Republic of the Philippines

CITY ENGINREERING OFFICE


City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period__________________________

Supervision and Monitoring of Infrastructure Projects for the given period.

Expected Date Alloted CEO Date of


Tittle of Supervised Projects Name of Contractor Date of NTP
Source of of Completion Supervision Designation
Fund
Rehabilitation of drainage at Times Transit
Terminal at Sto Nino Slaughter House DRRMF Merjan Hambon 02-Oct-18 28-Dec-17 7,190 27-Dec-17
1 Barangay
Improvement of Alley Road at Block 1,
2 Middle Quirino Hill
Improvement of covered court @
3 Engineer's Hill Barangay
Construction of pavement with canal at
4 Purok 3 @ Pinsao Proper Barangay
Rehabilitation of sewer line at Yap street
5 @ South Sanitary Camp Barangay

Prepared by:

Laurence P. Chugyawi
Supervising Assistant

NOTED:

EDGAR VICTORIO R. OLPINDO


Acting City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947
Republic of the Philippines
CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period__________________________

Supervision and Monitoring of Infrastructure Projects for the given period.

Expected Date Alloted CEO Date of


Tittle of Supervised Projects Source of Name of Contractor Date of NTP of Completion Supervision Designation
Fund
Rehabilitation of drainage at Times Transit
1 Terminal at Sto Nino Slaughter House
Barangay
Improvement of Alley Road at Block 1,
2 Middle Quirino Hill
Improvement of covered court @
3 Engineer's Hill Barangay
Construction of pavement with canal at
4 Purok 3 @ Pinsao Proper Barangay
Rehabilitation of sewer line at Yap street
5 @ South Sanitary Camp Barangay

Prepared by:

Laurence P. Chugyawi
Supervising Assistant

NOTED:

EDGAR VICTORIO R. OLPINDO


Acting City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947
Percentage of
Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
New Expected date of completion)
Previous Present

56-64% 64-100% Project completed as of Jauary 16, 2018, Lapsed

Reviewed by:

Agustin D. Dulnuan
Engineer II
Percentage of
Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
New Expected date of completion)
Previous Present

Reviewed by:

Agustin D. Dulnuan
Engineer II
Republic of the Philippines
CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: January 16-31, 2018

Supervision and Monitoring of Infrastructure Projects for the given period.

Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Tittle of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

1 Rehabilitation of Slope Protection and Drainage at Santo 2017 DRRM FUND PECDASEN BUILDERS 13 DEC. 2017 25-Apr-18 95,627 27 Dec. 2017 0.01-6% 6-17.8% Project On-going
Tomas Central Barangay

2 Rehabilitation of Drainage System Along Dr. Carino St. Lower DRRMF 2017 JJJ-A CONSTRUCTION & 13 NOV. 2017 8 DEC. 2017 15,818 18 NOV. 2017 20-60% 60-100% Project Completed(Jan. 27, 2018), Project Lapsed
Q.M. Barangay SUPPLIES
3 Repair of Damaged Riprap at Purok 3 Barangay Padre Zamora, 2016 LDRRMF JJJ-A CONSTRUCTION & 27 OCT. 2017 26 NOV. 2017 70-75% 75-100% Project Completed(Jan 25, 2018), Project Lapsed
Baguio City SUPPLIES

Prepared by: Reviewed by:

Rodel Q. Lagare Richard L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

EDGAR VICTORIO R. OLPINDO


Acting City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: February 1-15, 2018

Supervision and Monitoring of Infrastructure Projects for the given period.

Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Tittle of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

1 Rehabilitation of Slope Protection and Drainage at Santo 2017 DRRM FUND PECDASEN BUILDERS 13 DEC. 2017 25-Apr-18 95,627 27 Dec. 2017 6-17.8% 17.8-30% Project On-going
Tomas Central Barangay
2 Restoration of Slope Road Protection Riprap/Widening at Ordinance No. 67 CPS ENGINEERING 31-Jan-18 16-Mar-18 31, 636 05-Feb-18 2% Project Suspended (Date of Suspension: February
Lower Atok Trail Turning Point Series of 2017 CONSTRUCTION 09,2018)

Prepared by: Reviewed by:

Rodel Q. Lagare Richard L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

EDGAR VICTORIO R. OLPINDO


Acting City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: February 16-28, 2018

Supervision and Monitoring of Infrastructure Projects for the given period.

Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Tittle of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

1 Rehabilitation of Slope Protection and Drainage at Santo 2017 DRRM FUND PECDASEN BUILDERS 13 DEC. 2017 25-Apr-18 95,627 27 Dec. 2017 17.8-30% 30-38.24% Project On-going
Tomas Central Barangay
2 Restoration of Slope Road Protection Riprap/Widening at Ordinance No. 67 CPS ENGINEERING 31-Jan-18 16-Mar-18 31, 636 05-Feb-18 0-2% 2-5% Project On-going (Date of Suspension: February
Lower Atok Trail Turning Point Series of 2017 CONSTRUCTION 09,2018: Date of Resumption: Febr. 21, 2018:
New Expected Date of Complition: March 28,
2018)

Prepared by: Reviewed by:

Rodel Q. Lagare Richard L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

EDGAR VICTORIO R. OLPINDO


Acting City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: March 1-15, 2018

Supervision and Monitoring of Infrastructure Projects for the given period.

Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Tittle of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

1 Rehabilitation of Slope Protection and Drainage at Santo 2017 DRRM FUND PECDASEN BUILDERS 13 DEC. 2017 25-Apr-18 95,627 27 Dec. 2017 30-38.24% 38.24-50.02% Project On-going
Tomas Central Barangay

Prepared by: Reviewed by:

Rodel Q. Lagare Richard L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

EDGAR VICTORIO R. OLPINDO


Acting City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: March 16-31, 2018

Supervision and Monitoring of Infrastructure Projects for the given period.

Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Tittle of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

1 Rehabilitation of Slope Protection and Drainage at Santo 2017 DRRM FUND PECDASEN BUILDERS 13 DEC. 2017 25-Apr-18 95,627 27 Dec. 2017 38.24-50.02% 38.24-50.08% Project On-going
Tomas Central Barangay

Prepared by: Reviewed by:

Rodel Q. Lagare Richard L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

EDGAR VICTORIO R. OLPINDO


Acting City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: April 1-15, 2018

Supervision and Monitoring of Infrastructure Projects for the given period.

Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Tittle of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
rate= 719
Previous Present no. of days charged = 103
1 Rehabilitation of Slope Protection and Drainage at Santo 2017 DRRM FUND PECDASEN BUILDERS 13 DEC. 2017 25-Apr-18 95,627 27 Dec. 2017 38.24-50.08% 50.08-54% Project On-going
Tomas Central Barangay total charge= 74057

CEO remaining= 21,570

Prepared by: Reviewed by:

Rodel Q. Lagare Richard L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

EDGAR VICTORIO R. OLPINDO


Acting City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: April 16-30, 2018

Supervision and Monitoring of Infrastructure Projects for the given period.

Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Tittle of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
rate= 719
Previous Present no. of days charged = 12
1 Rehabilitation of Slope Protection and Drainage at Santo 2017 DRRM FUND PECDASEN BUILDERS 13 DEC. 2017 25-Apr-18 95,627 27 Dec. 2017 50.08-54% 54-65% Project On-going
Tomas Central Barangay total charge= 8628
2 Concreting of Riverbeds along GEFA-Lower Q.M. Barangay IRA FUND Jose Virgilio Lusterio 12-Apr-18 20-May-18 14,380 16-Apr-18 0-60% Project On-going
CEO remaining= 5,752

Prepared by: Reviewed by:

Rodel Q. Lagare Richard L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

EDGAR VICTORIO R. OLPINDO


Acting City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: May 1-15, 2018

Supervision and Monitoring of Infrastructure Projects for the given period. STO TOMAS
rate= 719
no. of days charged = 2
Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Tittle of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present 74057
Rehabilitation of Slope Protection and Drainage at Santo 1438
1 Tomas Central Barangay 2017 DRRM FUND PECDASEN BUILDERS 13 DEC. 2017 25-Apr-18 95,627 27 Dec. 2017 54-65% 65-72.96% Project On-going
total charge= 75495
CEO remaining= 20,132
2 Concreting of Riverbeds along GEFA-Lower Q.M. Barangay IRA FUND Jose Virgilio Lusterio 12-Apr-18 20-May-18 14,380 16-Apr-18 0-60% 60-93.5% Project On-going
GEFA
rate= 719
no. of days charged = 8

Prepared by: Reviewed by: 8628


5752
Rodel Q. Lagare Richard L. Lardizabal total charge= 14380
Supervising Assistant Acting Maintenance Division Head CEO remaining= 0

NOTED:

EDGAR VICTORIO R. OLPINDO


Acting City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: May 16-31, 2018

Supervision and Monitoring of Infrastructure Projects for the given period. STO TOMAS
rate= 719
no. of days charged = 12
Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Tittle of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present 75495
charged 8628

Rehabilitation of Slope Protection and Drainage at Santo Project On-going (with 43 Days time extension
1 Tomas Central Barangay 2017 DRRM FUND PECDASEN BUILDERS 13 DEC. 2017 1-May-18 95,627 27 Dec. 2017 65-72.96% 72.96-76.2% due to change/extra work) New Expected Date of
Completion: June 13, 2018

total charged= 84123


CEO remaining= 11,504
2 Concreting of Riverbeds along GEFA-Lower Q.M. Barangay IRA FUND Jose Virgilio Lusterio 12-Apr-18 20-May-18 14,380 16-Apr-18 60-93.5% 93.5-100% Project Completed as of May 19, 2018

Prepared by: Reviewed by:

Rodel Q. Lagare Richard L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

EDGAR VICTORIO R. OLPINDO


Acting City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: June 1-15, 2018

Supervision and Monitoring of Infrastructure Projects for the given period. STO TOMAS
rate= 719
no. of days charged = 12
Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Tittle of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present 84123
charged 8628

1 Rehabilitation of Slope Protection and Drainage at Santo 2017 DRRM FUND PECDASEN BUILDERS 13 DEC. 2017 1-May-18 95,627 27 Dec. 2017 72.96-76.2% 76.2-84.30% Project On-Going (with 43 Days time extension
Tomas Central Barangay due to change/extra work)
total charged= 92751
CEO remaining= 2,876

2 Rehabilitation of Slope Protection at Upper Malvar, Aurora Hill 2016 LDRRMF NORRIS B. ANOYAN 13-Jun-18 1-Jul-18 5,752 14-Jun-18 0.10% Project On-Going
Barangay

Prepared by: Reviewed by:

Rodel Q. Lagare Richard L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

EDGAR VICTORIO R. OLPINDO


Acting City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: June 16-30, 2018
total alloted supervision 101,379
Supervision and Monitoring of Infrastructure Projects for the given period. STO TOMAS
rate= 719
no. of days charged = 12
Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present 92751
charged 8628

Project On-Going (with 43 Days time extension


1 Rehabilitation of Slope Protection and Drainage at Santo 2017 DRRM FUND PECDASEN BUILDERS 13 DEC. 2017 1-May-18 95,627 27 Dec. 2017 76.2-84.30% 84.30-88.84% due to change/extra work: with 35 days time
Tomas Central Barangay extension due to rainy/unworkable days) New
Expected date of Completion: July 18, 2018

total charged= 101379


CEO remaining= 0

Rehabilitation of Slope Protection at Upper Malvar, Aurora Hill Project On-Going (with 5 days time extension due
2 Barangay 2016 LDRRMF NORRIS B. ANOYAN 13-Jun-18 1-Jul-18 5,752 14-Jun-18 0.10% 0.1- 92% to rainy/unworkable days) New Expected Date of
Completion: July 6, 2018

3 Rehabilitation of Pavement at Upper Rock Quarry Barangay Ordinance No. 101


S.2017 ANTONIO P. NA-OY 21-Jun-18 12-Aug-18 35291.36 22-Jun-18 0-6.5% Project On-Going

Prepared by: Reviewed by:

Rodel Q. Lagare Richard L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

EDGAR VICTORIO R. OLPINDO


Acting City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: July 1-15, 2018
total alloted supervision 136,670
Supervision and Monitoring of Infrastructure Projects for the given period. STO TOMAS
rate= 740.09
no. of days charged = 11
Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present 101379
charged 8140.99

Project On-Going (with 43 Days time extension


1 Rehabilitation of Slope Protection and Drainage at Santo 2017 DRRM FUND PECDASEN BUILDERS 13 DEC. 2017 1-May-18 95,627 27 Dec. 2017 84.30-88.84% 88.84-94.10% due to change/extra work: with 35 days time
Tomas Central Barangay extension due to rainy/unworkable days) New
Expected date of Completion: July 18, 2018

total charged= 109520


CEO remaining= 27,150

2 Rehabilitation of Slope Protection at Upper Malvar, Aurora Hill 2016 LDRRMF NORRIS B. ANOYAN 13-Jun-18 1-Jul-18 5,752 14-Jun-18 0.1- 92% 92-100% Project Completed as of July 3, 2018
Barangay

3 Rehabilitation of Pavement at Upper Rock Quarry Barangay Ordinance No. 101


S.2017 ANTONIO P. NA-OY 21-Jun-18 12-Aug-18 35291.36 22-Jun-18 0-6.5% 6.5-35.20% Project On-Going

Prepared by: Reviewed by:

Rodel Q. Lagare Richard L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

EDGAR VICTORIO R. OLPINDO


Acting City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: July 16-31, 2018
total alloted supervision 130,918
Supervision and Monitoring of Infrastructure Projects for the given period. STO TOMAS
rate= 740.09
no. of days charged = 11.5
Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present 109520
charged 8511
Project Lapsed (with 43 Days time extension due
1 Rehabilitation of Slope Protection and Drainage at Santo 2017 DRRM FUND PECDASEN BUILDERS 13 DEC. 2017 1-May-18 95,627 27 Dec. 2017 88.84-94.10% 94.10-95.30% to change/extra work: with 35 days time
Tomas Central Barangay extension due to rainy/unworkable days) New
Expected date of Completion: July 18, 2018
total charged= 118031
CEO remaining= 12,887

2 Rehabilitation of Pavement at Upper Rock Quarry Barangay Ordinance No. 101


S.2017 ANTONIO P. NA-OY 21-Jun-18 12-Aug-18 35291.36 22-Jun-18 6.5-35.20% 35.20-57.60% Project On-Going

Prepared by: Reviewed by:

Rodel Q. Lagare Richard L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

EDGAR VICTORIO R. OLPINDO


Acting City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: August 1-15, 2018
total alloted supervision 130,918
Supervision and Monitoring of Infrastructure Projects for the given period. STO TOMAS
rate= 740.09
no. of days charged = 12
Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present 118031
charged 8881.08

Project Lapsed (with 43 Days time extension due


1 Rehabilitation of Slope Protection and Drainage at Santo 2017 DRRM FUND PECDASEN BUILDERS 13 DEC. 2017 1-May-18 95,627 27 Dec. 2017 94.10-95.30% 95.30-95.80% to change/extra work: with 35 days time
Tomas Central Barangay extension due to rainy/unworkable days) New
Expected date of Completion: July 18, 2018

total charged= 126912


CEO remaining= 4,006
Project On-going (with 4 days time extension due
2 Rehabilitation of Pavement at Upper Rock Quarry Barangay Ordinance No. 101
S.2017 ANTONIO P. NA-OY 21-Jun-18 12-Aug-18 35291.36 22-Jun-18 35.20-57.60% 57.60-78.20% to heavy monsoon rain on August 10 to 13, 2018)
New Expected Date of Completion: August 16,
2018

Prepared by: Reviewed by:

Rodel Q. Lagare Richard L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

EDGAR VICTORIO R. OLPINDO


Acting City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: August 16-31, 2018
total alloted supervision 159,678
Supervision and Monitoring of Infrastructure Projects for the given period. STO TOMAS
rate= 740.09
no. of days charged = 13
Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present 126912
charged 9621.17

Project Lapsed (with 43 Days time extension due


1 Rehabilitation of Slope Protection and Drainage at Santo 2017 DRRM FUND PECDASEN BUILDERS 13 DEC. 2017 1-May-18 95,627 27 Dec. 2017 95.30-95.80% 95.80-95.80% to change/extra work: with 35 days time
Tomas Central Barangay extension due to rainy/unworkable days) New
Expected date of Completion: July 18, 2018

total charged= 136533


CEO remaining= 23,145

Project On-going (with 21 days time extension


2 Rehabilitation of Pavement at Upper Rock Quarry Barangay Ordinance No. 101
S.2017 ANTONIO P. NA-OY 21-Jun-18 12-Aug-18 35291.36 22-Jun-18 57.60-78.20% 78.20-88% due to heavy monsoon rain on August 6 to 26,
2018) New Expected Date of Completion:
September 2, 2018

CEPMO 2016 Project On-going (with 17 days time extension


3 Parks Improvement (Rehabilitation of Arch Trellis) at Botanical DEVELOPMENT ANTONIO P. NA-OY 9-Aug-18 6-Oct-18 28760 16-Aug-18 0% due to heavy monsoon rain on August 9 to 26,
Garden, Leonard Woodroad FUND 2018) New Expected Date of Completion:
October 23, 2018

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

Edgar Victorio R. Olpindo


Acting City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: September 1-15, 2018
total alloted supervision 159,678
Supervision and Monitoring of Infrastructure Projects for the given period. STO TOMAS
rate= 740.09
no. of days charged = 12
Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present 136533
charged 8881.08

1 Rehabilitation of Slope Protection and Drainage at Santo 2017 DRRM FUND PECDASEN BUILDERS 13 DEC. 2017 1-May-18 95,627 27 Dec. 2017 95.80-95.80% 95.80-100% Project Completed as of September 8, 2018
Tomas Central Barangay

total charged= 145414


CEO remaining= 14,264

2 Rehabilitation of Pavement at Upper Rock Quarry Barangay Ordinance No. 101


S.2017 ANTONIO P. NA-OY 21-Jun-18 12-Aug-18 35291.36 22-Jun-18 78.20-88% 88-100% Project Completed as of September 2, 2018

CEPMO 2016 Project On-going (with 17 days time extension


3 Parks Improvement (Rehabilitation of Arch Trellis) at Botanical DEVELOPMENT ANTONIO P. NA-OY 9-Aug-18 6-Oct-18 28760 16-Aug-18 0-6.2% due to heavy monsoon rain on August 9 to 26,
Garden, Leonard Woodroad FUND 2018) New Expected Date of Completion:
October 23, 2018

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

Edgar Victorio R. Olpindo


Acting City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: September 16-30, 2018 total alloted supervision 28,760
STO TOMAS
Supervision and Monitoring of Infrastructure Projects for the given period. rate= 740.09
no. of days charged = 12
8881.08
Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
charged 8881.08
Previous Present tot charged 17762
remaining 10,998

CEPMO 2016 Project On-going (with 17 days time extension


1 Parks Improvement (Rehabilitation of Arch Trellis) at Botanical DEVELOPMENT ANTONIO P. NA-OY 9-Aug-18 6-Oct-18 28760 16-Aug-18 0-6.2% 6.2-33% due to heavy monsoon rain on August 9 to 26,
Garden, Leonard Woodroad FUND 2018) New Expected Date of Completion:
October 23, 2018

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: October 1-15, 2018 total alloted supervision 156,886
STO TOMAS
Supervision and Monitoring of Infrastructure Projects for the given period. rate= 740.09
no. of days charged = 12
Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
charged 8881.08
Previous Present tot charged 8881.08
remaining 148,005

1 Improvement of the Dairy Farm Transfer Station @ Dairy 2014 LDF Pecdasen Builders by: 26-Sep-18 23-Feb-19 111,000.00 29-Sep-18 0-14.8% Project On-going
Farm, Department of Agriculture, Dontogan Barangay Rudy Pecdasen

Rehabilitation of Slope Protection, Drainage and


2 DRRMF 2017 MAKK Builders by: 3-Oct-18 18-Dec-18 45,885.58 4-Oct-18 0-3.90% Project On-going
Pavement at Saint Joseph Street at Purok 24-A @ Purok
Angel O. Piluden
24 San Carlos Heights, Irisan Barangay

