SHAPE Project, Ferring Laboratories Private Limited

3 Month Look ahead Schedule (Mar24 to May'24)

Comments Mar-24 Apr-24 May-24 Contract/ Design


Start Date End Date Status as on
Tasks WW --> 128 129 130 131 132 133 134 135 136 137 138 139 140 Change Materials Equipment Remarks
27.02.2024 Drawing Submittal RFI's
Days --> 4 11 18 25 1 8 15 22 29 6 13 20 27 Orders
6 Sub Station Works 18-Apr-22, Mon 19-May-24, Sun X X X X X X X X X X X
6.1 Watertight Building 18-Apr-22, Mon 25-Nov-23, Sat
6.1.2 Construction Works 10-May-22, Tue 06-Jul-24, Sat X X X X X X X X X X X X X
6.1.2.2 Structural Works (Transformer and DG foundation) 13-Jun-22, Mon 01-May-24, Wed X X X X X X X X X
clearance required
chain link fencing works 01-Apr-24, Mon 21-Apr-24, Sun Not started typical sketch to be X X X
submitted
flooring in dg foundation area 16-Apr-24, Tue 01-May-24, Wed Not started clearance required X X
4.1.2.3 Weather Proofing & Finishing Works 16-Jul-22, Sat 06-Jul-24, Sat X X X X X X X X X X X X X
clearance required
Flooring Works 15-May-24, Wed 21-May-24, Tue not started X
Epoxy only
External paint 1st coat 22-May-24, Wed 27-May-24, Mon work in progress subject to clearance
Internal First Coat of Paint 25-May-24, Sat 30-May-24, Thu not started subject to clearance
7 UG Water tank System 02-May-22, Mon 30-Apr-24, Tue X X X X X X X X X
7.1 Watertight Building 02-May-22, Mon 30-Apr-24, Tue X X X X X X X X X
7.1.1 Construction Activities 09-May-22, Mon 30-Apr-24, Tue X X X X X X X X X
Sub Structure Works 09-May-22, Mon 30-Apr-24, Tue X X X X X X X X X
shed fabrication and sheeting works 15-Jan-24, Mon 15-Mar-24, Fri work in progress X X
pump foundations 01-Apr-24, Mon 04-Apr-24, Thu Not started post anchoring details req X

