Professional Documents
Culture Documents
Intenship Renew
Intenship Renew
KARANATAKA - 570018
PRESENTED BY:
KIRAN KUMAR L 4GK20CV407
Dr . ARUN KUMAR K
Assistant professor
Department of civil engineering
INTRODUCTION
1. Scaffolding work .
2. Electric and equipment work.
3. Handling tool box at working site .
4. Staircase work .
5. Ladder usage stage .
6. During sand blasting .
7. During glass work and painting .
8. During concreting .
9. Wall construction .
10. Flooring and finishing ,etc.
11. During fencing and fire works .
12. Welding etc.
EQUIPMENTS WHICH ARE USING IN CONSTRUCTION SITE
1. CEMENT
2. BRICKS
3. STEEL
4. FINE AGGREGATES
5. COURSE AGGREGATES
6. BINDING WIRE
7. TRUSS STRUCTURE
8. BUILDING STONES ,etc.
COMPONENTS OF CIVIL
STRUCTURES
DETAILED REPORT ON SITES VISITED:-
1. Clear the area within the limit of the site dikes 1. After center line marking setting out ground tracing
of all vegetation, shrubs, trees (including woody process.
roots and tree stumps) and all large stones. 2. Maximum of 4 and minimum of 2 benchmarks are
2. Clear the work space and walkway around the marked in the corner
dikes. 3. 11. The excavated soil is to either removed out the
3. Clear all trees and shrubs within 10 m of dikes. site or stocked around the excavation pit.
Laying of PCC PCC curing
1. The proportioning is done based on the requirement 1. Freshly laid concrete shall be protected from rain by
or given specification. Generally, 1:2:4 or 1:3:6 mix suitable covering.
is used. 2. After the concrete has begun to harden- that is about
2. The measurement of material can be done by weight one to two hours after it has been laid- it shall be
batching or volume batching. protected with moist gunny bags.
3. Laying of Plain Cement Concrete 3. Curing shall be done for a minimum period of 7 days.
3. SIZE STONE
2. FOUNDATION
MASONRY
1. As per center line drawing of footing, marking should be 1. The SSM is a substructure is the lower portion of
done for excavation and p.c.c is laid at bottom level. After the building, which transmits the superstructure
completion of marking, simultaneously give the bar bending to the subsoil. SSM distributes the loads of the
schedule of footing and column to the bar bender so that it superstructure, to larger area so that intensity of
should be in one level. load at its base does not exceed the SBC of the
2. Locate the column position using thread and plumb bob on subsoil.
P.C.C as per centre line drawing 2. It is constructed either stepped or single stepped
its depend on the load.
MASONRY (BLOCK MASONRY)
1. Stretcher bond
2. Header bond
3. English Bond
4. Flemish Bond
5. Single Flemish
bond
1. The superstructure is the portion above the plinth level 1. Stirrups are closed-loop bars tied at regular intervals
of the building. The main component of the in beam reinforcement to hold the bars in position.
superstructure is a column and beam. 2. Mostly stirrups are designed in a rectangular or
2. The columns are built up to slab level and the frame for square shape but in some cases, it may be provided in
further construction is prepared. circular or diagonally.
SLABS Curing of slabs
1. A concrete slab is a common structural element of modern buildings. Horizontal slabs of steel reinforced concrete,
typically between 4 and 20 inches (100 and 500 millimeters) thick, are most often used to construct floors and ceilings,
while thinner slabs are also used for exterior paving.
2. These can either be “ground-bearing” or “suspended” slabs. The slab is ground-bearing if it rests directly on, otherwise
the slab is suspended. Based on length and breadth of conventional slab is classified into two types:
One way Slab
Two-way Slab
Shuttering De shuttering
1. The main objective of the industrial training is to provide an opportunity to undergraduates to identify, observe
and practice how engineering is applicable in the real industry.
2. It is not only to get experience on technical practices but also to observe management practices and to interact
with on field workers. It is easy to work with sophisticated machines, but not with people. I feel that I got
maximum out of the experience.
3. Also, I learnt the way of work in an organization, the importance of being punctual, the importance of
maximum commitment and the importance of team spirit.
CERTIFICATE
KIRAN KUMAR L
Certificate
ATTENDENCE SHEET
REFERENCE