ONGC
Contractor : M/s. L&T Hydrocarbon Engineering
PROJECT : Bassein Development Project
CA : M/S. ABSIV (INDIA) PVT.LTD. PRODUCTION DATE: 7/6/2017
TPI : M/S. VCS (INDIA) PVT.LTD. REPORTING DATE : 7/7/2017
ONGC/BDP/ABS/3607093/BCPA3& BLQ3/085
Location & Activity: BCPA3 & BLQ3 Platform - Green Field Hook up, Pre-commissioning & Commissioning Works
Barge: Hookup & Accommodation barge EASTWIND 365
SCOPE
Sr. no Description L-2 WTG Items/ Qty / No. Today's Progress Cumulative Progress Remarks
Unit Fit - up Welding NDT
0.00% 66.86%
0.00% 88.04%
ii Non - metallic 8 Joints / 126 Inch No. / Inch Dia. 126 Scope Completed
Dia
Total 39 Spools /190 Inch No. / Inch Dia. 0 190 Scope Completed
Dia
0.00% 100%
0.00% 72.00%
0.00% 100.00%
Total 68216 mtrs / 1583 2781 Mtrs. & 0 Nos. 49554 Mtrs. & 261 Nos.
Nos
2.04% 44.57%
1.4.2 BLQ3 Platform 1.36% 0.000% 1.03%
0.00% 75.81%
Total 112323 Mtrs / 935 Mtrs / Nos. 0 Mtrs & Nos 106620 Mtrs. & 265Nos.
Nos
1.07% 61.63%
Total 1287 Mtrs / 38 Nos Mtrs / Nos. 0 Mtrs & 10 Nos 1287 Mtrs & 27 Nos
0.00 85.53%
1.6 Architectural 1.60% 0.000% 0.800%
0.00 1.00
BLQ-3
2 (1) Assembly & Installation of furniture: 12 Nos completed.
PRE-COMMISSIONING
(1) Leak test of start up air system at BCPA3 in progress.
3 (2) Space heater powered up for primary fuel gas skid of PGC.
BLQ3
(1) Furniture installation to continue.
2
Area of Concern :
1) SAT Approved Procedures were not available at offshore for Life Boat David Load Test and STP Test. L&T Performed the Test and the acceptence subject to approval of Procedures.
2) During the SAT Test of Water Maker at BLQ3 Platform, Vibrations observed in HP Pump locations which needs to be rectified. Refer E-mail dated on 25.05.2017
3) Safety Surveyor is not availble at site from 01st June onwards and needs to be mobilized immediately
4) In order to avoid the corrosion during monsoon period, wherever the Parent Material Exposed to atmosphere needs to be painted immediately . Advised to L&T , to take needful action. Refer E-mail dated on 19.06.2017
5) Observations noticed in HVAC Package at BLQ3 Platform and needs to rectify the same. Refer E-mail dated on 21.06.2017
Note :
(a) Percentage progress break up (discipline wise) considered only if work fully completed. Regular cumulative progress is mentioned in appropriate columns.
(b) BCPA3 Hardcopy drawings yet to be submitted to ONGC TPI/CA.