outside shed area will be


Cover slab Waterproofing 05-Apr-24, Fri 12-Apr-24, Fri Not started started X
After pump foundation
Screed Over Cover slab 13-Apr-24, Sat 19-Apr-24, Fri Not started Dependent X
Finishing Works 20-Apr-24, Sat 30-Apr-24, Tue Not started Dependent X X
10 Boiler House 16-May-22, Mon 14-May-24, Tue X X X X X X X X X X X
10.1 Watertight Building 02-Jun-22, Thu 24-Jan-24, Wed
10.1.2 Construction Activities 02-Jun-22, Thu 14-May-24, Tue X X X X X X X X X X X
10.1.2.2 Super Structure Works 03-Sep-22, Sat 07-Feb-24, Wed
Weather Proofing Works 10-Nov-22, Thu 19-Dec-23, Tue
Joinery & Fixtures 10-Oct-23, Tue 24-Jan-24, Wed
Finishing Works 14-Oct-23, Sat 14-May-24, Tue
railing works 21-Feb-24, Wed 17-Mar-24, Sun work in progress X X
External First coat of Paint 20-Nov-23, Mon 18-Apr-24, Thu work in progress clearance required X X X X X X X
Internal First Coat of Paint 10-Jan-24, Wed 25-Apr-24, Thu work in progress subject to clearance X X X X X X X X
internal paint final coat 26-Apr-24, Fri 06-May-24, Mon Not started subject to clearance
external paint final coat 26-Apr-24, Fri 06-May-24, Mon Not started subject to clearance
handing over 07-May-24, Tue 14-May-24, Tue Not started
11 Tank farm Area 20-Oct-22, Thu 12-Jun-24, Wed X X X X X X X X X X X
11.1 Watertight Building 20-Oct-22, Thu 20-Dec-23, Wed
11.1.2 Construction Works 20-Oct-22, Thu 12-Jun-24, Wed X X X X X X X X X X X
11.1.2.2 Structural Works 19-Nov-22, Sat 12-Jun-24, Wed
subject to tank material
Filling over the Plot ( Inside Fencing Area) 31-Jul-23, Mon 19-May-24, Sun Work in progress X X X X X X X X X X X
clearance
stone pitching 09-May-24, Thu 02-Jun-24, Sun not started drawing required X X X
Fencing Works 19-May-24, Sun 12-Jun-24, Wed work in progress X X
railing works 02-Jan-24, Tue 22-Mar-24, Fri work in progress X X X
road and new footings work 27-Feb-24, Tue 28-Mar-24, Thu Not started
Panel Room Weather Proofing Works 01-Feb-23, Wed 20-Apr-24, Sat X X X X X X X
Internal Paint 1st coat 15-Jan-24, Mon 04-Apr-24, Thu Not started subject to clearance X X X X X
External Painting 1st coat 06-Dec-23, Wed 04-Apr-24, Thu work in progress subject to clearance X X X X X
internal paint final coat 05-Apr-24, Fri 07-Apr-24, Sun Not started subject to clearance
external paint final coat 05-Apr-24, Fri 08-Apr-24, Mon Not started subject to clearance X
handing over 09-Apr-24, Tue 20-Apr-24, Sat Not started X
12 Warehouse Works 05-Jun-22, Sun 27-Oct-24, Sun X X X X X X X X X X X X X
12.1 Watertight building 05-Jun-22, Sun 24-May-24, Fri X X X X X X X X X X X X
12.1.2 Construction Works 05-Jun-22, Sun 27-Oct-24, Sun X X X X X X X X X X X X X
12.1.2.1 Sub Structure 05-Jun-22, Sun 09-Mar-24, Sat X
dockleveller area grade
grade slab works 21-Feb-24, Wed 09-Mar-24, Sat work in progress X
slab pending
loading unloading blockwork 20-Jan-24, Sat 19-Feb-24, Mon work in progress
loading unloading plastering 20-Feb-24, Tue 06-Mar-24, Wed work in progress X
12.1.2.2 GF to FF Lvl Structural Works 04-Aug-22, Thu 10-Jul-23, Mon
Weather Proofing Works 15-Sep-22, Thu 05-Oct-24, Sat X X X X X X X X X X X X X
Second Floor Slab Works 02-Mar-23, Thu 20-Dec-23, Wed
First Floor Weather proofing works QC area 26-May-23, Fri 18-Sep-23, Mon
Staircase 1 mumty works and finishing works 14-Jun-23, Wed 11-Apr-24, Thu X X X X X X
flooring works 01-Feb-24, Thu 14-Mar-24, Thu work in progress X X
railing works 03-Apr-24, Wed 11-Apr-24, Thu Not started X
Staircase 2 mumty works and finishing works 24-Jun-23, Sat 29-May-24, Wed X X X X X X X X X X X X X
flooring works 01-May-24, Wed 29-May-24, Wed Not started X X X X
railing works 30-May-24, Thu 09-Jun-24, Sun Not started
Door window fixtures 01-Nov-23, Wed 24-May-24, Fri X X X X X X X X X X X X
Door fixtures 15-Mar-24, Fri 14-Apr-24, Sun Not started X X X X
except machinary
window fixtures 25-Jan-24, Thu 24-May-24, Fri work in progress X X X X X X X X X X X X
movement entry area
