WBS NAME Activity Name Weightage % REMARKS

Total 100%
ASEER SECOND INDUSTRIAL CITY PHASE 1A – ROADS & INFRASTRUCTURE 100%
Mass Earthwork 100%
Construction 100%
Earthwork For Road 100%
Road Cutting , Adjustment of excavated surfaces 100%
Road Backfilling / Embankment Works 100%
Earthwork For Plots 0%
Plots Cutting 100%
Plot Backfilling 100%
Civil/Structural Works (Box Culverts) 100%
Construction 100%
Excavation Works & Compaction 15%
P PC Shuttering & Cast 5%
Foundations RC Shuttering, Steel Fixing & Contraction Joint With Water Stop 7%
Concrete Cast, Curing & Waterproofing Membrane with Drain Pipe Installation 7%
Culvert Shear Walls RC Shuttering, Steel Fixing & Contraction Joint With Water Stop 10%
Concrete Cast, Curing & Waterproofing Membrane with Drain Pipe Installation 10%
Top Slab RC Shuttering, Steel Fixing & Expansion Joint With Water Stop 7%
Concrete Cast, Curing & Waterproofing Membrane Install 7%
Wing Walls RC Shuttering, Steel Fixing & Cast 7%
Concrete Cast, Curing & Waterproofing Membrane with Drain Pipe Installation 7%
Backfilling Works, Surface Finishing & Internal Cleaning 15%
Protection 100%
Bank Protection 100%
Scour Protection 100%
Open Drain Channel 100%
Construction 100%
Temporaray Open Channel 100%
Land Adjustment By Excavation, Backfilling & Compaction 70%
Geo-Texile & Protection Installation 20%
Stone Pitching - Gabions 10%
Wadi Widening 100%
Construction 100%
Excavation Woks 100%
Wall with Polimac coated gabions boxes and Gabion mattress 100%
Storm Water Network 100%
Construction 100%
Arterial Road MC-01 100%
Pipelines 100%
Excavation & Compaction 15%
Sand Bedding 10%
Pipe Laying 50%
Embedment & Testing 10%
Layers Backfilling 15%
Manholes 100%
Excavation & Compaction 15%
Blinding Conc, & RC Base 10%
Manhole Installation & Cover 50%
Backfilling 10%
Internal Finishing, Benching - Testing 15%
Soakaway Manholes 100%
Excavation 15%
Bedding, Compaction & Side Riprap 10%
Manhole RC Works, Cover Slab/Frame 65%
Internal Coating, Stairs Erection & Heavy Duty 10%
Catch Basins 100%
Excavation & Compaction 15%
Blinding Conc 10%
Gully Installation & Coating 50%
Pipe Connection & Joint Concrete 10%
Backfilling & Grate Cover/Frame Inst. 15%
Outfall 100%
Land Adjustment (Excavation & Compaction) 15%
Subgrade & Filter Material 10%
Concrete Works, Cast & Check Valve Installation 65%
Curing & Stone Pitching 10%
Potable Water Network 100%
Construction 100%
Pipelines 100%
Excavation Works 8%
Sand Bedding Works 8%
Pipe Laying Works 42%
Hydrotest 8%
Thrustblock & RC Slab 200mm 17%
Backfilling Works 17%
Valves 100%
Burried Gate Valves Installation & End Cap 60%
Spindle & Surface Box Installation 40%
Valves Chambers 100%
Excavation For Valves Chambers 20%
Foundations For Valves Chambers 40%
Chambers Walls Conc Cast In Situ 40%
Fire Hydrant 100%
Firehydrant Installation 75%
Fire hydrant Galvanized Barrier Installation 25%
Electrical Works 100%
Street Lighting Works 100%
Street Lighting Poles 100%
Excavation 15%
PC & RC Cast 15%
Lighting Poles Installation 50%
Backfilling, Grouting & Chamfering 20%
Lighting Luminares 100%
Lighting Luminares Inst 100%
Drawpits, Grounding 100%
Drawpits, Earth Rod Erection 100%
Lighting Cables - Ducts to Panels 100%
Cables 100%
Excavation Works 13%
Cables Pulling 60%
Backfilling Works including Warning Tape 27%
Ducts 100%
Underground Duct 100%
Panels 100%
Street Lighting Panels Installation 100%
Medium Voltage Network 100%
Construction 100%
Trench Excavation Works 100%
Cable 100%
Sand Bedding Works 10%
Encasement 5%
Cables Pulling 70%
Backfilling 15%
Ducts 100%
Ducts Laying Works 100%
Terminators & Straight Joints 100%
Cable Terminators & Straight Joints 100%
Telecommunication Networks 100%
Construction 100%
Ducts 100%
Trench Excavation Works 15%
Duct Installation Works, End Cap & Concrete Encasement 55%
Backfilling 30%
Manholes 100%
Excavation Works 16%
Manholes Installation Works 51%
Backfilling 33%
Electrical Cabins 100%
Construction 100%
Units Substation 100%
Excavation For Units Substation 10%
Foundations For Units Substation 20%
Fences Building & Finishing 10%
Supply & Install Unit Substation 33/0.4 KV, 300kVA No.01 8%
Supply & Install Unit Substation 33/0.4 KV, 300kVA No.02 8%
Supply & Install Unit Substation 33/0.4 KV, 300kVA No.03 8%
Supply & Install Unit Substation 33/0.4 KV, 300kVA No.04 8%
Supply & Install Unit Substation 33/0.4 KV, 300kVA No.05 8%
Supply & Install Unit Substation 33/0.4 KV, 300kVA No.06 8%
Supply & Install Unit Substation 33/0.4 KV,1000kVA 12%
RMUs 100%
Excavation For RMUs 10%
Foundations 20%
Supply & Install RMU No. 01 12%
Supply & Install RMU No. 02 12%
Supply & Install RMU No. 03 12%
Supply & Install RMU No. 04 12%
Supply & Install RMU No. 05 12%
Supply & Install RMU No. 06 12%
Feeder Pillar 100%
Excavation For Feeder Pillars 10%
Foundations For Feeder Pillars 20%
Supply & Install Feeder Pillars 70%
Road Works 100%
Construction 100%
Subgrade & Selectfill Layer 100%
Aggregate Base Coarse Layer 100%
Curbstone Concrete Base(5cm), Haunching & Installing Works 100%
MC1 Coating Layer & Bituminous Base Coarse Layer 100%
RC2 Coating Layer & Bituminous Wearing Coarse 100%
Road Pavement Marking 100%
Retroflective thermoplastic White Arrows 100%
Interlock Paving 100%
Traffic Signs Concrete Base Excavation, Cast & IP and Post Erection 100%
Testing & Commissioning 100%
Storm Water Network System Testing 10% From Stormwater Network
Potable Water Network System Testing 10% From Potable Water Network
Telecommunication Network System Testing 10% From Telecommunication Network
Street Lighting Network System Testing 10% From Street Lighting Network
M.V Network System Testing 10% From M.V Network
Electrical Cabins Testing & Commissioning 10% From Electrical Cabins