13 Client Review & Approval
VALUE ENGINEERING
550 Concept Design 01JUN13 31JUL13 Concept Design
TENDER DOCUMENTS
Technical Specifications
570 Technical Specifications 01MAY13 09NOV13
Bill of Quantities
580 Bill of Quantities 01MAY13 31DEC13
TENDER DOCUMENTS
590 Tender Drawings Preparation 08JUL13 31DEC13 Tender Drawings Preparation