external shaft and façade works 26-Nov-23, Sun 30-Jun-24, Sun X X X X X X X X X X X
completion based on
external shaft block work 01-Feb-24, Thu 11-May-24, Sat work in progress X X X X X X X X X X
clearance
completion based on
external shaft plastering 12-Mar-24, Tue 21-May-24, Tue Not started X X X X X X X X X X
clearance
completion based on
façade 01-May-24, Wed 05-Jun-24, Wed Not started
clearance
Paint works 26-Nov-23, Sun 30-Jun-24, Sun X X X X X X X X X X X
internal painting 26-Nov-23, Sun 13-Jun-24, Thu work in progress clearance requried X X X X X X X X X
external paint 01-May-24, Wed 30-Jun-24, Sun Not started clearance requried
exsiting Qc area 20-Oct-23, Fri 19-Jun-24, Wed X X X X X X X X X X X
toilet plumbing works 28-Feb-24, Wed 29-Mar-24, Fri work in progress shut down required X X X X
flooring works and dado 08-Apr-24, Mon 18-Apr-24, Thu Not started clearance requried X X
sanitary fixtures 19-Apr-24, Fri 29-Apr-24, Mon Not started clearance requried X X
flooring sheet removing 20-Feb-24, Tue 15-Mar-24, Fri work in progress X X
office area painting works 04-Apr-24, Thu 19-Apr-24, Fri Not started clearance requried X X
office area epoxy works 06-May-24, Mon 05-Jun-24, Wed Not started clearance requried
existing hole filling works 10-Mar-24, Sun 25-Mar-24, Mon Not started clearance requried X X X
exsiting warehouse area GF 01-Apr-24, Mon 25-May-24, Sat X X X X X X X X
Demolition works and material shifting 01-Apr-24, Mon 18-Apr-24, Thu Not started clearance requried X X X
blockwork and plaster 15-Apr-24, Mon 03-May-24, Fri Not started clearance requried X X X
doors fixing 15-Apr-24, Mon 21-Apr-24, Sun Not started clearance requried X
flooring works 02-May-24, Thu 12-May-24, Sun Not started clearance requried X
painting 18-May-24, Sat 25-May-24, Sat Not started clearance requried X
existing manufacturing terrace pipe Rack 24-Feb-24, Sat 15-Mar-24, Fri X X
pipe rack foundation works 24-Feb-24, Sat 15-Mar-24, Fri work in progress X X
core cutting
core cutting 15-Feb-24, Thu 06-Mar-24, Wed work in progress X
13 Manufacturing Block 04-Apr-22, Mon 14-Jul-24, Sun X X X X X X X X X X X
13.1 Watertight building 04-Apr-22, Mon 24-Apr-24, Wed X X X X X X X X
13.1.2 Construction Works 04-Apr-22, Mon 14-Jul-24, Sun X X X X X X X X X X X
13.1.2.1 Sub Structure 04-Apr-22, Mon 29-Mar-24, Fri X X X X
staircase4,staircase2 and
Grade slab Works 09-Jul-23, Sun 13-Mar-24, Wed work in progress entrance lobby area X X
pending
Plinth Beams near Staircase-2 10-Mar-24, Sun 20-Mar-24, Wed not started rerouting required X X
Filling up to Plinth Lvl with PCC 22-Mar-24, Fri 29-Mar-24, Fri not started rerouting required X
13.1.2.2 Super Structural Works 20-Jul-22, Wed 29-Aug-23, Tue
First Floor Slab Works 20-Jul-22, Wed 29-Aug-23, Tue
Ground Floor Weather Proofing Works 09-Nov-22, Wed 20-Jan-24, Sat
Flooring works epoxy,kota and tiles 05-May-24, Sun 04-Jul-24, Thu not started clearance req X X X X
Ground Floor Joinery & Fixtures Works 01-Nov-23, Wed 30-Jun-24, Sun X X X X X X X X X X X
Door Fixtures 15-Mar-24, Fri 14-Apr-24, Sun not started fixing based on clearnce X X X X
Window Fixtures 20-Feb-24, Tue 31-Mar-24, Sun work in progress X X X X
Internal First Coat of Paint 01-Apr-24, Mon 30-Jun-24, Sun not started based on clearance X X X X X X X X X
Second Floor Slab Works 20-Oct-22, Thu 11-Oct-23, Wed
First Floor Weather Proofing Works 10-Jan-23, Tue 14-Jul-24, Sun X X X X X X X X X X X
Flooring works epoxy,kota and tiles 15-May-24, Wed 14-Jul-24, Sun Not started X X
Door Fixtures 20-Mar-24, Wed 24-Apr-24, Wed Not started clearance X X X X X
Window Fixtures 20-Feb-24, Tue 31-Mar-24, Sun Not started clearance X X X X
Internal First Coat of Paint 11-Apr-24, Thu 05-Jul-24, Fri Not started clearance X X X X X X
repair and reworks 20-Mar-24, Wed 29-Apr-24, Mon Not started X X X X X X
Terrace Floor Slab Works 10-Jan-23, Tue 31-Jul-23, Mon
Second Floor Weather Proofing Works 26-May-23, Fri 10-Jul-24, Wed X X X X X X X X X X X X X
block work 31-May-23, Wed 03-Jun-24, Mon work in progress material entry area pending X X X X X X X X X X X X X
Wall Plastering 28-Jul-23, Fri 06-Jun-24, Thu Work In progress dependent X X X X X X X X X X X X X
Door Fixtures 22-Mar-24, Fri 24-Apr-24, Wed Not started based on clearance X X X X X
Window Fixtures 11-Feb-24, Sun 27-Mar-24, Wed Not started X X X X
Internal First Coat of Paint 16-Apr-24, Tue 10-Jul-24, Wed Not started based on clearance X X X X X X
foundation works RCC terrace 19-Sep-23, Tue 17-Mar-24, Sun work in progress X X
Flooring works epoxy 20-May-24, Mon 10-Jun-24, Mon Not started based on clearance
Upper Terrace Floor Slab Works 04-Jun-23, Sun 20-Sep-23, Wed
RTO slab 10-Nov-23, Fri 10-Dec-23, Sun
upper terrace finishign works 23-Oct-23, Mon 27-May-24, Mon X X X X X X X X X X X X X
Waterproofing at lower Terrace 20-Jan-24, Sat 27-Mar-24, Wed work in progress X X X X
external painting 1st coat 12-Apr-24, Fri 27-May-24, Mon Not started based on clearance X X X X X X
Door window fixtures 20-Feb-24, Tue 24-Apr-24, Wed work in progress X X X X X X X X
Staircase 1 mumty works & terrace dog house works ofcut 21-Sep-23, Thu 28-Apr-24, Sun X X X X X X X X
flooring work 28-Feb-24, Wed 29-Mar-24, Fri not started X X X X
railing works 30-Mar-24, Sat 12-Apr-24, Fri not started X X
painting works 1st coat 13-Apr-24, Sat 28-Apr-24, Sun not started clearance requried X X
Staircase 2 finishing works 03-Apr-24, Wed 10-May-24, Fri X X X X X
flooring works 03-Apr-24, Wed 18-Apr-24, Thu not started X X
railing works 19-Apr-24, Fri 29-Apr-24, Mon not started X X
painting works 1st coat 30-Apr-24, Tue 10-May-24, Fri not started clearance requried X
Staircase 3 finishing works 05-Dec-23, Tue 14-May-24, Tue X X X X X X X X X X X
pardi and masonry works 05-Dec-23, Tue 09-Jan-24, Tue works in prgress
flooring works 30-Mar-24, Sat 19-Apr-24, Fri not started X X X
railing works 18-Apr-24, Thu 03-May-24, Fri not started X X
painting works 1st coat 04-May-24, Sat 14-May-24, Tue not started clearance requried
Staircase 4 10-Oct-23, Tue 30-May-24, Thu X X X X X X X X X X X
fabrication of Stainless steel 30-Mar-24, Sat 14-May-24, Tue not started X X X X X X X
Erection of stanless steel 04-Apr-24, Thu 24-May-24, Fri not started X X X X X X X
railing works 25-May-24, Sat 30-May-24, Thu not started
painting works 1st coat 31-May-24, Fri 05-Jun-24, Wed not started
external plastering and shaft works 15-Oct-23, Sun 18-Jun-24, Tue X X X X X X X X X X X
front wall clearance
external shaft works 05-Jan-24, Fri 03-Jun-24, Mon work in progress X X X X X X X X X X X X X
pending
external shaft plastering works 04-Apr-24, Thu 18-Jun-24, Tue not started clearance required X X X X X X X X
Toilet works 15-Oct-23, Sun 29-Jun-24, Sat X X X X X X X X X X X X X
plumbing line 15-Oct-23, Sun 28-Mar-24, Thu work in progress X X X X
waterprooofing works 18-Mar-24, Mon 07-Apr-24, Sun work in progress X X X
flooring works and dado 10-Apr-24, Wed 30-Apr-24, Tue not started clearance required X X X
slab cutout reworks 05-Jan-24, Fri 28-Mar-24, Thu X X X X
structural steel works 28-Jan-24, Sun 28-Mar-24, Thu work in progress X X X X
Lift works 13-Feb-24, Tue 16-May-24, Thu X X X X X X X X X X X
lift blockwork,plaster,white wash 13-Feb-24, Tue 16-Mar-24, Sat
lift structure works 01-Apr-24, Mon 16-May-24, Thu not started drawing req X X X X X X X
ramp works 01-Apr-24, Mon 31-May-24, Fri X X X X X X X X X
entrance ramp works 01-Apr-24, Mon 01-May-24, Wed not started X X X X X
ramp flooring works 26-Apr-24, Fri 21-May-24, Tue not started X X X X
ramp railing works 11-May-24, Sat 31-May-24, Fri not started X X X
14 Creche Area 05-Dec-22, Mon 04-May-24, Sat X X X X X X X X X
14.1 Watertight Building 05-Dec-22, Mon 10-Mar-24, Sun X
14.1.2 Construction Works 01-Feb-23, Wed 04-May-24, Sat X X X X X X X X X
14.1.2.1 Sub Structure 01-Feb-23, Wed 27-Jul-23, Thu
