11-ZG20-F-654 Method Statement For MV SWGR Erection
11-ZG20-F-654 Method Statement For MV SWGR Erection
A FOR APPROVAL
وافق عليها التاريخ
تنقيح سبب اإلصدار بواسطة راجعها
REV ISSUED FOR BY CHECKED APPROVED DATE
Project No.رقم المشروع الرياض- مشروع نظام نقل مياه رأس الزور
31001 RAS AZ ZAWR - RIYADH WATER TRANSMISSION SYSTEM
تمديد وتنفيذ خط األنابيب من محطة الضخ الثالثة حتى النهايات الطرفية بالرياض
CONSTRUCTION OF PIPE LINE FROM PS3 TO RIYADH TERMINALS
(B2 + C) المجموعة
&
PACKAGE (B2 + C)
تنفيذ محطات الضخ ومحطات صمامات العزل ومحطات الربط
CONSTRUCTION OF PUMP STATIONS, LVS & TIE-IN STATIONS
المهندس
ENGINEER
CONSULTING ENGINEERS
CONSORTIUM
SSEM – AL RASHID – HAK
المقـــاول
CONTRACTOR
SUB-
CONTRACTOR
KINGDOM OF SAUDI ARABIA Page 2 of 27
Saline Water Conversion Corporation
- RAS AZ ZAWR - RIYADH WATER TRANSMISSION SYSTEM
2
- Spec. No.
Subject: METHOD STATEMENT FOR ERECTION OF MV SWITCHGEARS
ILF CONSULTING ENGINEERS
Issue Date:
1. Purpose..................................................................................................................................... 3
2. Definitions............................................................................................................................... 4
3. Preconditions......................................................................................................................... 4
3.1 Civil Engineering Requirements 4
3.1.1 Mechanical and Electrical
Requirements 4
4. List of required documents and compilation of documents ..................................5
4.1 Scope of validity 6
5. General ..................................................................................................................................... 7
5.1 Receiving 7
6. Preparation and transport ................................................................................................7
6.1 Check Base Frame 7
6.2 Tools 9
6.3 Transport 10
7. Erection.................................................................................................................................. 11
7.1 Preparation of Erection 11
7.2 Placing of transport units ….
11
7.3 Aligning, fixing and assembling
switchgear 11
7.4 Installation of the busbars and
bushings 14
7.5 Installation of top-mounted boxes
16
7.6 Pressure relief ducts 17
7.7 Cable connections 17
7.7.1 Power cables 17
7.7.2 Control Cables 19
7.8 Earthing the switchgear 20
7.9 Laying the ring circuits 20
7.10 Final erection work 20
8. Assembly photos................................................................................................................. 21
Issue Date:
1. Purpose
The purpose of this documents to describe the installation activities to be performed for erection
of 13,8kV Switchgears in the Shoiaba Phase 3 Water Transmission Project
KEY WORDS
Shoiaba Phase 3, Medium Voltage Switchgear, Installation
ABBREVIATIONS
AC Alternative current
DC Direct current
DCS Distributed Control System
DCM Drive Control Module
DDS Design Data Sheet
DIS Document for Information and Scrutiny
ETC Extended Type Test Certificate
FAT Final Acceptance Test
Ir Rated current
AKZ Identification System for Plants
LV Low Voltage
MV Medium Voltage
RC Routine test certificate
T Technical document
TC Type test certificate
Ur Rated voltage
Issue Date:
2. Definitions:
Only qualified and competent personal capable of identifying existing and predictable hazards
will be involved.
Only specially trained and skilled people are allowed to work on MV equipment.
Prior to the work start the erection crew must receive a work permission to work in SWCC
environment. This has to be organized by site supervision.
3. Preconditions
Issue Date:
Documents
Baseframe Drawings
Arrangement Drawings
Wiring diagrams
Equipment layout
drawings.
Equipment installation
drawings.
Manufactures Manuals
Transport instructions
Method Statement
Single line diagrams
Connection diagrams
Terminal diagrams
Cabinet wiring diagram
Manufacturer erection
requirements
Erection Contractor's civil
works guide drawings
Issue Date:
Issue Date:
5. GENERAL
5.1. Receiving
As soon as equipment is received, a visual examination of the packaging shall be carried out to
determine if there was any damage during transport and handling. If any damage is noticed
please inform site management.
Drying agent bags in the packing’s to be checked and renewed if intermediate storage will be
necessary.
6. Preparation and Transport
6.1. Check Base Frame
- Installation of base frame on the concrete floor has to be performed prior to
installation of switchgear panels and secondary concret must be available before
switchboard erection
- Check the base frames for straightness and evenness.
- The tolerable values are given in the sketch below.
- Protocol to be filled out.
Survey and elaborate the differences between the erection footprints of the different fields.
Differences are to be eliminated by placing shim plates between the base frame and the steel
frame of the 13,8kV switchgear.
Floor Level in front of MV switchgear panels must be leveled properly to ensure easy moving of
vacumm circuit breaker trolleys.
The single switchboards will be installed c profiles in the secondary concrete.
Issue Date:
Figure1 Guideline example for structural data for foundation frame on concrete floor
Issue Date:
6.2 Tools
- Transport equipment for longer distances inside switchgear building, see below or
equivalent
Issue Date:
Due to limited space on the transport route inside the switchgear building the switchgear arrives
in single fields. There are no transport units with two or even three 13,8kV fields together.
For transport by crane they are equipped with transport plates. See picture below.
A crane with sufficient height shall be used in order to achieve an angular of the ropes of
minimum 45 degrees. A smaller angular could damage switchgear.
Check the sequence of the transport. It is recommended to start at the left side of the switchgear.
7. Erection
Issue Date:
Before starting the erection read carefully the instruction and the documents acc. chapter 2, the
layout drawings according to detailed design and single line diagrams.
The method of placing transport units depends on the dimensions of the transport units, i.e. if a
unit contains two or three fields.
In our case, each transport unit consists of one field.
Erect and wire the units according the sequence as given by the layout drawings.
The fields have to be aligned bolted side by side and on the base frame in the correct sequence.
Do not lose any part, bolt or nuts etc.
Issue Date:
Issue Date:
Issue Date:
Issue Date:
Issue Date:
Issue Date:
Issue Date:
Issue Date:
Issue Date:
Check all contacts and interlock mechanism for smooth motion and grease with Tobas NP
52
Issue Date:
8. Assembly photos
Issue Date:
Issue Date:
Issue Date:
Issue Date:
Issue Date:
Issue Date: