11-QC40-F-667 - A Commissioning Test Procedure For 380kv GIS
11-QC40-F-667 - A Commissioning Test Procedure For 380kv GIS
11-QC40-F-667 - A Commissioning Test Procedure For 380kv GIS
Project No. رﻗﻢ اﻟﻤﺸﺮوع أﻧﻈﻤﺔ ﻧﻘﻞ ﻣﻴــﺎﻩ اﻟﺸـــﻌﻴﺒــﺔ – اﻟﻤﺮﺣﻠـــﺔ اﻟﺜﺎﻟﺜــــﺔ
14202-003-B SHOAIBA PHASE-3 WATER TRANSMISSION SYSTEMS
اﻻﺳﺘﺸﺎري
اﻟﻤﻬﻨﺪس
ENGINEER
CONSULTING ENGINEERS
اﻟﻤﻘﺎول
CONSORTIUM
AL RASHID – HAK – SSEM
اﻟﻤﻘـــﺎول
CONTRACTOR
1 Installation 03 - 30
2 Commissioning 31 - 91
Installation Manual
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. © Copyright 2007 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: GENERAL INFORMATION Template No.:
GENERAL INFORMATION
INTRODUCTION
The purpose of the "Site Test Program for Installation" is to set a guide to the way installation of SF6-
GIS has to be carried out.
DOCUMENTATION
Prior to any installation work the following documentation is mandatory:
- Approved drawings
- Approved "Site Test Program for Installation"
The Site Test Plan for Installation refers to test procedures and test records, from these it is possible
to follow the planned tests more in detail.
TEST EQUIPMENT
All test equipment used is registred and calibrated according our ISO 9001 quality certificate.
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2007 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: GIS INSTALLATION Template No.:
Table of Contents
General
General Information
Description 121 00010 E
Civil work
Identification
Assembly
Completion
Gas measurements
Description 121 04010 E
Test Report 221 04010 E
Filling pressure control
Description 121 04020 E
Test Report 221 04020 E
Final inspection GIS
Description 121 04030 E
Test Report 221 04030 E
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2007 ABB. All rights reserved.
ABB Switzerland Ltd
Page 2/2 021 00000 E KOR 001 AA
Acceptance
503 193
Form No.: ACCEPTANCE OF BUILDING AND Template No.:
1. Purpose of inspection
2. General checks
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2007 ABB. All rights reserved.
Page: Template No.:
During the installation of the SF6 switchgear, no rework of construction in the building
should be permitted. In the event that such work is unavoidable, the chief supervisor
should coordinate this work with the local construction management. In such a case,
installation of the SF6 switchgear shall have first priority.
The switchgear room must be lockable.
All breakthroughs, cable ducts etc. leading to the outside must be fitted with appropri-
ate covers.
During the installation, the switchgear room must be kept clean. Vacuum cleaning, wet
wiping of floors if necessary.
Note: The crane facility must be examined periodic on cleanness.
Case 2 Inspection of site has show, that conditions at site do not comply with ABB requirements.
A Start of installation is postponed until all deficiencies are “solved” and conditions fullfill
ABB requirements.
- ABB shall not be kept responsible for delay in schedule resulting from this action.
- ABB will claim for waiting period of supervisor and rental fee for tools.
In case of flashover during HV-Test the resulting repair costs of such couplings will be
claimed.
Amount of couplings & extend of installation which do not fullfill ABB requirements shall
jointly be “traced”.
proceed acc. to
Customers decision: A)
B)
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: ACCEPTANCE OF BUILDING AND Template No.:
The acceptance of building shall take place, if the above mentioned items are completed and to the
satisfaction of the ABB Switzerland Ltd field supervisor. Minor outstandings / deviations shall be reported.
ABB Switzerland Ltd shall not be responsable for any delay of installation due to
non acceptance of building and foundations.
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2007 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: CONTROL AND CONNECTION OF Template No.:
1. Purpose of performance
-Identity number
-Registration of condition
-Mechanical condition
-Nitrogen remaining gas pressure
-Registration of flange treatment
-After coupling, treatment on site
-Damage report reference if necessary
-Location
3. Control
Equipment and materials for installation are defined in the drawing "Assembly Drawing"
including the belonging material lists.
The allocations of equipment and loose materials are stated by "Unit-N°" e.g. 001, 002,
etc.
After unpacking, each unit must be controlled to the corresponding report form and after
to be installed in the determined location. (Assembly Drawing)
4. Connections
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2007 ABB. All rights reserved.
Page: Template No.:
While coupling the assembly units, make sure that the enclosures are only opened
shortly before the coupling is carried out. If that is not possible, the opened parts are to
be covered with plastic foil or protective hoods to limit the danger to a minimum of for-
eign materials (dust, chips) getting into them.
The insulators may not be touched with the bare hands, plastic gloves required!
For each connection between two assembly units, new O-rings are delivered and shall
be installed.
503 193
Form No.: CONTROL AND CONNECTION OF ASSEMBLY UNITS Template No.:
Remarks:
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.
© Copyright 2007 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: PRIMARY RESISTANCE Template No.:
1. Purpose of test
2. Test equipment
3. Test conditions
If a correction factor is applied, the ambient temperature is to be noted in the test report
form.
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2007 ABB. All rights reserved.
Page: Template No.:
4. Test arrangement
Open
link Open
link
A μΩ
CORRECT INCORRECT
U U
I I
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: PRIMARY RESISTANCE MEASUREMENTS Template No.:
Remarks:
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.
© Copyright 2007 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: EVACUATION AND FILLING Template No.:
1. Purpose of test
Check of tightness of gas compartments during evacuation phase and after filling with
SF6-Gas.
The monitoring of the pressure continues during all the installation time until commis-
sioning has finished. It consists of measurements of SF6 gas pressure drop in gas com-
partments.
2. Test equipment
3. Special precautions
As a general rule it is recommended that the insulators must not be subjected to unnec-
essary mechanical stressing.
lt is recommended that the gas compartments be filled (alternatively) such that the
pressure differences acting on the barrier insulators during the filling procedure do not
exceed approx. Pabs =350kPa.
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2007 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: EVACUATION AND FILLING Template No.:
Remarks:
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2007 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: DENSITY MONITORS OPERATING Template No.:
1. Purpose of test
For testing, the density monitors are mounted on the buffer container (item 3). In case
of firmly mounted density monitors, only the present switching condition can be indi-
cated.
The test pressure is indicated at the gauge (item 6). The indicator lamp in the indicat-
ing unit (item 7) lights up when the corresponding switch contact is closed.
SF6-gas over the coupling (item 1) or compressed air, which is generated by means of
the air pump (item 8), is used as testing medium
2. Test arrangement
Density Monitor
5
3
2 1
4
9
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2007 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: DENSITY MONITORS OPERATING Template No.:
To Procedure: 1HC0017413
Gas schematic diagram No.: Test equipment No.:
Rated value at 20°C: Signal 1: / Signal 2: / Signal 3: kPa abs
Remarks:
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2007 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: GAS MEASUREMENTS Template No.:
1. Objective
To proof that the gas insulated switchgear equipment will not exceed the maximum ad-
missible humidity in operation.
2. Applicability
SF6 gas insulated switchgear of ABB Switzerland Ltd. and associated components.
3. Procedure
The measurement should be done during the commissioning after the filling of the com-
ponents with gas after a balance of eventual equalisation phenomena in the distribution
of moisture in the gas compartment.
4. Scope of test
All gas compartments in the installation are to be checked for moisture, SF6 percentage
and pressure
5. Responsibility
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2007 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: GAS MEASUREMENTS Template No.:
Remarks:
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2007 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: FINAL INSPECTION GIS Template No.:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2007 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: FINAL INSPECTION GIS Template No.:
Remarks:
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2007 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: SPARE PARTS / SERVICE Template No.:
General Control
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2007 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: SPARE PARTS / SERVICE Template No.:
Remarks:
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2007 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: COMPLETION CERTIFICATE Template No.:
General Control
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2007 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: COMPLETION CERTIFICATE Template No.:
INSTALLATION OF GIS
PENDING ITEMS
ENCLOSURE
REMARKS
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2007 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: DOCUMENT LIST Template No.:
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.
© Copyright 2007 ABB. All rights reserved.
SHOAIBA 380kV GIS EXTENSION
Installation & Commissioning Schedule
ABB
ID Task Name Duration Start Finish % Complete November 2007 December 2007 January 2008 February 2008 March 2008 April 2008
25 28 31 03 06 09 12 15 18 21 24 27 30 03 06 09 12 15 18 21 24 27 30 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28
1 Installation 380kV GIS Shaoba Ext 103 days Thu 01.11.07 Thu 20.03.08 0%
3 Site Preparation & Taking over of Site 5 days Thu 01.11.07 Wed 07.11.07 0%
10 Cable Trays and Secondary Cabling 25 days Fri 07.12.07 Wed 09.01.08 0%
12 GIS Ready for cable termination 5 days Fri 18.01.08 Thu 24.01.08 0%
13 Installation of Cable Links ( To cordinate with cable supplier) 10 days Fri 25.01.08 Thu 07.02.08 0% To cordinate with cable supplier
14
21
25 Coupling of Ext. GIS to Exsiting GIS 9 days Mon 03.03.08 Thu 13.03.08 0% To Cordinate with Client for outage
26 Pack Tools and Installation Equipment 5 days Fri 01.02.08 Thu 07.02.08 0%
29
31 Supervisor: 400kV GIS 1 (Mechanical) 103 days Thu 01.11.07 Thu 20.03.08 0%
33
39
40 Personal Reguest Subcontractor (Subc) 103 days Thu 01.11.07 Thu 20.03.08 0%
Shoaiba Ext. Schedule Rev. 01 Page 1 V.Kola GIS Superv. ABB Switzerland Ltd.
Document No.:
ABB Switzerland Ltd 1HC0055332
Responsible department: Take over department: Revision: Doc.-type: File no.:
Commissioning Manual
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: GIS COMMISSIONING Template No.:
Table of Contents
General
General Information
Description 111 00010 E
Safety Procedure
Description 111 00020 E
VT Secondary Insulation
Description 111 03010 E
Test Report 211 03010 E
VT DC Resistance
Description 111 03030 E
Test Report 211 03030 E
VT Polarity
Description 111 03040 E
Test Report 211 03040 E
VT Transmission Ratio
Description 111 03050 E
Test Report 211 03050 E
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Page 2/2 011 00000 E KOR 001 AA
VT Distribution
Description 111 03060 E
Test Report 211 03060 E
CT Secondary Insulation
Description 111 03080 E
Test Report 211 03080 E
CT Magnetisation
Description 111 03090 E
Test Report 211 03090 E
CT Magnetisation with CPC 100
Description 111 03091 E
Test Report 211 03091 E
CT DC Resistance
Description 111 03100 E
Test Report 211 03100 E
CT Polarity
Description 111 03110 E
Test Report 211 03110 E
CT Primary Injection
Description 111 03130 E
Test Report 211 03130 E
Interlocking
Description 111 04010 E
Test Report 211 04010 E
Local Control REC216
Description 111 04031 E
Test Report 211 04031 E
Local Alarms
Description 111 04060 E
Test Report 211 04060 E
ABB Switzerland Ltd
503 193
Form No.: GENERAL INFORMATION Template No.:
GENERAL INFORMATION
INTRODUCTION
The purpose of the “Site Inspection and Test Plan for Testing & Commissioning” is to set a
guide to the way site testing & commissioning has to be carried out.
GENERAL ASPECTS
The site testing & commissioning of a transmission or distribution plant are the final activities
to confirm that the plant operates correctly and fulfils specified requirements. Normally, the
equipment is already factory tested and it is the duty and responsibility of the commissioning
engineers to make sure that the equipment is assembled/installed correctly. The main objec-
tives of the “Site Inspection and Test Plan for Testing & Commissioning” are:
⇒ That the equipment operates correctly and has not been damaged during transportation
or installation
⇒ Adjustment of all relay setting parameters to obtain the maximum selectivity in order to i-
solate the minimum amount of equipment when a fault occurs
⇒ To obtain a set of as-built drawings and test records as reference for future modifications
and periodic maintenance
In order to be able to perform the testing & commissioning systematically and professionally
it is a pre-requirement that the test procedures and test records have been agreed with the
client and that the commissioning engineer has got the correct mental approach to execute
the activities.
Commissioning Coordinator
A Commissioning Coordinator is responsible to organise all works related to testing & com-
missioning and to implement the “Site Inspection and Test Plan for Testing and Commission-
ing”.
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
Page: Template No.:
A Testing & Commissioning Engineer is responsible for the testing & commissioning of e-
quipment and to ensure that the correct procedures are followed. Upon completion of each
test he will sign the appropriate test record and request any witnessing representative to do
the same.
SAFETY REQUIREMENTS
All general site requirements shall apply to testing & commissioning. Suitable warning signs
shall be placed to ensure that personnel not involved with the testing & commissioning are
aware that additional hazards may exist. All personnel involved in the testing & commission-
ing shall be aware of all safety requirements.
DOCUMENTATION
Prior to any testing & commissioning work the following documentation is mandatory:
⇒ Approved drawings
⇒ Approved ”Site Inspection and Test Plan for Testing & Commissioning”
The Site Inspection and Test Plan deals with inspections and tests on site before and during
energisation of the substation.
The Site Inspection and Test Plan is listing the inspections and tests which are planned to be
done on site.
The Site Inspection and Test Plan refers to test descriptions and test reports, from these it is
possible to follow the planned tests more in detail.
TEST PROCEDURE
TEST RECORD
TEST EQUIPMENT
ABB Switzerland Ltd normally owns test equipment used at sites. But occasionally it may be
necessary to rent from third party. All test equipment used will be calibrated and have a valid
calibration certificate.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: SAFETY PROCEDURE Template No.:
1. General
From the safety point of view, the testing & commissioning of distribution and transmission plants is of-
ten done under hazardous conditions. The risk of accidents must always be taken into consideration
and the testing & commissioning personnel have to be fully aware of the dangers that exist and should
know how to conduct their work to avoid such hazards.
2. Electric shock
Without any doubt, the greatest risk associated with the testing & commissioning of electric plant is
that of electric shock. Accidents due to electric shock occupy an exclusive position since the persons
involved seldom receive any forewarning as the danger cannot be apprehended by the human senses.
For example, brief contact with a “live” part of an installation, which neither by sound or movement
shows any signs of being dangerous, is all that is necessary to cause a serious accident.
1. Disconnecting
2. Securing against reclosing
3. Testing for absence of voltage
4. Earthing and short-circuiting
5. Covering or fencing off adjacent live parts
3. Working method
The testing & commissioning of plant quite often has to be accomplished within a very short space of
time and with many people from different companies involved.
There are two potential reasons for accidents which testing & commissioning personnel must take into
consideration:
⇒ Stressful situation during the energizing sequence etc. when one party is unaware of the actions
taken by the other.
The testing & commissioning personnel must never allow themself to be influenced by customer de-
mands (economic pressure) etc. which can jeopardize the safety of personnel.
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
Page: Template No.:
During all energizing procedures, all orders and instructions regarding operations, connections, tempo-
rary earthing etc. are to be given by the person (customer/consulting engineer) responsible for the op-
eration of the plant. All contacts between the latter person and ABB’s testing & commissioning per-
sonnel are, during the energizing sequence, to be made via one person only (the chief commissioning
engineer) to prevent fatal misunderstanding.
Directives regarding the taking of measurements and any required fault-finding procedures in ener-
gized equipment, are to be given by ABB’s chief commissioning engineer in order to minimize the risk
of accidents which can occur when uncertainty arise as to who does what.
All personnel in the vicinity of the plant must be fully informed of the risks, which are present when
auxiliary circuits of the plant are energised.
A suitable way of informing assisting personnel of the hazards associated with testing & commission-
ing work is, in addition to oral instructions, to give them the opportunity of studying this document.
Work verification: A verification that a particular section of a plant is completely isolated from the power
supply, that it is earthed and short circuited to an extent as stated in the verification. This also implies
that the specified status of the section will be maintained until the holder of the work verification issues
an operational verification.
Operational verification: A verification that a particular section of the plant, on which the issuer of the
mentioned verification has been working, is ready for operation. This implies that the section in ques-
tion is in a condition as stated in the verification and that all earth connections and short circuits, made
by the issuer of the verification, have been removed.
The work and operational verifications are often combined to one document, a Work Permit. A Work
Permit is issued as a work verification by the person in charge of operations and is retained by the
commissioning personnel until such time as the requisite work has been completed and the applicable
section of the plant is ready for operation.. The commissioning personnel then signs the document
(Operational Verification) and returns it to the person in charge of operations.
IF THE CUSTOMER USES THE WORK PERMIT SYSTEM, SUCH A PERMIT HAS TO BE
OBTAINED BEFORE COMMENCING WORK ON A SECTION OF THE PLANT THAT HAS
PREVIOUSLY BEEN IN OPERATION.
Page: Template No.:
6. Operational responsibility
The person responsible for the operation of a new plant, and thus he who is responsible for the safety
of personnel, during the time from the commencement of plant energization to when the customer
takes over the plant, is not always clearly defined. The fundamental principle is that the customer is
always responsible for plant operation and safety as soon as energization has commenced.
The above implies that the customer is responsible for ensuring that, among other things, energized
section are cordoned off, locks are fitted to control room doors, cautionary signs are placed in position
and that all other precautionary measures are immediately taken.
Prior to plant energization, the customer/consulting engineer is to be informed that ABB’s plant/plant
section is ready for operation and that the customer, as soon as energization is commenced, is solely
responsible for the operation and safety of the plant. This may be in contradiction to any contract
agreement but nevertheless should be observed to make all parties aware of the prevailing situation.
Despite this, ABB’s testing & commissioning personnel must ensure that reasonable safety measures
have been taken by the customer. If the customer lacks a functional organization and the safety
measures are considered as being inadequate, ABB’s testing & commissioning personnel must ensure
that reasonable measures are taken, considering at least their own safety. Example of such measures
are:
Prior to commencing work on a plant section, e.g. a substation, where there is the slightest risk that
the equipment is, or can be, energized, the testing & commissioning personnel is always responsible
for ensuring that the equipment is “dead”. This can be determined in different ways:
⇒ With the aid of a voltmeter. Always used for low voltage but not normally for high voltage.
⇒ By making a visual inspection to ensure that the plant section is completely isolated from the supply
and that all temporary earthing measures have been taken.
If the plant is in operation, the customer is normally responsible for such and for ensuring that sections
are isolated and temporarily earthed. In other cases, it is to the testing & commissioning personnel in-
terest to ensure that necessary measures have been taken to ensure their own safety and that of other
personnel.
7.2 Disconnection
A plant section is considered as being completely isolated only when all the conductors, that can sup-
ply power to the section, are disconnected. This is accomplished by means of disconnectors incorpo-
rating visible break points or reliable position indicators, or by the extraction of fuses, truck-type circuit
breakers, etc.
