007-Commissioning Procedure of Fault Reorder System-R1
007-Commissioning Procedure of Fault Reorder System-R1
PROJECT NAME 900 MW BQPS-III Combined Cycle Plant & Associated Transmission Projects
Consultant
Vendor
:EPC Contractor TITLE:
Table of Contents
1. Objective................................................................................4
2. Application.....................................................................................................................................4
4. Reference Document...................................................................................................................4
5. Abbreviations.................................................................................................................................4
8. Turn-over Control..........................................................................................................................8
12. Attachments...............................................................................................................................11
1 Objective
2 Application
This procedure is applicable for all Fault Recorder Systems of 900 MW BQPS-III Combined
Cycle Plant
Main parameters (including voltage, current, etc) are monitored for Generator, GSUT,
SST4, UAT A, UAT B, 6.6kV bus-bar
4 Reference Document
5 Abbreviations
Abbreviation Designation
HV High Voltage
MV Medium Voltage
LV Low Voltage
CB Circuit Breaker
VT Voltage Transformer
CT Current Transformer
MCCB Molded Case Circuit Breaker
FR Fault Recorder
DFR Digital Fault Recorder
Form below shows the instruments and tester used for this test.
No. Description Numbers
1 Megger (500V) 1
2 Multi-meters 2
3 Phase rotation meter 1
4 Volt-ampere angle meter 1
The commissioning works of Metering and Measuring System shall be carried out under the
organization of Project Management. Management of Commissioning & Operation
Department is in charge to implement in detail.
Erection team should be co-operating and supporting, all the operations local or remote will
be carried out by staffs of pre-operation team under the instruction and command of
commissioning engineers.
HE HARBIN ELECTRIC (PVT) LIMITED
Pre-operation should supervise by DCS and/or periodically field inspecting on Metering and
Measuring System, any problem found should be reported to commissioning charge.
Cleaning and maintenance works happening during commissioning will be arranged and/or
fixed by erection team.
No physical damage
Test Procedure:
After wirings are terminated, the checks to identify the loops have to be conducted in
accordance with functional request. Design drawing should be followed up, a end-to-end
checking is chosen to verify the correction and reasonability.
After voltage injection successfully completes, all voltage box as well as loop terminals
should never be touched before energizing.
9 Hot Tests
On-load Checks
Once heavy loads are taken, the Attachment 4 Record Sheet of On-load Test should be
filled out in order to verify:
Following hazards identified with EHS concerns may be occurred during conducting
this procedure:
- Slips, trips and falls
- Electric shock to other personnel working in the area nearby
- Injury to others nearby due to commissioning activities
- Contact with live conductors
- Electric shock from insulation resistance check
- Site specific or work place conditions
Please see Attachment 5 for the Risk Analysis & Response Plan.
11 Attachments