FLY CONSULTANT SDN. BHD.

EARTHWORK SCHEDULE

PROJECT: PROPOSED DEVELOPMENT OF 2 STOREY SCHOOL ON LOT 20352 (LOT LAMA PT


272), LILITAN SUNGAI ARA, MUKIM 10, DAERAH BARAT DAYA, PULAU PINANG

TITLE: EARTHWORK SCHEDULE


OWNER: PERSATUAN KEBAJIKAN KANAL-KANAK TERENCAT AKAL, PULAU PINANG
PREPARED BY: FLY CONSULTANT SDN. BHD.

7/17/2023 7/24/2023 7/1/2023 7/8/2023 7/15/2023 7/22/2023 7/29/2023 8/5/2023 8/12/2023 8/19/2023 8/26/2023 9/2/2023 9/9/2023 9/16/2023 9/23/2023 9/30/2023 10/7/2023 10/14/2023 10/21/2023 10/28/2023
Week
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Item Description of work
1 Work to raise the level of the existing ditch
1a Initial work:
mobilization of machinery x x
sign installation x x
construction of tire wash and related works, including
exit/entry and concrete walkways x x
2 Perimeter cleaning/perimeter fill x x
dig a perimeter trench up to the final sedimentation
and disposal pond x x
surrounding soil accumulation x x x

construction of perimeter reinforcement retaining walls x x x


build a temporary ditch in the embankment area
hold a bund
plant grass close to the slope
3 Main cleaning x x x x x x
clearing / cutting down trees x x x x x x x
dispose of unsuitable materials for development
excavate top soil and build stock storage
4 Landfilling and excavation x x x x x x x
transport red soil to the site x x x x x x x x x x
Landfilling and dredging, leveling and compacting the
formation level x x x x x x x x x x
5 Inspection for the last formation level with the
authorities
6 Maintenance x x x x x x x x x x x x x x x x x x

Note: The earthwork execution schedule is subject to the weather.