Page: Template No.:
When isolating a plant section, certain items must be given special consideration:
⇒ Reverse supply. A great deal of accidents have occurred in cases when the persons involved were
unaware of the fact that the plant was being supplied in the reverse direction from ring circuits, local
auxiliary power generators, etc.
⇒ Erroneous action. Always make a careful check to ensure that the correct disconnectors are opened.
⇒ Inadvertent breaks. Before operating a disconnector, always ensure that the load current (if any) has
been interrupted since conventional disconnectors are not designed to break heavy current.
Disconnectors, truck type circuit breakers, etc. are to be locked in their open positions to prevent them
from being closed by mistake.
Temporary safety earthing means the earthing and short circuiting at the place of work to ensure that
the plant section in question will not be subject to any voltages which can be of danger to the person-
nel.
Prior to commencing work on a high-voltage installation, the latter must always be temporarily earthed.
If fixed earthing switches, earthing trucks, etc. are incorporated, these are to be used. If portable
earthing equipment is used, this must first be connected to earth and then to the phase conductors. If
the plant is “live” by mistake, a powerful arc can develop when making earth connections. For this
reasons, appropriate tools such as insulated rods are always to be used. Portable earthing equipment
must be capable of withstanding the highest short circuit current for a period of 1 second.
7.4 Barriers
If testing & commissioning work is to be done on a partially energized “hot“ plant where the testing &
commissioning personnel may inadvertently come in contact with a “live” plant section, barriers, are to
be set up to give warning of the “live” plant sections that are located in the vicinity of the place of work.
Example of such sections are:
Even when high-voltage tests are being made on plant sections, the equipment being tested and the
test equipment must be cordoned off to prevent accidents.
Special barriers ropes, fitted with appropriate warning signs are suitable for this purpose. The ropes
should be removed immediately after they have served their purpose.
7.5 Clothing
To reduce the risk of accidents and to minimize the effects of accidents which may occur, the commis-
sioning engineer should not wear rings, necklaces, wrist-watch straps, etc. of metal when making tests
in which he may come in contact with “live” parts.
Clothes of synthetic material should not be worn if there is any risk that arcs can develop. Synthetic
material melts and penetrates the skin resulting in severe burnings and other injuries.
Page: Template No.:
When measuring voltages on distribution busbars (high short-circuit power/powerful arcs), great care
must be exercised in order to avoid short circuits. The inputs of the instruments being used must in-
corporate fuses. If an output is connected between the phases of a busbar a fatal accident may be the
result.
If works has to be done in energized low-voltage switchgear etc., the handles of the tools used must
be adequately insulated. If screwdrivers are used, their shank must also be insulated. One of the
most common accidents occurs when a screwdriver slips and its shank causes an undesired short
circuit/arc.
9. Induced voltages
Non-energized plant sections, such as lines and busbars in outdoor substations, which are not
earthed, can often assume dangerous potential due to induction from near-lying “live” parts. The risk of
dangerous induction voltages is greatest in the vicinity of high-voltage (> 200 kv) substations. The
shock received by a person who inadvertently comes in contact with a part energized by means of in-
duction, for example in an outdoor apparatus, can be sufficient to throw him off a ladder. Induction
voltages in non-operating plants can be prevented by sufficient earthing, e.g. with normal copper wire.
If work has to be carried out on an energized substation, the tools used must therefore be adequately
insulated to prevent inadvertent short circuiting.
Voltage measuring instruments such as voltmeter or phase-sequence indicators, which are used dur-
ing the testing & commissioning work, are to be connected to the external side of an apparatus group,
i.e. on the fused side. Furthermore, the instruments used should, where possible, be provided with
fuses.
14. Batteries
For operational reasons, the station battery of a plant is normally connected directly to the DC-
distribution board without any intermediate fuses. The high short-circuit current from the battery is
therefore not limited by any fuse and great care must be exercised when taking measurements and
when working on the battery circuit.
15. Convertor
The output current of a convertor is, normally, limited only by the convertor’s current limiter which often
has a relatively high setting. As is the case with the battery, great care must be taken to ensure that
the convertor’s output port is not short-circuited by mistake.
16. Fuses
When removing/inserting high-rated fuses, such as blade fuses in low-voltage switchgear, or high-
voltage fuses, insulated fuse tongs are always to be used.
Where such is possible, fuses should always be replaced in the “dead” state, i.e. with the fuse-switch
in the “Off” position. If, for any reasons, the fuseholder cannot be de-energized (e.g. battery fuses),
one should always make a habit of ensuring that no short circuit occurs when large-size low-voltage
fuses are inserted in their holders. The best way of doing this, is to check that the voltage across the
other fuseholders is zero after inserting the first fuse.
Accidents of this type can be prevented by disconnecting the control circuits to electrically operated
equipment and, if possible, by securing such equipment mechanically.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: CB ELK HMB Template No.:
General Control
Function check
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: CB ELK HMB Template No.:
Remarks:
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: CB TIMING TEST Template No.:
Measurement
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: CB TIMING TEST Template No.:
Remarks:
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: CB PUMP START CONTROL Template No.:
CB pump check
To check the tightness of seals in the CB pump, the ammount of pump charges during
24 hours have to be recorded. Important are the pump starts due to pressure loss with-
out any switching operations.
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: CB PUMP START CONTROL Template No.:
Remarks:
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: ISOLATOR & EARTH SWITCH Template No.:
Automatic operation
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: ISOLATOR & EARTH SWITCH Template No.:
Remarks:
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
ABB Switzerland Ltd Telephone: Telefax: www.abb.ch
Utility Services +41 58 58 83300 +41 58 58 81188 VAT No.: 101 401
Brown Boveri Strasse 5
CH-8050 Zürich / Switzerland
503 193
Form No.: DENSITY MONITORS Template No.:
General Control
Simulation
Check of all alarms and functions with the simulation device
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: DENSITY MONITORS Template No.:
Remarks:
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: VT SECONDARY INSULATION Template No.:
Secondary Insulation
TEST ARRANGEMENT :
Ph1
Ph2
Ph3
A
1a 1n 2a 2n
ΜΩ ΜΩ ΜΩ
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: VT SECONDARY INSULATION Template No.:
winding 4 to earth
____kV
winding 5 to earth
/ winding 1 to winding 2
winding 1 to winding 3
____V
winding 1 to winding 4
winding 1 to winding 5
winding 2 to winding 3
winding 2 to winding 4
winding 2 to winding 5
winding 3 to winding 4
winding 3 to winding 5
winding 4 to winding 5
Remarks:
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: VT DC RESISTANCE Template No.:
DC-Resistance
TEST ARRANGEMENT :
Ph1
Ph2
Ph3
A
1a 1n 2a 2n
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: VT DC RESISTANCE Template No.:
Name Core Location Terminal Phase ___ Phase ___ Phase ___
Block [Ω] [Ω] [Ω]
# ______ to to to
1
T Result
# ______ to to to
_____ 2
Result
____kV # ______ to to to
3
Result
/ # ______ to to to
4
Result
____V
# ______ to to to
5
Result
Remarks:
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: VT POLARITY Template No.:
Checks
TEST ARRANGEMENT :
Ph1
Ph2
Ph3
A
1a
+
1n
2a 4.5-9 V
-
2n
N
+ V -
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: VT POLARITY Template No.:
Name Core Location Terminal Phase ___ Phase ___ Phase ___
Block VT No. _________ VT No. __________ VT No. __________
# ______
1
T Result
# ______
_____ 2
Result
____kV # ______
3
Result
/ # ______
4
Result
____V
# ______
5
Result
Name Core Location Terminal Phase ___ Phase ___ Phase ___
Block VT No. _________ VT No. __________ VT No. __________
# ______
1
T Result
# ______
_____ 2
Result
____kV # ______
3
Result
/ # ______
4
Result
____V
# ______
5
Result
A: + / N: -
Remarks:
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: VT TRANSMISSION RATIO Template No.:
Transmission Ratio
TEST ARRANGEMENT :
Ph1
Ph2
Ph3
A
1a
1n
2a
2n
V
N
AC Supply
50/60 Hz
V V
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: VT TRANSMISSION RATIO Template No.:
Name Core Location Terminal Phase ___ Phase ___ Phase ___
Block [V] [V] [V]
# ______ to to to
1
T Result
# ______ to to to
_____ 2
Result
____kV # ______ to to to
3
Result
/ # ______ to to to
4
Result
____V
# ______ to to to
5
Result
Name Core Location Terminal Phase ___ Phase ___ Phase ___
Block [V] [V] [V]
# ______ to to to
1
T Result
# ______ to to to
_____ 2
Result
____kV # ______ to to to
3
Result
/ # ______ to to to
4
Result
____V
# ______ to to to
5
Result
Remarks:
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: VT DISTRIBUTION Template No.:
General Control
Measurements, Tests
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: VT DISTRIBUTION Template No.:
Special function:
Checked
Voltage selection [ ]
Volt meter (switch) [ ]
* Power meter [ ]
* Reactive power [ ]
Transducer [ ]
* Counter [ ]
* In function with the current!
Remarks:
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: CT SECONDARY INSULATION Template No.:
Secondary Insulation
TEST ARRANGEMENT :
Ph1
Ph2
Ph3
ΜΩ ΜΩ ΜΩ
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: CT SECONDARY INSULATION Template No.:
core 4 to earth
____kA
core 5 to earth
/ core 1 to core 2
core 1 to core 3
____A
core 1 to core 4
core 1 to core 5
core 2 to core 3
core 2 to core 4
core 2 to core 5
core 3 to core 4
core 3 to core 5
core 4 to core 5
Remarks:
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: CT MAGNETISATION Template No.:
Magnetisation
TEST ARRANGEMENT :
Ph1
Ph2
Ph3
S1 S2
220 V
A 50/60 Hz
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: CT MAGNETISATION Template No.:
Remarks:
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
Page: Template No.:
CT Name
______ How to import a graphic of Metrawin :
1. Start Microsoft Word and open this page ( 211 03090 E )
Phase 2. Start Metrawin and open the file witch you want to insert.
______ 3. Point the cursor at the voltage level of the knie point.
4. Press „Print Screen“.
Core Nr 5. Press „Alt“ and „Tab“ and come back to Word.
______ 7. Come back on this page and mark the whole square.
8. Than „Ctrl“ and „V“
Ratio
_________/___A
Class
______
CT Name
______
Phase
______
Core Nr
______
Ratio
_________/___A
Class
______
Remarks:
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: CT MAGNETISATION WITH CPC100 Template No.:
Magnetisation
TEST ARRANGEMENT :
Ph1
Ph2
Ph3
S1 S2
220 V
A 50/60 Hz
V
CPC100
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: CT MAGNETISATION WITH CPC100 Template No.:
Feeder: =B1
Phase: A
CT: -T1
Core: X1-X2
38.42 V 2.24 A
37.73 V 1.99 A
36.96 V 1.77 A
36.1 V 1.58 A 30.0 V
35.14 V 1.4 A
34.08 V 1.25 A
32.9 V 1.11 A
25.0 V
31.44 V 0.99 A
29.7 V 0.88 A
27.53 V 0.79 A
25.1 V 0.7 A
20.0 V
22.52 V 0.62 A
20.01 V 0.55 A
15.95 V 0.44 A
12.56 V 0.36 A 15.0 V
9.88 V 0.29 A
7.84 V 0.23 A
6.21 V 0.19 A
4.87 V 0.15 A 10.0 V
3.84 V 0.12 A
2.13 V 0.07 A
1.69 V 0.05 A
1.35 V 0.04 A 5.0 V
1.1 V 0.04 A
0.91 V 0.03 A
0.75 V 0.02 A
0.0 V
0.64 V 0.02 A 0.0 A 0.5 A 1.0 A 1.5 A 2.0 A 2.5 A 3.0 A
Remarks:
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
Page: Template No.:
Feeder: =B1
Phase: A
CT: -T1
Core: X1-X3
V ma x: 200
I ma x: 2.5
Frequency: 60 90.0 V
Automa tic: 1
V I
80.0 V
87.46 V 2.65 A
86.41 V 2.14 A
85.55 V 1.79 A
84.76 V 1.49 A 70.0 V
83.89 V 1.24 A
81.89 V 0.97 A
79.87 V 0.77 A 60.0 V
79.41 V 0.73 A
76.29 V 0.6 A
73.04 V 0.51 A
50.0 V
68.72 V 0.44 A
62.79 V 0.37 A
54.97 V 0.32 A
47.82 V 0.27 A 40.0 V
35.7 V 0.21 A
26.51 V 0.16 A
19.73 V 0.12 A 30.0 V
14.67 V 0.09 A
10.88 V 0.07 A
8.09 V 0.05 A
20.0 V
5.99 V 0.04 A
3.74 V 0.03 A
2.81 V 0.02 A
2.13 V 0.02 A 10.0 V
1.6 V 0.01 A
1.21 V 0.01 A
0.93 V 0.01 A 0.0 V
0.0 A 0.5 A 1.0 A 1.5 A 2.0 A 2.5 A 3.0 A
Remarks:
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: CT DC RESISTANCE Template No.:
DC-Resistance
TEST ARRANGEMENT :
Ph1
Ph2
Ph3
Ω Ω
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: CT DC RESISTANCE Template No.:
Name Core Term. to Term. Phase ___ Phase ___ Phase ___
[Ω] [Ω] [Ω]
-
T_____
-
_____/___A -
-
-
T_____
-
_____/___A -
-
-
T_____
-
_____/___A
-
T_____
-
_____/___A
-
T_____
-
_____/___A
Remarks:
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: CT POLARITY Template No.:
Polarity
TEST ARRANGEMENT :
Ph1 + P1 P2 -
S1 S2
Ph2
- +
Ph3 4.5-9 V
+ A -
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: CT POLARITY Template No.:
Name Core Location Terminal Phase ___ Phase ___ Phase ___
Block CT No. _________ CT No. __________ CT No. __________
# ______
1
T Result
# ______
_____ 2
Result
____A # ______
3
Result
/ # ______
4
Result
____A
# ______
5
Result
Name Core Location Terminal Phase ___ Phase ___ Phase ___
Block CT No. _________ CT No. __________ CT No. __________
# ______
1
T Result
# ______
_____ 2
Result
____A # ______
3
Result
/ # ______
4
Result
____A
# ______
5
Result
P1: + / P2: -
Remarks:
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: CT PRIMARY INJECTION Template No.:
Primary Injection
TEST ARRANGEMENT :
Ph1
Ph2
A
Ph3
A A A A
AC Supply
50/60 Hz
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: CT PRIMARY INJECTION Template No.:
Core injected injected Phase Phase Phase Phase Phase Phase Phase Phase
Ratio [A] ___ ___ ___ N ___ ___ ___ N
T_____
_______
____/__A
Core injected injected Phase Phase Phase Phase Phase Phase Phase Phase
Ratio [A] ___ ___ ___ N ___ ___ ___ N
T_____
_______
____/__A
Remarks:
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: INTERLOCKING Template No.:
Checks
Circuit Breaker
Earthing Switch
Isolator
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: INTERLOCKING Template No.:
Apparatus Operation
close/open
Remarks:
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.
© Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: LOCAL CONTROL REC216 Template No.:
General Control
Electrical connections
Earthing
Recording of software version and relay settings
Analogue channels
Input and output signals
Internal logic (FUPLA)
Special functions (Synchrocheck etc.)
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: LOCAL CONTROL REC216 Template No.:
Settings:
According to separate print out Software version of relay ....................
Secondary injection (First analogue input module 216EA61):
Chan- Main C.T./ Rated AD chan- Injected Display AD channels
nel P.T.ratio value nel value calculated displayed
number ref. value
[A/A], [A], [V] [-] [A], [V] [IN], [UN] [°] [IN], [UN] [°]
[kV/V] *
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
*) 100/200 V or 1/2/5 A as appropriate
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
Page: Template No.:
Remark: If XS92a is used for checking (MOD UI, 3 voltages, 1 current) inject the currents in series to check the
angle between themselves and between the currents and the voltage. Set angle 0° between voltage R and the
current.
If AD channel reference value is not 1.0 it is advisable to inject rated value * ref. value to give the display of 1.00 *
UN/IN.
Example: Rated current protected object = 540 A, C.T.ratio = 600/5 ---> Ref. value = 0.9
Injected current = 5 * 0.9 = 4.5 A ---> Display = 1.00 * IN
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
Page: Template No.:
Function/Remark Result
CHI 01 ............................................................................................................................. ...............
CHI 02 ............................................................................................................................. ...............
CHI 03 ............................................................................................................................. ...............
CHI 04 ............................................................................................................................. ...............
CHI 05 ............................................................................................................................. ...............
CHI 06 ............................................................................................................................. ...............
CHI 07 ............................................................................................................................. ...............
CHI 08 ............................................................................................................................. ...............
CHI 09 ............................................................................................................................. ...............
CHI 10 ............................................................................................................................. ...............
CHI 11 ............................................................................................................................. ...............
CHI 12 ............................................................................................................................. ...............
CHI 13 ............................................................................................................................. ...............
CHI 14 ............................................................................................................................. ...............
CHI 15 ............................................................................................................................. ...............
CHI 16 ............................................................................................................................. ...............
Function/Remark Result
CHI 17 ............................................................................................................................. ...............
CHI 18 ............................................................................................................................. ...............
CHI 19 ............................................................................................................................. ...............
CHI 20 ............................................................................................................................. ...............
CHI 21 ............................................................................................................................. ...............
CHI 22 ............................................................................................................................. ...............
CHI 23 ............................................................................................................................. ...............
CHI 24 ............................................................................................................................. ...............
CHI 25 ............................................................................................................................. ...............
CHI 26 ............................................................................................................................. ...............
CHI 27 ............................................................................................................................. ...............
CHI 28 ............................................................................................................................. ...............
CHI 29 ............................................................................................................................. ...............
CHI 30 ............................................................................................................................. ...............
CHI 31 ............................................................................................................................. ...............
CHI 32 ............................................................................................................................. ...............
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
Page: Template No.:
Function/Remark Result
CHI 33 ............................................................................................................................. ...............
CHI 34 ............................................................................................................................. ...............
CHI 35 ............................................................................................................................. ...............
CHI 36 ............................................................................................................................. ...............
CHI 37 ............................................................................................................................. ...............
CHI 38 ............................................................................................................................. ...............
CHI 39 ............................................................................................................................. ...............
CHI 40 ............................................................................................................................. ...............
CHI 41 ............................................................................................................................. ...............
CHI 42 ............................................................................................................................. ...............
CHI 43 ............................................................................................................................. ...............
CHI 44 ............................................................................................................................. ...............
CHI 45 ............................................................................................................................. ...............
CHI 46 ............................................................................................................................. ...............
CHI 47 ............................................................................................................................. ...............