14.1.1.2 Structural Works 10-Mar-23, Fri 14-May-23, Sun
Weather Proofing Works 22-Apr-23, Sat 04-May-24, Sat X X X X X X X X X
ramp works and railign works 10-Dec-23, Sun 19-Mar-24, Tue work in progress X X X
flooring works 13-Apr-24, Sat 28-Apr-24, Sun not started subject to clearance X X
Door window fixtures 25-Oct-23, Wed 10-Mar-24, Sun work in progress Toilet doors pending X
wall painting internal and external with final coat 20-Dec-23, Wed 18-Apr-24, Thu work in progress subject to clearance X X X X X X X
toilet plumbing works 02-Mar-24, Sat 11-Mar-24, Mon work in progress X X
Toilet waterproofing works 13-Mar-24, Wed 19-Mar-24, Tue not started X
toilet flooring and dado 21-Mar-24, Thu 29-Mar-24, Fri not started X
pantry works 23-Mar-24, Sat 02-Apr-24, Tue not started X X
handing over 19-Apr-24, Fri 04-May-24, Sat not started X X
15 Scrap Yard 21-Sep-22, Wed 16-May-24, Thu X X X X X X X X X X X
15.1 Watertight Building 21-Sep-22, Wed 16-Dec-23, Sat
15.1.2 Construction Works 15-Nov-22, Tue 16-May-24, Thu X X X X X X X X X X X
15.1.1.2 Structural Works 20-Dec-22, Tue 16-May-24, Thu X X X X X X X X X X X
Weather Proofing Works 25-Feb-23, Sat 16-May-24, Thu X X X X X X X X X
railing works 07-Jan-24, Sun 17-Mar-24, Sun work in progress X X
flooring works 01-Apr-24, Mon 16-May-24, Thu Not started subject to clearance X X X X X
final coat based on
wall painting internal and external including final coat 25-Nov-23, Sat 23-Apr-24, Tue work in progress X X X X X X X X
clearance
handing over 24-Apr-24, Wed 04-May-24, Sat Not started X
16 Engineering Store Works 10-Apr-23, Mon 10-Jun-24, Mon X X X X X X X X X
Watertight Building 10-Apr-23, Mon 10-Mar-24, Sun X
16.1 Construction Works 10-Apr-23, Mon 21-May-24, Tue X X X X X X X X X
16.1.1 Substructure and finishing works 10-Apr-23, Mon 21-May-24, Tue X X X X X X X X X
railing works 31-Dec-23, Sun 15-Mar-24, Fri work in progress X X
Joinery & Fixtures 25-Oct-23, Wed 10-Mar-24, Sun work in progress Toilet doors pending X
Toilet works 20-Feb-24, Tue 06-Mar-24, Wed work in progress X
sanitary fixtures 21-Mar-24, Thu 10-Apr-24, Wed Not started X X X
final coat based on
internal and external paitning works upto final coat 27-Nov-23, Mon 25-Apr-24, Thu work in progress X X X X X X X X
clearance
handing over 26-Apr-24, Fri 21-May-24, Tue not started subject to clearance X X
17 External Piperack 05-Jul-23, Wed 16-Feb-24, Fri
17.1 CONSTRUCTION WORKS 05-Jul-23, Wed 18-Jan-24, Thu
17.1.1 Substructure 05-Jul-23, Wed 26-Jan-24, Fri
Phase1 Manufacturing to scrap yard 05-Jul-23, Wed 26-Jan-24, Fri
phase 2-scrap yard to CCOE tank 04-Aug-23, Fri 17-Sep-23, Sun
phase 3 ccoe to project office 25-Sep-23, Mon 20-Nov-23, Mon
phase 4 project office to creche 01-Nov-23, Wed 30-Dec-23, Sat
18 Engineering office 15-Jun-23, Thu 11-Apr-24, Thu X X X X X X X X X X X X X
18.1 CONSTRUCTION WORKS 15-Jun-23, Thu 11-Apr-24, Thu X X X X X X X X X X X X
18.1.1 superstructure 15-Jun-23, Thu 11-Apr-24, Thu X X X X X X
toilet washbasin platform works 20-Mar-24, Wed 30-Mar-24, Sat X
sanitary installation works 25-Mar-24, Mon 09-Apr-24, Tue Not started subject to clearance X X X X X X X X
Door window fixtures 04-Mar-24, Mon 14-Mar-24, Thu Not started X X X X X X X X X X X
painting works 31-Jan-24, Wed 31-Mar-24, Sun Not started X X X X
handing over 01-Apr-24, Mon 11-Apr-24, Thu Not started X X
19 temporary shed works 05-Jul-23, Wed 26-Oct-23, Thu
19.1 CONSTRUCTION WORKS 05-Jul-23, Wed 26-Oct-23, Thu
19.1.1 Substructure 05-Jul-23, Wed 26-Oct-23, Thu
20 others 10-Mar-24, Sun 11-Jun-24, Tue X X X X X X X X X X X X
storm water drain water, road crossing, chamber,rain
10-Mar-24, Sun 13-May-24, Mon Not started detail drawing req X X X X X X X X X X
water
external process line connection works 12-Mar-24, Tue 26-Apr-24, Fri Not started X X X X X X
road works at loading unloading warehouse 27-Apr-24, Sat 11-Jun-24, Tue Not started drawing req X X X X X
3 Month plan April24 to June 24 Design

