Professional Documents
Culture Documents
MTP132-Daily Report 23 July 2023
MTP132-Daily Report 23 July 2023
Day Shift Overtime Night Shift Day Shift Overtime Night Shift Day Shift Overtime Night Shift Start End Total Hours Remarks
Rebarman 25 11 121
Mason 20 10 110
Carpenter 25 13 143
Fitter 12 4 44
Boilermaker 8 1 11
Pipe Fitter 6 1 11
Indirect * 68 28 296
Planner 1
Surveyor 3 1 11
HR Staff/Administration 2 1 11
HR/Administration 1
GA & Supporting 1
Administration 1
Civil Foreman 2 1 11
Civil QC Engineer 2
Operator Trailer 1
PERI UP Supervisor 2
DAILY CUMULATIVE
BALANCE %
ACTIVITY UNIT QTY Variance REMARKS
ACT. COMPLETE
Plan Actual Plan Actual
Construction
Civil Work Percent 100.00% 0.16% 0.10% 24.71% 11.07% 13.65% 88.93% 11.07%
Piping Work Percent 100.00% 0.04% 0.001% 1.36% 0.52% 0.84% 99.48% 0.52%
2. MAJOR HIGHLIGHT
A. Civil A. Civil
Complete fabricate Swith Room pedestal formwork Start install Switch Room anchor
Remove Transformer Bay footing formwork Curing slab rebar Transformer Bay
Precast Fire Water Filtration Water Servie slab rebar Continue Precast Fire Water Filtration Water Servie slab rebar
B. Structure : B. Structure :
Pre-assembly Tailing transfer service & Pipe Rack Continue Pre-assembly Tailing transfer service & Pipe Rack
C. Mechanical : C. Mechanical :
D. Piping : D. Piping :
Joint pipe HDPE Field Pipeng & Fitting Ø OSU 400 PN10 Joint 78 Continue Joint pipe HDPE Field Pipe & Fitting Ø OSU 400 PN10
Joint pipe HDPE Field Pipeng & Fitting Ø PSL 400 PN25 Joint 42 Continue Joint pipe HDPE Field Pipe & Fitting Ø PSL 400 PN25
Joint pipe HDPE Field Piping Ø WPR 160 PN10 Joint 73 Continue Joint pipe HDPE Field Piping Ø WPR 160 PN10
Joint pipe HDPE Field Piping Ø PSL 160 PN10 Joint 4 Continue Joint pipe HDPE Field Piping Ø PSL 160 PN10
Joint pipe HDPE Field Piping Ø WFR 90 PN10 Joint 75 Continue Joint pipe HDPE Field Piping Ø WFR 90 PN10
Joint pipe HDPE Field Piping Ø WPO 63 PN10 Joint 70 Continue Joint pipe HDPE Field Piping Ø WPO 63 PN10
Joint pipe HDPE Field Piping Ø PSL 355 PN10 Joint 31 Continue Joint pipe HDPE Field Piping Ø PSL 355 PN10
E. Logistic : E. Logistic :
Unloading Rebar, tools & equipment to TMF area Continue Unloading Rebar, tools & equipment to TMF area
F. Scaffold : F. Scaffold :
G. Others G. Others
Concern :
DAILY PHOTOGRAPH
PHOTOGRAPH
GENERAL ACTIVITIES
Remove Transfomer Bay formwork support Install & reinforce Switchroom pedestal formwork
DAILY PHOTOGRAPH
PHOTOGRAPH
Install North side EMB horizontal rebar Moving scaffolding from SF02 to SF 01
Lifting material rebar vertikal wall area EMB Lifting rebar wall Emergency bunker
DAILY PHOTOGRAPH
PHOTOGRAPH
Install & reinforce Switchroom pedestal formwork Setting Switch room anchor
DAILY PHOTOGRAPH
PHOTOGRAPH
Memilah rebar colom yg mau di citing Install srtyrofoam on Switch Room anchor
Joint 78 HDPE pipe dia 400 PN10 HDPE pipe welding result
Joint 01 HDPE pipe dia PSL 160 PN10 new line Joint 02 HDPE pipe dia PSL 160 PN10 new line
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
DAILY PHOTOGRAPH
PHOTOGRAPH
Joint 03 HDPE pipe dia PSL 160 PN10 new line Joint 03 HDPE pipe dia PSL 160 PN10 new line
Structure
Continue sort out TFP structure Continue sort out TFP structure
Prepared by : Approved by :
Project Control