CHI 48 ............................................................................................................................. ...............
Function/Remark Result
CHI 49 ............................................................................................................................. ...............
CHI 50 ............................................................................................................................. ...............
CHI 51 ............................................................................................................................. ...............
CHI 52 ............................................................................................................................. ...............
CHI 53 ............................................................................................................................. ...............
CHI 54 ............................................................................................................................. ...............
CHI 55 ............................................................................................................................. ...............
CHI 56 ............................................................................................................................. ...............
CHI 57 ............................................................................................................................. ...............
CHI 58 ............................................................................................................................. ...............
CHI 59 ............................................................................................................................. ...............
CHI 60 ............................................................................................................................. ...............
CHI 61 ............................................................................................................................. ...............
CHI 62 ............................................................................................................................. ...............
CHI 63 ............................................................................................................................. ...............
CHI 64 ............................................................................................................................. ...............
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
Page: Template No.:
Function/Remark Result
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
Page: Template No.:
Function/Remark Result
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
Page: Template No.:
Activation of tripping relays (First and second tripping output unit 216DB61)
Function/Remark Result
CHT 01 Contact 1
................................................................................................................. ...............
CHT 01 Contact 2
................................................................................................................. ...............
CHT 02 Contact 1
................................................................................................................. ...............
CHT 02 Contact 2
................................................................................................................. ...............
CHT 03 Contact 1
................................................................................................................. ...............
CHT 03 Contact 2
................................................................................................................. ...............
CHT 04 Contact 1
................................................................................................................. ...............
CHT 04 Contact 2
................................................................................................................. ...............
CHT 05 Contact 1
................................................................................................................. ...............
CHT 05 Contact 2
................................................................................................................. ...............
CHT 06 Contact 1
................................................................................................................. ...............
CHT 06 Contact 2
................................................................................................................. ...............
CHT 07 Contact 1
................................................................................................................. ...............
CHT 07 Contact 2
................................................................................................................. ...............
CHT 08 Contact 1
................................................................................................................. ...............
CHT 08 Contact 2
................................................................................................................. ...............
CHT 01 Contact 1
................................................................................................................. ...............
CHT 01 Contact 2
................................................................................................................. ...............
CHT 02 Contact 1
................................................................................................................. ...............
CHT 02 Contact 2
................................................................................................................. ...............
CHT 03 Contact 1
................................................................................................................. ...............
CHT 03 Contact 2
................................................................................................................. ...............
CHT 04 Contact 1
................................................................................................................. ...............
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
Page: Template No.:
Function/Remark Result
CHT 04 Contact 2
................................................................................................................. ...............
CHT 05 Contact 1
................................................................................................................. ...............
CHT 05 Contact 2
................................................................................................................. ...............
CHT 06 Contact 1
................................................................................................................. ...............
CHT 06 Contact 2
................................................................................................................. ...............
CHT 07 Contact 1
................................................................................................................. ...............
CHT 07 Contact 2
................................................................................................................. ...............
CHT 08 Contact 1
................................................................................................................. ...............
CHT 08 Contact 2
................................................................................................................. ...............
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
Page: Template No.:
Activation of tripping relays (Third and fourth tripping output unit 216DB61)
Function/Remark Result
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
Page: Template No.:
Check of "FUPLA"
Close Open
Breaker / Isola- Interlocking function command command
tor
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: LOCAL ALARMS Template No.:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
ABB Switzerland Ltd
Client: Project name: Contract:
503 193
Form No.: LOCAL ALARMS Template No.:
Alarm Checked
DC supply failure [ ]
AC supply failure [ ]
SF6 refill [ ]
Attention interlock [ ]
__________________________________________________ [ ]
__________________________________________________ [ ]
__________________________________________________ [ ]
__________________________________________________ [ ]
__________________________________________________ [ ]
Remarks:
For and behalf of ABB Switzerland Ltd. For and behalf of the Client
Date: Date:
Name: Name:
Signature: Signature:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without
express authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
380 kV GIS-Switchgear
SHOAIBA PHASE 3 EXTENSION ABB
ID Task Name Start Finish Duration Jan 27 '08 Feb 03 '08 Feb 10 '08 Feb 17 '08 Feb 24 '08 Mar 02 '08 Mar 09 '08 Mar 16 '08 Mar 23 '08 Mar 30 '08 Apr 06 '08 Apr 13 '08 Apr 20 '08 Apr 27 '08 May 04
28 31 03 06 09 12 15 18 21 24 27 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24 27 30 03 06
1
2 Stage 1 Only Feeders Tue 08-02-05 Sun 08-03-30 47 days
3
4 PREPARATION Tue 08-02-05 Sat 08-02-09 4 days
5 LCC POWER UP (AC/DC) Sun 08-02-10 Mon 08-02-11 2 days
6 Commissioning Cordination Meeting Sat 08-02-09 Sat 08-02-09 0 days 02-09
7
8 SWITCHGEAR Sat 08-02-16 Wed 08-02-20 5 days
9 Circuit Breaker function test Sat 08-02-16 Sun 08-02-17 2 days
10 Circuit Breaker timing test Mon 08-02-18 Mon 08-02-18 1 day
11 Isolator/Earth Switch function test Tue 08-02-19 Wed 08-02-20 2 days
12
13 Local and Remote Control / Supervision Tue 08-02-12 Tue 08-03-11 25 days
14 Local Contrl REC216 Tue 08-02-12 Thu 08-02-14 3 days
15 Feeder Interlocking Sat 08-03-08 Sat 08-03-08 1 day
16 Local Alarms Sun 08-03-09 Tue 08-03-11 3 days
17 Density Monitors Thu 08-02-21 Sat 08-02-23 2 days
18
19 CURRENT TRANSFORMERS Sun 08-02-24 Sun 08-03-16 19 days
20 CT Secondary Insulation Sun 08-02-24 Sun 08-02-24 4 hrs
21 CT Magnetisation Sun 08-02-24 Sun 08-02-24 4 hrs
22 CT DC Resistance Mon 08-02-25 Mon 08-02-25 4 hrs
23 CT Polarity Mon 08-02-25 Mon 08-02-25 4 hrs
24 CT Primary Injection Thu 08-03-13 Sun 08-03-16 3 days
25
26 VOLTAGE TRANSFORMERS Wed 08-02-27 Thu 08-03-13 14 days
27 VT Secondary Insulation Wed 08-02-27 Wed 08-02-27 4 hrs
28 VT DC Resistance Wed 08-02-27 Wed 08-02-27 4 hrs
29 VT Polarity Thu 08-02-28 Thu 08-02-28 4 hrs
30 VT Transmission Ratio (During HV Test) Sat 08-03-01 Mon 08-03-03 3 days
31 VT Distribution Sat 08-03-08 Sat 08-03-08 1 day
32
33 Feeder Protection Mon 08-03-10 Thu 08-03-13 4 days
34 Transformer protection Backup (REC) Mon 08-03-10 Thu 08-03-13 4 days
35
36 HV Test Feeders only Sat 08-03-01 Sat 08-03-08 7 days
37
38 BUSBAR PROTECTION REB500 Wed 08-03-19 Sun 08-03-30 10 days
39 before BB coupling Wed 08-03-19 Sun 08-03-30 10 days
40
41 SCS100 Sat 08-03-08 Sat 08-03-29 19 days
42 SCS Start Up Sat 08-03-08 Tue 08-03-11 4 days
43 Point To Point SCS Side Wed 08-03-12 Sat 08-03-29 15 days
44 Point to Point GIS Side Wed 08-03-12 Sat 08-03-29 15 days
45
46 Stage 2 Sat 08-03-22 Sat 08-04-12 18 days
47
48 BB Coupling Sat 08-03-29 Tue 08-04-08 10 days
49
50 Work during BB coupling Mon 08-03-31 Tue 08-04-01 2 days
51 Station Interlocking Mon 08-03-31 Mon 08-03-31 1 day
52 Busbar Stability Mon 08-03-31 Tue 08-04-01 2 days
53
54 Sat 08-03-22
Remote (Power Plant Control System ABB D) P214 Sat 08-03-29 7 days
55
56 Transformer Signal/Trip Tests ABB (D) Sat 08-04-12 Sat 08-04-12 0 days 04-12
57
58 Mesuring & Metering ABB (D) Sat 08-04-12 Sat 08-04-12 0 days 04-12
59
60 FINAL WORK (As Built, Testsheets) GIS part Sun 08-04-06 Thu 08-04-10 5 days
Project: MSProj11 Task Split Progress Milestone Summary Project Summary External Tasks External Milestone Deadline
Date: Tue 08-01-22
Page 1
Document No.:
ABB Switzerland Ltd 1HC0048621
Responsible department: Take over department: Revision: Doc.-type: File no.:
Commissioning Manual
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. © Copyright 2007 ABB. All rights reserved.
Document No.:
ABB Switzerland Ltd 1HC0048621
Responsible department: Take over department: Revision: Doc.-type: File no.:
The High Voltage Test on-site will be done in accordance with the IEC 62271-203. The existing
GIS is not contend of this test. This test procedure contains all specific information for this
particular substation all other are written in the following ABB internal norm:
1HC0048490; On-Site High Voltage Test Type ELK (attached)
All Test Sections will be tested with the following
Test voltage:
380 kVrms for 10 minutes (conditioning)
515 kVrms for 1 minute (test voltage)
Test procedure:
600
test voltage 515 kV for 1 minute
applied voltage in kV
500
400
200
100
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13
time in minutes
Voltage application:
The injection of the test voltage will be done via encapsulated reactor connected to the end of
busbar 1. The distance between parts of the test set on high voltage and grounded or
conducting objects (as ground, walls, pieces of installation, crane,…) has to be ≥ 1,5m. Any
conducting object near the test set must be proper earthed.
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. © Copyright 2007 ABB. All rights reserved.
Revision: Language: Page: Document No.:
Test Section 1
Für dieses Dokument und den darin dargestellten Gegenstand behalten wir uns alle Rechte vor. We reserve all rights in this document and in the information contained therein. Reproduction,
Vervielfältigung, Bekanntgabe an Dritte oder Verwendung ausserhalb des vereinbarten Zweckes use or disclosure to third parties without express authority is strictly forbidden.
sind nicht gestattet. © ABB Schweiz AG © ABB Switzerland Ltd
Installation Manual
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. © Copyright 2007 ABB. All rights reserved.
Document No.:
ABB Switzerland Ltd 1HC0056495
Responsible department: Take over department: Revision: Doc.-type: File no.:
METHOD STATEMENT
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. © Copyright 2007 ABB. All rights reserved.
Revision: Language: Page: Document No.:
CONTENT
4. Procedure .................................................................................................... 3
5. Tests............................................................................................................. 5
1. Executive summary
Task
ABB Switzerland Ltd’s (ABB) quality department has prepared this special procedure for the modification
of the existing Gas Insulated Substation (GIS) SHOIBA and coupling of three new feeders AA19, AA20
and AA21.
Actions to be taken
Coupling of the new feeders AA19, AA20 and AA21 to existing GIS followed by leakage test,
commissioning tests and high voltage test.
4. Procedure
All activities are to be understood to be on a three-phase basis. Designation of apparatus and gas
compartments as per Single Line & Gas Schematic Diagrams HASV090237 (existing part of switchgear)
and 1HC0042525 (new part of switchgear).
The relevant part of GIS has to be shut down and earthed according to description underneath and to
attachments 1 and 2.
Regarding pressure reducing and emptying of gas compartments refer to description underneath and to
attachments 3 and 4.
10 AA19, AA20, Isolate bays by opening Q0 followed by opening Q1, Q2 and Customer
AA21 Q9
12 AA08, AA10 Isolate busbar 2 from busbars 1A and 1B by opening of B0, Customer
followed by opening B1 and B2
19 AA01, AA19 Insert compensator ELK VQ3 and couple adjacent ABB
compartments of busbar 2
20 AA01, AA19 Evacuate and fill coupled compartment of busbar 2 with SF6 ABB
gas to 460 kPa
28 AA19, AA20, Isolate bays by opening Q0 followed by opening Q1, Q2 and Customer
AA21 Q9
30 AA08, AA10 Isolate busbars 1A and 1B from busbar 2 by opening of B0, Customer
followed by opening B1 and B2
37 AA01, AA19 Insert compensator ELK VQ3 and couple adjacent ABB
compartments of busbar 1A
38 AA01, AA19 Evacuate and fill coupled compartment of busbar 1A with SF6 ABB
gas to 460 kPa
5. Tests
Beside comissioning tests and HV-test (mentioned above) a leakage test at the connected flanges has to
be carried out.
6. Risk assessment
This procedure involves working on pressure vessels and access to active parts of high voltage
switchgear. All necessary measures have to be taken to avoid ingress of humidity, dust and dirt
into the compartments.
Norbert Zeller
In Service Reliability and Quality Assurance Manager
=AA02
=AA03 =AA01
Revision: Language: Page: Document No.:
=AA02
=AA03 =AA01
Revision: Language: Page: Document No.:
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
503195 SHOAIBA Method Statement (SCS100) Page 1/6
Introduction
The following document describes the required steps for the commissioning of the
SCS100 extension at Shoaiba 380kV S/S.
Reference: new
File name: Method Statement for SCS100.DOC
Document References:
All rights, in particular copyrights and other proprietary rights are reserved.
Copying of the documents and/or distribution to third parties, and/or the use or
disclosure to others of the contents thereof, is not permitted without the previous written
approval by ABB Switzerland Ltd.
Table of contents
1 TEST PROCEDURE 3
1.1 SCOPE 3
1 Test Procedure
1.1 Scope
The existing ABB SCS100 systems (MicroSCADA) for the Shoaiba 380kV S/S will be
extended with 3 feeders. Therefore the following components will be added or
modified.
For point-to-point test personal of switchgear (local control) and protection is on site to
generate all signals which are displayed on the SAS and P14.
The new feeders must be accessible and de-energized for all tests (to SCS and to P14).
The customer (responsible person for the tests) must be on site during the tests for at
least 6 hours per day.
Is there any visible damage at the delivered equipment, cabinet or electronic rack?
Are the different units and cables properly mounted, installed and connected?
Are the fiber optics correctly installed and have they been tested?
Prior to the start of work we will make an actual SCS100 system backup. This allows a
return to the current status if anything unforeseen will happen.
503195 SHOAIBA Method Statement (SCS100) Page 5/6
Before starting the signal tests the existing system has to be updated with the latest
project data:
Note: more or less the same has to be done for the P14 system (not in our scope)
Prior to the point-to-point tests the following communication set-up must be done:
All signals must be simulated at the process (switchgear or relays) with a point-to-point
test. We will verify the signals on the SCS (screen, event- and alarmlist, printer) and in
case of a NCC link on a simulator (e.g. ASE-tool) connected to the SRIO1000.
Sequence of tests:
- ABB internal test to/ from process to SCS100
- ABB internal test to/from process to P14 simulator / Terminal
- Witness test to/from process to SCS100
- Witness test to/from process to P14
The exact commissioning procedure may vary on actual conditions on site and will be
modified accordingly. The procedure shall therefore be seen as guidelines, which are
open for changes.
Remarks:
- some signals can not be tested (e.g. CPU failure of REC216).
- all signals of the new feeders will be tested according to the signal list.
- If changes are to be made, they shall be documented in the commissioning test reports.
- functional tests like control handling, etc. are part of the point-to-point test and
described in the document “SCS/SMS Prüfprotokoll / SCS/SMS Test Record”
Are all tests according to the test sheet (test record) done?