Status as on
date Materials Equipment Remarks
Drawing Submittal RFI's
SLNo Description Start Date End date 27-3-24 comments Apr-24 May-24 Jun-24

Zone1 Warehouse First floor QC area ### ### X X

Door fixtures ### ### not started Except hold area and loading,unloading area X

internal painting ### ### not started clearance required


3 Core cutting for process drain ### ###
ss trap fixing ### ### not started shop drawing to be approved,other vendor clearance X

Toilet works ### Monday, April 29, 2024 X

plumbing works ### ### work in progress shut down required for core cutting , plumbingline X

flooring works dado ### ### not started material approval required by 30-03-2024
sanitary fixtures Friday, April 19, 2024 ### not started material approval required by 30-03-2024
Finishing works QC area ### ### clearance required for area beyond partition area/post X

floor Tiles works ### ### not started engineering office occupation by others X

epoxy works ### ### not started clearance required by 1-4-2024


9 terrace pipe rack works ### Friday, March 15, 2024
Zone2 Warehouse Loading unloading area ### ### X X X

1 substructure works ### ###


insulated rolling shutter and doors ### ### not started after shop drawing approval X

window fixtures ### ### not started X

internal painting first coat ### ### not started clearance required
internal painting final coat ### ### not started clearance required
flooring works epoxy ### ### not started clearance required X

Demolition works of existing steps ### ### not started after fire line rerouting
new steps construction ### ### not started X

ss railing works Sunday, July 7, 2024 ### not started sample to be submitted
Zone3 Warehouse ground floor ### ### X X X

Door fixtures ### ### not started except staircase2 door and entrance X

staircase 2 , entrance door ### ### not started


ss trap fixing ### ### not started shop drawing to be approved,other vendor clearance
external shaft works Monday, April 1, 2024 ### X X X

existing scaffolding removal ### ### not started X

Block work ### ### not started Work to be started after MEP works X

external plaster works Friday, June 21, 2024 ### not started
staircase 1 ### ### X X X

painting 1st coat works ### ### not started clearance requried
railing works Friday, May 17, 2024 Friday, May 24, 2024 not started sample to be submitted
polish works for flooring ### ### not started X

painting final coat ### ### not started clearance requried


staircase2 ### Sunday, June 30, 2024 X X

flooring works ### ### not started clearance requried X

painting 1st coat works ### ### not started clearance requried
railing works ### ### not started X

polish works for flooring ### Friday, June 14, 2024 not started
painting final coat ### ### not started clearance requried
window fixtures ### ###
window,louvers fixtures entrance ### ### not started
Zone4 Warehouse triple height ### Saturday, July 27, 2024 X X

double bank louvers ### Sunday, May 5, 2024 not started shop drawing submitted to be approved by 30-3-24, X

internal painting ### ### not started X

grinding works Sunday, June 2, 2024 Friday, June 7, 2024 not started
flooring works Tuesday, July 2, 2024 ### not started depends upon mositure content
fire stop wall cutout filling ### Sunday, May 5, 2024 not started start based on MEP clearance X

Zone5 Warehouse second floor ### Friday, July 5, 2024 X X X

Door fixtures ### ### not started


Door fixtures existing side ### ### not started
window fixtures ### ### not started equipment area X

internal painting final coat ### ### not started clearance required
3 Core cutting for process drain ### ###
epoxy flooring ### Friday, July 5, 2024 not started clearance required
ss trap fixing
Existing area A/L,material in and ### ### not started shop drawing to be approved,other vendor clearance
Zone6 existing
waste warehouse
collection outmodification
rooms ### ### X X

1 modification ### ### X X

Demolition works ### Friday, May 10, 2024 not started Rate revision required for existing building works X

blockwork Sunday, May 5, 2024 ### not started


plaster ### ### not started
doors fixing ### ### not started
flooring works ### ### not started X

painting Sunday, June 2, 2024 ### not started


Zone7 Utility area & lower terrace Manufact ### ### X X X

finishing works ### ### X X X

khurra fixing ### ### not started


Door fixtures rolling shutter ### ### not started X

window glass fixing and louvers ### ### not started


fooring works utility area ### ### not started
diamond cutting for new cutouts ### ### not started scaffolding required
dog house works
Manufacturing block Ground floor ### ### not started X

