TAILING MINE FILTRATION PROJECT

Site Installation Civil, Structural, Mechanical & Piping (CSMP)


PT. Agincourt Resources
Rev. 0
Sunday, 23 July 2023

DAILY PROGRESS REPORT


0. DAILY PROGRESS & MANPOWER Construction Phase

MANPOWER WORK HOURS RAINFALL RECORD

PLAN ACTUAL ACTUAL ACTUAL


DISCIPLINE/ACTIVITY

Day Shift Overtime Night Shift Day Shift Overtime Night Shift Day Shift Overtime Night Shift Start End Total Hours Remarks

Direct Labor * 141 55 742

Skilled Worker (Source : Jakarta) 110 43 617

Rebarman 25 11 121

Mason 20 10 110

Carpenter 25 13 143

Fitter 12 4 44

Boilermaker 8 1 11

Pipe Fitter 6 1 11

HDPE Piping 4 2 30 OTHER CONDITION

Welder Steel (SMAW+GTAW) 8 1 11


Total
Start End Remarks
Hours
Painter 2

Unskilled Worker (Source : Local) : Helper 31 11 125

Unskilled Worker (Source : Local) : Watchmen 3 1 11

Indirect * 68 28 296

Construction Manager 1 Total Hours :

Site Manager 1 Note :

Planner 1

Surveyor 3 1 11

Field Engineer/Project Engineer 1

HR Staff/Administration 2 1 11

HR/Administration 1

GA & Supporting 1

Administration 1

Civil Foreman 2 1 11

Civil Supervisor 1 1 11 EQUIPMENT ON SITE QTY

Civil QC Engineer 2

Civil Superintendent 1 Roughter Crane 50 Ton 1

QC Staff 2 1 11 Roughter Crane 90 Ton 1

Mechanical 6 1 8 Boomtruck 15 Ton 1

SMP Foreman 2 1 15 Concrete Pump 1

SMP Supervisor 1 Mixer Truck 01 1

SMP QC Engineer (WI qualification) 2 1 11 Mixer Truck 02 1

Scaffolding Inspector 1 Mixer Truck 03 1

Scaffolder 7 5 55 Mixer Truck 04 1

HSE Supervisor 1 Telehandler 1

Safety Officer 3 2 26 Tractor Head 6X6 1

Logistic and Warehouse 2 LV 01 (Pajero) 1

Rigger 3 2 22 LV 02 Double Cabin 1

Assisstant Deputy Construction Manager 2 LV 03 Double Cabin 1

Assistant CM 1 1 15 Generator 45 kVA 4

Electrician 2 2 22 Generator 165 kVA 1

Operator Crane 50T 1 Compressor 2

Operator Crane 90T 1 1 11 Stamper 4

Operator Telehandler 1 Light Tower 2

Operator Manlift 1 Total Equipment 26

Operator Boom Truck 1

Operator Trailer 1

Operator Concrete Pump 1 1 8

Driver Concrete Pump 1 1 8


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
Rev. 0
Sunday, 23 July 2023

DAILY PROGRESS REPORT

Assistant Ops Concrete Pump 1 1 8

Operator Mixer Truck 4 4 32

PERI UP Supervisor 2

TOTAL 206 83 913

1. CONSTRUCTION KEY QUANTITIES (*Plan Based on Work Completion Schedule - WCS)

DAILY CUMULATIVE
BALANCE %
ACTIVITY UNIT QTY Variance REMARKS
ACT. COMPLETE
Plan Actual Plan Actual