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
37 0MAA19D200 107 XG01 PUMP PH3 T1 Q0 PUMP FAILURE N FAILURE A 1 X X
38
39 0MAA19E200 112 XG19 PUMP PH3 T1 Q0 PUMP VOLT FAILURE N FAILURE A 2 X X
40
41 0MAA19Q200 112 XG04 PUMP PH3 T1 Q0 POLE DAGRMT FAILURE N FAILURE A 1 X X
42
43 0MAA19Q200 108 XG03 PUMP PH3 T1 Q0 BLOCKED BLOCKED N BLOCKED A 1 X X
44 0MAA19E200 107 XG01 PUMP PH3 T1 Q0 INTF RLY FAILURE N FAILURE A 1 X X
45
46 0MAA19Q200 107 XG11 PUMP PH3 T1 Q0 FAILURE FAILURE N FAILURE A 1 X X
47
48
49
50 0MAA19E201 100 XG01 PUMP PH3 T1 Q0 PH R TRPCIRC1 FAILURE N FAILURE A 1 X
51 0MAA19E202 100 XG01 PUMP PH3 T1 Q0 PH Y TRPCIRC1 FAILURE N FAILURE A 1 X
52 0MAA19E203 100 XG01 PUMP PH3 T1 Q0 PH B TRPCIRC1 FAILURE N FAILURE A 1 X
53
54 0MAA19E201 107 XG02 PUMP PH3 T1 Q0 PH R TRPCIRC2 FAILURE N FAILURE A 1 X
55 0MAA19E202 107 XG02 PUMP PH3 T1 Q0 PH Y TRPCIRC2 FAILURE N FAILURE A 1 X
56 0MAA19E203 107 XG02 PUMP PH3 T1 Q0 PH B TRPCIRC2 FAILURE N FAILURE A 1 X
57
58 0MAA19E200 103 XG03 PUMP PH3 T1 Q0 TRPCIRC FAIL FAILURE N FAILURE A 1 X X
59
60
61
62 0MAA19Q210 2 XG01 PUMP PH3 T1 Q1 CLOSED N CLOSED I X
63 0MAA19Q210 1 XG02 PUMP PH3 T1 Q1 OPEN N OPEN I X
64
65 0MAA19Q210 6 XU93 PUMP PH3 T1 Q1 CMD CLOSE C X 1 X
66 0MAA19Q210 5 XU94 PUMP PH3 T1 Q1 CMD OPEN C X 1 X
67 0MAA19Q210 8 XU91 PUMP PH3 T1 Q1 CMD CLOSE C X
68 0MAA19Q210 7 XU92 PUMP PH3 T1 Q1 CMD OPEN C X
69 0MAA19Q210 4 XG21 PUMP PH3 T1 Q1 CMD CLOSE I X
70 0MAA19Q210 3 XG22 PUMP PH3 T1 Q1 CMD OPEN I X
71
72 0MAA19Q210 108 XG03 PUMP PH3 T1 Q1 BLOCKED N BLOCKED A 1 X X
73
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
74 0MAA19E210 100 XG01 PUMP PH3 T1 Q1 INTF RLY FAILURE N FAILURE A 1 X X
75
76 0MAA19E210 107 XG02 PUMP PH3 T1 Q1 CTRL VOLT FAILURE N FAILURE A 2 X X
77
78 0MAA19Q210 109 XG39 PUMP PH3 T1 Q1 CRANK HANDLE INSERTED N INSERTED A 2 X X
79
80
81
82 0MAA19Q220 2 XG01 PUMP PH3 T1 Q2 CLOSED N CLOSED I X
83 0MAA19Q220 1 XG02 PUMP PH3 T1 Q2 OPEN N OPEN I X
84
85 0MAA19Q220 6 XU93 PUMP PH3 T1 Q2 CMD CLOSE C X 1 X
86 0MAA19Q220 5 XU94 PUMP PH3 T1 Q2 CMD OPEN C X 1 X
87 0MAA19Q220 8 XU91 PUMP PH3 T1 Q2 CMD CLOSE C X
88 0MAA19Q220 7 XU92 PUMP PH3 T1 Q2 CMD OPEN C X
89 0MAA19Q220 4 XG21 PUMP PH3 T1 Q2 CMD CLOSE I X
90 0MAA19Q220 3 XG22 PUMP PH3 T1 Q2 CMD OPEN I X
91
92 0MAA19Q220 108 XG03 PUMP PH3 T1 Q2 BLOCKED N BLOCKED A 1 X X
93
94 0MAA19E220 100 XG01 PUMP PH3 T1 Q2 INTF RLY FAILURE N FAILURE A 1 X X
95
96 0MAA19E220 107 XG02 PUMP PH3 T1 Q2 CTRL VOLT FAILURE N FAILURE A 2 X X
97
98 0MAA19Q220 109 XG39 PUMP PH3 T1 Q2 CRANK HANDLE INSERTED N INSERTED A 2 X X
99
100
101
102 0MAA19Q251 2 XG01 PUMP PH3 T1 Q51 CLOSED N CLOSED I X
103 0MAA19Q251 1 XG02 PUMP PH3 T1 Q51 OPEN N OPEN I X
104
105 0MAA19Q251 6 XU93 PUMP PH3 T1 Q51 CMD CLOSE C X 1 X
106 0MAA19Q251 5 XU94 PUMP PH3 T1 Q51 CMD OPEN C X 1 X
107 0MAA19Q251 8 XU91 PUMP PH3 T1 Q51 CMD CLOSE C X
108 0MAA19Q251 7 XU92 PUMP PH3 T1 Q51 CMD OPEN C X
109 0MAA19Q251 4 XG21 PUMP PH3 T1 Q51 CMD CLOSE I X
110 0MAA19Q251 3 XG22 PUMP PH3 T1 Q51 CMD OPEN I X
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
111
112 0MAA19Q251 108 XG03 PUMP PH3 T1 Q51 BLOCKED N BLOCKED A 1 X X
113
114 0MAA19E251 100 XG01 PUMP PH3 T1 Q51 INTF RLY FAILURE N FAILURE A 1 X X
115
116 0MAA19E251 107 XG02 PUMP PH3 T1 Q51 CTRL VOLT FAILURE N FAILURE A 2 X X
117
118 0MAA19Q251 109 XG39 PUMP PH3 T1 Q51 CRANK HANDLE INSERTED N INSERTED A 2 X X
119
120
121
122 0MAA19Q252 2 XG01 PUMP PH3 T1 Q52 CLOSED N CLOSED I X
123 0MAA19Q252 1 XG02 PUMP PH3 T1 Q52 OPEN N OPEN I X
124
125 0MAA19Q252 6 XU93 PUMP PH3 T1 Q52 CMD CLOSE C X 1 X
126 0MAA19Q252 5 XU94 PUMP PH3 T1 Q52 CMD OPEN C X 1 X
127 0MAA19Q252 8 XU91 PUMP PH3 T1 Q52 CMD CLOSE C X
128 0MAA19Q252 7 XU92 PUMP PH3 T1 Q52 CMD OPEN C X
129 0MAA19Q252 4 XG21 PUMP PH3 T1 Q52 CMD CLOSE I X
130 0MAA19Q252 3 XG22 PUMP PH3 T1 Q52 CMD OPEN I X
131
132 0MAA19Q252 108 XG03 PUMP PH3 T1 Q52 BLOCKED N BLOCKED A 1 X X
133
134 0MAA19E252 100 XG01 PUMP PH3 T1 Q52 INTF RLY FAILURE N FAILURE A 1 X X
135
136 0MAA19E252 107 XG02 PUMP PH3 T1 Q52 CTRL VOLT FAILURE N FAILURE A 2 X X
137
138 0MAA19Q252 109 XG39 PUMP PH3 T1 Q52 CRANK HANDLE INSERTED N INSERTED A 2 X X
139
140
141
142 0MAA19Q281 2 XG01 PUMP PH3 T1 Q8 PH R CLOSED N CLOSED I X
143 0MAA19Q281 1 XG02 PUMP PH3 T1 Q8 PH R OPEN N OPEN I X
144 0MAA19Q282 2 XG01 PUMP PH3 T1 Q8 PH Y CLOSED N CLOSED I X
145 0MAA19Q282 1 XG02 PUMP PH3 T1 Q8 PH Y OPEN N OPEN I X
146 0MAA19Q283 2 XG01 PUMP PH3 T1 Q8 PH B CLOSED N CLOSED I X
147 0MAA19Q283 1 XG02 PUMP PH3 T1 Q8 PH B OPEN N OPEN I X
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
148
149 0MAA19Q280 2 XG01 PUMP PH3 T1 Q8 CLOSED N CLOSED I X
150 0MAA19Q280 1 XG02 PUMP PH3 T1 Q8 OPEN N OPEN I X
151
152 0MAA19Q280 6 XU93 PUMP PH3 T1 Q8 CMD CLOSE C X 1 X
153 0MAA19Q280 5 XU94 PUMP PH3 T1 Q8 CMD OPEN C X 1 X
154 0MAA19Q280 8 XU91 PUMP PH3 T1 Q8 CMD CLOSE C X
155 0MAA19Q280 7 XU92 PUMP PH3 T1 Q8 CMD OPEN C X
156 0MAA19Q280 4 XG21 PUMP PH3 T1 Q8 CMD CLOSE I X
157 0MAA19Q280 3 XG22 PUMP PH3 T1 Q8 CMD OPEN I X
158
159 0MAA19E280 100 XG02 PUMP PH3 T1 Q8 CTRL VOLT FAILURE N FAILURE A 2 X X
160
161 0MAA19Q280 108 XG03 PUMP PH3 T1 Q8 BLOCKED N BLOCKED A 1 X X
162
163 0MAA19E281 100 XG01 PUMP PH3 T1 Q8 PH R INTF RLY FAILURE N FAILURE A 1 X X
164 0MAA19E282 100 XG01 PUMP PH3 T1 Q8 PH Y INTF RLY FAILURE N FAILURE A 1 X X
165 0MAA19E283 100 XG01 PUMP PH3 T1 Q8 PH B INTF RLY FAILURE N FAILURE A 1 X X
166
167 0MAA19Q281 109 XG39 PUMP PH3 T1 Q8 PH R CRK HDL INSERTED N INSERTED A 2 X X
168 0MAA19Q282 109 XG39 PUMP PH3 T1 Q8 PH Y CRK HDL INSERTED N INSERTED A 2 X X
169 0MAA19Q283 109 XG39 PUMP PH3 T1 Q8 PH B CRK HDL INSERTED N INSERTED A 2 X X
170
171
172
173 0MAA19Q290 2 XG01 PUMP PH3 T1 Q9 CLOSED N CLOSED I X
174 0MAA19Q290 1 XG02 PUMP PH3 T1 Q9 OPEN N OPEN I X
175
176 0MAA19Q290 6 XU93 PUMP PH3 T1 Q9 CMD CLOSE C X 1 X
177 0MAA19Q290 5 XU94 PUMP PH3 T1 Q9 CMD OPEN C X 1 X
178 0MAA19Q290 8 XU91 PUMP PH3 T1 Q9 CMD CLOSE C X
179 0MAA19Q290 7 XU92 PUMP PH3 T1 Q9 CMD OPEN C X
180 0MAA19Q290 4 XG21 PUMP PH3 T1 Q9 CMD CLOSE I X
181 0MAA19Q290 3 XG22 PUMP PH3 T1 Q9 CMD OPEN I X
182
183 0MAA19Q290 108 XG03 PUMP PH3 T1 Q9 BLOCKED N BLOCKED A 1 X X
184
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
185 0MAA19E290 100 XG01 PUMP PH3 T1 Q9 INTF RLY FAILURE N FAILURE A 1 X X
186
187 0MAA19E290 107 XG02 PUMP PH3 T1 Q9 CTRL VOLT FAILURE N FAILURE A 2 X X
188
189 0MAA19Q290 109 XG39 PUMP PH3 T1 Q9 CRANK HANDLE INSERTED N INSERTED A 2 X X
190
191
192
193 0MAA19P200 114 XG04 PUMP PH3 T1 Q0 P SF6 TRP 1 BLOCKED N BLOCKED A 1 X X
194 0MAA19P200 116 XG05 PUMP PH3 T1 Q0 P SF6 TRP 2 BLOCKED N BLOCKED A 1 X X
195
196 0MAA19P204 101 XG01 PUMP PH3 T1 Q0 PH R P SF6 < MIN 1 > MIN 1 A X 1 1 X X
197 0MAA19P205 101 XG01 PUMP PH3 T1 Q0 PH Y P SF6 < MIN 1 > MIN 1 A X 1 1 X X
198 0MAA19P206 101 XG01 PUMP PH3 T1 Q0 PH B P SF6 < MIN 1 > MIN 1 A X 1 1 X X
199
200 0MAA19P211 101 XG01 PUMP PH3 T1 P SF6 PH R B1 < MIN 1 > MIN 1 A X 1 2 X X
201 0MAA19P212 101 XG01 PUMP PH3 T1 P SF6 PH Y B1 < MIN 1 > MIN 1 A X 1 2 X X
202 0MAA19P213 101 XG01 PUMP PH3 T1 P SF6 PH B B1 < MIN 1 > MIN 1 A X 1 2 X X
203
204 0MAA19P211 111 XG02 PUMP PH3 T1 P SF6 PH R B1 < MIN 2 > MIN 2 A X 1 1 X X
205 0MAA19P212 111 XG02 PUMP PH3 T1 P SF6 PH Y B1 < MIN 2 > MIN 2 A X 1 1 X X
206 0MAA19P213 111 XG02 PUMP PH3 T1 P SF6 PH B B1 < MIN 2 > MIN 2 A X 1 1 X X
207
208 0MAA19P221 101 XG01 PUMP PH3 T1 P SF6 PH R B2 < MIN 1 > MIN 1 A X 1 2 X X
209 0MAA19P222 101 XG01 PUMP PH3 T1 P SF6 PH Y B2 < MIN 1 > MIN 1 A X 1 2 X X
210 0MAA19P223 101 XG01 PUMP PH3 T1 P SF6 PH B B2 < MIN 1 > MIN 1 A X 1 2 X X
211
212 0MAA19P221 111 XG02 PUMP PH3 T1 P SF6 PH R B2 < MIN 2 > MIN 2 A X 1 1 X X
213 0MAA19P222 111 XG02 PUMP PH3 T1 P SF6 PH Y B2 < MIN 2 > MIN 2 A X 1 1 X X
214 0MAA19P223 111 XG02 PUMP PH3 T1 P SF6 PH B B2 < MIN 2 > MIN 2 A X 1 1 X X
215
216 0MAA19P231 101 XG01 PUMP PH3 T1 P SF6 PH R B3 < MIN 1 > MIN 1 A X 1 2 X X
217 0MAA19P232 101 XG01 PUMP PH3 T1 P SF6 PH Y B3 < MIN 1 > MIN 1 A X 1 2 X X
218 0MAA19P233 101 XG01 PUMP PH3 T1 P SF6 PH B B3 < MIN 1 > MIN 1 A X 1 2 X X
219
220 0MAA19P231 111 XG02 PUMP PH3 T1 P SF6 PH R B3 < MIN 2 > MIN 2 A X 1 1 X X
221 0MAA19P232 111 XG02 PUMP PH3 T1 P SF6 PH Y B3 < MIN 2 > MIN 2 A X 1 1 X X
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
222 0MAA19P233 111 XG02 PUMP PH3 T1 P SF6 PH B B3 < MIN 2 > MIN 2 A X 1 1 X X
223
224 0MAA19P241 101 XG01 PUMP PH3 T1 P SF6 PH R B4 < MIN 1 > MIN 1 A X 1 2 X X
225 0MAA19P242 101 XG01 PUMP PH3 T1 P SF6 PH Y B4 < MIN 1 > MIN 1 A X 1 2 X X
226 0MAA19P243 101 XG01 PUMP PH3 T1 P SF6 PH B B4 < MIN 1 > MIN 1 A X 1 2 X X
227
228 0MAA19P241 111 XG02 PUMP PH3 T1 P SF6 PH R B4 < MIN 2 > MIN 2 A X 1 1 X X
229 0MAA19P242 111 XG02 PUMP PH3 T1 P SF6 PH Y B4 < MIN 2 > MIN 2 A X 1 1 X X
230 0MAA19P243 111 XG02 PUMP PH3 T1 P SF6 PH B B4 < MIN 2 > MIN 2 A X 1 1 X X
231
232 0MAA19P251 101 XG01 PUMP PH3 T1 P SF6 PH R B5 < MIN 1 > MIN 1 A X 1 2 X X
233 0MAA19P252 101 XG01 PUMP PH3 T1 P SF6 PH Y B5 < MIN 1 > MIN 1 A X 1 2 X X
234 0MAA19P253 101 XG01 PUMP PH3 T1 P SF6 PH B B5 < MIN 1 > MIN 1 A X 1 2 X X
235
236 0MAA19P251 111 XG02 PUMP PH3 T1 P SF6 PH R B5 < MIN 2 > MIN 2 A X 1 1 X X
237 0MAA19P252 111 XG02 PUMP PH3 T1 P SF6 PH Y B5 < MIN 2 > MIN 2 A X 1 1 X X
238 0MAA19P253 111 XG02 PUMP PH3 T1 P SF6 PH B B5 < MIN 2 > MIN 2 A X 1 1 X X
239
240 0MAA19P261 101 XG01 PUMP PH3 T1 P SF6 PH R B6 < MIN 1 > MIN 1 A X 1 2 X X
241 0MAA19P262 101 XG01 PUMP PH3 T1 P SF6 PH Y B6 < MIN 1 > MIN 1 A X 1 2 X X
242 0MAA19P263 101 XG01 PUMP PH3 T1 P SF6 PH B B6 < MIN 1 > MIN 1 A X 1 2 X X
243
244 0MAA19P261 111 XG02 PUMP PH3 T1 P SF6 PH R B6 < MIN 2 > MIN 2 A X 1 1 X X
245 0MAA19P262 111 XG02 PUMP PH3 T1 P SF6 PH Y B6 < MIN 2 > MIN 2 A X 1 1 X X
246 0MAA19P263 111 XG02 PUMP PH3 T1 P SF6 PH B B6 < MIN 2 > MIN 2 A X 1 1 X X
247
248 0MAA19P271 101 XG01 PUMP PH3 T1 P SF6 PH R B7 < MIN 1 > MIN 1 A X 1 2 X X
249 0MAA19P272 101 XG01 PUMP PH3 T1 P SF6 PH Y B7 < MIN 1 > MIN 1 A X 1 2 X X
250 0MAA19P273 101 XG01 PUMP PH3 T1 P SF6 PH B B7 < MIN 1 > MIN 1 A X 1 2 X X
251
252 0MAA19P271 111 XG02 PUMP PH3 T1 P SF6 PH R B7 < MIN 2 > MIN 2 A X 1 1 X X
253 0MAA19P272 111 XG02 PUMP PH3 T1 P SF6 PH Y B7 < MIN 2 > MIN 2 A X 1 1 X X
254 0MAA19P273 111 XG02 PUMP PH3 T1 P SF6 PH B B7 < MIN 2 > MIN 2 A X 1 1 X X
255
256 0MAA19E350 104 XG01 PUMP PH3 T1 TFMR DIFF TRIP N TRIP A 3 X X
257 0MAA19T321 104 XG02 PUMP PH3 T1 TFMR OVERTEMP TRIP N TRIP A 3 X X
258 0MAA19F301 104 XG02 PUMP PH3 T1 BHZ TFMR TRIP N TRIP A 3 X X
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
259 0MAA19T301 104 XG02 PUMP PH3 T1 T OIL TFMR TRIP N TRIP A 3 X X
260 0MAA19T311 104 XG02 PUMP PH3 T1 T 13.8 WDG TFMR TRIP N TRIP A 3 X X
261 0MAA19F323 104 XG01 PUMP PH3 T1 BHZ CBL BOX TFMR TRIP N TRIP A 3 X X
262 0MAA19P331 104 XG01 PUMP PH3 T1 PRESSURE RELIEF TRIP N TRIP A 3 X X
263 0MAA19P321 104 XG01 PUMP PH3 T1 P TFMR OLTC TRIP N TRIP A 3 X X
264
265
266 0MAA19E301 100 XG01 PUMP PH3 T1 230V AC SPLY FAILURE N FAILURE A 2 X X
267
268 0MAA19E302 100 XG01 PUMP PH3 T1 220V DC SPLY 1 FAILURE N FAILURE A 2 X
269 0MAA19E303 100 XG01 PUMP PH3 T1 220V DC SPLY 2 FAILURE N FAILURE A 2 X
270 0MAA19E304 100 XG01 PUMP PH3 T1 24V DC SPLY 1 FAILURE N FAILURE A 2 X
271 0MAA19E305 100 XG01 PUMP PH3 T1 24V DC SPLY 2 FAILURE N FAILURE A 2 X
272
273 0MAA19E309 107 XG01 PUMP PH3 T1 DC SUPPLY FAILURE N FAILURE A 2 X X
274
275 0MAA19E306 11 XG01 PUMP PH3 T1 CTRL MODE REMOTE LOCAL I X X
276 0MAA19E307 9 XG01 PUMP PH3 T1 CTRL MODE OVRD ON N ON I X X
