TAILING MINE FILTRATION PROJECT

Site Installation Civil, Structural, Mechanical & Piping (CSMP)


PT. Agincourt Resources
Rev. 0
Tuesday, 01 August 2023

DAILY PROGRESS REPORT


0. DAILY PROGRESS & MANPOWER Construction Phase

MANPOWER WORK HOURS RAINFALL RECORD

PLAN ACTUAL ACTUAL ACTUAL


DISCIPLINE/ACTIVITY

Day Shift Overtime Night Shift Day Shift Overtime Night Shift Day Shift Overtime Night Shift Start End Total Hours Remarks

Direct Labor * 141 118 1595

Skilled Worker (Source : Jakarta) 110 88 1298

Rebarman 25 25 275

Mason 20 18 198

Carpenter 25 25 275

Fitter 12 8 88

Boilermaker 8 4 44

Pipe Fitter 6 2 22

HDPE Piping 4 4 44 OTHER CONDITION

Welder Steel (SMAW+GTAW) 8 2 22


Total
Start End Remarks
Hours
Painter 2

Unskilled Worker (Source : Local) : Helper 31 27 297

Unskilled Worker (Source : Local) : Watchmen 3 3 33

Indirect * 68 60 633

Site Manager 1 1 11 Total Hours :

Asst. Construction Manager 1 1 11 Note :

Planner 1 1 11

Surveyor 3 2 22

Field Engineer/Project Engineer 1 1 11

HR Staff/Administration 2 1 11

HR/Administration 1 1 11

GA & Supporting 1 1 11

Administration 1 1 11

Civil Foreman 2 3 33

Civil Supervisor 1 1 11 EQUIPMENT ON SITE QTY

Civil QC Engineer 2 1 11

Civil Superintendent 1 Roughter Crane 50 Ton 1

QC Staff 2 2 22 Roughter Crane 90 Ton 1

Mechanical 6 1 8 Boomtruck 15 Ton 1

SMP Foreman 2 2 22 Concrete Pump 1

SMP Supervisor 1 1 11 Mixer Truck 01 1

SMP QC Engineer (WI qualification) 2 1 11 Mixer Truck 02 1

Scaffolding Inspector 1 1 11 Mixer Truck 03 1

Scaffolder 7 9 99 Mixer Truck 04 1

HSE Supervisor 1 Telehandler 1

Safety Officer 3 4 44 Tractor Head 6X6 1

Logistic and Warehouse 2 3 33 LV 01 (Pajero) 1

Rigger 3 4 44 LV 02 Double Cabin 1

Assisstant Deputy Construction Manager 2 1 11 LV 03 Double Cabin 1

Assistant CM 1 1 11 Generator 45 kVA 4

Electrician 2 2 22 Generator 165 kVA 1

Operator Crane 50T 1 1 11 Compressor 2

Operator Crane 90T 1 1 11 Stamper 4

Operator Telehandler 1 1 11 Light Tower 2

Operator Manlift 1 Total Equipment 26

Operator Boom Truck 1 1 11

Operator Trailer 1 1 11

Operator Concrete Pump 1 1 8

Driver Concrete Pump 1 1 8


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
Rev. 0
Tuesday, 01 August 2023

DAILY PROGRESS REPORT

Assistant Ops Concrete Pump 1 1 8

Operator Mixer Truck 4 4 32

PERI UP Supervisor 2 1 8

TOTAL 206 178 1931

1. CONSTRUCTION KEY QUANTITIES (*Plan Based on Work Completion Schedule - WCS)

DAILY CUMULATIVE
BALANCE %
ACTIVITY UNIT QTY Variance REMARKS
ACT. COMPLETE
Plan Actual Plan Actual