Overhead (Indirect)* Percent 100% Monthly Update

On Site Management and Control* Percent 100% Monthly Update

Construction

Civil Work Percent 100.00% 0.16% 0.10% 24.71% 11.07% 13.65% 88.93% 11.07%

Mechanical Work Percent 100.00% 1.52% 1.52% 100.00%

Piping Work Percent 100.00% 0.04% 0.001% 1.36% 0.52% 0.84% 99.48% 0.52%

Structural Percent 100.00% 0.10% 3.00% 0.74% 2.26% 99.26% 0.74%

Plate Works Percent 100.00% 0.31% 0.31% 100.00%

Erected Tanks Percent 100.00% 0.02% 0.06% 0.06% 100.00%

Electrical Percent 100.00% 0.94% 0.94% 100.00%

Testing and Punch list Percent 100.00% 100.00%

Pre-commisioning Percent 100.00% 100.00%

Total Percent 0.33% 0.10% 31.91% 12.33% 19.58% 12.33%

2. MAJOR HIGHLIGHT

Sunday, 23 July 2023 Monday, 24 July 2023

ACTIVITY UNIT QTY ACTIVITY UNIT QTY

A. Civil A. Civil

Complete fabricate Swith Room pedestal formwork Start install Switch Room anchor

Complete remove EMB footing formwork Finishing EMB footing concrete

Remove Transformer Bay footing formwork Curing slab rebar Transformer Bay

Dismantle precasted SF column rebar Continue dismantle precasted SF column rebar

Precast Fire Water Filtration Water Servie slab rebar Continue Precast Fire Water Filtration Water Servie slab rebar

B. Structure : B. Structure :

Pre-assembly Tailing transfer service & Pipe Rack Continue Pre-assembly Tailing transfer service & Pipe Rack

C. Mechanical : C. Mechanical :

D. Piping : D. Piping :

Mobilize HDPE piping material Continue Mobilize HDPE piping material

Joint pipe HDPE Field Pipeng & Fitting Ø OSU 400 PN10 Joint 78 Continue Joint pipe HDPE Field Pipe & Fitting Ø OSU 400 PN10

Joint pipe HDPE Field Pipeng & Fitting Ø PSL 400 PN25 Joint 42 Continue Joint pipe HDPE Field Pipe & Fitting Ø PSL 400 PN25

Joint pipe HDPE Field Piping Ø WPR 160 PN10 Joint 73 Continue Joint pipe HDPE Field Piping Ø WPR 160 PN10

Joint pipe HDPE Field Piping Ø PSL 160 PN10 Joint 4 Continue Joint pipe HDPE Field Piping Ø PSL 160 PN10

Joint pipe HDPE Field Piping Ø WFR 90 PN10 Joint 75 Continue Joint pipe HDPE Field Piping Ø WFR 90 PN10

Joint pipe HDPE Field Piping Ø WPO 63 PN10 Joint 70 Continue Joint pipe HDPE Field Piping Ø WPO 63 PN10

Joint pipe HDPE Field Piping Ø PSL 355 PN10 Joint 31 Continue Joint pipe HDPE Field Piping Ø PSL 355 PN10

E. Logistic : E. Logistic :

Unloading Rebar, tools & equipment to TMF area Continue Unloading Rebar, tools & equipment to TMF area

F. Scaffold : F. Scaffold :

Install PERI UP footing GL 1-5 Continue install PERI UP footing GL 1-5

G. Others G. Others

Online & offline Training Online & offline Training

Concern :

Overall progress minus -19.58% Base on updated Schedule R

Need Civil to give way to SMP team

Prepared by : Checked By : Acknowledged By :

Project Control Site Manager


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Sunday, 23 July 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

GENERAL ACTIVITIES

General Pre-start meeting General Pre-start meeting


CIVIL

Remove Transfomer Bay formwork support Install & reinforce Switchroom pedestal formwork

Switch Room anchor installation Cuting EMB wall

Chipping EMB wall Dismantle precasted column


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Sunday, 23 July 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

Install North side EMB horizontal rebar Moving scaffolding from SF02 to SF 01

Cleaning formwork waste Moving scaffolding from SF02 to SF 01

Lifting material rebar vertikal wall area EMB Lifting rebar wall Emergency bunker

Install north EMB wall starter bar Setting Switchroom anchor


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Sunday, 23 July 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

Finishing EMB footing Dispose TMF waste

Install & reinforce Switchroom pedestal formwork Setting Switch room anchor

Perkuatan sapot formwork pedistal switchroom Install Switch Room anchor

Remove used formwork material Fabricate anchor template


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Sunday, 23 July 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

Memilah rebar colom yg mau di citing Install srtyrofoam on Switch Room anchor

Finishing EMB footing Sort out wall cast in plate


Piping

Joint 78 HDPE pipe dia 400 PN10 HDPE pipe welding result

Joint 01 HDPE pipe dia PSL 160 PN10 new line Joint 02 HDPE pipe dia PSL 160 PN10 new line
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Sunday, 23 July 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

Joint 03 HDPE pipe dia PSL 160 PN10 new line Joint 03 HDPE pipe dia PSL 160 PN10 new line
Structure

Continue sort out TFP structure Continue sort out TFP structure
Prepared by : Approved by :

Project Control