Code WBS NAME BOQ Item No.

Activity Name Weightage % REMARKS


Total 100.00%
ASEER SECOND INDUSTRIAL CITY PHASE 1A – ROADS & INFRASTRUCTURE 100.00%
A Mass Earthwork B1.1 100.00%
Construction 100.00%
A.1 Earthwork For Road 100.00%
A.1.1 B1.1.2 Road Cutting , Adjustment of excavated surfaces 100.00%
A.1.2 B1.1.4 Road Backfilling / Embankment Works 100.00%
A.2 Earthwork For Plots 0.00%
A.2.1 B1.1.1 Plots Cutting 100.00%
A.2.2 B1.1.3 Plot Backfilling 100.00%
B Civil/Structural Works (Box Culverts) B6.11 100.00%
Construction 100.00%
B.1 Material Delivery (Steel) 20.00%
B.2 Excavation Works & Compaction 10.00%
B.3 PC Shuttering & Cast 4.00%
B.4 Foundations RC Shuttering, Steel Fixing & Contraction Joint With Water Stop 8.00%
B.5 Concrete Cast, Curing & Waterproofing Membrane with Drain Pipe Installation 6.00%
B.6 Culvert Shear Walls RC Shuttering, Steel Fixing & Contraction Joint With Water Stop8.00%
B.7 Concrete Cast, Curing & Waterproofing Membrane with Drain Pipe Installation 8.00%
B.8 Top Slab RC Shuttering, Steel Fixing & Expansion Joint With Water Stop 6.00%
B.9 Concrete Cast, Curing & Waterproofing Membrane Install 6.00%
B.10 Wing Walls RC Shuttering, Steel Fixing & Cast 6.00%
B.11 Concrete Cast, Curing & Waterproofing Membrane with Drain Pipe Installation 6.00%
B.12 Backfilling Works, Surface Finishing & Internal Cleaning 12.00%
Protection 100.00%
B.13 B6.11.2.4 Bank Protection 100.00%
B.14 B6.11.2.2,3 Scour Protection 100.00%
C Open Drain Channel 100.00%
Construction 100.00%
Temporaray Open Channel B6.7 100.00%
C.1 Land Adjustment By Excavation, Backfilling & Compaction 70.00%
C.2 Geo-Texile & Protection Installation 20.00%
C.3 Stone Pitching - Gabions 10.00%
D Wadi Widening B6.9 100.00%
Construction 100.00%
D.1 B6.9.1 Excavation Woks 100.00%
D.2 B6.9.2 Wall with Polimac coated gabions boxes and Gabion mattress 100.00%
E Storm Water Network 100.00%
Construction 100.00%
E.1 Pipelines B6.1 100.00%
E.1.1 Material Delivery (GRP Pipes) 20.00%
E.1.2 Excavation & Compaction 12.00%
E.1.3 Sand Bedding 8.00%
E.1.4 Pipe Laying 40.00%
E.1.5 Embedment & Testing 8.00%
E.1.6 Layers Backfilling 12.00%
E.2 Manholes B6.2 100.00%
E.2.1 Material Delivery (Manholes) 20.00%
E.2.2 Excavation & Compaction 12.00%
E.2.3 Blinding Conc, & RC Base 8.00%
E.2.4 Manhole Installation & Cover 40.00%
E.2.5 Backfilling 8.00%
E.2.6 Internal Finishing, Benching - Testing 12.00%
E.3 Soakaway Manholes B6.5.2 100.00%
E.3.1 Excavation 15.00%
E.3.2 Bedding, Compaction & Side Riprap 10.00%
E.3.3 Manhole RC Works, Cover Slab/Frame 65.00%
E.3.4 Internal Coating, Stairs Erection & Heavy Duty 10.00%
E.4 Catch Basins B6.5.1 100.00%
E.4.1 Material Delivery (Catch Basins) 20.00%
E.4.2 Excavation & Compaction 12.00%
E.4.3 Blinding Conc 8.00%
E.4.4 Gully Installation & Coating 40.00%
E.4.5 Pipe Connection & Joint Concrete 8.00%
E.4.6 Backfilling & Grate Cover/Frame Inst. 12.00%
E.5 Outfall B6.8 100.00%
E.5.1 Land Adjustment (Excavation & Compaction) 15.00%
E.5.2 Subgrade & Filter Material 10.00%
E.5.3 Concrete Works, Cast & Check Valve Installation 65.00%
E.5.4 Curing & Stone Pitching 10.00%
F Potable Water Network 100.00%
Construction 100.00%
F.1 Pipelines B3.1 100.00%
F.1.1 Material Delivery (HDPE & GRP Pipes) 20.00%
F.1.2 Excavation Works 8.00%
F.1.3 Sand Bedding Works 7.00%
F.1.4 Pipe Laying Works 30.00%
F.1.5 Hydrotest 7.00%
F.1.6 Thrustblock & RC Slab 200mm 13.00%
F.1.7 Backfilling Works 15.00%
F.2 Valves B3.2 100.00%
F.2.1 Material Delivery (Valves) 20.00%
F.2.2 Valves Installation & End Cap 48.00%
F.2.3 Spindle & Surface Box Installation 32.00%
F.3 Valves Chambers B3.3 100.00%
F.3.1 Excavation For Valves Chambers 20.00%
F.3.2 Foundations For Valves Chambers 40.00%