Overhead (Indirect)* Percent 100% Monthly Update

On Site Management and Control* Percent 100% Monthly Update

Construction

Civil Work Percent 100.00% 0.09% 0.03% 26.80% 11.60% 15.20% 88.40% 11.60%

Mechanical Work Percent 100.00% 1.52% 1.52% 100.00%

Piping Work Percent 100.00% 0.05% 0.001% 1.87% 0.56% 1.31% 99.44% 0.56%

Structural Percent 100.00% 0.01% 0.00% 4.79% 0.75% 4.03% 99.25% 0.75%

Plate Works Percent 100.00% 0.31% 0.31% 100.00%

Erected Tanks Percent 100.00% 0.02% 0.26% 0.26% 100.00%

Electrical Percent 100.00% 0.94% 0.94% 100.00%

Testing and Punch list Percent 100.00% 100.00%

Pre-commisioning Percent 100.00% 100.00%

Total Percent 0.17% 0.03% 36.50% 12.91% 23.58% 12.91%

2. MAJOR HIGHLIGHT

Tuesday, 01 August 2023 Wednesday, 02 August 2023

ACTIVITY UNIT QTY ACTIVITY UNIT QTY

A. Civil A. Civil

Complete SwitchRoom Anchor instalation Continue backfill SwitchRoom Area

Ongoing chipping & finishing EMB footing Continue chipping & finishing EMB footing

Ongoing install vertical rebar for wall 5 Continue install vertical rebar for wall 5

Ongoing cutting wall rebar stage 1 Contnue cutting wall rebar stage 1

Prepare area for Water Service Continue Prepare area for Water Service

B. Structure : B. Structure :

Pre-assembly Tailing transfer service & Pipe Rack Continue Pre-assembly Tailing transfer service & Pipe Rack

C. Mechanical : C. Mechanical :

D. Piping : D. Piping :

Mobilize HDPE piping material Continue Mobilize HDPE piping material

Joint pipe HDPE Field Pipeng & Fitting Ø OSU 400 PN10 Joint 89 Continue Joint pipe HDPE Field Pipe & Fitting Ø OSU 400 PN10

Joint pipe HDPE Field Pipeng & Fitting Ø PSL 400 PN25 Joint 42 Continue Joint pipe HDPE Field Pipe & Fitting Ø PSL 400 PN25

Joint pipe HDPE Field Piping Ø WPR 160 PN10 Joint 73 Continue Joint pipe HDPE Field Piping Ø WPR 160 PN10

Joint pipe HDPE Field Piping Ø PSL 160 PN10 Joint 20 Continue Joint pipe HDPE Field Piping Ø PSL 160 PN10

Joint pipe HDPE Field Piping Ø WFR 90 PN10 Joint 75 Continue Joint pipe HDPE Field Piping Ø WFR 90 PN10

Joint pipe HDPE Field Piping Ø WPO 63 PN10 Joint 70 Continue Joint pipe HDPE Field Piping Ø WPO 63 PN10

Joint pipe HDPE Field Piping Ø PSL 355 PN10 Joint 32 Continue Joint pipe HDPE Field Piping Ø PSL 355 PN10

Joint pipe HDPE Field Piping Ø WFI 225 PN16 Joint 10 Continue Joint pipe HDPE Field Piping Ø WFI 225 PN16

E. Logistic : E. Logistic :

Unloading Rebar, tools & equipment to TMF area Continue Unloading Rebar, tools & equipment to TMF area

F. Scaffold : F. Scaffold :

Install PERI UP footing GL 1-5 Continue install PERI UP footing GL 1-5

G. Others G. Others

Online & offline Training Online & offline Training

Concern :

Overall progress minus -23.58% Base on updated Schedule R

Need Civil to give way to SMP team

Prepared by : Checked By : Acknowledged By :

Project Control Site Manager


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Tuesday, 01 August 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

GENERAL ACTIVITIES

General Pre-start meeting General Pre-start meeting


CIVIL

Remove Switch Room pedestal support Mobilize rebar to process plant

Ciping wall emg Lifting rebar wall 4 D32 , 2 ton

Waste material wall/FCP/FPR dan FWS transfer to TMF Unloading rebar


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Tuesday, 01 August 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

Unloading rebar on Pad C Install rebar wall 5

Install ties wall 1 Check material

LC for Widening EMB side area Cutting rebar D 25 wall1

Prepare lc area for water service


Piping
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Tuesday, 01 August 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

Joint 20 HDPE pipe dia OSU 400 Joint 89 HDPE pipe dia PSL 160

Joint 85 HDPE pipe dia PSL 160 Continue fit up HDPE pipe
Structure

Continie pre assembly TFP Continie pre assembly TFP


Prepared by : Approved by :

Project Control