277
278 0MAA19E308 113 XG01 PUMP PH3 T1 PRIM INTLCK OFF N OFF A 1 X X
279
280 0MAA19E319 104 XG01 PUMP PH3 T1 PT MCB TRIP N TRIP A 1 X X
281
282 0MAA19E310 118 XG01 PUMP PH3 T1 DRIVE INTERLOCKED ON N ON A 2 X X
283
284 0MAA19E311 100 XG01 PUMP PH3 T1 DRIVE OPERATION FAILURE N FAILURE A 2 X X
285 0MAA19E312 100 XG01 PUMP PH3 T1 DRIVE POSITION FAILURE N FAILURE A 1 X X
286 0MAA19E318 100 XG01 PUMP PH3 T1 GENERAL ALARM FAILURE N FAILURE A 1 X X
287 0MAA19E314 118 XG01 PUMP PH3 T1 LOCKOUT RLY 1 ON N ON A 3 X
288 0MAA19E315 118 XG01 PUMP PH3 T1 LOCKOUT RLY 2 ON N ON A 3 X
289 0MAA19E316 118 XG01 PUMP PH3 T1 TRIP RELAY 1 ON N ON A 3 X
290 0MAA19E317 118 XG01 PUMP PH3 T1 TRIP RELAY 2 ON N ON A 3 X
291 0MAA19E326 118 XG01 PUMP PH3 T1 TRIP RELAY ON N ON A 3 X X
292 0MAA19E320 15 XG02 PUMP PH3 T1 TRFM PROT TEST ON N ON I X
293 0MAA19E320 60 XG03 PUMP PH3 T1 B-UP PROT TEST ON N ON I X
294 22BJ02E330 1 XG02 PUMP PH3 T1 13.8KV CB + ES I X X
295 0MAA19E509 1 PUMP PH3 T1 DUMMY 111I26 I X X
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
296 12AT01Q060 2 XG01 PUMP PH3 T1 TFMR NEUT ES I X X
297 12AT01Q060 1 XG02 PUMP PH3 T1 TFMR NEUT ES I X X
298
299 0MAA19E313 119 XG01 PUMP PH3 T1 SYNCHRONIZ N SUCSFUL SUCSFUL A 1 X X
300
301 0MAA19F305 100 XG01 PUMP PH3 T1 BUSBAR PROT FAILURE N FAILURE A 1 X X
302 0MAA19F305 104 XG02 PUMP PH3 T1 CB FAIL PROT TRIP N TRIP A 3 X X
303
304
305 0MAA19E500 1 PUMP PH3 T1 DUMMY 121I1 OPEN N OPEN I X X
306 0MAA19E501 1 PUMP PH3 T1 DUMMY 121I17 OPEN N OPEN I X X
307 0MAA19E502 1 PUMP PH3 T1 DUMMY 122I1 OPEN N OPEN I X X
308 0MAA19E503 1 PUMP PH3 T1 DUMMY 122I17 OPEN N OPEN I X X
309 0MAA19E504 1 PUMP PH3 T1 DUMMY 122I31 OPEN N OPEN I X X
310 0MAA19E505 1 PUMP PH3 T1 DUMMY 122I32 OPEN N OPEN I X X
311 0MAA19E506 1 PUMP PH3 T1 DUMMY 123I1 OPEN N OPEN I X X
312 0MAA19E507 1 PUMP PH3 T1 DUMMY 123I17 OPEN N OPEN I X X
313 0MAA19E508 1 PUMP PH3 T1 DUMMY 124I1 OPEN N OPEN I X X
314 0MAA19E517 1 PUMP PH3 T1 DUMMY 125I9 OPEN N OPEN I X X
315 0MAA19E518 1 PUMP PH3 T1 DUMMY 125I10 OPEN N OPEN I X X
316 0MAA19E519 1 PUMP PH3 T1 DUMMY 125I11 OPEN N OPEN I X X
317 0MAA19E520 1 PUMP PH3 T1 DUMMY 125I12 OPEN N OPEN I X X
318 0MAA19E521 1 PUMP PH3 T1 DUMMY 126I27 OPEN N OPEN I X X
319 0MAA19E522 1 PUMP PH3 T1 DUMMY 107I14 OPEN N OPEN I X
320 0MAA19E523 1 PUMP PH3 T1 DUMMY 107I15 OPEN N OPEN I X
321 0MAA19E524 1 PUMP PH3 T1 DUMMY 107I16 OPEN N OPEN I X
322 0MAA19E525 1 PUMP PH3 T1 DUMMY 107I19 OPEN N OPEN I X
323 0MAA19E526 1 PUMP PH3 T1 DUMMY 107I22 OPEN N OPEN I X
324 0MAA19E527 1 PUMP PH3 T1 DUMMY 107I25 OPEN N OPEN I X
325
326 0MAA19E528 1 PUMP PH3 T1 EV-DATA DUMMY 71I1 OPEN N OPEN M X
327
328
329 0MAA19E342 44 XQ50 PUMP PH3 T1 SY-CHECK U M X
330 0MAA19E343 45 XQ50 PUMP PH3 T1 SY-CHECK PH M X
331 0MAA19E344 46 XQ50 PUMP PH3 T1 SY-CHECK F M X
332
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
333
334 0MAA19E401 34 XQ50 PUMP PH3 T1 CURRENT PH R M X X
335 0MAA19E402 35 XQ50 PUMP PH3 T1 CURRENT PH Y M X X
336 0MAA19E403 36 XQ50 PUMP PH3 T1 CURRENT PH B M X X
337
338 0MAA19E404 31 XQ50 PUMP PH3 T1 VOLTAGE PH RY M X X
339 0MAA19E405 32 XQ50 PUMP PH3 T1 VOLTAGE PH YB M X X
340 0MAA19E406 33 XQ50 PUMP PH3 T1 VOLTAGE PH BR M X X
341
342 0MAA19E407 37 XQ50 PUMP PH3 T1 ACTIVE PWR M X X
343 0MAA19E408 38 XQ50 PUMP PH3 T1 REACTIVE PWR M X X
344
345
346
347
348 0MAA19E320 100 XG10 PUMP PH3 T1 CTRLR REC216 FAILURE N FAILURE A 1 X
349 0MAA19E321 100 XG04 PUMP PH3 T1 CTRLR REC216 COM FAILURE N FAILURE A 1 X
350 0MAA19E322 100 XG25 PUMP PH3 T1 CTRLR REC216 CPU FAILURE N FAILURE A 1 X
351 0MAA19E323 100 XG05 PUMP PH3 T1 CTRLR REC216 FUP FAILURE N FAILURE A 1 X
352 0MAA19E325 100 XG08 PUMP PH3 T1 CTRLR REC216 SYS FAILURE N FAILURE A 1 X
353
354
355
356
357 0MAA19E331 104 XG01 PUMP PH3 T1 TFMR O/C PH R TRIP N TRIP A 3 X
358 0MAA19E332 104 XG01 PUMP PH3 T1 TFMR O/C PH Y TRIP N TRIP A 3 X
359 0MAA19E333 104 XG01 PUMP PH3 T1 TFMR O/C PH B TRIP N TRIP A 3 X
360 0MAA19E330 104 XG01 PUMP PH3 T1 TFMR O/C TRIP N TRIP A 3 X
361 0MAA19E340 104 XG01 PUMP PH3 T1 TFMR MIN REACT TRIP N TRIP A 3 X
362 0MAA19E361 104 XG01 PUMP PH3 T1 TFMR REF TRIP N TRIP A 3 X
363 0MAA19E342 108 XG01 PUMP PH3 T1 SY-CHECK TRIG BLOCKED N BLOCKED A 1 X
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
37 0MAA20D200 107 XG01 PUMP PH3 T2 Q0 PUMP FAILURE N FAILURE A 1 X X
38
39 0MAA20E200 112 XG19 PUMP PH3 T2 Q0 PUMP VOLT FAILURE N FAILURE A 2 X X
40
41 0MAA20Q200 112 XG04 PUMP PH3 T2 Q0 POLE DAGRMT FAILURE N FAILURE A 1 X X
42
43 0MAA20Q200 108 XG03 PUMP PH3 T2 Q0 BLOCKED BLOCKED N BLOCKED A 1 X X
44 0MAA20E200 107 XG01 PUMP PH3 T2 Q0 INTF RLY FAILURE N FAILURE A 1 X X
45
46 0MAA20Q200 107 XG11 PUMP PH3 T2 Q0 FAILURE FAILURE N FAILURE A 1 X X
47
48
49
50 0MAA20E201 100 XG01 PUMP PH3 T2 Q0 PH R TRPCIRC1 FAILURE N FAILURE A 1 X
51 0MAA20E202 100 XG01 PUMP PH3 T2 Q0 PH Y TRPCIRC1 FAILURE N FAILURE A 1 X
52 0MAA20E203 100 XG01 PUMP PH3 T2 Q0 PH B TRPCIRC1 FAILURE N FAILURE A 1 X
53
54 0MAA20E201 107 XG02 PUMP PH3 T2 Q0 PH R TRPCIRC2 FAILURE N FAILURE A 1 X
55 0MAA20E202 107 XG02 PUMP PH3 T2 Q0 PH Y TRPCIRC2 FAILURE N FAILURE A 1 X
56 0MAA20E203 107 XG02 PUMP PH3 T2 Q0 PH B TRPCIRC2 FAILURE N FAILURE A 1 X
57
58 0MAA20E200 103 XG03 PUMP PH3 T2 Q0 TRPCIRC FAIL FAILURE N FAILURE A 1 X X
59
60
61
62 0MAA20Q210 2 XG01 PUMP PH3 T2 Q1 CLOSED N CLOSED I X
63 0MAA20Q210 1 XG02 PUMP PH3 T2 Q1 OPEN N OPEN I X
64
65 0MAA20Q210 6 XU93 PUMP PH3 T2 Q1 CMD CLOSE C X 1 X
66 0MAA20Q210 5 XU94 PUMP PH3 T2 Q1 CMD OPEN C X 1 X
67 0MAA20Q210 8 XU91 PUMP PH3 T2 Q1 CMD CLOSE C X
68 0MAA20Q210 7 XU92 PUMP PH3 T2 Q1 CMD OPEN C X
69 0MAA20Q210 4 XG21 PUMP PH3 T2 Q1 CMD CLOSE I X
70 0MAA20Q210 3 XG22 PUMP PH3 T2 Q1 CMD OPEN I X
71
72 0MAA20Q210 108 XG03 PUMP PH3 T2 Q1 BLOCKED N BLOCKED A 1 X X
73
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
74 0MAA20E210 100 XG01 PUMP PH3 T2 Q1 INTF RLY FAILURE N FAILURE A 1 X X
75
76 0MAA20E210 107 XG02 PUMP PH3 T2 Q1 CTRL VOLT FAILURE N FAILURE A 2 X X
77
78 0MAA20Q210 109 XG39 PUMP PH3 T2 Q1 CRANK HANDLE INSERTED N INSERTED A 2 X X
79
80
81
82 0MAA20Q220 2 XG01 PUMP PH3 T2 Q2 CLOSED N CLOSED I X
83 0MAA20Q220 1 XG02 PUMP PH3 T2 Q2 OPEN N OPEN I X
84
85 0MAA20Q220 6 XU93 PUMP PH3 T2 Q2 CMD CLOSE C X 1 X
86 0MAA20Q220 5 XU94 PUMP PH3 T2 Q2 CMD OPEN C X 1 X
87 0MAA20Q220 8 XU91 PUMP PH3 T2 Q2 CMD CLOSE C X
88 0MAA20Q220 7 XU92 PUMP PH3 T2 Q2 CMD OPEN C X
89 0MAA20Q220 4 XG21 PUMP PH3 T2 Q2 CMD CLOSE I X
90 0MAA20Q220 3 XG22 PUMP PH3 T2 Q2 CMD OPEN I X
91
92 0MAA20Q220 108 XG03 PUMP PH3 T2 Q2 BLOCKED N BLOCKED A 1 X X
93
94 0MAA20E220 100 XG01 PUMP PH3 T2 Q2 INTF RLY FAILURE N FAILURE A 1 X X
95
96 0MAA20E220 107 XG02 PUMP PH3 T2 Q2 CTRL VOLT FAILURE N FAILURE A 2 X X
97
98 0MAA20Q220 109 XG39 PUMP PH3 T2 Q2 CRANK HANDLE INSERTED N INSERTED A 2 X X
99
100
101
102 0MAA20Q251 2 XG01 PUMP PH3 T2 Q51 CLOSED N CLOSED I X
103 0MAA20Q251 1 XG02 PUMP PH3 T2 Q51 OPEN N OPEN I X
104
105 0MAA20Q251 6 XU93 PUMP PH3 T2 Q51 CMD CLOSE C X 1 X
106 0MAA20Q251 5 XU94 PUMP PH3 T2 Q51 CMD OPEN C X 1 X
107 0MAA20Q251 8 XU91 PUMP PH3 T2 Q51 CMD CLOSE C X
108 0MAA20Q251 7 XU92 PUMP PH3 T2 Q51 CMD OPEN C X
109 0MAA20Q251 4 XG21 PUMP PH3 T2 Q51 CMD CLOSE I X
110 0MAA20Q251 3 XG22 PUMP PH3 T2 Q51 CMD OPEN I X
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
111
112 0MAA20Q251 108 XG03 PUMP PH3 T2 Q51 BLOCKED N BLOCKED A 1 X X
113
114 0MAA20E251 100 XG01 PUMP PH3 T2 Q51 INTF RLY FAILURE N FAILURE A 1 X X
115
116 0MAA20E251 107 XG02 PUMP PH3 T2 Q51 CTRL VOLT FAILURE N FAILURE A 2 X X
117
118 0MAA20Q251 109 XG39 PUMP PH3 T2 Q51 CRANK HANDLE INSERTED N INSERTED A 2 X X
119
120
121
122 0MAA20Q252 2 XG01 PUMP PH3 T2 Q52 CLOSED N CLOSED I X
123 0MAA20Q252 1 XG02 PUMP PH3 T2 Q52 OPEN N OPEN I X
124
125 0MAA20Q252 6 XU93 PUMP PH3 T2 Q52 CMD CLOSE C X 1 X
126 0MAA20Q252 5 XU94 PUMP PH3 T2 Q52 CMD OPEN C X 1 X
127 0MAA20Q252 8 XU91 PUMP PH3 T2 Q52 CMD CLOSE C X
128 0MAA20Q252 7 XU92 PUMP PH3 T2 Q52 CMD OPEN C X
129 0MAA20Q252 4 XG21 PUMP PH3 T2 Q52 CMD CLOSE I X
130 0MAA20Q252 3 XG22 PUMP PH3 T2 Q52 CMD OPEN I X
131
132 0MAA20Q252 108 XG03 PUMP PH3 T2 Q52 BLOCKED N BLOCKED A 1 X X
133
134 0MAA20E252 100 XG01 PUMP PH3 T2 Q52 INTF RLY FAILURE N FAILURE A 1 X X
135
136 0MAA20E252 107 XG02 PUMP PH3 T2 Q52 CTRL VOLT FAILURE N FAILURE A 2 X X
137
138 0MAA20Q252 109 XG39 PUMP PH3 T2 Q52 CRANK HANDLE INSERTED N INSERTED A 2 X X
139
140
141
142 0MAA20Q281 2 XG01 PUMP PH3 T2 Q8 PH R CLOSED N CLOSED I X
143 0MAA20Q281 1 XG02 PUMP PH3 T2 Q8 PH R OPEN N OPEN I X
144 0MAA20Q282 2 XG01 PUMP PH3 T2 Q8 PH Y CLOSED N CLOSED I X
145 0MAA20Q282 1 XG02 PUMP PH3 T2 Q8 PH Y OPEN N OPEN I X
146 0MAA20Q283 2 XG01 PUMP PH3 T2 Q8 PH B CLOSED N CLOSED I X
147 0MAA20Q283 1 XG02 PUMP PH3 T2 Q8 PH B OPEN N OPEN I X
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
148
149 0MAA20Q280 2 XG01 PUMP PH3 T2 Q8 CLOSED N CLOSED I X
150 0MAA20Q280 1 XG02 PUMP PH3 T2 Q8 OPEN N OPEN I X
151
152 0MAA20Q280 6 XU93 PUMP PH3 T2 Q8 CMD CLOSE C X 1 X
153 0MAA20Q280 5 XU94 PUMP PH3 T2 Q8 CMD OPEN C X 1 X
154 0MAA20Q280 8 XU91 PUMP PH3 T2 Q8 CMD CLOSE C X
155 0MAA20Q280 7 XU92 PUMP PH3 T2 Q8 CMD OPEN C X
156 0MAA20Q280 4 XG21 PUMP PH3 T2 Q8 CMD CLOSE I X
157 0MAA20Q280 3 XG22 PUMP PH3 T2 Q8 CMD OPEN I X
158
159 0MAA20E280 100 XG02 PUMP PH3 T2 Q8 CTRL VOLT FAILURE N FAILURE A 2 X X
160
161 0MAA20Q280 108 XG03 PUMP PH3 T2 Q8 BLOCKED N BLOCKED A 1 X X
162
163 0MAA20E281 100 XG01 PUMP PH3 T2 Q8 PH R INTF RLY FAILURE N FAILURE A 1 X X
164 0MAA20E282 100 XG01 PUMP PH3 T2 Q8 PH Y INTF RLY FAILURE N FAILURE A 1 X X
165 0MAA20E283 100 XG01 PUMP PH3 T2 Q8 PH B INTF RLY FAILURE N FAILURE A 1 X X
166
167 0MAA20Q281 109 XG39 PUMP PH3 T2 Q8 PH R CRK HDL INSERTED N INSERTED A 2 X X
168 0MAA20Q282 109 XG39 PUMP PH3 T2 Q8 PH Y CRK HDL INSERTED N INSERTED A 2 X X
169 0MAA20Q283 109 XG39 PUMP PH3 T2 Q8 PH B CRK HDL INSERTED N INSERTED A 2 X X
170
171
172
173 0MAA20Q290 2 XG01 PUMP PH3 T2 Q9 CLOSED N CLOSED I X
174 0MAA20Q290 1 XG02 PUMP PH3 T2 Q9 OPEN N OPEN I X
175
176 0MAA20Q290 6 XU93 PUMP PH3 T2 Q9 CMD CLOSE C X 1 X
177 0MAA20Q290 5 XU94 PUMP PH3 T2 Q9 CMD OPEN C X 1 X
178 0MAA20Q290 8 XU91 PUMP PH3 T2 Q9 CMD CLOSE C X
179 0MAA20Q290 7 XU92 PUMP PH3 T2 Q9 CMD OPEN C X
180 0MAA20Q290 4 XG21 PUMP PH3 T2 Q9 CMD CLOSE I X
181 0MAA20Q290 3 XG22 PUMP PH3 T2 Q9 CMD OPEN I X
182
183 0MAA20Q290 108 XG03 PUMP PH3 T2 Q9 BLOCKED N BLOCKED A 1 X X
184
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
185 0MAA20E290 100 XG01 PUMP PH3 T2 Q9 INTF RLY FAILURE N FAILURE A 1 X X
186
187 0MAA20E290 107 XG02 PUMP PH3 T2 Q9 CTRL VOLT FAILURE N FAILURE A 2 X X
188
189 0MAA20Q290 109 XG39 PUMP PH3 T2 Q9 CRANK HANDLE INSERTED N INSERTED A 2 X X
190
191
192
193 0MAA20P200 114 XG04 PUMP PH3 T2 Q0 P SF6 TRP 1 BLOCKED N BLOCKED A 1 X X
194 0MAA20P200 116 XG05 PUMP PH3 T2 Q0 P SF6 TRP 2 BLOCKED N BLOCKED A 1 X X
195
196 0MAA20P204 101 XG01 PUMP PH3 T2 Q0 PH R P SF6 < MIN 1 > MIN 1 A X 1 1 X X
197 0MAA20P205 101 XG01 PUMP PH3 T2 Q0 PH Y P SF6 < MIN 1 > MIN 1 A X 1 1 X X
198 0MAA20P206 101 XG01 PUMP PH3 T2 Q0 PH B P SF6 < MIN 1 > MIN 1 A X 1 1 X X
199
200 0MAA20P211 101 XG01 PUMP PH3 T2 P SF6 PH R B1 < MIN 1 > MIN 1 A X 1 2 X X
201 0MAA20P212 101 XG01 PUMP PH3 T2 P SF6 PH Y B1 < MIN 1 > MIN 1 A X 1 2 X X
202 0MAA20P213 101 XG01 PUMP PH3 T2 P SF6 PH B B1 < MIN 1 > MIN 1 A X 1 2 X X
203
204 0MAA20P211 111 XG02 PUMP PH3 T2 P SF6 PH R B1 < MIN 2 > MIN 2 A X 1 1 X X
205 0MAA20P212 111 XG02 PUMP PH3 T2 P SF6 PH Y B1 < MIN 2 > MIN 2 A X 1 1 X X