Zone8 grid P1 to P5 Friday, January 5, 2024 ### X X X

1 finishing works Friday, January 5, 2024 ### X X X

existing scaffolding removal ### ### not started works held up due to scaffolding,works to be started after
shaft block work external ### ### work in progress MEP works X X X

shaft plastering works external ### ### not started


epoxy grinding works ### Sunday, May 5, 2024 not started based on MEP completion X

epoxy flooring 1st coat screed works ### ### not started based on MEP completion X

lift1 structure works ### ### not started After clearance X

Door fixtures ### ### not started completion based on clearance X X

window glass fixtures ### ### not started completion based on clearance X X

louvers ### Friday, June 21, 2024 not started shop drawing approval X

rolling shutter ### ### not started X

lift pedestal work ### ### not started after structure work
fire stop wall cutout filling ### ### not started completion based on clearance X

ss trap fixing ### ### not started shop drawing to be approved,other vendor clearance X

2 Staircase 1 works ### Sunday, July 21, 2024 X X X

painting 1st coat works ### ### not started clearance requried X

railing works ### ### not started


polish works for flooring ### Friday, July 5, 2024 not started
painting final coat ### ### not started clearance requried
3 staircase
Staircase 44 fabrication
works and erection Monday, April 1, 2024 Sunday, June 16, 2024 X X X

works ### ### not started X

staricase 4 railing works


dumb waiter dismantling works and Friday, May 31, 2024 Friday, June 7, 2024 not started X

diamond cutting ### ### not started X

masonry works of dumb waiter Friday, April 12, 2024 ### not started X

Door window fixtures ### ### not started


painting works ### ### not started
Zone9 First floor grid P1 to P5 ### ### X X X

1 finishing works ### ### X X X

Flooring works epoxy ### Friday, May 31, 2024 not started
door fixtures ### ### not started completion based on clearance X

window fixtures ### ### not started completion based on clearance X

rolling shutter ### ### not started completion based on clearance


louvers ### ### not started shop drawing approval
painting works ### ### work in progress completion based on clearance X X

Zone10 Second floor grid P1 to P5 ### Monday, July 8, 2024 X X X

1 finishing works ### Monday, July 8, 2024 X X X

Flooring works epoxy ### ### not started X

Door fixtures ### ### not started X

window glass fixtures ### ### not started


rolling shutter Friday, June 28, 2024 Monday, July 8, 2024 not started
louvers ### Monday, July 1, 2024 not started
painting works ### ### not started X X X

2 Rework and repair ### Monday, April 29, 2024 X

Zone11 Ground floor grid P5 to P10 Friday, March 29, 2024 ### X X X

1 finishing works Monday, April 1, 2024 Sunday, July 21, 2024 X X X

wall dismantling works ### ### not started X

Block works for server room ### ### not started Kone material to be shifted
Plastering for server room ### Sunday, April 7, 2024 not started Kone material to be shifted
flooring works epoxy ### ### not started After clearance X X

flooring works tiles,kota,granite ### ### not started X X

grade slab works entrance lobby ### ### work in progress after fire line rerouting X

lift2 structure works ### ### not started After clearance X

lift 3 structure works ### ### not started After clearance


lift 4 structure works ### ### not started After clearance
Door fixtures ### ### not started
window glass fixtures ### ### not started
rolling shutter ### ### not started
louvers Friday, June 14, 2024 Friday, June 21, 2024 not started
2 Staircase 2 works ### Friday, July 19, 2024 X X

staircase 2 grade slab works ### ### not started after fire line rerouting
staircase 2 flooring ### ### not started
staricase2 railing works ### ### not started
staricase2 painting works Friday, July 12, 2024 Friday, July 19, 2024 not started
3 Staircase 3 works ### ### X X

staircase 3 flooring ### ### not started X

staricase3 railing works ### ### not started


staricase 3 painting works 1st coat ### ### not started
4 toilet works Monday, April 1, 2024 ### X X

sunken filling works ### ### not started X

flooring,dado works ### ### not started


sanitary fixtures Friday, May 10, 2024 ### not started based on clearance
Zone12 First floor grid P5 to P10 ### ### X X X

1 finishing works ### ### X X X

epoxy works ### ### work in progress X X

kota,tiles works ### ### work in progress X X

Door fixtures ### ### not started only external doors


window glass fixtures ### ### not started only external doors
rolling shutter ### ###
louvers ### ###
painting works ### ### work in progress X X X