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947
Republic of the Philippines
CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: October 16-31, 2018 total alloted supervision 156,886
STO TOMAS
Supervision and Monitoring of Infrastructure Projects for the given period. rate= 740.09
no. of days charged = 11.5
8881.08
Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
charged 8511
Previous Present tot charged 17392
remaining 139,493

1 Improvement of the Dairy Farm Transfer Station @ Dairy 2014 LDF Pecdasen Builders by: 26-Sep-18 23-Feb-19 111,000.00 29-Sep-18 0-14.8% 14.8-50.1% Project On-going
Farm, Department of Agriculture, Dontogan Barangay Rudy Pecdasen

Rehabilitation of Slope Protection, Drainage and


2 DRRMF 2017 MAKK Builders by: 3-Oct-18 18-Dec-18 45,885.58 4-Oct-18 0-3.90% 3.90-20.12% Project On-going
Pavement at Saint Joseph Street at Purok 24-A @ Purok
Angel O. Piluden
24 San Carlos Heights, Irisan Barangay

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: November 1-15, 2018 total alloted supervision 156,886

Supervision and Monitoring of Infrastructure Projects for the given period. rate= 740.09
no. of days charged = 10
17392
Percentage of Completion
Expected Date of Alloted CEO REMARKS (On-going,Lapsed, SWO-date, RWO- Date, charged 7400.9
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present
tot charged 24793
remaining 132,093

1 Improvement of the Dairy Farm Transfer Station @ Dairy 2014 LDF Pecdasen Builders by: 26-Sep-18 23-Feb-19 111,000.00 29-Sep-18 14.8-50.1% 50.1-57.30% Project On-going
Farm, Department of Agriculture, Dontogan Barangay Rudy Pecdasen

Rehabilitation of Slope Protection, Drainage and


2 DRRMF 2017 MAKK Builders by: 3-Oct-18 18-Dec-18 45,885.58 4-Oct-18 3.90-20.12% 20.12-26% Project Suspended on Nov. 7, 2018, due to
Pavement at Saint Joseph Street at Purok 24-A @ Purok Preparation of Change Order
Angel O. Piluden
24 San Carlos Heights, Irisan Barangay

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: November 16-30, 2018 total alloted supervision 156,886

Supervision and Monitoring of Infrastructure Projects for the given period. rate= 740.09
no. of days charged = 12
24793
Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
charged 8881.08
Previous Present tot charged 33674
remaining 123,211

1 Improvement of the Dairy Farm Transfer Station @ Dairy 2014 LDF Pecdasen Builders by: 26-Sep-18 23-Feb-19 111,000.00 29-Sep-18 50.1-57.30% 57.30-59.70% Project On-going
Farm, Department of Agriculture, Dontogan Barangay Rudy Pecdasen

Rehabilitation of Slope Protection, Drainage and


2 DRRMF 2017 MAKK Builders by: 3-Oct-18 18-Dec-18 45,885.58 4-Oct-18 20.12-26% 20.12-61.20% Project Resumed on Nov. 19, 2018
Pavement at Saint Joseph Street at Purok 24-A @ Purok
Angel O. Piluden
24 San Carlos Heights, Irisan Barangay

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: December 1-15, 2018 total alloted supervision 156,886

Supervision and Monitoring of Infrastructure Projects for the given period. rate= 740.09
no. of days charged = 13
33674
Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
charged 9621.17
Previous Present tot charged 43295
remaining 113,590

1 Improvement of the Dairy Farm Transfer Station @ Dairy 2014 LDF Pecdasen Builders by: 26-Sep-18 23-Feb-19 111,000.00 29-Sep-18 57.30-59.70% 59.70-60.70% Project On-going
Farm, Department of Agriculture, Dontogan Barangay Rudy Pecdasen

Rehabilitation of Slope Protection, Drainage and


2 DRRMF 2017 MAKK Builders by: 3-Oct-18 18-Dec-18 45,885.58 4-Oct-18 20.12-61.20% 61.20-91% Project On-going (Resumed on Nov. 19,
Pavement at Saint Joseph Street at Purok 24-A @ Purok
Angel O. Piluden 2018)
24 San Carlos Heights, Irisan Barangay

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: December 16-31, 2018 total alloted supervision 156,886

Supervision and Monitoring of Infrastructure Projects for the given period. rate= 740.09
no. of days charged = 9
43295
Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
charged 6660.81
Previous Present tot charged 49956
remaining 106,930

1 Improvement of the Dairy Farm Transfer Station @ Dairy 2014 LDF Pecdasen Builders by: 26-Sep-18 23-Feb-19 111,000.00 29-Sep-18 59.70-60.70% 60.70-65.10% Project On-going
Farm, Department of Agriculture, Dontogan Barangay Rudy Pecdasen

Rehabilitation of Slope Protection, Drainage and


2 DRRMF 2017 MAKK Builders by: 3-Oct-18 18-Dec-18 45,885.58 4-Oct-18 61.20-91% 91-100% Project Completed (as of Dec. 21, 2018)
Pavement at Saint Joseph Street at Purok 24-A @ Purok
Angel O. Piluden
24 San Carlos Heights, Irisan Barangay

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: January 1-15, 2019 total alloted supervision 111,000

Supervision and Monitoring of Infrastructure Projects for the given period. rate= 740.09
no. of days charged = 9
49956
Percentage of Completion
Expected Date of Alloted CEO REMARKS (On-going,Lapsed, SWO-date, RWO- Date, charged 6660.81
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present
tot charged 56617
remaining 54,383

1 Improvement of the Dairy Farm Transfer Station @ Dairy 2014 LDF Pecdasen Builders by: 26-Sep-18 23-Feb-19 111,000.00 29-Sep-18 60.70-65.10% 65.10-70% Project On-going
Farm, Department of Agriculture, Dontogan Barangay Rudy Pecdasen

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: January 16-31, 2019 total alloted supervision 111,000

Supervision and Monitoring of Infrastructure Projects for the given period. rate= 740.09
no. of days charged = 9
6660.81
Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
charged 6660.81
Previous Present tot charged 13322
remaining 97,678

1 Improvement of the Dairy Farm Transfer Station @ Dairy 2014 LDF Pecdasen Builders by: 26-Sep-18 23-Feb-19 111,000.00 29-Sep-18 65.10-70% 70-82.63% Project On-going
Farm, Department of Agriculture, Dontogan Barangay Rudy Pecdasen

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: February 1-15, 2019 total alloted supervision 111,000

Supervision and Monitoring of Infrastructure Projects for the given period. rate= 740.09
no. of days charged = 9
6660.81
Percentage of Completion
Expected Date of Alloted CEO REMARKS (On-going,Lapsed, SWO-date, RWO- Date, charged 6660.81
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present
tot charged 13322
remaining 97,678

1 Improvement of the Dairy Farm Transfer Station @ Dairy 2014 LDF Pecdasen Builders by: 26-Sep-18 23-Feb-19 111,000.00 29-Sep-18 70-82.63% 82.63-89.0% Project On-going
Farm, Department of Agriculture, Dontogan Barangay Rudy Pecdasen

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: February 16-28, 2019 total alloted supervision 152,445

Supervision and Monitoring of Infrastructure Projects for the given period. rate= 740.09
no. of days charged = 9
6660.81
Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
charged 6660.81
Previous Present tot charged 13322
remaining 139,123

1 Improvement of the Dairy Farm Transfer Station @ Dairy 2014 LDF Pecdasen Builders by: 26-Sep-18 23-Feb-19 111,000.00 29-Sep-18 82.63-89.0% 89.0-91.0% Project On-going
Farm, Department of Agriculture, Dontogan Barangay Rudy Pecdasen
19-010
2 Repair and Improvement of Road at Purok 8, Kias Infrastructure NORBANO Builders by: 19-Feb-19 16-Apr-19 41,445.04 20-Feb-19 0-12.20% Project On-going
Barangay Assets (Capital Norris B. Anoyan
Outlay)

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: March 1-15, 2019 total alloted supervision 152,445

Supervision and Monitoring of Infrastructure Projects for the given period. rate= 740.09
no. of days charged = 9
6660.81
Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
charged 6660.81
Previous Present tot charged 13322
remaining 139,123

1 Improvement of the Dairy Farm Transfer Station @ Dairy 2014 LDF Pecdasen Builders by: 26-Sep-18 23-Feb-19 111,000.00 29-Sep-18 89.0-91.0% 91.0-92.15% Project Lapsed on March 15, 2019
Farm, Department of Agriculture, Dontogan Barangay Rudy Pecdasen

19-010
2 Repair and Improvement of Road at Purok 8, Kias Infrastructure NORBANO Builders by: 19-Feb-19 16-Apr-19 41,445.04 20-Feb-19 0-12.20% 12.20-21% Project On-going
Barangay Assets (Capital Norris B. Anoyan
Outlay)

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: March 16-31, 2019 total alloted supervision 152,445

Supervision and Monitoring of Infrastructure Projects for the given period. rate= 740.09
no. of days charged = 9
139123
Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
charged 6660.81
Previous Present tot charged 145784
remaining 6,661

1 Improvement of the Dairy Farm Transfer Station @ Dairy 2014 LDF Pecdasen Builders by: 26-Sep-18 23-Feb-19 111,000.00 29-Sep-18 91.0-92.15% 92.15-93.60% Project Lapsed on March 15, 2019
Farm, Department of Agriculture, Dontogan Barangay Rudy Pecdasen

19-010
2 Repair and Improvement of Road at Purok 8, Kias Infrastructure NORBANO Builders by: 19-Feb-19 16-Apr-19 41,445.04 20-Feb-19 12.20-21% 21-56.70% Project On-going
Barangay Assets (Capital Norris B. Anoyan
Outlay)

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: April 1-15, 2019 total alloted supervision 152,445

Supervision and Monitoring of Infrastructure Projects for the given period. rate= 740.09
no. of days charged = 9
6660.81
Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
charged 6660.81
Previous Present tot charged 13322
remaining 139,123

1 Improvement of the Dairy Farm Transfer Station @ Dairy 2014 LDF Pecdasen Builders by: 26-Sep-18 23-Feb-19 111,000.00 29-Sep-18 92.15-93.60% 93.60-94.45% Project Lapsed on March 15, 2019
Farm, Department of Agriculture, Dontogan Barangay Rudy Pecdasen

