3 Month Plan Apr-June 24
3 Month Plan Apr-June 24
Status as on
date Materials Equipment Remarks
Drawing Submittal RFI's
SLNo Description Start Date End date 27-3-24 comments Apr-24 May-24 Jun-24
Door fixtures ### ### not started Except hold area and loading,unloading area X
plumbing works ### ### work in progress shut down required for core cutting , plumbingline X
flooring works dado ### ### not started material approval required by 30-03-2024
sanitary fixtures Friday, April 19, 2024 ### not started material approval required by 30-03-2024
Finishing works QC area ### ### clearance required for area beyond partition area/post X
floor Tiles works ### ### not started engineering office occupation by others X
internal painting first coat ### ### not started clearance required
internal painting final coat ### ### not started clearance required
flooring works epoxy ### ### not started clearance required X
Demolition works of existing steps ### ### not started after fire line rerouting
new steps construction ### ### not started X
ss railing works Sunday, July 7, 2024 ### not started sample to be submitted
Zone3 Warehouse ground floor ### ### X X X
Door fixtures ### ### not started except staircase2 door and entrance X
Block work ### ### not started Work to be started after MEP works X
external plaster works Friday, June 21, 2024 ### not started
staircase 1 ### ### X X X
painting 1st coat works ### ### not started clearance requried
railing works Friday, May 17, 2024 Friday, May 24, 2024 not started sample to be submitted
polish works for flooring ### ### not started X
painting 1st coat works ### ### not started clearance requried
railing works ### ### not started X
polish works for flooring ### Friday, June 14, 2024 not started
painting final coat ### ### not started clearance requried
window fixtures ### ###
window,louvers fixtures entrance ### ### not started
Zone4 Warehouse triple height ### Saturday, July 27, 2024 X X
double bank louvers ### Sunday, May 5, 2024 not started shop drawing submitted to be approved by 30-3-24, X
grinding works Sunday, June 2, 2024 Friday, June 7, 2024 not started
flooring works Tuesday, July 2, 2024 ### not started depends upon mositure content
fire stop wall cutout filling ### Sunday, May 5, 2024 not started start based on MEP clearance X
internal painting final coat ### ### not started clearance required
3 Core cutting for process drain ### ###
epoxy flooring ### Friday, July 5, 2024 not started clearance required
ss trap fixing
Existing area A/L,material in and ### ### not started shop drawing to be approved,other vendor clearance
Zone6 existing
waste warehouse
collection outmodification
rooms ### ### X X
Demolition works ### Friday, May 10, 2024 not started Rate revision required for existing building works X
existing scaffolding removal ### ### not started works held up due to scaffolding,works to be started after
shaft block work external ### ### work in progress MEP works X X X
epoxy flooring 1st coat screed works ### ### not started based on MEP completion X
window glass fixtures ### ### not started completion based on clearance X X
louvers ### Friday, June 21, 2024 not started shop drawing approval X
lift pedestal work ### ### not started after structure work
fire stop wall cutout filling ### ### not started completion based on clearance X
ss trap fixing ### ### not started shop drawing to be approved,other vendor clearance X
painting 1st coat works ### ### not started clearance requried X
masonry works of dumb waiter Friday, April 12, 2024 ### not started X
Flooring works epoxy ### Friday, May 31, 2024 not started
door fixtures ### ### not started completion based on clearance X
Zone11 Ground floor grid P5 to P10 Friday, March 29, 2024 ### X X X
Block works for server room ### ### not started Kone material to be shifted
Plastering for server room ### Sunday, April 7, 2024 not started Kone material to be shifted
flooring works epoxy ### ### not started After clearance X X
grade slab works entrance lobby ### ### work in progress after fire line rerouting X
staircase 2 grade slab works ### ### not started after fire line rerouting
staircase 2 flooring ### ### not started
staricase2 railing works ### ### not started
staricase2 painting works Friday, July 12, 2024 Friday, July 19, 2024 not started
3 Staircase 3 works ### ### X X
Toilet waterproofing works ### Friday, April 12, 2024 not started
toilet flooring and dado ### ### not started
handing over Friday, April 19, 2024 ### not started X
with final coat ### ### work in progress completion based on clearance X
16 Engineering Store Works Monday, April 10, 2023 Sunday, May 12, 2024 X X
Joinery & Fixtures ### ### work in progress Toilet doors pending X
toilet flooring and dado ### Friday, April 26, 2024 not started material approval required dado
sanitary and
internal fixtures
external paitning works ### ### not started start based on clearance X
upto final coat ### ### work in progress final coat based on clearance X X
17 Engineering office Monday, April 10, 2023 Tuesday, May 21, 2024 X X
soil filling works ### ### not started based on MEP material clearance X
chain link fencing ### Friday, May 17, 2024 work in progress based on MEP material clearance X X
stone pitching ### Friday, May 17, 2024 not started based on MEP material clearance X
painting final coat ### Friday, June 7, 2024 not started subject to clearance X
19 Boiler house Monday, April 10, 2023 Friday, June 21, 2024 X X X
core cutting Friday, April 5, 2024 ### not started subject to clearance
inside tank epoxy reworks Sunday, April 7, 2024 Friday, April 12, 2024 not started subject to clearance
tank top waterproofing works ### ### not started
21 Substation Monday, April 10, 2023 ### X X
fire stop cutout filling ### ### not started subject to clearance X
21 Pipe rack work PS21a,21b,17a Monday, April 10, 2023 Tuesday, April 16, 2024 X
storm water drain works ### ### work in progress Drawing clearance requried by 5-4-24 X X
effluent drain works ### Friday, May 31, 2024 work in progress X X
pathway works ### Monday, July 1, 2024 not started drawing required X
Manpower deployment plan
SLNO Manpower Apr-24 May-24 Jun-24
1 Mason & helper 16 16 16
2 unskilled 20 20 20
3 carpenter & helper 10 10 10
4 barbender & helper 6 6 6
5 plumber & helper 3 3 3
6 welder & helper 10 10
7 fitter for door windows 2 2 2
8 painters& helper 5 5 5
9 epoxy layman 4 4 4
10 Hilti fire stop 2 2 2
11 Expansion joint layman 2 2 2
12 Tiles,kota,granite Flooring m 10 10 10
Total 90 90 80