206 0MAA20P213 111 XG02 PUMP PH3 T2 P SF6 PH B B1 < MIN 2 > MIN 2 A X 1 1 X X
207
208 0MAA20P221 101 XG01 PUMP PH3 T2 P SF6 PH R B2 < MIN 1 > MIN 1 A X 1 2 X X
209 0MAA20P222 101 XG01 PUMP PH3 T2 P SF6 PH Y B2 < MIN 1 > MIN 1 A X 1 2 X X
210 0MAA20P223 101 XG01 PUMP PH3 T2 P SF6 PH B B2 < MIN 1 > MIN 1 A X 1 2 X X
211
212 0MAA20P221 111 XG02 PUMP PH3 T2 P SF6 PH R B2 < MIN 2 > MIN 2 A X 1 1 X X
213 0MAA20P222 111 XG02 PUMP PH3 T2 P SF6 PH Y B2 < MIN 2 > MIN 2 A X 1 1 X X
214 0MAA20P223 111 XG02 PUMP PH3 T2 P SF6 PH B B2 < MIN 2 > MIN 2 A X 1 1 X X
215
216 0MAA20P231 101 XG01 PUMP PH3 T2 P SF6 PH R B3 < MIN 1 > MIN 1 A X 1 2 X X
217 0MAA20P232 101 XG01 PUMP PH3 T2 P SF6 PH Y B3 < MIN 1 > MIN 1 A X 1 2 X X
218 0MAA20P233 101 XG01 PUMP PH3 T2 P SF6 PH B B3 < MIN 1 > MIN 1 A X 1 2 X X
219
220 0MAA20P231 111 XG02 PUMP PH3 T2 P SF6 PH R B3 < MIN 2 > MIN 2 A X 1 1 X X
221 0MAA20P232 111 XG02 PUMP PH3 T2 P SF6 PH Y B3 < MIN 2 > MIN 2 A X 1 1 X X
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
222 0MAA20P233 111 XG02 PUMP PH3 T2 P SF6 PH B B3 < MIN 2 > MIN 2 A X 1 1 X X
223
224 0MAA20P241 101 XG01 PUMP PH3 T2 P SF6 PH R B4 < MIN 1 > MIN 1 A X 1 2 X X
225 0MAA20P242 101 XG01 PUMP PH3 T2 P SF6 PH Y B4 < MIN 1 > MIN 1 A X 1 2 X X
226 0MAA20P243 101 XG01 PUMP PH3 T2 P SF6 PH B B4 < MIN 1 > MIN 1 A X 1 2 X X
227
228 0MAA20P241 111 XG02 PUMP PH3 T2 P SF6 PH R B4 < MIN 2 > MIN 2 A X 1 1 X X
229 0MAA20P242 111 XG02 PUMP PH3 T2 P SF6 PH Y B4 < MIN 2 > MIN 2 A X 1 1 X X
230 0MAA20P243 111 XG02 PUMP PH3 T2 P SF6 PH B B4 < MIN 2 > MIN 2 A X 1 1 X X
231
232 0MAA20P251 101 XG01 PUMP PH3 T2 P SF6 PH R B5 < MIN 1 > MIN 1 A X 1 2 X X
233 0MAA20P252 101 XG01 PUMP PH3 T2 P SF6 PH Y B5 < MIN 1 > MIN 1 A X 1 2 X X
234 0MAA20P253 101 XG01 PUMP PH3 T2 P SF6 PH B B5 < MIN 1 > MIN 1 A X 1 2 X X
235
236 0MAA20P251 111 XG02 PUMP PH3 T2 P SF6 PH R B5 < MIN 2 > MIN 2 A X 1 1 X X
237 0MAA20P252 111 XG02 PUMP PH3 T2 P SF6 PH Y B5 < MIN 2 > MIN 2 A X 1 1 X X
238 0MAA20P253 111 XG02 PUMP PH3 T2 P SF6 PH B B5 < MIN 2 > MIN 2 A X 1 1 X X
239
240 0MAA20P261 101 XG01 PUMP PH3 T2 P SF6 PH R B6 < MIN 1 > MIN 1 A X 1 2 X X
241 0MAA20P262 101 XG01 PUMP PH3 T2 P SF6 PH Y B6 < MIN 1 > MIN 1 A X 1 2 X X
242 0MAA20P263 101 XG01 PUMP PH3 T2 P SF6 PH B B6 < MIN 1 > MIN 1 A X 1 2 X X
243
244 0MAA20P261 111 XG02 PUMP PH3 T2 P SF6 PH R B6 < MIN 2 > MIN 2 A X 1 1 X X
245 0MAA20P262 111 XG02 PUMP PH3 T2 P SF6 PH Y B6 < MIN 2 > MIN 2 A X 1 1 X X
246 0MAA20P263 111 XG02 PUMP PH3 T2 P SF6 PH B B6 < MIN 2 > MIN 2 A X 1 1 X X
247
248 0MAA20P271 101 XG01 PUMP PH3 T2 P SF6 PH R B7 < MIN 1 > MIN 1 A X 1 2 X X
249 0MAA20P272 101 XG01 PUMP PH3 T2 P SF6 PH Y B7 < MIN 1 > MIN 1 A X 1 2 X X
250 0MAA20P273 101 XG01 PUMP PH3 T2 P SF6 PH B B7 < MIN 1 > MIN 1 A X 1 2 X X
251
252 0MAA20P271 111 XG02 PUMP PH3 T2 P SF6 PH R B7 < MIN 2 > MIN 2 A X 1 1 X X
253 0MAA20P272 111 XG02 PUMP PH3 T2 P SF6 PH Y B7 < MIN 2 > MIN 2 A X 1 1 X X
254 0MAA20P273 111 XG02 PUMP PH3 T2 P SF6 PH B B7 < MIN 2 > MIN 2 A X 1 1 X X
255
256 0MAA20E350 104 XG01 PUMP PH3 T2 TFMR DIFF TRIP N TRIP A 3 X X
257 0MAA20T321 104 XG02 PUMP PH3 T2 TFMR OVERTEMP TRIP N TRIP A 3 X X
258 0MAA20F301 104 XG02 PUMP PH3 T2 BHZ TFMR TRIP N TRIP A 3 X X
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
259 0MAA20T301 104 XG02 PUMP PH3 T2 T OIL TFMR TRIP N TRIP A 3 X X
260 0MAA20T311 104 XG02 PUMP PH3 T2 T 13.8 WDG TFMR TRIP N TRIP A 3 X X
261 0MAA20F323 104 XG01 PUMP PH3 T2 BHZ CBL BOX TFMR TRIP N TRIP A 3 X X
262 0MAA20P331 104 XG01 PUMP PH3 T2 PRESSURE RELIEF TRIP N TRIP A 3 X X
263 0MAA20P321 104 XG01 PUMP PH3 T2 P TFMR OLTC TRIP N TRIP A 3 X X
264
265
266 0MAA20E301 100 XG01 PUMP PH3 T2 230V AC SPLY FAILURE N FAILURE A 2 X X
267
268 0MAA20E302 100 XG01 PUMP PH3 T2 220V DC SPLY 1 FAILURE N FAILURE A 2 X
269 0MAA20E303 100 XG01 PUMP PH3 T2 220V DC SPLY 2 FAILURE N FAILURE A 2 X
270 0MAA20E304 100 XG01 PUMP PH3 T2 24V DC SPLY 1 FAILURE N FAILURE A 2 X
271 0MAA20E305 100 XG01 PUMP PH3 T2 24V DC SPLY 2 FAILURE N FAILURE A 2 X
272
273 0MAA20E309 107 XG01 PUMP PH3 T2 DC SUPPLY FAILURE N FAILURE A 2 X X
274
275 0MAA20E306 11 XG01 PUMP PH3 T2 CTRL MODE REMOTE LOCAL I X X
276 0MAA20E307 9 XG01 PUMP PH3 T2 CTRL MODE OVRD ON N ON I X X
277
278 0MAA20E308 113 XG01 PUMP PH3 T2 PRIM INTLCK OFF N OFF A 1 X X
279
280 0MAA20E319 104 XG01 PUMP PH3 T2 PT MCB TRIP N TRIP A 1 X X
281
282 0MAA20E310 118 XG01 PUMP PH3 T2 DRIVE INTERLOCKED ON N ON A 2 X X
283
284 0MAA20E311 100 XG01 PUMP PH3 T2 DRIVE OPERATION FAILURE N FAILURE A 2 X X
285 0MAA20E312 100 XG01 PUMP PH3 T2 DRIVE POSITION FAILURE N FAILURE A 1 X X
286 0MAA20E318 100 XG01 PUMP PH3 T2 GENERAL ALARM FAILURE N FAILURE A 1 X X
287 0MAA20E314 118 XG01 PUMP PH3 T2 LOCKOUT RLY 1 ON N ON A 3 X
288 0MAA20E315 118 XG01 PUMP PH3 T2 LOCKOUT RLY 2 ON N ON A 3 X
289 0MAA20E316 118 XG01 PUMP PH3 T2 TRIP RELAY 1 ON N ON A 3 X
290 0MAA20E317 118 XG01 PUMP PH3 T2 TRIP RELAY 2 ON N ON A 3 X
291 0MAA20E326 118 XG01 PUMP PH3 T2 TRIP RELAY ON N ON A 3 X X
292 0MAA20E320 15 XG02 PUMP PH3 T2 TRFM PROT TEST ON N ON I X
293 0MAA20E320 60 XG03 PUMP PH3 T2 B-UP PROT TEST ON N ON I X
294 22BJ02E330 1 XG02 PUMP PH3 T2 13.8KV CB + ES I X X
295 0MAA20E509 1 PUMP PH3 T2 DUMMY 111I26 I X X
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
296 12AT01Q060 2 XG01 PUMP PH3 T2 TFMR NEUT ES I X X
297 12AT01Q060 1 XG02 PUMP PH3 T2 TFMR NEUT ES I X X
298
299 0MAA20E313 119 XG01 PUMP PH3 T2 SYNCHRONIZ N SUCSFUL SUCSFUL A 1 X X
300
301 0MAA20F305 100 XG01 PUMP PH3 T2 BUSBAR PROT FAILURE N FAILURE A 1 X X
302 0MAA20F305 104 XG02 PUMP PH3 T2 CB FAIL PROT TRIP N TRIP A 3 X X
303
304
305 0MAA20E500 1 PUMP PH3 T2 DUMMY 121I1 OPEN N OPEN I X X
306 0MAA20E501 1 PUMP PH3 T2 DUMMY 121I17 OPEN N OPEN I X X
307 0MAA20E502 1 PUMP PH3 T2 DUMMY 122I1 OPEN N OPEN I X X
308 0MAA20E503 1 PUMP PH3 T2 DUMMY 122I17 OPEN N OPEN I X X
309 0MAA20E504 1 PUMP PH3 T2 DUMMY 122I31 OPEN N OPEN I X X
310 0MAA20E505 1 PUMP PH3 T2 DUMMY 122I32 OPEN N OPEN I X X
311 0MAA20E506 1 PUMP PH3 T2 DUMMY 123I1 OPEN N OPEN I X X
312 0MAA20E507 1 PUMP PH3 T2 DUMMY 123I17 OPEN N OPEN I X X
313 0MAA20E508 1 PUMP PH3 T2 DUMMY 124I1 OPEN N OPEN I X X
314 0MAA20E517 1 PUMP PH3 T2 DUMMY 125I9 OPEN N OPEN I X X
315 0MAA20E518 1 PUMP PH3 T2 DUMMY 125I10 OPEN N OPEN I X X
316 0MAA20E519 1 PUMP PH3 T2 DUMMY 125I11 OPEN N OPEN I X X
317 0MAA20E520 1 PUMP PH3 T2 DUMMY 125I12 OPEN N OPEN I X X
318 0MAA20E521 1 PUMP PH3 T2 DUMMY 126I27 OPEN N OPEN I X X
319 0MAA20E522 1 PUMP PH3 T2 DUMMY 107I14 OPEN N OPEN I X
320 0MAA20E523 1 PUMP PH3 T2 DUMMY 107I15 OPEN N OPEN I X
324 0MAA20E524 1 PUMP PH3 T2 DUMMY 107I16 OPEN N OPEN I X
325 0MAA20E525 1 PUMP PH3 T2 DUMMY 107I19 OPEN N OPEN I X
326 0MAA20E526 1 PUMP PH3 T2 DUMMY 107I22 OPEN N OPEN I X
327 0MAA20E527 1 PUMP PH3 T2 DUMMY 107I25 OPEN N OPEN I X
328
329 0MAA20E528 1 PUMP PH3 T2 EV-DATA DUMMY 71I1 OPEN N OPEN M X
330
331
332 0MAA20E342 44 XQ50 PUMP PH3 T2 SY-CHECK U M X
333 0MAA20E343 45 XQ50 PUMP PH3 T2 SY-CHECK PH M X
334 0MAA20E344 46 XQ50 PUMP PH3 T2 SY-CHECK F M X
335
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
336
337 0MAA20E401 34 XQ50 PUMP PH3 T2 CURRENT PH R M X X
338 0MAA20E402 35 XQ50 PUMP PH3 T2 CURRENT PH Y M X X
339 0MAA20E403 36 XQ50 PUMP PH3 T2 CURRENT PH B M X X
340
341 0MAA20E404 31 XQ50 PUMP PH3 T2 VOLTAGE PH RY M X X
342 0MAA20E405 32 XQ50 PUMP PH3 T2 VOLTAGE PH YB M X X
343 0MAA20E406 33 XQ50 PUMP PH3 T2 VOLTAGE PH BR M X X
344
345 0MAA20E407 37 XQ50 PUMP PH3 T2 ACTIVE PWR M X X
346 0MAA20E408 38 XQ50 PUMP PH3 T2 REACTIVE PWR M X X
347
348
349
350
351 0MAA20E320 100 XG10 PUMP PH3 T2 CTRLR REC216 FAILURE N FAILURE A 1 X
352 0MAA20E321 100 XG04 PUMP PH3 T2 CTRLR REC216 COM FAILURE N FAILURE A 1 X
353 0MAA20E322 100 XG25 PUMP PH3 T2 CTRLR REC216 CPU FAILURE N FAILURE A 1 X
354 0MAA20E323 100 XG05 PUMP PH3 T2 CTRLR REC216 FUP FAILURE N FAILURE A 1 X
355 0MAA20E325 100 XG08 PUMP PH3 T2 CTRLR REC216 SYS FAILURE N FAILURE A 1 X
356
357
358
359
360 0MAA20E331 104 XG01 PUMP PH3 T2 TFMR O/C PH R TRIP N TRIP A 3 X
361 0MAA20E332 104 XG01 PUMP PH3 T2 TFMR O/C PH Y TRIP N TRIP A 3 X
362 0MAA20E333 104 XG01 PUMP PH3 T2 TFMR O/C PH B TRIP N TRIP A 3 X
363 0MAA20E330 104 XG01 PUMP PH3 T2 TFMR O/C TRIP N TRIP A 3 X
364 0MAA20E340 104 XG01 PUMP PH3 T2 TFMR MIN REACT TRIP N TRIP A 3 X
365 0MAA20E361 104 XG01 PUMP PH3 T2 TFMR REF TRIP N TRIP A 3 X
366 0MAA20E342 108 XG01 PUMP PH3 T2 SY-CHECK TRIG BLOCKED N BLOCKED A 1 X
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
37 0MAA21D200 107 XG01 PUMP PH3 T3 Q0 PUMP FAILURE N FAILURE A 1 X X
38
39 0MAA21E200 112 XG19 PUMP PH3 T3 Q0 PUMP VOLT FAILURE N FAILURE A 2 X X
40
41 0MAA21Q200 112 XG04 PUMP PH3 T3 Q0 POLE DAGRMT FAILURE N FAILURE A 1 X X
42
43 0MAA21Q200 108 XG03 PUMP PH3 T3 Q0 BLOCKED BLOCKED N BLOCKED A 1 X X
44 0MAA21E200 107 XG01 PUMP PH3 T3 Q0 INTF RLY FAILURE N FAILURE A 1 X X
45
46 0MAA21Q200 107 XG11 PUMP PH3 T3 Q0 FAILURE FAILURE N FAILURE A 1 X X
47
48
49
50 0MAA21E201 100 XG01 PUMP PH3 T3 Q0 PH R TRPCIRC1 FAILURE N FAILURE A 1 X
51 0MAA21E202 100 XG01 PUMP PH3 T3 Q0 PH Y TRPCIRC1 FAILURE N FAILURE A 1 X
52 0MAA21E203 100 XG01 PUMP PH3 T3 Q0 PH B TRPCIRC1 FAILURE N FAILURE A 1 X
53
54 0MAA21E201 107 XG02 PUMP PH3 T3 Q0 PH R TRPCIRC2 FAILURE N FAILURE A 1 X
55 0MAA21E202 107 XG02 PUMP PH3 T3 Q0 PH Y TRPCIRC2 FAILURE N FAILURE A 1 X
56 0MAA21E203 107 XG02 PUMP PH3 T3 Q0 PH B TRPCIRC2 FAILURE N FAILURE A 1 X
57
58 0MAA21E200 103 XG03 PUMP PH3 T3 Q0 TRPCIRC FAIL FAILURE N FAILURE A 1 X X
59
60
61
62 0MAA21Q210 2 XG01 PUMP PH3 T3 Q1 CLOSED N CLOSED I X
63 0MAA21Q210 1 XG02 PUMP PH3 T3 Q1 OPEN N OPEN I X
64
65 0MAA21Q210 6 XU93 PUMP PH3 T3 Q1 CMD CLOSE C X 1 X
66 0MAA21Q210 5 XU94 PUMP PH3 T3 Q1 CMD OPEN C X 1 X
67 0MAA21Q210 8 XU91 PUMP PH3 T3 Q1 CMD CLOSE C X
68 0MAA21Q210 7 XU92 PUMP PH3 T3 Q1 CMD OPEN C X
69 0MAA21Q210 4 XG21 PUMP PH3 T3 Q1 CMD CLOSE I X
70 0MAA21Q210 3 XG22 PUMP PH3 T3 Q1 CMD OPEN I X
71
72 0MAA21Q210 108 XG03 PUMP PH3 T3 Q1 BLOCKED N BLOCKED A 1 X X
73
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
74 0MAA21E210 100 XG01 PUMP PH3 T3 Q1 INTF RLY FAILURE N FAILURE A 1 X X
75
76 0MAA21E210 107 XG02 PUMP PH3 T3 Q1 CTRL VOLT FAILURE N FAILURE A 2 X X
77
78 0MAA21Q210 109 XG39 PUMP PH3 T3 Q1 CRANK HANDLE INSERTED N INSERTED A 2 X X
79
80
81
82 0MAA21Q220 2 XG01 PUMP PH3 T3 Q2 CLOSED N CLOSED I X
83 0MAA21Q220 1 XG02 PUMP PH3 T3 Q2 OPEN N OPEN I X
84
85 0MAA21Q220 6 XU93 PUMP PH3 T3 Q2 CMD CLOSE C X 1 X
86 0MAA21Q220 5 XU94 PUMP PH3 T3 Q2 CMD OPEN C X 1 X
87 0MAA21Q220 8 XU91 PUMP PH3 T3 Q2 CMD CLOSE C X
88 0MAA21Q220 7 XU92 PUMP PH3 T3 Q2 CMD OPEN C X
89 0MAA21Q220 4 XG21 PUMP PH3 T3 Q2 CMD CLOSE I X
90 0MAA21Q220 3 XG22 PUMP PH3 T3 Q2 CMD OPEN I X
91
92 0MAA21Q220 108 XG03 PUMP PH3 T3 Q2 BLOCKED N BLOCKED A 1 X X
93
94 0MAA21E220 100 XG01 PUMP PH3 T3 Q2 INTF RLY FAILURE N FAILURE A 1 X X
95
96 0MAA21E220 107 XG02 PUMP PH3 T3 Q2 CTRL VOLT FAILURE N FAILURE A 2 X X
97
98 0MAA21Q220 109 XG39 PUMP PH3 T3 Q2 CRANK HANDLE INSERTED N INSERTED A 2 X X
99
100
101
102 0MAA21Q251 2 XG01 PUMP PH3 T3 Q51 CLOSED N CLOSED I X
103 0MAA21Q251 1 XG02 PUMP PH3 T3 Q51 OPEN N OPEN I X
104
105 0MAA21Q251 6 XU93 PUMP PH3 T3 Q51 CMD CLOSE C X 1 X
106 0MAA21Q251 5 XU94 PUMP PH3 T3 Q51 CMD OPEN C X 1 X
107 0MAA21Q251 8 XU91 PUMP PH3 T3 Q51 CMD CLOSE C X
108 0MAA21Q251 7 XU92 PUMP PH3 T3 Q51 CMD OPEN C X
109 0MAA21Q251 4 XG21 PUMP PH3 T3 Q51 CMD CLOSE I X
110 0MAA21Q251 3 XG22 PUMP PH3 T3 Q51 CMD OPEN I X
