AL-MATRAFIYA HOUSING PROJECT-TENTATIVE PROGRAMME


CLIENTS LETTER OF AWARD
010 Clients Letter of Award 01OCT12 07OCT12 Clients Letter of Award

Subtotal 01OCT12 07OCT12

PROGRAMME OF WORK
020 Preparation and Submission of Detailed 08OCT12 24OCT12 Preparation and Submission of Detailed Programme
Programme
030 Client Review and Approval 25OCT12 07NOV12 Client Review and Approval

Subtotal 08OCT12 07NOV12

DATA COLLECTION AND SITE EVALUATION


040 Existing Topographical Survey Report 08OCT12 24OCT12 Existing Topographical Survey Report

050 Existing Utilities Information 08OCT12 24OCT12 Existing Utilities Information

060 Traffic Study Report 08OCT12 24OCT12 Traffic Study Report

Subtotal 08OCT12 24OCT12

METHODOLOGY, ANALYSIS & CONCEPTUALISATION


070 Analysis of Existing Land Use Survey, Site 09NOV12 15DEC12 Analysis of Existing Land Use Survey, Site Infor
Infor
080 Urban Design Methodology 24NOV12 31DEC12 Urban Design Methodology

090 Urban Design Principles, Development 08DEC12 15JAN13 Urban Design Principles, Development Rationale
Rationale
100 Inquiry by Design Documentation for Workshop 01JAN13 22JAN13 Inquiry by Design Documentation for Workshop

110 Workshop 01JAN13 22JAN13 Workshop

120 Complete Project Inception Report 23JAN13 31JAN13 Complete Project Inception Report

130 Submission of Project Inception Report 01FEB13 15FEB13 Submission of Project Inception Report

Start Date 11SEP12 Sheet 1 of 5


Finish Date 21JUN22 Early Bar Date Revision CheckedApproved
AL-MATRAFIYA HOUSING PROJECT
Data Date 11SEP12 Progress Bar 20SEP12Issued for Approval SVR KAM
Run Date 21SEP12 17:43 ITB#GPP-ITB-12-08
Critical Activity

© Primavera Systems, Inc.


Activity Activity Rem
Orig
% Early Early 2012 2013 2014
S OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Description Dur Start Finish

METHODOLOGY, ANALYSIS & CONCEPTUALISATION


140 Client's Approval 16FEB13 28FEB13 Client's Approval

Subtotal 09NOV12 28FEB13

TOPOGRAPHICAL SURVEY
150 3D Topographical Survey 23OCT12 15JAN13 3D Topographical Survey

160 Verify and confirm existing Topographical 16DEC12 24JAN13 Verify and confirm existing Topographical Report
Report
170 Clients Submission 26JAN13 31JAN13 Clients Submission

Subtotal 23OCT12 31JAN13

GEOTECHNICAL INVESTIGATION
180 Site Investigation 08DEC12 31JAN13 Site Investigation

190 Submission of Report 24JAN13 07FEB13 Submission of Report

200 Clients Approval 09FEB13 21FEB13 Clients Approval

Subtotal 08DEC12 21FEB13

URBAN DESIGN
210 Transportation Engineering, analysis & 01JAN13 31MAY13 Transportation Engineering, analysis & mapping
mapping
220 Civil Engineering analysis & mapping 01JAN13 31MAY13 Civil Engineering analysis & mapping

230 Landscape Analysis and Mapping 01JAN13 31MAY13 Landscape Analysis and Mapping

240 Planning and Policy Analysis 01JAN13 31MAY13 Planning and Policy Analysis

250 Urban Plan Concept Design 01JAN13 31MAY13 Urban Plan Concept Design

260 Design Workshop 20FEB13 30APR13 Design Workshop

270 Preparation & Submission 01MAY13 15JUN13 Preparation & Submission

Start Date 11SEP12 Sheet 2 of 5


Finish Date 21JUN22 Early Bar Date Revision CheckedApproved
AL-MATRAFIYA HOUSING PROJECT
Data Date 11SEP12 Progress Bar 20SEP12Issued for Approval SVR KAM
Run Date 21SEP12 17:43 ITB#GPP-ITB-12-08
Critical Activity

© Primavera Systems, Inc.


