LEC (4) Elastic Settlement of Piles

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

University of Benghazi

Faculty of Engineering and Petroleum Jalu


Civil Engineering Department

Lecture (4)

Elastic Settlement of Piles

Foundation Engineering II (CE422)

Mr. Hamza Makeen


Lecture (4): Elastic Settlement of Piles Mr. Hamza Makeen

Lecture (4)
Elastic Settlement of Piles

39
Lecture (4): Elastic Settlement of Piles Mr. Hamza Makeen

40
Lecture (4): Elastic Settlement of Piles Mr. Hamza Makeen

41
Lecture (4): Elastic Settlement of Piles Mr. Hamza Makeen

42
Lecture (4): Elastic Settlement of Piles Mr. Hamza Makeen

Solved example

The allowable working load on a prestressed concrete pile 21 m


long that has been driven into sand is 502 kN. The pile is
octagonal in shape with D = 356 mm (see Table 11.3a) in the
reference.
Skin resistance carries 350 kN of the allowable load, and point
bearing carries the rest. Determine the settlement of the pile.
Use:
EP = 21 × 106 kN/m2 ES = 25 × 103 kN/m2
μs = 0.35 ξ = 0.62

Solution

43
Lecture (4): Elastic Settlement of Piles Mr. Hamza Makeen

Home work 2
Problem 11.13 , Page 632

44