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
111
112 0MAA21Q251 108 XG03 PUMP PH3 T3 Q51 BLOCKED N BLOCKED A 1 X X
113
114 0MAA21E251 100 XG01 PUMP PH3 T3 Q51 INTF RLY FAILURE N FAILURE A 1 X X
115
116 0MAA21E251 107 XG02 PUMP PH3 T3 Q51 CTRL VOLT FAILURE N FAILURE A 2 X X
117
118 0MAA21Q251 109 XG39 PUMP PH3 T3 Q51 CRANK HANDLE INSERTED N INSERTED A 2 X X
119
120
121
122 0MAA21Q252 2 XG01 PUMP PH3 T3 Q52 CLOSED N CLOSED I X
123 0MAA21Q252 1 XG02 PUMP PH3 T3 Q52 OPEN N OPEN I X
124
125 0MAA21Q252 6 XU93 PUMP PH3 T3 Q52 CMD CLOSE C X 1 X
126 0MAA21Q252 5 XU94 PUMP PH3 T3 Q52 CMD OPEN C X 1 X
127 0MAA21Q252 8 XU91 PUMP PH3 T3 Q52 CMD CLOSE C X
128 0MAA21Q252 7 XU92 PUMP PH3 T3 Q52 CMD OPEN C X
129 0MAA21Q252 4 XG21 PUMP PH3 T3 Q52 CMD CLOSE I X
130 0MAA21Q252 3 XG22 PUMP PH3 T3 Q52 CMD OPEN I X
131
132 0MAA21Q252 108 XG03 PUMP PH3 T3 Q52 BLOCKED N BLOCKED A 1 X X
133
134 0MAA21E252 100 XG01 PUMP PH3 T3 Q52 INTF RLY FAILURE N FAILURE A 1 X X
135
136 0MAA21E252 107 XG02 PUMP PH3 T3 Q52 CTRL VOLT FAILURE N FAILURE A 2 X X
137
138 0MAA21Q252 109 XG39 PUMP PH3 T3 Q52 CRANK HANDLE INSERTED N INSERTED A 2 X X
139
140
141
142 0MAA21Q281 2 XG01 PUMP PH3 T3 Q8 PH R CLOSED N CLOSED I X
143 0MAA21Q281 1 XG02 PUMP PH3 T3 Q8 PH R OPEN N OPEN I X
144 0MAA21Q282 2 XG01 PUMP PH3 T3 Q8 PH Y CLOSED N CLOSED I X
145 0MAA21Q282 1 XG02 PUMP PH3 T3 Q8 PH Y OPEN N OPEN I X
146 0MAA21Q283 2 XG01 PUMP PH3 T3 Q8 PH B CLOSED N CLOSED I X
147 0MAA21Q283 1 XG02 PUMP PH3 T3 Q8 PH B OPEN N OPEN I X
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
148
149 0MAA21Q280 2 XG01 PUMP PH3 T3 Q8 CLOSED N CLOSED I X
150 0MAA21Q280 1 XG02 PUMP PH3 T3 Q8 OPEN N OPEN I X
151
152 0MAA21Q280 6 XU93 PUMP PH3 T3 Q8 CMD CLOSE C X 1 X
153 0MAA21Q280 5 XU94 PUMP PH3 T3 Q8 CMD OPEN C X 1 X
154 0MAA21Q280 8 XU91 PUMP PH3 T3 Q8 CMD CLOSE C X
155 0MAA21Q280 7 XU92 PUMP PH3 T3 Q8 CMD OPEN C X
156 0MAA21Q280 4 XG21 PUMP PH3 T3 Q8 CMD CLOSE I X
157 0MAA21Q280 3 XG22 PUMP PH3 T3 Q8 CMD OPEN I X
158
159 0MAA21E280 100 XG02 PUMP PH3 T3 Q8 CTRL VOLT FAILURE N FAILURE A 2 X X
160
161 0MAA21Q280 108 XG03 PUMP PH3 T3 Q8 BLOCKED N BLOCKED A 1 X X
162
163 0MAA21E281 100 XG01 PUMP PH3 T3 Q8 PH R INTF RLY FAILURE N FAILURE A 1 X X
164 0MAA21E282 100 XG01 PUMP PH3 T3 Q8 PH Y INTF RLY FAILURE N FAILURE A 1 X X
165 0MAA21E283 100 XG01 PUMP PH3 T3 Q8 PH B INTF RLY FAILURE N FAILURE A 1 X X
166
167 0MAA21Q281 109 XG39 PUMP PH3 T3 Q8 PH R CRK HDL INSERTED N INSERTED A 2 X X
168 0MAA21Q282 109 XG39 PUMP PH3 T3 Q8 PH Y CRK HDL INSERTED N INSERTED A 2 X X
169 0MAA21Q283 109 XG39 PUMP PH3 T3 Q8 PH B CRK HDL INSERTED N INSERTED A 2 X X
170
171
172
173 0MAA21Q290 2 XG01 PUMP PH3 T3 Q9 CLOSED N CLOSED I X
174 0MAA21Q290 1 XG02 PUMP PH3 T3 Q9 OPEN N OPEN I X
175
176 0MAA21Q290 6 XU93 PUMP PH3 T3 Q9 CMD CLOSE C X 1 X
177 0MAA21Q290 5 XU94 PUMP PH3 T3 Q9 CMD OPEN C X 1 X
178 0MAA21Q290 8 XU91 PUMP PH3 T3 Q9 CMD CLOSE C X
179 0MAA21Q290 7 XU92 PUMP PH3 T3 Q9 CMD OPEN C X
180 0MAA21Q290 4 XG21 PUMP PH3 T3 Q9 CMD CLOSE I X
181 0MAA21Q290 3 XG22 PUMP PH3 T3 Q9 CMD OPEN I X
182
183 0MAA21Q290 108 XG03 PUMP PH3 T3 Q9 BLOCKED N BLOCKED A 1 X X
184
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
185 0MAA21E290 100 XG01 PUMP PH3 T3 Q9 INTF RLY FAILURE N FAILURE A 1 X X
186
187 0MAA21E290 107 XG02 PUMP PH3 T3 Q9 CTRL VOLT FAILURE N FAILURE A 2 X X
188
189 0MAA21Q290 109 XG39 PUMP PH3 T3 Q9 CRANK HANDLE INSERTED N INSERTED A 2 X X
190
191
192
193 0MAA21P200 114 XG04 PUMP PH3 T3 Q0 P SF6 TRP 1 BLOCKED N BLOCKED A 1 X X
194 0MAA21P200 116 XG05 PUMP PH3 T3 Q0 P SF6 TRP 2 BLOCKED N BLOCKED A 1 X X
195
196 0MAA21P204 101 XG01 PUMP PH3 T3 Q0 PH R P SF6 < MIN 1 > MIN 1 A X 1 1 X X
197 0MAA21P205 101 XG01 PUMP PH3 T3 Q0 PH Y P SF6 < MIN 1 > MIN 1 A X 1 1 X X
198 0MAA21P206 101 XG01 PUMP PH3 T3 Q0 PH B P SF6 < MIN 1 > MIN 1 A X 1 1 X X
199
200 0MAA21P211 101 XG01 PUMP PH3 T3 P SF6 PH R B1 < MIN 1 > MIN 1 A X 1 2 X X
201 0MAA21P212 101 XG01 PUMP PH3 T3 P SF6 PH Y B1 < MIN 1 > MIN 1 A X 1 2 X X
202 0MAA21P213 101 XG01 PUMP PH3 T3 P SF6 PH B B1 < MIN 1 > MIN 1 A X 1 2 X X
203
204 0MAA21P211 111 XG02 PUMP PH3 T3 P SF6 PH R B1 < MIN 2 > MIN 2 A X 1 1 X X
205 0MAA21P212 111 XG02 PUMP PH3 T3 P SF6 PH Y B1 < MIN 2 > MIN 2 A X 1 1 X X
206 0MAA21P213 111 XG02 PUMP PH3 T3 P SF6 PH B B1 < MIN 2 > MIN 2 A X 1 1 X X
207
208 0MAA21P221 101 XG01 PUMP PH3 T3 P SF6 PH R B2 < MIN 1 > MIN 1 A X 1 2 X X
209 0MAA21P222 101 XG01 PUMP PH3 T3 P SF6 PH Y B2 < MIN 1 > MIN 1 A X 1 2 X X
210 0MAA21P223 101 XG01 PUMP PH3 T3 P SF6 PH B B2 < MIN 1 > MIN 1 A X 1 2 X X
211
212 0MAA21P221 111 XG02 PUMP PH3 T3 P SF6 PH R B2 < MIN 2 > MIN 2 A X 1 1 X X
213 0MAA21P222 111 XG02 PUMP PH3 T3 P SF6 PH Y B2 < MIN 2 > MIN 2 A X 1 1 X X
214 0MAA21P223 111 XG02 PUMP PH3 T3 P SF6 PH B B2 < MIN 2 > MIN 2 A X 1 1 X X
215
216 0MAA21P231 101 XG01 PUMP PH3 T3 P SF6 PH R B3 < MIN 1 > MIN 1 A X 1 2 X X
217 0MAA21P232 101 XG01 PUMP PH3 T3 P SF6 PH Y B3 < MIN 1 > MIN 1 A X 1 2 X X
218 0MAA21P233 101 XG01 PUMP PH3 T3 P SF6 PH B B3 < MIN 1 > MIN 1 A X 1 2 X X
219
220 0MAA21P231 111 XG02 PUMP PH3 T3 P SF6 PH R B3 < MIN 2 > MIN 2 A X 1 1 X X
221 0MAA21P232 111 XG02 PUMP PH3 T3 P SF6 PH Y B3 < MIN 2 > MIN 2 A X 1 1 X X
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
222 0MAA21P233 111 XG02 PUMP PH3 T3 P SF6 PH B B3 < MIN 2 > MIN 2 A X 1 1 X X
223
224 0MAA21P241 101 XG01 PUMP PH3 T3 P SF6 PH R B4 < MIN 1 > MIN 1 A X 1 2 X X
225 0MAA21P242 101 XG01 PUMP PH3 T3 P SF6 PH Y B4 < MIN 1 > MIN 1 A X 1 2 X X
226 0MAA21P243 101 XG01 PUMP PH3 T3 P SF6 PH B B4 < MIN 1 > MIN 1 A X 1 2 X X
227
228 0MAA21P241 111 XG02 PUMP PH3 T3 P SF6 PH R B4 < MIN 2 > MIN 2 A X 1 1 X X
229 0MAA21P242 111 XG02 PUMP PH3 T3 P SF6 PH Y B4 < MIN 2 > MIN 2 A X 1 1 X X
230 0MAA21P243 111 XG02 PUMP PH3 T3 P SF6 PH B B4 < MIN 2 > MIN 2 A X 1 1 X X
231
232 0MAA21P251 101 XG01 PUMP PH3 T3 P SF6 PH R B5 < MIN 1 > MIN 1 A X 1 2 X X
233 0MAA21P252 101 XG01 PUMP PH3 T3 P SF6 PH Y B5 < MIN 1 > MIN 1 A X 1 2 X X
234 0MAA21P253 101 XG01 PUMP PH3 T3 P SF6 PH B B5 < MIN 1 > MIN 1 A X 1 2 X X
235
236 0MAA21P251 111 XG02 PUMP PH3 T3 P SF6 PH R B5 < MIN 2 > MIN 2 A X 1 1 X X
237 0MAA21P252 111 XG02 PUMP PH3 T3 P SF6 PH Y B5 < MIN 2 > MIN 2 A X 1 1 X X
238 0MAA21P253 111 XG02 PUMP PH3 T3 P SF6 PH B B5 < MIN 2 > MIN 2 A X 1 1 X X
239
240 0MAA21P261 101 XG01 PUMP PH3 T3 P SF6 PH R B6 < MIN 1 > MIN 1 A X 1 2 X X
241 0MAA21P262 101 XG01 PUMP PH3 T3 P SF6 PH Y B6 < MIN 1 > MIN 1 A X 1 2 X X
242 0MAA21P263 101 XG01 PUMP PH3 T3 P SF6 PH B B6 < MIN 1 > MIN 1 A X 1 2 X X
243
244 0MAA21P261 111 XG02 PUMP PH3 T3 P SF6 PH R B6 < MIN 2 > MIN 2 A X 1 1 X X
245 0MAA21P262 111 XG02 PUMP PH3 T3 P SF6 PH Y B6 < MIN 2 > MIN 2 A X 1 1 X X
246 0MAA21P263 111 XG02 PUMP PH3 T3 P SF6 PH B B6 < MIN 2 > MIN 2 A X 1 1 X X
247
248 0MAA21P271 101 XG01 PUMP PH3 T3 P SF6 PH R B7 < MIN 1 > MIN 1 A X 1 2 X X
249 0MAA21P272 101 XG01 PUMP PH3 T3 P SF6 PH Y B7 < MIN 1 > MIN 1 A X 1 2 X X
250 0MAA21P273 101 XG01 PUMP PH3 T3 P SF6 PH B B7 < MIN 1 > MIN 1 A X 1 2 X X
251
252 0MAA21P271 111 XG02 PUMP PH3 T3 P SF6 PH R B7 < MIN 2 > MIN 2 A X 1 1 X X
253 0MAA21P272 111 XG02 PUMP PH3 T3 P SF6 PH Y B7 < MIN 2 > MIN 2 A X 1 1 X X
254 0MAA21P273 111 XG02 PUMP PH3 T3 P SF6 PH B B7 < MIN 2 > MIN 2 A X 1 1 X X
255
256 0MAA21P281 101 XG01 PUMP PH3 T3 P SF6 PH R B8 < MIN 1 > MIN 1 A X 1 2 X X
257 0MAA21P282 101 XG01 PUMP PH3 T3 P SF6 PH Y B8 < MIN 1 > MIN 1 A X 1 2 X X
258 0MAA21P283 101 XG01 PUMP PH3 T3 P SF6 PH B B8 < MIN 1 > MIN 1 A X 1 2 X X
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
259
260 0MAA21P281 111 XG02 PUMP PH3 T3 P SF6 PH R B8 < MIN 2 > MIN 2 A X 1 1 X X
261 0MAA21P282 111 XG02 PUMP PH3 T3 P SF6 PH Y B8 < MIN 2 > MIN 2 A X 1 1 X X
262 0MAA21P283 111 XG02 PUMP PH3 T3 P SF6 PH B B8 < MIN 2 > MIN 2 A X 1 1 X X
263
264 0MAA21P291 101 XG01 PUMP PH3 T3 P SF6 PH R B9 < MIN 1 > MIN 1 A X 1 2 X X
265 0MAA21P292 101 XG01 PUMP PH3 T3 P SF6 PH Y B9 < MIN 1 > MIN 1 A X 1 2 X X
266 0MAA21P293 101 XG01 PUMP PH3 T3 P SF6 PH B B9 < MIN 1 > MIN 1 A X 1 2 X X
267
268 0MAA21P291 111 XG02 PUMP PH3 T3 P SF6 PH R B9 < MIN 2 > MIN 2 A X 1 1 X X
269 0MAA21P292 111 XG02 PUMP PH3 T3 P SF6 PH Y B9 < MIN 2 > MIN 2 A X 1 1 X X
270 0MAA21P293 111 XG02 PUMP PH3 T3 P SF6 PH B B9 < MIN 2 > MIN 2 A X 1 1 X X
271
272
273 0MAA21E350 104 XG01 PUMP PH3 T3 TFMR DIFF TRIP N TRIP A 3 X X
274 0MAA21T321 104 XG02 PUMP PH3 T3 TFMR OVERTEMP TRIP N TRIP A 3 X X
275 0MAA21F301 104 XG02 PUMP PH3 T3 BHZ TFMR TRIP N TRIP A 3 X X
276 0MAA21T301 104 XG02 PUMP PH3 T3 T OIL TFMR TRIP N TRIP A 3 X X
277 0MAA21T311 104 XG02 PUMP PH3 T3 T 13.8 WDG TFMR TRIP N TRIP A 3 X X
278 0MAA21F323 104 XG01 PUMP PH3 T3 BHZ CBL BOX TFMR TRIP N TRIP A 3 X X
279 0MAA21P331 104 XG01 PUMP PH3 T3 PRESSURE RELIEF TRIP N TRIP A 3 X X
280 0MAA21P321 104 XG01 PUMP PH3 T3 P TFMR OLTC TRIP N TRIP A 3 X X
281
282
283 0MAA21E301 100 XG01 PUMP PH3 T3 230V AC SPLY FAILURE N FAILURE A 2 X X
284
285 0MAA21E302 100 XG01 PUMP PH3 T3 220V DC SPLY 1 FAILURE N FAILURE A 2 X
286 0MAA21E303 100 XG01 PUMP PH3 T3 220V DC SPLY 2 FAILURE N FAILURE A 2 X
287 0MAA21E304 100 XG01 PUMP PH3 T3 24V DC SPLY 1 FAILURE N FAILURE A 2 X
288 0MAA21E305 100 XG01 PUMP PH3 T3 24V DC SPLY 2 FAILURE N FAILURE A 2 X
289
290 0MAA21E309 107 XG01 PUMP PH3 T3 DC SUPPLY FAILURE N FAILURE A 2 X X
291
292 0MAA21E306 11 XG01 PUMP PH3 T3 CTRL MODE REMOTE LOCAL I X X
293 0MAA21E307 9 XG01 PUMP PH3 T3 CTRL MODE OVRD ON N ON I X X
294
295 0MAA21E308 113 XG01 PUMP PH3 T3 PRIM INTLCK OFF N OFF A 1 X X
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
296
297 0MAA21E319 104 XG01 PUMP PH3 T3 PT MCB TRIP N TRIP A 1 X X
298
299 0MAA21E310 118 XG01 PUMP PH3 T3 DRIVE INTERLOCKED ON N ON A 2 X X
300
301 0MAA21E311 100 XG01 PUMP PH3 T3 DRIVE OPERATION FAILURE N FAILURE A 2 X X
302 0MAA21E312 100 XG01 PUMP PH3 T3 DRIVE POSITION FAILURE N FAILURE A 1 X X
303 0MAA21E318 100 XG01 PUMP PH3 T3 GENERAL ALARM FAILURE N FAILURE A 1 X X
304 0MAA21E314 118 XG01 PUMP PH3 T3 LOCKOUT RLY 1 ON N ON A 3 X
305 0MAA21E315 118 XG01 PUMP PH3 T3 LOCKOUT RLY 2 ON N ON A 3 X
306 0MAA21E316 118 XG01 PUMP PH3 T3 TRIP RELAY 1 ON N ON A 3 X
307 0MAA21E317 118 XG01 PUMP PH3 T3 TRIP RELAY 2 ON N ON A 3 X
308 0MAA21E326 118 XG01 PUMP PH3 T3 TRIP RELAY ON N ON A 3 X X
309 0MAA21E320 15 XG02 PUMP PH3 T3 TRFM PROT TEST ON N ON I X
310 0MAA21E320 60 XG03 PUMP PH3 T3 B-UP PROT TEST ON N ON I X
311 22BJ02E330 1 XG02 PUMP PH3 T3 13.8KV CB + ES I X X
312 0MAA21E509 1 PUMP PH3 T3 DUMMY 111I26 I X X
313 12AT01Q060 2 XG01 PUMP PH3 T3 TFMR NEUT ES I X X
314 12AT01Q060 1 XG02 PUMP PH3 T3 TFMR NEUT ES I X X
315
316 0MAA21E313 119 XG01 PUMP PH3 T3 SYNCHRONIZ N SUCSFUL SUCSFUL A 1 X X
317
318 0MAA21F305 100 XG01 PUMP PH3 T3 BUSBAR PROT FAILURE N FAILURE A 1 X X
319 0MAA21F305 104 XG02 PUMP PH3 T3 CB FAIL PROT TRIP N TRIP A 3 X X
320
321
322 0MAA21E521 1 PUMP PH3 T3 DUMMY 126I27 OPEN N OPEN I X X
323 0MAA21E522 1 PUMP PH3 T3 DUMMY 107I14 OPEN N OPEN I X
324 0MAA21E523 1 PUMP PH3 T3 DUMMY 107I15 OPEN N OPEN I X
325 0MAA21E524 1 PUMP PH3 T3 DUMMY 107I16 OPEN N OPEN I X
326 0MAA21E525 1 PUMP PH3 T3 DUMMY 107I19 OPEN N OPEN I X
327 0MAA21E526 1 PUMP PH3 T3 DUMMY 107I22 OPEN N OPEN I X
328 0MAA21E527 1 PUMP PH3 T3 DUMMY 107I25 OPEN N OPEN I X
329
330 0MAA21E528 1 PUMP PH3 T3 EV-DATA DUMMY 71I1 OPEN N OPEN M X
331
332
No. OBJECT REF. In SIGNAL SOURCE Signal ID SCS- Index Signaltext english Statustext Sign. Event Print. Alarm GTW. GTW. TESTRESULTS SCS100 TESTRESU.
