Professional Documents
Culture Documents
W134 Plan
W134 Plan
W134 Plan
Week134
shade approval
pendingfor dado
Zone 1 warehouse 1st
sqm 5.2 5.2 5.2 5.2 5.2 5.2 31.20 tiles, dado fixing will
floor QC area be started after
sanitary approval
flooring works dado toilet ### ###
Zone 1 warehouse 1st sanitary approval
no's 1 1.00 pending
-
floor QC area sanitary fixtures toilet Friday, April 19, 2024 ###
Zone 1 warehouse 1st
sqm 5.00 5.00 5.00 5.00 5.00 5.00 30.00 - work in progress -
floor QC area floor Tiles worksQC area ### ###
Zone 1 warehouse 1st
sqm 40 40 40 40 40 200.00 shifted
floor QC area epoxy works QC area ### ###
Zone 2 warehouse
laoding unloading internal painting first coat ### ### sqm 42 42.00 clearance required
area
Zone 2 warehouse
laoding unloading sqm 0.14 0.14 clearance required -
area Demolition works of existing steps ### ###
Zone 3 warehous
sqm 71.43 71.43 71.43 71.43 71.43 71.43 428.58 shifted
ground floor staircase 1painting 1st coat works ### ###
Zone 4 warehous
sqm - shifted
triple height fire stop wall cutout filling ### Sunday, May 5, 2024
Zone 5 warehous
no's 1.00 1.00 - work in progress
second floor Door fixtures ### ###
Zone 7 utility area
and lower terrace no's 1.00 1.00 1.00 1.00 1.00 1.00 6.00 - not started
manufacturing khurra fixing ### ###
Zone 8 Manufacturing
block Ground floor sqm 37.89 37.89 37.89 37.89 37.89 37.89 227.34 - no area clearance
grid P1 to P5
epoxy grinding works ### Sunday, May 5, 2024
Zone 8 Manufacturing
block Ground floor sqm 20.21 20.21 clearance required
grid P1 to P5 epoxy flooring 1st coat screed
works ### ###
Zone 8 Manufacturing
block Ground floor kgs 250.00 250.00 250.00 250.00 250.00 250.00 1,500.00 - not started
grid P1 to P5
lift1 structure works Monday, April 1, 2024 ###
Zone 8 Manufacturing
block Ground floor no's 1.00 1.00 1.00 1.00 1.00 1.00 6.00 - not started
grid P1 to P5
Door fixtures Monday, April 1, 2024 ###
Zone 8 Manufacturing
block Ground floor no's 3.00 3.00 - not started
grid P1 to P5
Zone 8 Manufacturing window glass fixtures Monday, April 1, 2024 ###
shifted due to
block Ground floor lift pedestal work ### ### no's 1 1.00 scaffolding
grid P1 to P5
Zone 8 Manufacturing
block Ground floor sqm - - shifted
grid P1 to P5
staircase 1painting 1st coat works Monday, April 1, 2024 Monday, April 8, 2024
Zone 8 Manufacturing
block Ground floor MT 0.13 0.13 0.13 0.13 0.13 0.13 0.78
grid P1 to P5 staircase 4 fabrication and
erection works ### ###
Zone 8 Manufacturing
block Ground floor sqm 2.17 2.17 2.17 2.17 2.17 2.17 13.02 - work in progress
grid P1 to P5
masonry works of dumb waiter Friday, April 12, 2024Thursday, May 2, 2024
Zone 9 Manufacturing
block 1st floor grid no;s 1.00 1.00 2.00 - work in progress
P1 to P5
door fixtures Monday, April 1, 2024 ###
Zone 9 Manufacturing
block 1st floor grid no;s 1.00 1.00 2.00 - work in progress
P1 to P5
window fixtures Monday, April 1, 2024 ###
Zone 9 Manufacturing
block 1st floor grid sqm 11.83 11.83 11.83 11.83 11.83 11.83 70.98 - work in progress
