Title : Scope of Works

Rev. 0

Scope of Works (General)


Material Supply Work & Service
R : Responsibility S : Support
No. Description LEC Bidder LEC Bidder Remarks
(Contracto (Subcontr (Contracto (Subcontr
r) actor) r) actor)

1.0 Engineering and Design

1.1 Basic & Detail Engineering R

1.2 Detail Design for Fabrication & Construction

1) Equipment Lifting & Rigging Plan & Details R

2) Field Construction Detail as required R

3) Shop Drawings for Fabrication as required R

Marking-upon Construction Drawings for Updating & As-built


4) R
Drawings
Construction Execution Procedures and Method Statements as
5) R
required

2.0 Construction Planning and Control

1) Detail Construction Schedule R

2) Project Organization Plan and Staff & Labor Mobilization Plan R

3) Temporary Facility Plan R

4) Construction Equipment Mobilization Plan R

5) Construction Work Procedures / Method Statements R

6) QA/QC Plan R

7) HSE Plan R

3.0 Construction Manpower

3.1 Direct & Indirect Manpower

1) Salaries, Wages and Bonus R

2) Board (Meals) and Lodging R

3) Safety Gear, Personal Protective Equipment R

4) Recruitment, Dismissal and Retirement R

Taxes and Duties to be Imposed in connection with Personal


5) R
Income

6) Social Insurances and Welfare R

Any & All Costs and Expenses related to the Provision of


7) R
Manpower

3.2 Staffs and Indirect Labors for the Works

1) Construction Management R

2) Construction Supervision R

3) Construction Planning & Cost /Schedule Control R

4) Site Material Handling R

5) Site Administration & Coordination with related Parties R


Title : Scope of Works
Rev. 0

Scope of Works (General)


Material Supply Work & Service
R : Responsibility S : Support
No. Description LEC Bidder LEC Bidder Remarks
(Contracto (Subcontr (Contracto (Subcontr
r) actor) r) actor)

6) Safety & Security Control R

7) Quality Assurance and Control R

8) Others as required for the Works R

4.0 Construction Equipment, Tools & Consumable

1) Mobilization and Demobilization R

2) Fuel, Lubrication, Greasing R R

3) Testing Certification as required R

Any and All Costs and Expenses related to Construction


4) R
Equipment

5.0 Temporary Facilities and Camp Facility for Bidder's Use

Land for Temporary Facilities (Site Office, Fabrication Shop,


1) R
Warehouse, Laydown Area etc.)

2) Land for Camp, Housing & Catering Facilities R

Temporary Facilities (Site Office, Fabrication Shop, Warehouse,


3) R R
Laydown Area etc.)
Camp, Housing & Catering Facilities (Including Electricity, Water
4) R R
etc.)

6.0 Field Expenses for Subcontractor's Staffs and Labors

1) Accommodation and Catering Services R

2) Travel, Mobilization and Demobilization R

3) Communication, Internet and Mail Services R R

Safety Devices, Personal Protective Equipments, Security,


4) R R
Medical Services, etc.

5) Office Consumable, Stationary and Supplies R R

6) Office Furniture and Machinery (Copy / Fax Machines, PCs. ) R R

7) Vehicles R R

8) Others necessary for the Works R R

7.0 Construction Work & Performance

Construction Work as Defined in Scope of Work and Bills of


1) Quantities strictly in accordnace with the Requirements of Project R R
Specifications and Codes/Standards applicable.

Integration of All the Works associated in the nature with the


2) Subcontracted Work to ensure the required performance of the R R
Items.

3) Interface Work in the Existing Plant as Indicated in the BOQ R R

Precommissioning for the Subcontracted Portions of the Project


4) R R
Facilities

8.0 Commissioning Assistance


Title : Scope of Works
Rev. 0

Scope of Works (General)


Material Supply Work & Service
R : Responsibility S : Support
No. Description LEC Bidder LEC Bidder Remarks
(Contracto (Subcontr (Contracto (Subcontr
r) actor) r) actor)

Assistance for Commissioning and Performance Test Including


R R
Labors, Equipment, Tools, Consumables, etc.

9.0 Quality Control

1) Inspection & Test Plan (ITP) for Respective Categories of Works R

2) Inspection Procedures R

3) Coordination for Inspection among Concerned Parties R

4) All Test and Inspection applicable for the Works R

5) Corrective Actions as required R

6) Inspection Record Keeping & Reporting R

10.0 Health, Safety, Environmental Matters

1) Safety Control Plan for Subcontracted Work R

Safety Gear, such as Working Wear, Shoes, Helmets, Gloves,


2) R R
Safety Belts, Goggles, etc.
Safety Indoctrination / Training Supervision for Subcontractor's
3) R
Personnel
Participating in the Owner's and/or CONTRACTOR's Safety
4) R
Orientation Course and Trainings

5) Medical Care (including First Aid Care) R

6) Accident / Incident Report, as required R

Housekeeping, Disposal of Garbage, Trashes and Cleaning-up


7) R
after completion of the Work

8) All Other HSE Activities as per Standard and Regulations R R

11.0 Regulatory Approval Matters and Security for the Works

1) Security Control Plan for Subcontracted Work R

2) Governmental License for the Work in the Subcontractor's Scope R

3) Gate Pass for Subcontractor's Personnel and Equipment R

Government Authorities' Permit to Work in Local Country for


4) R
Laborers
Work Permits in accordance with Owner/Contractor's
5) R
Requirements
Procedures necessary for the Works in accordance with Owner's
6) R
Requirements
All other Security related Activities as per Standard and
7) R
Regulations

Handling of Materials including those Supplied by Contractor at


12.0
Site
Unloading from / Loading to Truck/Lorry at Laydown /Storage
1) R
Area

2) Securing & Preservation of Equipment & Materials R

3) Procedures for handling Materials and Preservation R


Title : Scope of Works
Rev. 0

Scope of Works (General)


Material Supply Work & Service
R : Responsibility S : Support
No. Description LEC Bidder LEC Bidder Remarks
(Contracto (Subcontr (Contracto (Subcontr
r) actor) r) actor)

13.0 Insurances

1) Erection All Risk Insurance R

2) Comprehensive General Third Party Insurance R

Workmen’s Compensation Liability Insurance for Subcontractor’s


3) R
Staff and Labors
Insurance for Vehicle and Construction Equipment Mobilized by
4) R
Subcontractor

5) Other Insurance necessary for Subcontract Works R