19-010
2 Repair and Improvement of Road at Purok 8, Kias Infrastructure NORBANO Builders by: 19-Feb-19 16-Apr-19 41,445.04 20-Feb-19 21-56.70% 56.70-97.00% Project On-going
Barangay Assets (Capital Norris B. Anoyan
Outlay)

Concrete Water Impounding Structure (Impounding of


3 CEPMO Capital MHIGS Construction 4-Apr-19 13-Jun-19 51,806.30 5-Apr-19 0-3.10% Project On-going
Water Spring from the Japanese Tunnel and Rainwater) at
Outlay 2018 by: Miguel A. Kiswa
Botanical Garden

4 Rehabilitation of Modesta Street, Mines View Barangay 2018 LDF Bao-idang Construction 26-Feb-19 10-Jun-19 76,960.00 1-Apr-19 0-6.30% Project On-going (with 3rd notice dated
by Agusto B. Bao-idang March 26, 2019)

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: April 16-30, 2019 total alloted supervision 152,445

Supervision and Monitoring of Infrastructure Projects for the given period. rate= 740.09
no. of days charged = 9
13322
Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
charged 6660.81
Previous Present tot charged 19982
remaining 132,463
1 Improvement of the Dairy Farm Transfer Station @ Dairy 2014 LDF Pecdasen Builders by: 26-Sep-18 23-Feb-19 111,000.00 29-Sep-18 93.60-94.45% 94.45-97.30% Project Lapsed on March 15, 2019
Farm, Department of Agriculture, Dontogan Barangay Rudy Pecdasen

19-010
2 Repair and Improvement of Road at Purok 8, Kias Infrastructure NORBANO Builders by: 19-Feb-19 16-Apr-19 41,445.04 20-Feb-19 56.70-97.00% 97.00-100% Project Completed on April 16,2019
Barangay Assets (Capital Norris B. Anoyan
Outlay)

Concrete Water Impounding Structure (Impounding of


3 CEPMO Capital MHIGS Construction 4-Apr-19 13-Jun-19 51,806.30 5-Apr-19 0-3.10% 3.10-26.95% Project On-going
Water Spring from the Japanese Tunnel and Rainwater) at
Outlay 2018 by: Miguel A. Kiswa
Botanical Garden

4 Rehabilitation of Modesta Street, Mines View Barangay 2018 LDF Bao-idang Construction 26-Feb-19 10-Jun-19 76,960.00 1-Apr-19 0-6.30% 6.30-20.55% Project On-going (with 3rd notice dated
by Agusto B. Bao-idang March 26, 2019)

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: May 1-15, 2019 total alloted supervision #REF!

Supervision and Monitoring of Infrastructure Projects for the given period. rate= 740.09
no. of days charged = 9
0
Percentage of Completion
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Expected Date of Alloted CEO Date of Designation REMARKS (On-going,Lapsed, SWO-date, RWO- Date, charged 6660.81
Completion Supervision New Expected date of completion)
Previous Present
tot charged 6660.81
remaining #REF!
1 Improvement of the Dairy Farm Transfer Station @ Dairy 2014 LDF Pecdasen Builders by: 26-Sep-18 23-Feb-19 111,000.00 29-Sep-18 94.45-97.30% 97.30-98.10% Project Lapsed on March 15, 2019
Farm, Department of Agriculture, Dontogan Barangay Rudy Pecdasen

Concrete Water Impounding Structure (Impounding of


2 CEPMO Capital MHIGS Construction 4-Apr-19 13-Jun-19 51,806.30 5-Apr-19 3.10-26.95% 26.95-47.30% Project On-going
Water Spring from the Japanese Tunnel and Rainwater) at
Outlay 2018 by: Miguel A. Kiswa
Botanical Garden

3 Rehabilitation of Modesta Street, Mines View Barangay 2018 LDF Bao-idang Construction 26-Feb-19 10-Jun-19 76,960.00 1-Apr-19 6.30-20.55% 20.55-27.19% Project On-going (with 3rd notice dated
by Agusto B. Bao-idang March 26, 2019)

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: May 16-31, 2019 total alloted supervision #REF!

Supervision and Monitoring of Infrastructure Projects for the given period. rate= 740.09
no. of days charged = 9
#REF!
Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
charged 6660.81
Previous Present tot charged #REF!
remaining #REF!
1 Improvement of the Dairy Farm Transfer Station @ Dairy 2014 LDF Pecdasen Builders by: 26-Sep-18 23-Feb-19 111,000.00 29-Sep-18 97.30-98.10% 98.10-100% Project Completed on May 25, 2019
Farm, Department of Agriculture, Dontogan Barangay Rudy Pecdasen

Concrete Water Impounding Structure (Impounding of


2 CEPMO Capital MHIGS Construction 4-Apr-19 13-Jun-19 51,806.30 5-Apr-19 26.95-47.30% 47.30-75.92% Project On-going
Water Spring from the Japanese Tunnel and Rainwater) at
Outlay 2018 by: Miguel A. Kiswa
Botanical Garden

3 Rehabilitation of Modesta Street, Mines View Barangay 2018 LDF Bao-idang Construction 26-Feb-19 10-Jun-19 76,960.00 1-Apr-19 20.55-27.19% 27.19-42.44% Project On-going
by Agusto B. Bao-idang

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: June 1-15, 2019

Supervision and Monitoring of Infrastructure Projects for the given period.

Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

Repair and Rehabilitation of River Bank Protection Along APN Construction


1 Camp 8 Creek Towards Bued River Near Busacay 2018 CDRRMF QRF Supply and Aggregates 21-May-19 6-Dec-19 147,260.00 3-Jun-19 0.00-1.80% Project On-going
Residence at Camp 8, Baguio City by Antonio P. Naoy

Concrete Water Impounding Structure (Impounding of


2 CEPMO Capital MHIGS Construction 4-Apr-19 13-Jun-19 51,806.30 5-Apr-19 47.30-75.92% 75.92-85.15% Project On-going
Water Spring from the Japanese Tunnel and Rainwater) at
Outlay 2018 by: Miguel A. Kiswa
Botanical Garden

3 Rehabilitation of Modesta Street, Mines View Barangay 2018 LDF Bao-idang Construction 26-Feb-19 10-Jun-19 76,960.00 1-Apr-19 27.19-42.44% 42.44-73.80% Project On-going
by Agusto B. Bao-idang

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:
Edgar Victorio R. Olpindo
City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: June 16-30, 2019

Supervision and Monitoring of Infrastructure Projects for the given period.

Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

Repair and Rehabilitation of River Bank Protection Along APN Construction


1 Camp 8 Creek Towards Bued River Near Busacay 2018 CDRRMF QRF Supply and Aggregates 21-May-19 6-Dec-19 147,260.00 3-Jun-19 0.00-1.80% 1.80-5.70% Project On-going
Residence at Camp 8, Baguio City by Antonio P. Naoy

Concrete Water Impounding Structure (Impounding of


2 CEPMO Capital MHIGS Construction 4-Apr-19 13-Jun-19 51,806.30 5-Apr-19 75.92-85.15% 85.15-100% Project Completed on June 29, 2019
Water Spring from the Japanese Tunnel and Rainwater) at
Outlay 2018 by: Miguel A. Kiswa
Botanical Garden

3 Rehabilitation of Modesta Street, Mines View Barangay 2018 LDF Bao-idang Construction 26-Feb-19 10-Jun-19 76,960.00 1-Apr-19 42.44-73.80% 73.80-97.70% Project Lapsed on June 27,2019
by Agusto B. Bao-idang

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: July 1-15, 2019

Supervision and Monitoring of Infrastructure Projects for the given period.

Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

Repair and Rehabilitation of River Bank Protection Along APN Construction


1 Camp 8 Creek Towards Bued River Near Busacay 2018 CDRRMF QRF Supply and Aggregates 21-May-19 6-Dec-19 147,260.00 3-Jun-19 1.80-5.70% 5.70-9.43% Project On-going
Residence at Camp 8, Baguio City by Antonio P. Naoy

2 Rehabilitation of Modesta Street, Mines View Barangay 2018 LDF Bao-idang Construction 26-Feb-19 10-Jun-19 76,960.00 1-Apr-19 73.80-97.70% 97.70-100% Project Completed on July 5,2019
by Agusto B. Bao-idang

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: July 16-31, 2019

Supervision and Monitoring of Infrastructure Projects for the given period.

Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

Repair and Rehabilitation of River Bank Protection Along APN Construction


1 Camp 8 Creek Towards Bued River Near Busacay 2018 CDRRMF QRF Supply and Aggregates 21-May-19 6-Dec-19 147,260.00 3-Jun-19 5.70-9.43% 9.43-16.54% Project On-going
Residence at Camp 8, Baguio City by Antonio P. Naoy

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: August 1-15, 2019

Supervision and Monitoring of Infrastructure Projects for the given period.

Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

Repair and Rehabilitation of River Bank Protection Along APN Construction


1 Camp 8 Creek Towards Bued River Near Busacay 2018 CDRRMF QRF Supply and Aggregates 21-May-19 6-Dec-19 147,260.00 3-Jun-19 9.43-16.54% 16.54-19.10% Project On-going
Residence at Camp 8, Baguio City by Antonio P. Naoy

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: August 16-31, 2019

Supervision and Monitoring of Infrastructure Projects for the given period.

Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

Repair and Rehabilitation of River Bank Protection Along APN Construction Project On-going (with time extension due to
1 Camp 8 Creek Towards Bued River Near Busacay 2018 CDRRMF QRF Supply and Aggregates 21-May-19 6-Dec-19 147,260.00 3-Jun-19 16.54-19.10% 19.10-30.19% rains),New Expected Date of Completion;
Residence at Camp 8, Baguio City by Antonio P. Naoy Feb. 5, 2020

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: Septembe r 1-15, 2019

Supervision and Monitoring of Infrastructure Projects for the given period.

Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

Repair and Rehabilitation of River Bank Protection Along APN Construction Project On-going (with time extension due to
1 Camp 8 Creek Towards Bued River Near Busacay 2018 CDRRMF QRF Supply and Aggregates 21-May-19 6-Dec-19 147,260.00 3-Jun-19 19.10-30.19% 30.19-34.80% rains),New Expected Date of Completion;
Residence at Camp 8, Baguio City by Antonio P. Naoy Feb. 5, 2020

(a) Repair and Rehabilitation of Eroded Shoulder Near


Wagner Masing's Residence; (b) Repair and
2 Rehabilitation of Eroded Road Side Slope Near Nito 2019 LDF MHIGS Construction 2-Sep-19 14-Oct-19 15,540.00 3-Sep-19 0.00-24.20% Project On-going
Simeon Residence and; © Repair and Rehabilitation of by: Miguel A. Kiswa
Eroded Pavement Near benjamin Olsino's Residence @
Sitio Bilis, Santo Tomas Central Barangay

3 Restoration and Rehabilitation of Eroded Road Shoulder IRA Fund B.B Lat-iw Construction 7-Aug-19 22-Sep-19 18,694.00 1-Sep-19 52.25-64.30% 64.30-68.20% Project On-going
at Sepic Street @ Campo Filipino Barangay

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: Septembe r 16-30, 2019

Supervision and Monitoring of Infrastructure Projects for the given period.

Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

Repair and Rehabilitation of River Bank Protection Along APN Construction Project On-going (with time extension due to
1 Camp 8 Creek Towards Bued River Near Busacay 2018 CDRRMF QRF Supply and Aggregates 21-May-19 6-Dec-19 147,260.00 3-Jun-19 30.19-34.80% 34.80-38.40% rains),New Expected Date of Completion;
Residence at Camp 8, Baguio City by Antonio P. Naoy Feb. 5, 2020

(a) Repair and Rehabilitation of Eroded Shoulder Near


Wagner Masing's Residence; (b) Repair and
2 Rehabilitation of Eroded Road Side Slope Near Nito 2019 LDF MHIGS Construction 2-Sep-19 14-Oct-19 15,540.00 3-Sep-19 0.00-24.20% 24.20-74.80% Project On-going
Simeon Residence and; © Repair and Rehabilitation of by: Miguel A. Kiswa
Eroded Pavement Near benjamin Olsino's Residence @
Sitio Bilis, Santo Tomas Central Barangay

3 Restoration and Rehabilitation of Eroded Road Shoulder IRA Fund B.B Lat-iw Construction 7-Aug-19 22-Sep-19 18,694.00 1-Sep-19 64.30-68.20% 68.20-100% Project Completed on Sept. 20, 2019
at Sepic Street @ Campo Filipino Barangay

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: October 1-15, 2019

Supervision and Monitoring of Infrastructure Projects for the given period.

Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

Repair and Rehabilitation of River Bank Protection Along APN Construction Project On-going (with time extension due to
1 Camp 8 Creek Towards Bued River Near Busacay 2018 CDRRMF QRF Supply and Aggregates 21-May-19 6-Dec-19 147,260.00 3-Jun-19 34.80-38.40% 38.40-45.63% rains),New Expected Date of Completion;
Residence at Camp 8, Baguio City by Antonio P. Naoy Feb. 5, 2020
(a) Repair and Rehabilitation of Eroded Shoulder Near
Wagner Masing's Residence; (b) Repair and
2 Rehabilitation of Eroded Road Side Slope Near Nito 2019 LDF MHIGS Construction 2-Sep-19 14-Oct-19 15,540.00 3-Sep-19 24.20-74.80% 74.80-91.32% Project On-going
Simeon Residence and; © Repair and Rehabilitation of by: Miguel A. Kiswa
Eroded Pavement Near benjamin Olsino's Residence @
Sitio Bilis, Santo Tomas Central Barangay

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Acting Maintenance Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE device
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: October 16-31, 2019

Supervision and Monitoring of Infrastructure Projects for the given period.

Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

Repair and Rehabilitation of River Bank Protection Along APN Construction Project On-going (with time extension due to
1 Camp 8 Creek Towards Bued River Near Busacay 2018 CDRRMF QRF Supply and Aggregates 21-May-19 6-Dec-19 147,260.00 3-Jun-19 45.63-48.10% 48.10-53.00% rains),New Expected Date of Completion;
Residence at Camp 8, Baguio City by Antonio P. Naoy Feb. 5, 2020

(a) Repair and Rehabilitation of Eroded Shoulder Near


Wagner Masing's Residence; (b) Repair and
Project Suspended on October 11, 2019 due
2 Rehabilitation of Eroded Road Side Slope Near Nito 2019 LDF MHIGS Construction 2-Sep-19 14-Oct-19 15,540.00 3-Sep-19 91.32-91.32% 91.32-91.32% to pending preparation and approval of
Simeon Residence and; © Repair and Rehabilitation of by: Miguel A. Kiswa
change order
Eroded Pavement Near benjamin Olsino's Residence @
Sitio Bilis, Santo Tomas Central Barangay

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant OIC-Maintenance Division

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT

For the Period: November 1-15, 2019

Supervision and Monitoring of Infrastructure Projects for the given period.

Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

Repair and Rehabilitation of River Bank Protection Along APN Construction Project On-going (with time extension due to
1 Camp 8 Creek Towards Bued River Near Busacay 2018 CDRRMF QRF Supply and Aggregates 21-May-19 6-Dec-19 147,260.00 3-Jun-19 45.63-48.10% 48.10-53.00% rains),New Expected Date of Completion;
Residence at Camp 8, Baguio City by Antonio P. Naoy Feb. 5, 2020

(a) Repair and Rehabilitation of Eroded Shoulder Near


Wagner Masing's Residence; (b) Repair and
Project Suspended on October 11, 2019 due
2 Rehabilitation of Eroded Road Side Slope Near Nito 2019 LDF MHIGS Construction 2-Sep-19 14-Oct-19 15,540.00 3-Sep-19 91.32-91.32% 91.32-91.32% to pending preparation and approval of
Simeon Residence and; © Repair and Rehabilitation of by: Miguel A. Kiswa
change order
Eroded Pavement Near benjamin Olsino's Residence @
Sitio Bilis, Santo Tomas Central Barangay

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant OIC-Maintenance Division

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT

For the Period: November 16-30, 2019

Supervision and Monitoring of Infrastructure Projects for the given period.

Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

Repair and Rehabilitation of River Bank Protection Along APN Construction Project On-going (with time extension due to
1 Camp 8 Creek Towards Bued River Near Busacay 2018 CDRRMF QRF Supply and Aggregates 21-May-19 6-Dec-19 147,260.00 3-Jun-19 48.10-53.00% 53.00-53.60% rains),New Expected Date of Completion;
Residence at Camp 8, Baguio City by Antonio P. Naoy Feb. 5, 2020

(a) Repair and Rehabilitation of Eroded Shoulder Near


Wagner Masing's Residence; (b) Repair and
2 Rehabilitation of Eroded Road Side Slope Near Nito 2019 LDF MHIGS Construction 2-Sep-19 14-Oct-19 15,540.00 3-Sep-19 91.32-91.32% 91.32-98.5% Project Resume on November 28, 2019,
Simeon Residence and; © Repair and Rehabilitation of by: Miguel A. Kiswa
Eroded Pavement Near benjamin Olsino's Residence @
Sitio Bilis, Santo Tomas Central Barangay

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant OIC-Maintenance Division

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: December 1-15, 2019

Supervision and Monitoring of Infrastructure Projects for the given period.

Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

Repair and Rehabilitation of River Bank Protection Along APN Construction Project Suspended on Novemeber 25, 2019
1 Camp 8 Creek Towards Bued River Near Busacay 2018 CDRRMF QRF Supply and Aggregates 21-May-19 6-Dec-19 147,260.00 3-Jun-19 53.00-53.60% 53.60-53.60% pending the preparation and approval of
Residence at Camp 8, Baguio City by Antonio P. Naoy change order

(a) Repair and Rehabilitation of Eroded Shoulder Near


Wagner Masing's Residence; (b) Repair and
2 Rehabilitation of Eroded Road Side Slope Near Nito 2019 LDF MHIGS Construction 2-Sep-19 14-Oct-19 15,540.00 3-Sep-19 91.32-98.5% 98.5-100% Project Completed on Dec. 2, 2019
Simeon Residence and; © Repair and Rehabilitation of by: Miguel A. Kiswa
Eroded Pavement Near benjamin Olsino's Residence @
Sitio Bilis, Santo Tomas Central Barangay

3 Repair and Rehabilitation of Hanging Creek Bridge and 2019 DRRMF MHIGS Construction 6-Nov-19 10-Jan-20 51,350.65 2-Dec-19 12.20-34.50% 34.50-55.46% Project On-going
Flood Control at Camp 7 Barangay by: Miguel A. Kiswa

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant OIC-Maintenance Division

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: December 16-31, 2019

Supervision and Monitoring of Infrastructure Projects for the given period.

Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

Repair and Rehabilitation of River Bank Protection Along APN Construction Project Suspended on Novemeber 25, 2019
1 Camp 8 Creek Towards Bued River Near Busacay 2018 CDRRMF QRF Supply and Aggregates 21-May-19 6-Dec-19 147,260.00 3-Jun-19 53.00-53.60% 53.60-53.60% pending the preparation and approval of
Residence at Camp 8, Baguio City by Antonio P. Naoy change order

2 Repair and Rehabilitation of Hanging Creek Bridge and 2019 DRRMF MHIGS Construction 6-Nov-19 10-Jan-20 51,350.65 2-Dec-19 34.50-55.46% 55.46-82.10% Project On-going
Flood Control at Camp 7 Barangay by: Miguel A. Kiswa

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant OIC-Maintenance Division

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: January 1-15,2020

Supervision and Monitoring of Infrastructure Projects for the given period.


Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

Repair and Rehabilitation of River Bank Protection Along APN Construction Project Suspended on Novemeber 25, 2019
1 Camp 8 Creek Towards Bued River Near Busacay 2018 CDRRMF QRF Supply and Aggregates 21-May-19 6-Dec-19 147,260.00 3-Jun-19 53.00-53.60% 53.60-53.60% pending the preparation and approval of
Residence at Camp 8, Baguio City by Antonio P. Naoy change order

Project Suspended on December 12, 2019


2 Repair and Rehabilitation of Hanging Creek Bridge and 2019 DRRMF MHIGS Construction 6-Nov-19 10-Jan-20 51,350.65 2-Dec-19 55.46-82.10% 82.10-82.10% pending the preparation and approval of
Flood Control at Camp 7 Barangay by: Miguel A. Kiswa
change order

G.A. FLORES
3 Rehabilitation of Pavement at Lexber Heights 2018 LDF 30-Sep-19 17-Feb-20 66,690.00 2-Jan-20 42.10-50.35% 50.35-61.62% Project On-going(Project Resumed on
Construction, Inc. by:
Subdivision Road at Camp 7 Barangay November 11, 2019)
Glenliel Flores

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant OIC-Maintenance Division

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: January 16-31,2020

Supervision and Monitoring of Infrastructure Projects for the given period.


Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

Repair and Rehabilitation of River Bank Protection Along APN Construction Project Suspended on Novemeber 25, 2019
1 Camp 8 Creek Towards Bued River Near Busacay 2018 CDRRMF QRF Supply and Aggregates 21-May-19 6-Dec-19 147,260.00 3-Jun-19 53.00-53.60% 53.60-53.60% pending the preparation and approval of
Residence at Camp 8, Baguio City by Antonio P. Naoy change order

Project Suspended on December 12, 2019


2 Repair and Rehabilitation of Hanging Creek Bridge and 2019 DRRMF MHIGS Construction 6-Nov-19 10-Jan-20 51,350.65 2-Dec-19 55.46-82.10% 82.10-82.10% pending the preparation and approval of
Flood Control at Camp 7 Barangay by: Miguel A. Kiswa
change order

G.A. FLORES
3 Rehabilitation of Pavement at Lexber Heights 2018 LDF 30-Sep-19 17-Feb-20 66,690.00 2-Jan-20 50.35-61.62% 61.62-92.23% Project On-going(Project Resumed on
Construction, Inc. by:
Subdivision Road at Camp 7 Barangay November 11, 2019)
Glenliel Flores
Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant OIC-Maintenance Division

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: February 1-15, 2020

Supervision and Monitoring of Infrastructure Projects for the given period.


Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

Repair and Rehabilitation of River Bank Protection Along APN Construction Project Suspended on Novemeber 25, 2019
1 Camp 8 Creek Towards Bued River Near Busacay 2018 CDRRMF QRF Supply and Aggregates 21-May-19 6-Dec-19 147,260.00 3-Jun-19 53.00-53.60% 53.60-53.60% pending the preparation and approval of
Residence at Camp 8, Baguio City by Antonio P. Naoy change order

Project Suspended on December 12, 2019


2 Repair and Rehabilitation of Hanging Creek Bridge and 2019 DRRMF MHIGS Construction 6-Nov-19 10-Jan-20 51,350.65 2-Dec-19 55.46-82.10% 82.10-82.10% pending the preparation and approval of
Flood Control at Camp 7 Barangay by: Miguel A. Kiswa
change order

Post Closure Maintenance of Irisan Facility / Benching


3 LDF 2011 & LDF RAJCE Construction by: 16-Jan-20 9-Jul-20 131,017.56 27-Jan-20 0.00-6.32% 6.32-9.60% Project On-going
and Stabilization and Post Closure of Irisan Dumpsite
2014 Rowald A. Julian
(First Phase) at Irisan Barangay

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant OIC-Maintenance Division

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: February 16-29, 2020

Supervision and Monitoring of Infrastructure Projects for the given period.


Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

Repair and Rehabilitation of River Bank Protection Along APN Construction


1 Camp 8 Creek Towards Bued River Near Busacay 2018 CDRRMF QRF Supply and Aggregates 21-May-19 6-Dec-19 147,260.00 3-Jun-19 53.00-53.60% 53.60-53.80% Project Resumed on February 25, 2020
Residence at Camp 8, Baguio City by Antonio P. Naoy

Project Suspended on December 12, 2019


2 Repair and Rehabilitation of Hanging Creek Bridge and 2019 DRRMF MHIGS Construction 6-Nov-19 10-Jan-20 51,350.65 2-Dec-19 55.46-82.10% 82.10-82.10% pending the preparation and approval of
Flood Control at Camp 7 Barangay by: Miguel A. Kiswa
change order

Post Closure Maintenance of Irisan Facility / Benching


3 LDF 2011 & LDF RAJCE Construction by: 16-Jan-20 9-Jul-20 131,017.56 27-Jan-20 6.32-9.60% 9.60-11.70% Project On-going
and Stabilization and Post Closure of Irisan Dumpsite
2014 Rowald A. Julian
(First Phase) at Irisan Barangay

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant OIC-Maintenance Division

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: March 1-15, 2020

Supervision and Monitoring of Infrastructure Projects for the given period.


Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

Repair and Rehabilitation of River Bank Protection Along APN Construction


1 2018 CDRRMF QRF Supply and Aggregates 21-May-19 6-Dec-19 147,260.00 3-Jun-19 53.60-53.80% 53.80-75.10% Project On-going (Project Resumed on
Camp 8 Creek Towards Bued River Near Busacay
February 25, 2020)
Residence at Camp 8, Baguio City by Antonio P. Naoy

Project Suspended on December 12, 2019


2 Repair and Rehabilitation of Hanging Creek Bridge and 2019 DRRMF MHIGS Construction 6-Nov-19 10-Jan-20 51,350.65 2-Dec-19 82.10-82.10% 82.10-82.10% pending preparation and approval of change
Flood Control at Camp 7 Barangay by: Miguel A. Kiswa
order

Project Suspended due to pending


Post Closure Maintenance of Irisan Facility / Benching
3 LDF 2011 & LDF RAJCE Construction by: 16-Jan-20 9-Jul-20 131,017.56 27-Jan-20 9.60-11.70% 11.70-16.20% preparation and approval of change order to
and Stabilization and Post Closure of Irisan Dumpsite
2014 Rowald A. Julian include installation of methane gas exhaust
(First Phase) at Irisan Barangay
holes

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant OIC-Maintenance Division

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: June 1-15, 2020

Supervision and Monitoring of Infrastructure Projects for the given period.


Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

Post Closure Maintenance of Irisan Facility / Benching


1 LDF 2011 & LDF RAJCE Construction by: 16-Jan-20 9-Jul-20 131,017.56 27-Jan-20 11.70-16.20% 16.20-13.10% Project On-going
and Stabilization and Post Closure of Irisan Dumpsite
2014 Rowald A. Julian
(First Phase) at Irisan Barangay

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant OIC-Maintenance Division

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: June 16-30, 2020

Supervision and Monitoring of Infrastructure Projects for the given period.


Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

Post Closure Maintenance of Irisan Facility / Benching


1 LDF 2011 & LDF RAJCE Construction by: 16-Jan-20 9-Jul-20 131,017.56 27-Jan-20 16.20-13.10% 13.10-16.56% Project On-going
and Stabilization and Post Closure of Irisan Dumpsite
2014 Rowald A. Julian
(First Phase) at Irisan Barangay

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant OIC-Maintenance Division

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: July 1-15, 2020

Supervision and Monitoring of Infrastructure Projects for the given period.


Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

Post Closure Maintenance of Irisan Facility / Benching


1 LDF 2011 & LDF RAJCE Construction by: 16-Jan-20 9-Jul-20 131,017.56 27-Jan-20 13.10-16.56% 16.56-22.85% Project On-going
and Stabilization and Post Closure of Irisan Dumpsite
2014 Rowald A. Julian
(First Phase) at Irisan Barangay

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: July 16-31, 2020

Supervision and Monitoring of Infrastructure Projects for the given period.


Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

Post Closure Maintenance of Irisan Facility / Benching


1 LDF 2011 & LDF RAJCE Construction by: 16-Jan-20 26-Dec-20 131,017.56 27-Jan-20 16.56-22.85% 22.85-28.73% Project On-going
and Stabilization and Post Closure of Irisan Dumpsite
2014 Rowald A. Julian
(First Phase) at Irisan Barangay

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: August 1-15, 2020

Supervision and Monitoring of Infrastructure Projects for the given period.


Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

Post Closure Maintenance of Irisan Facility / Benching


1 LDF 2011 & LDF RAJCE Construction by: 16-Jan-20 26-Dec-20 131,017.56 27-Jan-20 22.85-28.73% 28.73-34.45% Project On-going
and Stabilization and Post Closure of Irisan Dumpsite
2014 Rowald A. Julian
(First Phase) at Irisan Barangay

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: August 16-31, 2020

Supervision and Monitoring of Infrastructure Projects for the given period.


Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present
Post Closure Maintenance of Irisan Facility / Benching
1 LDF 2011 & LDF RAJCE Construction by: 16-Jan-20 26-Dec-20 131,017.56 27-Jan-20 28.73-34.45% 34.45-47.28% Project On-going
and Stabilization and Post Closure of Irisan Dumpsite
2014 Rowald A. Julian
(First Phase) at Irisan Barangay

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: September 1-15, 2020

Supervision and Monitoring of Infrastructure Projects for the given period.


Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

Post Closure Maintenance of Irisan Facility / Benching


1 LDF 2011 & LDF RAJCE Construction by: 16-Jan-20 26-Dec-20 131,017.56 27-Jan-20 34.45-47.28% 47.28-49.26% Project On-going
and Stabilization and Post Closure of Irisan Dumpsite
2014 Rowald A. Julian
(First Phase) at Irisan Barangay

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: September 16-30, 2020

Supervision and Monitoring of Infrastructure Projects for the given period.


Expected Date of Alloted CEO Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO- Date,
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Completion Supervision Date of Designation New Expected date of completion)
Previous Present

Post Closure Maintenance of Irisan Facility / Benching


1 LDF 2011 & LDF RAJCE Construction by: 16-Jan-20 26-Dec-20 131,017.56 27-Jan-20 47.28-49.26% 49.26-56.30% Project On-going
and Stabilization and Post Closure of Irisan Dumpsite
2014 Rowald A. Julian
(First Phase) at Irisan Barangay

Prepared by: Reviewed by:

Rodel Q. Lagare Richard Benjamin L. Lardizabal


Supervising Assistant Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947
Republic of the Philippines
CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: October 1-15, 2020

Supervision and Monitoring of Infrastructure Projects for the given period.

