RFI
SLno RFI no Date of RFI raised Reply Date Reply from Consultant LOCATION STATUS response
RFI raised delay in
days
250 RFI 249 10/17/2023 As per drawing MANUFACTURING BLOCK layout and details of 22.4m lvl open 179.00
terrace level in section 2 inverted rungs are given in the slab but details of
the same is missing. It is mentioned to refer lift pit vendor detail drawing.
Kindly provide the same.
As per existing QC plumbing drawing number of core cut arrived are 9 no's,
accordingly we requested Ferring team for permission of the same.
But due to numerous MEP lines below toilet area as per the attached
photos, Ferring team denied permission for proposed no's of core cut and
331 RFI330 4/6/2024 asked to look for possibility if core cutting no's can be reduced. open 7.00
We would like to suggest to raise toilet area flooring upto 200mm same as
engineering office so that all drainage lines will pass over top of slab and the
core cutting will be limited to only 2 no's as mentioned in the attached hand
sketch for your ready reference.
Kindly suggest
RFI
SLno RFI no Date of RFI raised Reply Date Reply from Consultant LOCATION STATUS response
RFI raised delay in
days
Kindly suggest.