F.3.3 Chambers Walls Conc Cast In Situ 40.00%
F.4 Fire Hydrant B3.2.13 100.00%
F.4.1 Material Delivery (Firehydrant) 20.00%
F.4.2 Firehydrant Installation 60.00%
F.4.3 Fire hydrant Galvanized Barrier Installation 20.00%
G Electrical Works 100.00%
G.1 Street Lighting Works 100.00%
G.1.1 Street Lighting Poles B2.9 100.00%
G.1.1.1 Material Delivery (SL Poles) 20.00%
G.1.1.2 Excavation 12.00%
G.1.1.3 PC & RC Cast 12.00%
G.1.1.4 Lighting Poles Installation 40.00%
G.1.1.5 Backfilling, Grouting & Chamfering 16.00%
G.1.2 Lighting Luminares B2.10 100.00%
G.1.2.1 Material Delivery (Luminares) 40.00%
G.1.2.2 Lighting Luminares Inst 60.00%
G.1.3 Drawpits, Grounding B2.11.1 100.00%
G.1.3.1 Drawpits, Earth Rod Erection 100.00%
G.2 LV Cables - Ducts to Panels 100.00%
G.2.1 Cables B2.8 100.00%
G.2.1.1 Material Delivery (Cables) 20.00%
G.2.1.2 Excavation Works 10.00%
G.2.1.3 Cables Pulling 50.00%
G.2.1.4 Backfilling Works including Warning Tape 20.00%
G.2.2 Ducts B2.12,13 100.00%
G.2.2.1 Underground Duct 100.00%
G.2.3 Panels B2.15 100.00%
G.2.3.1 Material Delivery (Panels) 40.00%
G.2.3.2 Street Lighting Panels Installation 60.00%
G3 Medium Voltage Network 100.00%
Construction 100.00%
G3.0 B2.1.1,2,3,4 Trench Excavation Works 100.00%
G3.1 Cable B2.3.1 100.00%
G3.1.1 Material Delivery (Cables) 20.00%
G3.1.2 Sand Bedding Works & Encasement 15.00%
G3.1.3 Cables Pulling 50.00%
G3.1.4 Backfilling 15.00%
G3.2 Ducts B2.1,2 100.00%
G3.2.1 Ducts Laying Works 100.00%
G3.3 Terminators & Straight Joints B2.4,5 100.00%
G3.3.1 Cable Terminators & Straight Joints 100.00%
G4 Telecommunication Networks 100.00%
Construction 100.00%
G4.1 Ducts B2.16 100.00%
G4.1.1 Trench Excavation Works 15.00%
G4.1.2 Duct Installation Works, End Cap & Concrete Encasement 55.00%
G4.1.3 Backfilling 30.00%
G4.2 Manholes B2.17 100.00%
G4.2.1 Excavation Works 15.00%
G4.2.2 Manholes Installation Works 50.00%
G4.2.3 Backfilling 35.00%
G5 Electrical Cabins 100.00%
Construction 100.00%
G5.1 Units Substation B2.7 100.00%
G5.1.1 Material Delivery (Units Substation) 20.00%
G5.1.2 Excavation For Units Substation 8.00%
G5.1.3 Foundations For Units Substation 12.00%
G5.1.4 Fences Building & Finishing 8.00%
G5.1.5 Install Unit Substation 33/0.4 KV, 300kVA No.01 7.00%
G5.1.6 Install Unit Substation 33/0.4 KV, 300kVA No.02 7.00%
G5.1.7 Install Unit Substation 33/0.4 KV, 300kVA No.03 7.00%
G5.1.8 Install Unit Substation 33/0.4 KV, 300kVA No.04 7.00%
G5.1.9 Install Unit Substation 33/0.4 KV, 300kVA No.05 7.00%
G5.1.10 Install Unit Substation 33/0.4 KV, 300kVA No.06 7.00%
G5.1.11 Install Unit Substation 33/0.4 KV,1000kVA 10.00%
G5.2 RMUs B2.6.1 100.00%
G5.2.1 Material Delivery (RMUs) 20.00%
G5.2.2 Excavation For RMUs 7.00%
G5.2.3 Foundations 7.00%
G5.2.4 Install RMU No. 01 11.00%
G5.2.5 Install RMU No. 02 11.00%
G5.2.6 Install RMU No. 03 11.00%
G5.2.7 Install RMU No. 04 11.00%
G5.2.8 Install RMU No. 05 11.00%
G5.2.9 Install RMU No. 06 11.00%
G5.3 Feeder Pillar B2.15.2 100.00%
G5.3.1 Material Delivery (Feeder) 20.00%
G5.3.2 Excavation For Feeder Pillars 8.00%
G5.3.3 Foundations For Feeder Pillars 12.00%
G5.3.4 Install Feeder Pillars 60.00%
H Road Works 100.00%
Construction 100.00%
H.1 B1.1.5 Subgrade & Selectfill Layer 100.00%
H.2 B1.1.6,7 Aggregate Base Coarse Layer 100.00%
H.3 B1.3.2,3,4,5,6 Curbstone Concrete Base(5cm), Haunching & Installing Works 100.00%
H.4 B1.2.1,23 MC1 Coating Layer & Bituminous Base Coarse Layer 100.00%
H.5 B1.2.4 RC2 Coating Layer & Bituminous Wearing Coarse 100.00%
H.6 B1.4.1,2,3,4 Road Pavement Marking 100.00%
H.7 B1.4.5,6,7,8,9 Retroflective thermoplastic White Arrows 100.00%
H.8 B1.3.1 Interlock Paving 100.00%
H.9 B1.5 Traffic Signs Concrete Base Excavation, Cast & IP and Post Erection 100.00%