Activity Activity Rem
Orig
% Early Early 2012 2013 2014
S OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Description Dur Start Finish

URBAN DESIGN
280 Client Review & Approval of Urban Plan 16JUN13 30JUN13 Client Review & Approval of Urban Plan

Subtotal 01JAN13 30JUN13

LANDSCAPE PLAN
290 Preparation of Draft Concept Landscape Plan 02FEB13 15APR13 Preparation of Draft Concept Landscape Plan

300 Preparation of Concept Landscape Strategy 16FEB13 15APR13 Preparation of Concept Landscape Strategy

310 Preparation & Submission 16MAR13 30APR13 Preparation & Submission

320 Client Review & Approval 01MAY13 15MAY13 Client Review & Approval

Subtotal 02FEB13 15MAY13

PRIMARY ROADS AND INFRASTRUCTURE DESIGN


330 Concept Grading Plan 02FEB13 28FEB13 Concept Grading Plan

340 Roads Layout 01MAR13 16JUL13 Roads Layout

350 Potable Water Network 01MAY13 09SEP13 Potable Water Network

360 Sewerage Network 01MAY13 09SEP13 Sewerage Network

370 Drainage Network 01MAY13 09SEP13 Drainage Network

380 Electrical Network 01MAY13 09SEP13 Electrical Network

390 Telecom Network 01MAY13 09SEP13 Telecom Network

410 Irrigation Network 01MAY13 09SEP13 Irrigation Network

420 Fire Fighting Network 01MAY13 09SEP13 Fire Fighting Network

430 Preparation & Submission Primary utilities 24AUG13 15SEP13 Preparation & Submission Primary utilities dwgs
dwgs
440 Client Review & Approval 16SEP13 30SEP13 Client Review & Approval

Start Date 11SEP12 Sheet 3 of 5


Finish Date 21JUN22 Early Bar Date Revision CheckedApproved
AL-MATRAFIYA HOUSING PROJECT
Data Date 11SEP12 Progress Bar 20SEP12Issued for Approval SVR KAM
Run Date 21SEP12 17:43 ITB#GPP-ITB-12-08
Critical Activity

© Primavera Systems, Inc.


Activity Activity Rem
Orig
% Early Early 2012 2013 2014
S OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Description Dur Start Finish

PRIMARY ROADS AND INFRASTRUCTURE DESIGN


Subtotal 02FEB13 30SEP13

SECONDARY ROADS AND INFRASTRUCTURE DESIGN


450 Roads Layout 01MAY13 30SEP13 Roads Layout

Potable Water Network


460 Potable Water Network 08JUL13 07NOV13

470 Sewerage Network 08JUL13 07NOV13 Sewerage Network

480 Drainage Network 08JUL13 07NOV13 Drainage Network

490 Electrical Network 08JUL13 07NOV13 Electrical Network

500 Telecom Network 08JUL13 07NOV13 Telecom Network

510 Irrigation Network 08JUL13 07NOV13 Irrigation Network

520 Fire Fighting Network 08JUL13 07NOV13 Fire Fighting Network

Preparation & Submission of Primary drawings


530 Preparation & Submission of Primary drawings 23OCT13 16NOV13

Client Review & Approval


540 Client Review & Approval 17NOV13 30NOV13

Subtotal 01MAY13 30NOV13

VALUE ENGINEERING
550 Concept Design 01JUN13 31JUL13 Concept Design

560 Detailed Design 01SEP13 23OCT13 Detailed Design

Subtotal 01JUN13 23OCT13

TENDER DOCUMENTS
Technical Specifications
570 Technical Specifications 01MAY13 09NOV13

Bill of Quantities
580 Bill of Quantities 01MAY13 31DEC13

Start Date 11SEP12 Sheet 4 of 5


Finish Date 21JUN22 Early Bar Date Revision CheckedApproved
AL-MATRAFIYA HOUSING PROJECT
Data Date 11SEP12 Progress Bar 20SEP12Issued for Approval SVR KAM
Run Date 21SEP12 17:43 ITB#GPP-ITB-12-08
Critical Activity

© Primavera Systems, Inc.


Activity Activity Rem
Orig
% Early Early 2012 2013 2014
S OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Description Dur Start Finish

TENDER DOCUMENTS
590 Tender Drawings Preparation 08JUL13 31DEC13 Tender Drawings Preparation

600 Cost Estimate 01JAN14 08JAN14 Cost Estimate

Subtotal 01MAY13 08JAN14

Subtotal 01OCT12 08JAN14

Start Date 11SEP12 Sheet 5 of 5


Finish Date 21JUN22 Early Bar Date Revision CheckedApproved
AL-MATRAFIYA HOUSING PROJECT
Data Date 11SEP12 Progress Bar 20SEP12Issued for Approval SVR KAM
Run Date 21SEP12 17:43 ITB#GPP-ITB-12-08
Critical Activity