BARGE LTS-3000 DPR No: DPR-C8MFP-LTS3000-004 CLIENT / COMPANY OIL & NATURAL GAS CORPORATION LTD. (ONGCL) Progress Date: 07.03.2020 (00:00 to 24:00 Hrs.) CONTRACTOR L&T HYDROCARBON ENGINEERING Reporting Date 08.03.2020 ONGC – CA ABS INDUSTRIAL VERIFICATION ( INDIA ) PVT LTD Vessel Location D30-2 Platform ONGC – TPI VCS QUALITY SERVICES A) Planned Activities for LTS-3000 in Construction Season 2019-2020 Sl. No. Activity Description Start Date Completion Date Remarks 1 D30-2 Jacket Installation 27.02.2020 2 WO 24-3 Jacket Installation 3 WO 24-3 Deck Installation 4 B192-10 Jacket Installation 5 B192-10 Deck Installation 6 D30-2 Deck Installation B) D30-2 Jacket Installation Details Position / Co-ordinates Location Orientation Jacket Level Jacket Elevation Remarks Latitude - N Longitude - E As Per Bid Document / Drg. 0 from True North 0 - (+) 7.6000 M 190 14' 37.7025" 700 53' 02.5596" As Installed Parameters (Initial) As Installed Parameters (Final) Tolerances ± 2.5 Mtrs. ± 2° 1:140 / 25 minutes ± 750 mm C) D30-2 Piles Details Pile Penetration below Mudline (Mtrs) QTY of Piles (Nos.) Remarks QTY of Grouting ( Nos.) Remarks Skirt Pile Dia (Inch) A1 A2 B1 B2 Previous Today Cumulative Previous Today Cumulative Target 116.93 117.23 117.43 117.43 96" 0 0 0 0 0 0 Actual D) D30-2 Conductor Details Conductor Target Penetration (below QTY of Conductors (Nos.) Remarks Jacket Appurtenances Remarks No. of Wells Conductor Dia (Inch) Mudline) Previous Today Cumulative Boat Landing 1 No. 6 30" 70 m 0 0 0 Barge Bumpers 4 Nos. C) Activities of 07.03.2020 1 Awaiting for favourable weather Conditions for lifting D30-2 Jacket.
D) Activities Planned on 08.03.2020
1 Jacket Cargo Barge TRITON 330 to be brought at stern of LTS-3000. 2 Connect lifting slings to LTS-3000 Crane Main block. 3 Cutting Sea fastening on Jacket cargo barge. 4 Lift D30-2 Jacket off the Cargo barge.