P1 to P5
painting works ### ###
Zone 10
Manufacturing block
no's 2 2 2 1 7.00
2nd floor grid P1 to
P5 window glass fixtures ### ###
Zone 10
Manufacturing block
sqm 7.76 7.76 7.76 7.76 7.76 7.76 46.56 - work in progress
2nd floor grid P1 to
P5
painting works Monday, April 1, 2024 Sunday, June 16, 2024
Zone 11
Manufacturing block
sqm - shifted
ground floor grid P5
to P10 flooring works epoxy ### Sunday, July 21, 2024
Zone 11
Manufacturing block
sqm 0.54 0.54 0.54 0.54 2.16
ground floor grid P5
to P10 flooring works tiles,kota,granite ### Sunday, July 21, 2024
Zone 11
Manufacturing block
sqm 2.33 2.33 2.33 2.33 2.33 2.33 13.98 - work in progress
ground floor grid P5
to P10
grade slab works entrance lobby Monday, April 1, 2024 ###
Zone 11
Manufacturing block
kgs 150.00 150.00 150.00 150.00 150.00 150.00 900.00 - not started
ground floor grid P5
to P10
lift2 structure works Monday, April 1, 2024 ###
Zone 11
Manufacturing block
kgs 150.00 150.00 150.00 150.00 150.00 150.00 900.00 - not started
ground floor grid P5
to P10
lift 3 structure works Saturday, April 6, 2024 ###
Zone 11
Manufacturing block
MT 150.00 150.00 150.00 150.00 150.00 150.00 900.00 - not started
ground floor grid P5
to P10 lift 4 structure works ### Sunday, April 28, 2024
Zone 11
Manufacturing block
sqm 1.50 1.50 1.50 1.50 1.50 1.50 9.00 - work in progress
ground floor grid P5
to P10 staircase 2 grade slab works ### ###
shade approval
Zone 11
pendingfor dado
Manufacturing block
sqm 0.52 0.52 0.52 0.52 0.52 0.52 3.12 - tiles, dado fixing will
ground floor grid P5 be started after
to P10 sanitary approval
toilet flooring,dado works Tuesday, April 9, 2024 ###
Zone 12
Manufacturing block
sqm 1.48 1.48 1.48 1.48 1.48 1.48 8.88 not started
1st floor grid P5 to
P10 epoxy works ### ###
Zone 12
Manufacturing block
sqm 0.29 0.29 0.29 0.29 0.29 0.29 1.74 - work in progress
1st floor grid P5 to
P10
kota,tiles works ### Saturday, May 4, 2024
Zone 12
Manufacturing block
no's 1.55 1.55 1.55 1.55 1.55 1.55 9.30
1st floor grid P5 to
P10 Door fixtures ### ###
Zone 12
Manufacturing block
no's 1.55 1.55 1.55 1.55 1.55 7.75
1st floor grid P5 to
P10 window glass fixtures ### ###
Zone 12
Manufacturing block
sqm 2.77 2.77 2.77 2.77 2.77 2.77 16.62 - work in progress
1st floor grid P5 to
P10
painting works ### ###
Zone 12
Manufacturing block
sqm 3.00 3.00 3.00 3.00 3.00 3.00 18.00 - work in progress
1st floor grid P5 to
P10
sunken filling works Monday, April 1, 2024 ###
shade approval
Zone 12
pendingfor dado
Manufacturing block
sqm' 9.47 9.47 9.47 9.47 37.88 tiles, dado fixing will
1st floor grid P5 to be started after
P10 sanitary approval
flooring,dado works ###Thursday, May 2, 2024
Zone 13
Manufacturing block
sqm 120 120 120 120 120 120 720.00 clearance required
2nd floor grid P5 to
P10 epoxy works 1st coat ### ###
Zone 13
Manufacturing block
no's 1.00 1.00 2.00 - work in progress
2nd floor grid P5 to
P10
Door fixtures ### Friday, April 19, 2024
Zone 13
Manufacturing block
sqm 150.00 150.00 - work in progress
2nd floor grid P5 to
P10
painting works Friday, April 5, 2024 ###
Creche sqm 0.53 0.53 0.53 0.53 0.53 0.53 3.18 - works will complete
after MEP works
wall painting internal and external
with final coat ### ###
Creche toilet flooring and dado ### ### sqm 3.5 3.5 3.5 3.5 3.5 3.5 21.00 shade approval pendingfor dado tiles, dado fixing will be started after sanitary app
shade approval
pendingfor dado
Engineering store sqm 2.00 2.00 - tiles, dado fixing will
be started after
sanitary approval
toilet flooring and dado ### Friday, April 26, 2024
external service rmt 1.60 1.60 1.60 1.60 1.60 1.60 9.60 - work in progress
external service rmt 1.04 1.04 1.04 1.04 1.04 1.04 6.24 - hard rock
external service sqm 3.73 3.73 3.73 3.73 3.73 18.65 - work in progress
Planned Activities 24 18 24 11
Achieved Activities 14 12
Cumulative Achieved% 18 34 34 34
Start Activities
100
25
86
20
55
15
31
10 34 34 34
18
5
24 14 18 12 24 11
0
Week 132 Week 133 Week 134 Week 135 XX
Completion Activities
00
100 35 120
90 30 100
100
80
25
58 80
70
20
60 60
15
50 21
29 40
40 10
4 8 21 21
30 5 11 20
8 6 13 9 21 30
20 0 0
Week 132 Week 133 Week 134 Week 135 XX
10
0
k 135 XX
Planned Activities Achieved Activities
ed% Cumulative Achieved% Cummulative Planned% Cummulative Achieved%
n
Week 135 XX
30
100
21
120
00
100
80
60
40
1
20
0
k 135 XX
vities
Achieved%
Dealy in Start /
Sl.No. Contractor Area
Delay in Completion
Zone 8 Manufacturing block Ground
1 CIVIL Delay in start
floor grid P1 to P5
Zone 8 Manufacturing block Ground
2 CIVIL Delay in start
floor grid P1 to P5
Zone 11 Manufacturing block ground
3 CIVIL Delay in start
floor grid P5 to P10
Zone 11 Manufacturing block ground
4 CIVIL Delay in start
floor grid P5 to P10
5 CIVIL Delay in start 20KL storage tank foundation
Zone 7 utility area and lower terrace
6 CIVIL Delay in start
manufacturing
Zone 11 Manufacturing block ground
7 CIVIL Delay in start
floor grid P5 to P10
Zone 11 Manufacturing block ground
8 CIVIL Delay in start
floor grid P5 to P10
9 CIVIL Delay in start Engineering store
8Logistics
Jacobs/Ferring 0
Ferring 2
3
Ferring/Savills 0
Jacobs/Savils 0
Variance Category
1Drawing 1
2Material 1
3Manpower 0
4Machinery 0
2
7Previous work
Va
8Logistics 1
9Safety 0
2
10Weather 0
Total 16
1Drawing
3Manpower
5 Clarification - BOQ/Procurem
7Previous work
9Safety
Ownership
1
Variance Categeory
1 1
1
2
Drawing 2Material
Manpower 4Machinery
Clarification - BOQ/Procurement/ NT Item 11 6Site Clearances & (Interface Isues)
Previous work 8Logistics
Safety 10Weather
Sl.No. Contractor Delay in Finish Area
Metrix 0
I CLEAN 0
Ferring/Savills 0
Ferring 2
other vendor 0
Jacobs/Ferring 0
Srichalla / Metrix 0
Total 2
Variance
Finish V
1Drawing 1
2Material 1 1
3Manpower 0
4Machinery 0
5 Clarification - BOQ/Procurement/ NT 0
7Previous work 1
8Logistics 0
9Safety 0
10Weather 0
Total 6
2Material 3Manpower 4
3
6Site Clearances & (Interface Isues) 7Previous work 8
10Weather
Ownership
Finish Variance
1 1
1
1