Expected Date of Percentage of Completion REMARKS (On-going,Lapsed, SWO-date, RWO-


Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Alloted CEO Supervision Date of Designation
Completion Date, New Expected date of completion)
Previous Present

Repair and Rehabilitation of Slope Protection


BEMADA Construction Project On-going, Project transferred to Karen
1 Near Mines View Park Hotel at Pucsusan 2019 LDF
by: Billy M. Daliling 05-Feb-20 21-Jan-21 201,858.45 02-Mar-20 45.36-50.32% 50.32-53.44%
T. Guillermo On October 13, 2020
Barangay

Prepared by: Reviewed by:

Randy A. Reyes Richard Benjamin L. Lardizabal


Supervising Assistant Division Head

NOTED:

Edgar Victorio R. Olpindo


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947
Char t Title

R evi ew ed by:
35

30

25

20

15

10

1. CON - 1. 2.) 3.) 4.) S U B JECT: Project 5.) J 6.) 7.) 1.) 2.) 3.) DATA G ATHER IN G 1.) 1.) AS - 3.) 4.) 1.) 2.) 3.) 4.) 5.) 6.) 7.) 8.)
TIN U A- AG E S UB IN - Title: “CON S TR U C- US - LIS T CO PHO PHO F OR THE F EB R U AR Y CON - S IS TED AS - AS - F AC F AC F AC F AC F AC F AC F AC F ACE-
TION OF ND JEC DO TION OF DR AIN AG E TIF I OF MM TO TO F ACEB OOK POS TIN G S TR U C- THE CITY S IS T S IS T EB O EB B EB O EB O EB O EB O EB O B OOK
THE A : T: RSE CAN AL F R OM CAT PR O EN - DOC DOC F R OM EN G R . TION OF HIG H ED ED OK OOK OK OK OK OK OK POS T:
POS T LIS T Proj ME MICHAEL KIDPALOS ’ ION JEC TAR UM UM AG U S TIN , EN G R . S IDE- S TU - EN S IR POS POS POS POS POS POS POS PU B LIC
CLO- OF ect NT R ES IDEN CE TO B E IN TS Y EN - EN - LAR DIZ AB AL, EN G R . W ALK DEN TS GR. ED T: T: T: T: T: T: T: ADV I-
S UR E PR O Ti - LET CON N ECTED TO THE THE F OR F OR TAT TAT COMICHO R ECOV - W HO JER GU N O- PU B S TA PU B S TA S TA PU B S OR Y:
S TAB I- JEC tle: TER EXIS TIN G DR AIN AG E PR O IN - THE ION ION ER Y AR E AS - ALD NZ TICE LIC TU S LIC TU S TU S LIC TEMPO-
LIZ A- TS “R E : At- CAN AL ALON G AL- CU R S PE DI- ALO ALO AN D PIR IN G ON : TO AD- R E- AN R E- R E- AD- R AR Y
TION OF F OR COV ta ch B ER T R EYES ’ R ES I- EM CTI VI- NG NG IM- TO B E THE VI- POR NO POR POR VI- R OAD
IR IS AN IN - ER Y ed DEN CEAT PU R OK 4 EN T ON S IO MIN IR IS PR OVE AN AR - PU B S OR T: UN- T: T: S OR CLO-
DU MP- S PE OF re- AN D; B ) CON CR ETIN G OF ( Ti N ES AN MN ET CHITECT LIC: Y: S ho CE- R E: R E: Y: S U R E AT
S ITE CTI RO quir OF R OAD F R OM VI- GO m e: HEA VIE ECO F R OM S OME- An In- w in ME CO F I- RO CER IS E
( PHAS E ON AD- em CEN TE B ALAO’S R ES - ODS 9:00 DS W - JOS E DAY Ad- f or g N T: MPI N AL AD LAN E
II IR IS AN ( Ti R IG ents IDEN CE TO LOLITA a nd a .m ON N EA PAR F ELIPE ( W OR K vi - m a- the S TA LA- CON CLO R OAD,
ECO m e: HT- f or CON CEPTION ’S R ES I- S ER ./ LIS T R K S TR EET IMMER - s ory ti on per- TU S TIO S UL S UR PU R OK
PAR K) 9:00 OF - COV DEN CE AT PU R OK 2” VIC Da t OF PI- TO TO S ION ) to Di s - cen- R E- N TATI E 4,
a .m WA ID- B OTH LOCATED AT ES e: PR O LAK G ET LEG AR D ALL s em ta g e POR OF ON AT LOW ER
./ Y 19 MIN ES VIEW PR O Ma r JEC R ES HER A R OAD THE ina - of T: CO R E- MO F AIR
Da t ALO prio B AR AN G AY”. GR ch TS IDE W IT CON ti on a c- R E: MPL G AR DES VIEW
e: NG r to AM 29, F OR N CE H TR A to com "Th ETE DIN TA
Ma r MA the ME 202 WE TO EN CTO the pli s e D G S TR
ch GSA com D 3- DN E G ET GR. RS pub- hm e Prep PR O THE EET
22, YS A me UN We S DA HER DO a nd li c nt a ra - JECT LAN
202 Y nce DER dne Y W IT MI- ME re- of ti on S D
3- AV - me GO s da IN - H NA MO g a rd the of LO- R EC
We EN nt VER y) S PE EN DO R AN ing PPC Pro- CAT LAM
dne UE of ME CTI
Colum Gn R.N R Colum n O Colum n P Colum n Q DU the Di - g ra ED ATI
s da FRO the NT ON R IC MA M roa d vi - m IN ON
y) M proj FU HAR TB A di- - re- s i on of CER AT
LY- ect N DE D GA rect cov- con- W or TAI F OR
MA en- D LAR N ed ery cern ks N B ES
N ti - PR O DIZ to a nd ing of B AR PAR
OG I tled JEC AB A the con- the a ll AN K ***-
LB Y , TS L *** *** Di - s tru pro- the G AY Pos ti ng
CEN R E: Cre Let- vi - cti o cure Proj AR - of the
TR U “R E a ti o ter s i on n at m en ect EAS Advi s ory
M COV n of Con Hea B OK t, R e- OF ***
B UI ER Y trim tent ds AW cre- que B AG Pos t
LD- OF ble s ( PPC KAN a ti o s ts U IO ing
IN G R IG a c- , - n, of f or CITY of
TO HT- cou Ma i MA pro- the F OR the
WA OF - nt nte- GSA g ra Yea r THE Ad-
R DS WA f or na n YS A m 202 WH vi -
M. Y s ket ce Y of 3 OLE s ory
R OX ALO chu a nd AV - w or li s te MO
AS NG p MT EN U ks , d N TH
RO MA mo QC) E up un- OF
AD, GSA delli a nd to der F EB
” At YS A ng the the the RU-
Ma Y s oft S ec- bid- B ar AR Y
gsa AV - w ar ti on ding a n-
ys a y EN es Chie s ta g g ay
Pri- UE ( Ma f s of e of IR A
va te FRO rch the the F UN ***
R oa M 22) PPC LO- D Phot
d LY- Di - CAL w i ll o
B ar MA *** vi - DE- now Edit-
a n- N G AVE s i on VEL be ti ng
g a y, OG I THEM A con- OP a c- thro
B ag LB Y TAS K TO cern ME com ug h
uio CEN DES IG N ing NT m o- Pho-
City. TR U A PU B - the F UN da te tos h
M LIC fina l D d op
B UI COM- in- PR O s ta rt
LD- F OR T s pec JECT ing
IN G R OOM ti on S f ro
TO TEACH- of F OR m
WA IN G ev- CY the
R DS THEM ery 202 La t-
M. THE B A- *** com 3 es t
R OX S ICS OF S ket plet to
AS TECHN I- ch- ed the
RO CAL up proj Mos ***
AD DR AW - proj ect t Phot
AT IN G ect un- R e- o
MA PR O- mo der cent Edit-
GSA DU C- del - the R e- ti ng
YS A TION ing City que thro
Y CON - a nd En- *** st ug h
PR I CER N - la y- g i- Pub- by Pho-
VAT IN G out neer li c the tos h
E B U ILD- f or ing Ad- B a r op
RO IN G blue Of- vi - a n-
AD F LOOR w al fice s ory g ay
B AR PLAN S k *** Edit- Of-
AN Pub- ti ng fi- ***
G AY li c thro ci a l s Pos t
AN Ad- ug h " ing
D; vi - Pho- of
A.) s ory tos h the
R E- Edit- op Ad-
HA- ti ng vi -
B IL- thro s ory
ITA ug h
TIO Pho-
N tos h
OF op
EX-
IS T-
IN G
R IP
R AP ***
N EA TEACH-
R IN G ***
CA THEM Vi de
W IS THE B A- o
R ES S ICS OF Edit-
IDE TECHN I- ti ng
N CE CAL thro
AT DR AW - ug h
NA IN G F il m
RRA PR O- ora
S TR DU C- ***
EET, TION Pos t ***
KIA CON - ing Pub-
S CER N - of li c
B AR IN G the Ad-
AN B U ILD- Ad- vi -
G AY IN G *** vi - s ory
AN F LOOR Ac- s ory Edit-
D; PLAN S qui- ti ng
B .) AN D EL- s i ti o thro
CO EVA- n ug h
NS T TION S a nd Pho-
R UC pos t tos h
TIO ing op
N of
OF the
DR A Me
IN - m or
AG E a n-
CAN dum
AL da te
FRO d
M Ma r ***
CR E ch Pos t
EK 14, ing
TO 201 of
DU L 6 the
NU sig n Ad-
AN ed vi -
R ES by s ory
IDE *** the
N CE TEACH- City
AT IN G En-
PU R THEM g i-
OK MAN - neer
4, U AL ***
LOA DR AW - Pos t
KAN IN G ing
LI- METH- of
WA ODS the
NA Ad-
G vi -
B AR s ory
AN
G AY
”.