2 toilet works Monday, April 1, 2024 Monday, May 27, 2024 X X

sunken filling works ### ### not started X

flooring,dado works ### ### not started X

sanitary fixtures ### ### not started based on clearance


Zone13 second floor grid P5 to P10 ### ### X X X

PWS foundation ### ### not started X

epoxy works 1st coat ### ### not started


Door fixtures ### Friday, April 19, 2024 not started X

window glass fixtures ### Sunday, May 5, 2024 not started X

rolling shutter Monday, July 8, 2024 ### not started


louvers ### ### not started
painting works Friday, April 5, 2024 ### not started
14 Creche Friday, April 5, 2024 ### X X

1 finishing works Friday, April 5, 2024 ### X X

ramp railing works Friday, April 5, 2024 ### not started


flooring works ### ### not started
Door fixtures ### ### not started Toilet doors pending
ventilators Friday, April 26, 2024 ### not started
dog
wall house
paintinglouvers
internal and external ### ### not started
with final coat ### ### work in progress completion based on clearance X

Toilet waterproofing works ### Friday, April 12, 2024 not started
toilet flooring and dado ### ### not started
handing over Friday, April 19, 2024 ### not started X

15 scrap yard ### ### X

1 finishing works ### ### X

flooring worksinternal and external


wall painting ### ### not started start based on clearance X

with final coat ### ### work in progress completion based on clearance X

16 Engineering Store Works Monday, April 10, 2023 Sunday, May 12, 2024 X X

Joinery & Fixtures ### ### work in progress Toilet doors pending X

toilet plumbing works ### ### work in progress X

toilet flooring and dado ### Friday, April 26, 2024 not started material approval required dado
sanitary and
internal fixtures
external paitning works ### ### not started start based on clearance X

upto final coat ### ### work in progress final coat based on clearance X X

17 Engineering office Monday, April 10, 2023 Tuesday, May 21, 2024 X X

Joinery & Fixtures ### ### work in progress crash panel


sanitary and
internal fixtures
external paitning works ### ### not started
final coat ### ### not started final coat based on clearance
18 CCOE tank, panel room Monday, April 10, 2023 Friday, June 7, 2024 X X X

railing works ### ### not started X

soil filling works ### ### not started based on MEP material clearance X

chain link fencing ### Friday, May 17, 2024 work in progress based on MEP material clearance X X

stone pitching ### Friday, May 17, 2024 not started based on MEP material clearance X

painting final coat ### Friday, June 7, 2024 not started subject to clearance X

19 Boiler house Monday, April 10, 2023 Friday, June 21, 2024 X X X

fire stop final


painting wall cutout filling and
coat internal ### ### not started subject to clearance
external ### Friday, June 21, 2024 not started subject to clearance X

20 UG tank Monday, April 10, 2023 Monday, April 15, 2024 X

core cutting Friday, April 5, 2024 ### not started subject to clearance
inside tank epoxy reworks Sunday, April 7, 2024 Friday, April 12, 2024 not started subject to clearance
tank top waterproofing works ### ### not started
21 Substation Monday, April 10, 2023 ### X X
fire stop cutout filling ### ### not started subject to clearance X

painting final coat ### ### not started subject to clearance


flooring works ### ### work in progress completion based on clearance X X

21 Pipe rack work PS21a,21b,17a Monday, April 10, 2023 Tuesday, April 16, 2024 X

excavation works ### ### work in progress X

pcc works ### ### not started


footing rcc works Sunday, April 7, 2024 ### not started
pedestal works ### ### not started
22 20KL storage tank foundation Monday, April 10, 2023 Saturday, May 4, 2024 RFI clearance by 30-3-24,matrix material to be removed, X X

excavation works ### ### not started Ferring clearance requried X

pcc works ### ### not started


RCC works wall ### ### not started
soil filling works ### ### not started
grade slab works ### ### not started X

23 external service Monday, April 10, 2023 Monday, July 1, 2024 X X X

storm water drain works ### ### work in progress Drawing clearance requried by 5-4-24 X X

effluent drain works ### Friday, May 31, 2024 work in progress X X

road works ### Friday, May 31, 2024 work in progress X X

pathway works ### Monday, July 1, 2024 not started drawing required X
Manpower deployment plan
SLNO Manpower Apr-24 May-24 Jun-24
1 Mason & helper 16 16 16
2 unskilled 20 20 20
3 carpenter & helper 10 10 10
4 barbender & helper 6 6 6
5 plumber & helper 3 3 3
6 welder & helper 10 10
7 fitter for door windows 2 2 2
8 painters& helper 5 5 5
9 epoxy layman 4 4 4
10 Hilti fire stop 2 2 2
11 Expansion joint layman 2 2 2
12 Tiles,kota,granite Flooring m 10 10 10
Total 90 90 80