Professional Documents
Culture Documents
MTP132-Daily Report 02 August
MTP132-Daily Report 02 August
Day Shift Overtime Night Shift Day Shift Overtime Night Shift Day Shift Overtime Night Shift Start End Total Hours Remarks
Rebarman 25 25 275
Mason 20 18 198
Carpenter 25 25 275
Fitter 12 8 88
Boilermaker 8 4 44
Pipe Fitter 6 2 22
Indirect * 68 60 633
Planner 1 1 11
Surveyor 3 2 22
HR Staff/Administration 2 1 11
HR/Administration 1 1 11
GA & Supporting 1 1 11
Administration 1 1 11
Civil Foreman 2 3 33
Civil QC Engineer 2 1 11
Operator Trailer 1 1 11
PERI UP Supervisor 2 1 8
DAILY CUMULATIVE
BALANCE %
ACTIVITY UNIT QTY Variance REMARKS
ACT. COMPLETE
Plan Actual Plan Actual
Construction
Civil Work Percent 100.00% 0.09% 0.03% 26.80% 11.60% 15.20% 88.40% 11.60%
Piping Work Percent 100.00% 0.05% 0.001% 1.87% 0.56% 1.31% 99.44% 0.56%
Structural Percent 100.00% 0.01% 0.00% 4.79% 0.75% 4.03% 99.25% 0.75%
2. MAJOR HIGHLIGHT
A. Civil A. Civil
Ongoing chipping & finishing EMB footing Continue chipping & finishing EMB footing
Ongoing install vertical rebar for wall 5 Continue install vertical rebar for wall 5
Ongoing cutting wall rebar stage 1 Contnue cutting wall rebar stage 1
Prepare area for Water Service Continue Prepare area for Water Service
B. Structure : B. Structure :
Pre-assembly Tailing transfer service & Pipe Rack Continue Pre-assembly Tailing transfer service & Pipe Rack
C. Mechanical : C. Mechanical :
D. Piping : D. Piping :
Joint pipe HDPE Field Pipeng & Fitting Ø OSU 400 PN10 Joint 89 Continue Joint pipe HDPE Field Pipe & Fitting Ø OSU 400 PN10
Joint pipe HDPE Field Pipeng & Fitting Ø PSL 400 PN25 Joint 42 Continue Joint pipe HDPE Field Pipe & Fitting Ø PSL 400 PN25
Joint pipe HDPE Field Piping Ø WPR 160 PN10 Joint 73 Continue Joint pipe HDPE Field Piping Ø WPR 160 PN10
Joint pipe HDPE Field Piping Ø PSL 160 PN10 Joint 20 Continue Joint pipe HDPE Field Piping Ø PSL 160 PN10
Joint pipe HDPE Field Piping Ø WFR 90 PN10 Joint 75 Continue Joint pipe HDPE Field Piping Ø WFR 90 PN10
Joint pipe HDPE Field Piping Ø WPO 63 PN10 Joint 70 Continue Joint pipe HDPE Field Piping Ø WPO 63 PN10
Joint pipe HDPE Field Piping Ø PSL 355 PN10 Joint 32 Continue Joint pipe HDPE Field Piping Ø PSL 355 PN10
Joint pipe HDPE Field Piping Ø WFI 225 PN16 Joint 10 Continue Joint pipe HDPE Field Piping Ø WFI 225 PN16
E. Logistic : E. Logistic :
Unloading Rebar, tools & equipment to TMF area Continue Unloading Rebar, tools & equipment to TMF area
F. Scaffold : F. Scaffold :
G. Others G. Others
Concern :
DAILY PHOTOGRAPH
PHOTOGRAPH
GENERAL ACTIVITIES
DAILY PHOTOGRAPH
PHOTOGRAPH
DAILY PHOTOGRAPH
PHOTOGRAPH
Joint 20 HDPE pipe dia OSU 400 Joint 89 HDPE pipe dia PSL 160
Joint 85 HDPE pipe dia PSL 160 Continue fit up HDPE pipe
Structure
Project Control