3

0 15.04.2021 Han YE Jiang Peng Li Songtao

Revision
Rev. Created by Checked by Approved by Description Status
Date

PROJECT NAME 900 MW BQPS-III Combined Cycle Plant & Associated Transmission Projects

PROJECT COMPANY HE HARBIN ELECTRIC (PVT) LIMITED Owner:

Consultant

Vendor
:EPC Contractor TITLE:

Test Procedure of Energizing SST4

Project Doc No. HEP-180011-3-MS-COMMISSIONING -HEPE-017 REV:0

Originator Doc No. HTP-BQPS-TP-E-03 REV:0

Format A4 SCALE MKS PAGE: 1 of 8


HE HARBIN ELECTRIC (PVT) LIMITED

Procedure No : HEP-180011-3-MS-COMMISSIONING-HEPE-017 Date : 15.04.2021


Rev : 0 Page : Page 2 of 8
Test Procedure of Energizing SST4

Test Procedure of Energizing

SST4(Startup Standby Transformer 4)


HE HARBIN ELECTRIC (PVT) LIMITED

Procedure No : HEP-180011-3-MS-COMMISSIONING-HEPE-017 Date : 15.04.2021


Rev : 0 Page : Page 3 of 8
Test Procedure of Energizing SST4

Table of Contents
1. Purpose & Work Scope.................................................................................................................4

2. Reference Document...................................................................................................................4

3. System Brief Description..............................................................................................................4

4. Testers & Instruments..................................................................................................................5

5. Pre-requisitions & Pre-cautions....................................................................................................5

6. Organization & Responsibility......................................................................................................5

7. Test Procedure.............................................................................................................................6

8. HSE Management.........................................................................................................................7

9. Attachments.................................................................................................................................8
HE HARBIN ELECTRIC (PVT) LIMITED

Procedure No : HEP-180011-3-MS-COMMISSIONING-HEPE-017 Date : 15.04.2021


Rev : 0 Page : Page 4 of 8
Test Procedure of Energizing SST4

1. Purpose & Work Scope


The procedure is description of power back-feeding from BQPS-III 220kV GIS
substation. It includes as following

- Energize SST4
- Energize 6.6kV bus-bar(00BCA).
During this procedure, following functions and checked will be carried out:
- To verify status of SST4.
- To check the status of CVTs during energizing.
- To verify the polarity & continuity of voltage circuit and indications as well.
- To verify the status of protection relays.
- To verify the status of 6.6kV Bus-bar.

2. Reference Document
Main Design Drawings
- F08643S-D0613
- F08643S-D0707
- F08643S-D0712
- F08643S-D0801
Manufacture Specification on Equipment

3. System Brief Description


System Description

Please see Attachment 1 for single line diagram for power back-feeding scope

List & Data Sheet of Main Equipment

Find out Attachment 2 for the List & Data Sheet of Main Equipment.
HE HARBIN ELECTRIC (PVT) LIMITED

Procedure No : HEP-180011-3-MS-COMMISSIONING-HEPE-017 Date : 15.04.2021


Rev : 0 Page : Page 5 of 8
Test Procedure of Energizing SST4

4. Testers & Instruments


No Description Numbers
1 Megger MIT515 (5kV) 1
2 Multi-meters 2
3 Voltage Sequencer 1

5. Pre-requisitions & Pre-cautions


Please find out in Attachment 3 (Check Sheet Before Test).

Before conducting test of power back-feeding, all necessary items in Attachment 3 must
be satisfied.

An official certificate is also issued to HEI.

6. Organization & Responsibility


An Organization Chart involving all concerned parties will be built up just before power back-
feeding.

An engineer from Client should be appointed as a Coordinator discussing with NTDC to approve
this procedure before test, and communicating with NTDC during test.

An electrical engineer from HEI commissioning team will be close with Client Coordinator during
test, any command by NTDC should be recorded and transferred to HEI engineer, who gives
order to electrical operators to act.

Commissioning team will be in charge to carry out this test, erection team should be co-
operating, all the operations local or remote will be carried out by Pre-operation team.

Detail inspection & tests will be performed & implemented by professional commissioning group.

All temporary measurement, cleaning and maintenance works happening during commissioning
will be arranged or fixed by erection team.
HE HARBIN ELECTRIC (PVT) LIMITED

Procedure No : HEP-180011-3-MS-COMMISSIONING-HEPE-017 Date : 15.04.2021


Rev : 0 Page : Page 6 of 8
Test Procedure of Energizing SST4

7. Test Procedure
7.1 Insulation Resistance Measurement
Fill out in form of Attachment 4.
7.2 Line-up Checks Before energizing
Properly organize the line-up and checks by concerning teams on as per Attachment
5. Definitely basic ways are described as:

- Related 220kV CB is in OPEN position and control power supplies should be ON.
- Related 220kV ES is in OPEN position and control power supplies should be OFF.
- Control power of related closed DS should be OFF.
- Proper isolation measures should be conducted for safety concerns.

7.3 Energizing Steps


NTDC should be informed through Client Coordinator before any operation on 220kV
GIS equipments, such as CB, DS or ES, etc.

The energizing procedure is shown in Attachment 6 and fill out in Attachment 7 (Record
Sheets) during test.

The brief steps are described as:

- Temporarily modify protection (50/ 51) setting of Bus Coupler2 bay for power grid safety, and
prepare to energize SST4
- Open FES1
- Close DS3
- Charging SST4 for 3 times
- Energizing 6.6kV bus-bar 00BCA

7.4 Emergency Response


A commissioning engineer will be nominated as Test Charge, who keeps contacting
with LDC through Client Coordinator by hot line and contacting with local staffs by
walky-talky during test.
HE HARBIN ELECTRIC (PVT) LIMITED

Procedure No : HEP-180011-3-MS-COMMISSIONING-HEPE-017 Date : 15.04.2021


Rev : 0 Page : Page 7 of 8
Test Procedure of Energizing SST4
SST4 area should be properly enclosed in order to prevent unauthorized staffs from
entry.

A hot line communicating with LDC will be available and smooth.

A personnel will be appointed to be in charge of fire fighting system, who keeps


contacting with the charge of electrical commissioning engineer in order to give fast
action.

Local area before any energizing or charging should be arranged with engineers, who
is with walky-talky for communication with test charge

8. HSE Management
Please refer to followings:

- Strictly follow all rules regulated by EPC Contractor (HEI) and Client Requirement

- Company ISO system should be implemented in all activities at site location, cautions and cares
and related measurement should be forecasted.

- Necessary tagging & labelling should be arranged for field test, personal protective equipment
should be available for every commissioning staff.

- Switchyard should be properly enclosed and safety signs or tags should be valid.

- Portable fire extinguishers should be organized for each room and local area.

- Fire-fighting brigade must be full and ready any time during test and fast response to any visual
fire call.

- Persons should be at local area to supervise any operation.

9. Attachments
- Attachment 1:Single Line Diagram for Power Back-feeding
HE HARBIN ELECTRIC (PVT) LIMITED

Procedure No : HEP-180011-3-MS-COMMISSIONING-HEPE-017 Date : 15.04.2021


Rev : 0 Page : Page 8 of 8
Test Procedure of Energizing SST4
- Attachment 2:List & Data Sheet of Main Equipments

- Attachment 3:Check Sheet Before Test

- Attachment 4:Insulation Resistance Measurement Before Test

- Attachment 5:Line-up Checks Before Test

- Attachment 6:Test Procedure

- Attachment 7:Record Sheets