Schematic Logic Index (10 Character) Cat. List Code Class 2 3 SINGLE- ALARM- EVENT- DCS
HAET 321447 HV EQUIPMENT in REC216 (10 Character) (24 Character) On (=1) Off (=0) (SCS) (DCS) LINE LIST LIST
333 0MAA21E342 44 XQ50 PUMP PH3 T3 SY-CHECK U M X
334 0MAA21E343 45 XQ50 PUMP PH3 T3 SY-CHECK PH M X
335 0MAA21E344 46 XQ50 PUMP PH3 T3 SY-CHECK F M X
336
337
338 0MAA21E401 34 XQ50 PUMP PH3 T3 CURRENT PH R M X X
339 0MAA21E402 35 XQ50 PUMP PH3 T3 CURRENT PH Y M X X
340 0MAA21E403 36 XQ50 PUMP PH3 T3 CURRENT PH B M X X
341
342 0MAA21E404 31 XQ50 PUMP PH3 T3 VOLTAGE PH RY M X X
343 0MAA21E405 32 XQ50 PUMP PH3 T3 VOLTAGE PH YB M X X
344 0MAA21E406 33 XQ50 PUMP PH3 T3 VOLTAGE PH BR M X X
345
346 0MAA21E407 37 XQ50 PUMP PH3 T3 ACTIVE PWR M X X
347 0MAA21E408 38 XQ50 PUMP PH3 T3 REACTIVE PWR M X X
348
349
350
351
352 0MAA21E320 100 XG10 PUMP PH3 T3 CTRLR REC216 FAILURE N FAILURE A 1 X
353 0MAA21E321 100 XG04 PUMP PH3 T3 CTRLR REC216 COM FAILURE N FAILURE A 1 X
354 0MAA21E322 100 XG25 PUMP PH3 T3 CTRLR REC216 CPU FAILURE N FAILURE A 1 X
355 0MAA21E323 100 XG05 PUMP PH3 T3 CTRLR REC216 FUP FAILURE N FAILURE A 1 X
356 0MAA21E325 100 XG08 PUMP PH3 T3 CTRLR REC216 SYS FAILURE N FAILURE A 1 X
357
358
359
360
361 0MAA21E331 104 XG01 PUMP PH3 T3 TFMR O/C PH R TRIP N TRIP A 3 X
362 0MAA21E332 104 XG01 PUMP PH3 T3 TFMR O/C PH Y TRIP N TRIP A 3 X
363 0MAA21E333 104 XG01 PUMP PH3 T3 TFMR O/C PH B TRIP N TRIP A 3 X
364 0MAA21E330 104 XG01 PUMP PH3 T3 TFMR O/C TRIP N TRIP A 3 X
365 0MAA21E340 104 XG01 PUMP PH3 T3 TFMR MIN REACT TRIP N TRIP A 3 X
366 0MAA21E361 104 XG01 PUMP PH3 T3 TFMR REF TRIP N TRIP A 3 X
367 0MAA21E342 108 XG01 PUMP PH3 T3 SY-CHECK TRIG BLOCKED N BLOCKED A 1 X
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. © Copyright 2008 ABB. All rights reserved.
COMMISSIONING PROCEDURE FOR NUMERICAL
BUSBAR PROTECTION TYPE REB500
06-05 GR/WK
This procedure is based on the „Operating Instructions“ 1MRB520292-Uen Edition August 2005
(REB500/REB500sys Numerical Station Protection System Busbar Protection with integrated Breaker
Failure, Line and Transformer Protection) respectively chapter 7: Commissioning.
The commissioning shall be done by trained personal only and measures against unwanted operation of
any primary equipment should be taken.
The exact commissioning procedure depends on factors that differ in every power plant. The procedure
shall therefore be seen as a guide and may not be applicable in all circumstances.
All points mentioned in the „Check list“ below have to be checked either by the client, the commissioning
engineer or third parties (e.g. subcontractor). This checklist also gives an idea of the sequence of the
different tests, but it may be necessary to alter this sequence in accordance to the situation on site.
The tests listed in this checklist are our proposal, based on our experience and knowledge as the
manufacturer of the protection equipment. It is however the responsibility of the client to determine what
shall actually be tested on site.
The checklist shall be a part of the documentation and signed by the commissioning engineer and the
client.
General data
Check of transport damage
Visual check of external wiring
Check of cubicle / relay earthing
Check of supply voltage (DC)
Check of settings (calculated by ....)
Check of current transformer circuits
Check of voltage transformer circuits
Check of allocation of bus section and device ID
Secondary injection with test set type ......
Isolator auxiliary contacts (isolator image)
Breaker auxiliary contacts / manual close
Starting of the integrated breaker failure protection
Starting of the external breaker failure protection
Check of input signals
Check of signalling circuits / alarms
Point to point test to the SAS
Check of tripping circuits
Stability check
System time setting
Uploading of traceability datas (version ≥5.0)
Change index of MDB-File
Final check
Description
General data
Are the wires correctly terminated (no insulation between wire and terminal)?
Has the correct wire diameter been used?
Are the shields of the cables correctly terminated?
Are the current input terminals equipped with shorting links?
Are the CT/PT outputs connected to star?
Is the panel/rack grounded according to the operating instructions (braided copper band)?
Check of settings
The calculation of the settings is part of the client’s responsibility. A setting proposal can be made by ABB
Switzerland Ltd. upon request by order.
The commissioning engineer shall check the main points of the setting calculation with respect to:
- the rated values of the generator, block transformer and excitation transformer in line with the
calculation
- the correct CT/PT ratios used
- the implemented functions correctly used
The checking of the CT (current transformer) circuits shall be done by the client or third parties. If
explicitly ordered it can be done by the ABB Switzerland commissioning engineer.
Following shall be checked:
• Polarity. The correct polarity is essential for directional and differential functions.
• Ratio. The ratio influences the behaviour of all functions.
• Magnetising curve. It must be proven, that the protection is connected to a protection core and not to
a measuring core.
• Grounding. Every galvanically separated CT circuit shall be grounded at one point only to avoid
balancing currents.
The checking of the PT (potential/voltage transformer) circuits shall be done by the client or third parties.
If explicitly ordered it can be done by the ABB Switzerland commissioning engineer.
This test is done to verify that the correct bay unit is mounted in the correct feeder. It is possible to print a
report in the REBWIN program to view a list of all node and device ID’s.
Injection of currents and voltages respectively must be done in every analogue input in order to prove the
correctness of the hardware (no defect, correct rating, correct wiring).
Remark: the protection functions are made within the software that is continuously monitored. It is
therefore not necessary to check the functions itself.
Typically the pick-up current of the busbar differential function is measured.
It is extremely important to verify that the position indication of the isolator is coming from the correct
object and fullfills the time / status sequence described in the operating instructions.
Equally important is to verify the correct position indication of the breaker coming from the correct object
and fullfills the time / status sequence. The manual close command has to come well in advance of the
closing position indication of the breaker.
The starting signals from all main protections have to be checked. If single pole auto-reclosure is
provided the starting of the correct phase must be checked. Can be checked at the display and the event
list.
Check of the tripping signals to the breaker failure protection input. This can be done using the internal
test function.
Remark: In some cases instead of a particular contact the trip output itself is used. Simulating this output
will lead to a trip of the breaker.
Activating and de-activating of every used binary input signal. Wherever possible the check shall be done
as a function check. Simulation shall take place only in special condition where a function check is not
feasible.
Check of signalisation/alarms
Checking of all used signals and alarms up to the final destination. This can be done using the internal
test function.
Shall be done in collaboration with the commissioning personal of the SAS and highly depends on the
communication protocols used.
Check of all tripping outputs. All breakers must be tripped. If two tripping coils are connected, the tripping
has to be done separately for each coil. In case a trip circuit supervision is equipped, it should be
checked prior to the tripping circuit.
Stability check
For a busbar differential protection upon energising and sufficient load or beforehand with primary
injection it should be checked if the differential current is significant small and the restraint or holding
current significant high. This should be done for all bay units taking one as reference feeder per
protection zone. This test is also known as balance check.
This time setting can be done either manually or automatically via the SCS.
This saves all relevant tracebility data in the setfile. It can be used for extensions and spare material
ordering.
The MDB-File or setfile is provided with a revision index that is displayed on the LDU, this should be
augmented after changes in the setfile. Typically it is set to V1.0 A after commissioning.
Final check
Is the original setfile loaded in the relay? Some settings may have been changed during the tests.
Are all tripping circuits closed?
Are all CT/PT circuits connected to the protection relay (no shorting links in)?
Are all tests according to the test sheet done?
General data
Point to point test to the SAS refer to the SAS test sheets
Stability check
Final check
If non ABB Switzerland Ltd (Dept. PSAT) test sets were used, note type, number, calibration date:
Client
Date: Signature: Date: Signature:
TEST SHEET Page:
STATION:
REB500 Protocol E.doc / 07-03
Busbar protection type REB500
General datas
Measured voltages:
If end-fault function is used, the location of the CT’s in relation to the circuit breaker has to be compared
with the location shown in the single line diagram of the REBWIN.
“Closed” auxiliary
contact (N/O) Remarks:
“Open” auxiliary
....................................................................................
contact (N/C)
....................................................................................
....................................................................................
Auxiliary contact must be closed
....................................................................................
Auxiliary contact ideally closed ....................................................................................
Auxiliary contact must be open ....................................................................................
Client
Date: Signature: Date: Signature:
TEST SHEET Page:
STATION:
REB500 Protocol E.doc / 07-03
Busbar protection type REB500
Central unit
OC01 ..................................................................................................
1
OC01
2 OC02 ..................................................................................................
OC02
3 OC03 ..................................................................................................
OC03
4
OC04 5 OC04 ..................................................................................................
6
7
OC05 OC05 ..................................................................................................
8
OC06
9 OC06 ..................................................................................................
OC07
10 OC07 ..................................................................................................
OC08 11
12
13 OC08 ..................................................................................................
OC09
14
OC10 OC09 ..................................................................................................
15
OC11
16 OC10 ...................................................................................................
OC12 17
18
OC11 ..................................................................................................
OC12 ..................................................................................................
1 CR01 ..................................................................................................
2
CR01 3 CR02 ..................................................................................................
CR02 4
CR03 5 CR03 ..................................................................................................
6
CR04 7
CR04 ..................................................................................................
8
9
CR05 ..................................................................................................
CR05 10
11
12
CR06 ..................................................................................................
CR06 13
14 CR07 ..................................................................................................
15
CR07 16 CR08 ..................................................................................................
CR08 17
CR09 18 CR09 ..................................................................................................
Client
Date: Signature: Date: Signature:
TEST SHEET Page:
STATION:
REB500 Protocol E.doc / 07-03
Busbar protection type REB500
Bay unit 500BU02
Feeder ..................................
OC01 ..................................................................................................
OC01 1 A
2 OC02 ..................................................................................................
OC02 3
4
OC03 ..................................................................................................
OC03 5
6 OC04 ..................................................................................................
OC04 7
8
OC05 ..................................................................................................
OC05 9
10 OC06 ..................................................................................................
OC06 11
12
OC07 ..................................................................................................
OC07 13
14 OC08 ..................................................................................................
OC08 15
1 B
OC09 ..................................................................................................
OC09
2
OC10 3 OC10 ...................................................................................................
4
5
OC11 ..................................................................................................
OC11
6
OC12 7 OC12 ..................................................................................................
8
9
OC13 ..................................................................................................
OC13
10
OC14 11
OC14 ..................................................................................................
12
OC15 ..................................................................................................
OC15 13
14
OC16 15
OC16 ...................................................................................................
Client
Date: Signature: Date: Signature:
TEST SHEET Page:
STATION:
REB500 Protocol E.doc / 07-03
Busbar protection type REB500
Bay unit 500BU02
Feeder ..................................
1 C CR01 ..................................................................................................
2
CR01 3 CR02 ..................................................................................................
4
5 CR03 ..................................................................................................
CR02 6
7
CR04 ..................................................................................................
CR03 8
CR04 9
10
CR05 ..................................................................................................
CR05 11
CR06 12 CR06 ..................................................................................................
13
CR07 14 CR07 ..................................................................................................
CR08 15
CR08 ..................................................................................................
1 D
CR09 ..................................................................................................
CR9 2
CR10 3 CR10 ..................................................................................................
4
5 CR11 ..................................................................................................
6
CR11 7 CR12 ..................................................................................................
CR12 8
CR13 9 CR13 ..................................................................................................
10
11
CR14 ..................................................................................................
12
CR14 13
CR15 14 CR15 ..................................................................................................
CR16 15
CR16 ..................................................................................................
Client
Date: Signature: Date: Signature:
TEST SHEET Page:
STATION:
REB500 Protocol E.doc / 07-03
Busbar protection type REB500
Secondary injection: Check of the input current transformers
Remarks:
Client
Date: Signature: Date: Signature:
TEST SHEET Page:
STATION:
REB500 Protocol E.doc / 07-03
Busbar protection type REB500
Secondary injection: Check of the input voltage transformers
Remarks:
Client
Date: Signature: Date: Signature:
TEST SHEET Page:
STATION:
REB500 Protocol E.doc / 07-03
Busbar protection type REB500
Stability check with primary injection with load current
Client
Date: Signature: Date: Signature: