Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

SRI CHALLA CONSTRUCTIONS

RFI Tracker Date 4/13/2024

RFI
SLno RFI no Date of RFI raised Reply Date Reply from Consultant LOCATION STATUS response
RFI raised delay in
days

Please found the attached RFI 249

250 RFI 249 10/17/2023 As per drawing MANUFACTURING BLOCK layout and details of 22.4m lvl open 179.00
terrace level in section 2 inverted rungs are given in the slab but details of
the same is missing. It is mentioned to refer lift pit vendor detail drawing.
Kindly provide the same.

1. Without cladding columns in clean room areas to be protected with SS


As per drawing MISCELLANEOUS CONSTRUCTION DETAILS
269 RFI 268 12/20/2023 (87AE1700/A.01/0502) SS angle for column edge protection is shown. Kindly 4/10/2024 Corner angle. closed 115.00
2. SS corner angle protection not required in Technical area columns
provide the layout of columns for every building for the same
3.Open edge for cleanroom to be protected as per details given in drawings

As per drawing WAREHOUSE FIRST FLOOR PLAN (87A01700-WB/A.01/0041)


317 RFI 316 3/11/2024 down take pipe at grid W3-W4/WA and W1/WA is shown which is openly 4/9/2024 there are only 2 RWP at south side and this would taken in shafts , no exposed closed 33.00
visible. Kindly confirm whether metal cladding to be done to cover the pipe pipe should be considered
or not.

As per drawing STORM & ROAD WATER DRAIN LAYOUT PLAN


(87A01700/C.01/0101) near CCOE tank hume pipe before road crossing is
320 RFI 319 3/21/2024 mentioned as Class NP2 300mm dia and hume pipe crossing the road is 4/10/2024 NP3 , 300mm dia closed 23.00
mentioned as Class NP3, but dia of the pipe is not mentioned. Kindly clarify
the dia of the pipe.

As per drawing ROAD AND STORM WATER PLAN (87A01700-SI/C.01D/0101)


321 RFI 320 3/21/2024 sizes of the pipes are not provided. As per the attached sketch kindly clarify 4/10/2024 NP3 , 300mm dia closed 23.00
the size of pipes heighted in the sketch.

As per drawing ENGINEERING OFFICE LAYOUT PLAN (87A01700-A.010055)


322 RFI 321 3/22/2024 proposed counter platform and washbasin are very congested in toilet. open 22.00
Kindly suggest alternate way.

As per the warehouse ground floor process drain drawing


87A01700-WB/C.01D/0101/A0,
4/6/2024 4/9/2024 Please work on the marked levels as mentioned in Drawing no. 87A01700- 7.00
330 RFI 329 MH P1 and MH P2 invert levels are 95.50 and 95.47 respectively. closed
WB/C.01D/0101/A0
But as per the attached sketch hard sheet rock arrived for 2 manholes at
95.586 and 96.643.Kindly clarify.

As per existing QC plumbing drawing number of core cut arrived are 9 no's,
accordingly we requested Ferring team for permission of the same.
But due to numerous MEP lines below toilet area as per the attached
photos, Ferring team denied permission for proposed no's of core cut and
331 RFI330 4/6/2024 asked to look for possibility if core cutting no's can be reduced. open 7.00
We would like to suggest to raise toilet area flooring upto 200mm same as
engineering office so that all drainage lines will pass over top of slab and the
core cutting will be limited to only 2 no's as mentioned in the attached hand
sketch for your ready reference.
Kindly suggest
RFI
SLno RFI no Date of RFI raised Reply Date Reply from Consultant LOCATION STATUS response
RFI raised delay in
days

As per our discussion it was conveyed to us verbally that in ccoe entrance


road upto fencing gate and loading unloading area shall be bitumen road.
331 RFI331 4/8/2024 Please note ,for this amount of small work vendor mobilization is not open 5.00
possible.

Kindly suggest.

You might also like