***S -
CALE
MODEL
B AS IC
B U ILD-
IN G
METH-
ODS

CR E- Com m uni ca ti on R eports DATA G ATHER IN G , S ITE PR OJECT CON DU CTED PR ES EN TATION S Pre
ATION IN S PECTION S , PHOTO S U PER - AS S IS TAN CE ( CR EATION OF POW ER POIN T, VIDEO pa r
OF DOCU MEN TATION S VIS ION EDITS / AN Y VIS U AL AIDES ) ed
CHAN G E AN D by:
OR DER MON I-
TOR IN G
AC- 2 3 4 5 6 7
TIV -
ITIE
S
Republic of the Philippines
CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT

For the Period: September 1-15, 2023

Supervision and Monitoring of Infrastructure Projects for the given period.


Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Expected Date of Date of Designation Percentage of Completion REMARKS (On-going,Lapsed,
Completion SWO-date, RWO- Date, New
Previous Present Expected date of completion)

ACTIVITIES
2 1.) DATA GATHERING: LOWER ROCK QUARRY, ECOPARK WITH UNDERDRAIN DRAINAGE SYSTEM
***Assistance on their Thesis Project concerning the Goverment Lot at AM 11
Lower Rock Barangay
2.) 2020 UNIMPLEMENTED PROJECTS
***Data gatherning and consolidation
AM/PM 7,8,15
***Finalization of List
DATA GATHERING/INQUIRY SITE 3.) 2021 UNIMPLEMENTED PROJECTS
VISITATIONS/INSPECTIONS, PHOTO ***Data gatherning and consolidation
DOCUMENTATIONS, AM/PM 8,11,12,15
***Finalization of List
4.) 2022 UNIMPLEMENTED PROJECTS
***Data gatherning and consolidation
AM/PM 14,15
***Finalization of List
1.) FACEBOOK POST: PUBLIC ADVISORY!
CONTENT: Second consultation meeting conducted last August 29,2023, to address certain issues related to the ongoing project entitled, "ROAD RECOVERY FROM MILITARY
CUT-OFF ROAD TO LOAKAN ROAD via STA. ESCOLASTICA VILLAGE BARANGAY".
#PublicAdvisory
#cityprojectupdate PM 5
#cityengineeringoffice_baguio

2.) PUBLIC ADVISORY!


CONTENT: To those traversing Yangco Road, please be informed that it is now reopened for vehicular traffic as of 4:00 p.m., August 31,2023.
2a FACEBOOK POSTINGS (Edits, Data-Gathering) #RoadRepairs
PM 5
#cityengineeringoffice_baguio

3.) PROJECT ACCOMPLISHMENT STATUS UPDATE


A compilation of the office/field work accomplishments of the PPC Division for the whole month of AUGUST.
#cityengineeringoffice_baguio
#accomplishmentreport_ppcdivision AM/PM 14
#August2023_projectaccomp

4.) PROJECT ACCOMPLISHMENT STATUS UPDATE


Project Title: Sidewalk Recovery At Hillside Rd. Going to BCNHS Hillside Annex
Activities:
-Demolition/Clearing Works at Residents Near Rotunda
-Curing Of Concrete Poured on Beam Prior to Riprap Works.
Supervised By: Engr. Genver Hora
#cityprojectupdate
#cityengineeringoffice_baguio AM/PM 6,14
#monitoring_and_supervisory_works
***Photodocumentation procurement from Project Engineer
***Photo-editting thru Photoshop
***Facebook Posting

5.) PROJECT ACCOMPLISHMENT STATUS UPDATE


Project Title: Recovery of Road Right-of-way Along Magsaysay Avenue From Lyman Ogilby Centrum Building Towards M. Roxas Road
Activities:
-Excavation Works Prior To Installation of Footing and Column Reinforcements
#cityprojectupdate
#cityengineeringoffice_baguio
#monitoring_and_supervisory_works AM/PM 6,15
***Photodocumentation procurement from Project Engineer
***Photo-editting thru Photoshop
***Facebook Posting

2b FACEBOOK POSTINGS (Edits, Data-Gathering) 6.) PROJECT ACCOMPLISHMENT STATUS UPDATE


Project Title: Sidewalk Recovery At Hillside Rd. Going to BCNHS Hillside Annex
Activities:
-Demolition/Clearing Works At Residents Near Rotunda
-Backfilling/Embankment
-Riprap Works
-installation of Railings
#cityprojectupdate
#cityengineeringoffice_baguio AM/PM 7,15
#monitoring_and_supervisory_works
***Photodocumentation procurement from Project Engineer
***Photo-editting thru Photoshop
***Facebook Posting

7.) PROJECT ACCOMPLISHMENT STATUS UPDATE


Project Title: Improvement Of Drainage Canal At Sarok
Activities:
1. Concrete Pouring Of Canal Cover
#cityprojectupdate
#cityengineeringoffice_baguio
#monitoring_and_supervisory_works AM/PM 7,15
***Photodocumentation procurement from Project Engineer
***Photo-editting thru Photoshop
***Facebook Posting

8.) PROJECT MONITORING AND SUPERVISION STATUS UPDATE


Project Title: Concreting of Montinola Road, Burnham-
Legarda
Activities:
1. Breaking of existing PCCP.
#cityprojectupdate
#cityengineeringoffice_baguio AM/PM 8,15
#monitoring_and_supervisory_works
***Photodocumentation procurement from Project Engineer
***Photo-editting thru Photoshop
***Facebook Posting

2c FACEBOOK POSTINGS (Edits, Data-Gathering)


ACTIVITIES
9.) PROJECT MONITORING AND SUPERVISION STATUS UPDATE
"Road Recovery from military Cut-off road to loakan road
via sta scholastica barangay street" at sta scholastica
Contractor: Mhigs Construction
Activities:
-Excavation for the Drainage Pipe at Sta 0+000 (near the Bridge)
- Facilitation the Traffic Flow at Hillside Road
#cityprojectupdate
#cityengineeringoffice_baguio AM/PM 8,15
#monitoring_and_supervisory_works
***Photodocumentation procurement from Project Engineer
***Photo-editting thru Photoshop
***Facebook Posting

10. ) PROJECT ACCOMPLISHMENT STATUS UPDATE


Project Title: Phase 3 Improvement of Sidewalk
2c FACEBOOK POSTINGS (Edits, Data-Gathering) Location: Kayang, Extension
Activities Accomplished As Of Inspection:
1. Welding Works
2. Installation of stainless steel
#cityprojectupdate
#cityengineeringoffice_baguio
#monitoring_and_supervisory_works AM/PM 15
***Photodocumentation procurement from Project Engineer
***Photo-editting thru Photoshop
***Facebook
Posting

11.) PROJECT ACCOMPLISHMENT STATUS UPDATE


Project Title: Improvement of pathway alley with railings and
canal at purok 7, Gabriela Silang
Activities
-Formworks for the Concrete Stair
#cityprojectupdate
#cityengineeringoffice_baguio
#monitoring_and_supervisory_works
***Photodocumentation procurement from Project Engineer AM/PM 8,15

***Photo-editting thru Photoshop


***Facebook Posting
ACTIVITIES
12.) PROJECT ACCOMPLISHMENT STATUS UPDATE
Project Title: Drainage Rerouting from Lourdes
Subdivision Rd to Mystical Street near Barangay Hall
Activities:
1: Installation of Rebar for the Box Culvert
#cityprojectupdate
#cityengineeringoffice_baguio AM/PM 8,15
#monitoring_and_supervisory_works
***Photodocumentation procurement from Project Engineer
***Photo-editting thru Photoshop
***Facebook Posting

13.) PROJECT ACCOMPLISHMENT STATUS UPDATE


Project Title: Repair and Restoration of Cut Road at
Interior A, Balacbac
#cityprojectupdate
#cityengineeringoffice_baguio
#monitoring_and_supervisory_works AM/PM 11,15
***Photodocumentation procurement from Project Engineer
***Photo-editting thru Photoshop
***Facebook Posting

14.) PROJECT ACCOMPLISHMENT STATUS UPDATE


2d FACEBOOK POSTINGS (Edits, Data-Gathering) Project Title: Sidewalk Recovery at CBD
Activities:
1. Installation of Concrete Blocks
#cityprojectupdate
#cityengineeringoffice_baguio
#monitoring_and_supervisory_works AM/PM 11,15
***Photodocumentation procurement from Project
Engineer
***Photo-editting thru Photoshop
***Facebook Posting

15.) PROJECT ACCOMPLISHMENT STATUS UPDATE


Project Title: Rehabilitation of Drainage Canal At Monticello Camp 7
Activities:
-Installation of Drainage Reinforcement bars prior to concrete pouring
#cityprojectupdate
#cityengineeringoffice_baguio
#monitoring_and_supervisory_works AM/PM 11, 15
***Photodocumentation procurement from Project Engineer
***Photo-editting thru Photoshop
***Facebook
Posting
ACTIVITIES
16.) PROJECT ACCOMPLISHMENT STATUS UPDATE
Project Title: Recovery of Road Right-of-way Along
Magsaysay Avenue From Lyman Ogilby Centrum Building Towards M. Roxas Road
Activities Accomplished As Of Inspection:
1. Partial Removal Of Structure's Inside and Out side of The Affected Resident
2. Backfilling/Embankment Works
3. Installation of Footing and Column Reinforcement bars
#cityprojectupdate AM/PM `11,15
#cityengineeringoffice_baguio
#monitoring_and_supervisory_works
***Photodocumentation procurement from Project Engineer
***Photo-editting thru Photoshop
***Facebook Posting
17.) PROJECT ACCOMPLISHMENT STATUS UPDATE
"Road Recovery from military Cut-
off road to loakan road via sta scholastica barangay street" at sta scholastica
Activities:
2e FACEBOOK POSTINGS (Edits, Data-Gathering) -Excavation for the Drainage Pipe at Near the Intersection ( Sta sCholastica Rd and Hill Side Road
- Facilitating the Traffic Flow at Hillside Road
#cityprojectupdate AM/PM 12,15
#cityengineeringoffice_baguio
#monitoring_and_supervisory_works
***Photodocumentation procurement from Project Engineer
***Photo-editting thru Photoshop
***Facebook Posting

18.) PROJECT ACCOMPLISHMENT STATUS UPDATE


Project Title: Sidewalk Recovery At Hillside Rd. Going to
BCNHS Hillside Annex
Activities:
-Demolition/Clearing Works At Residents Near Rotunda
-Clearing and Haul-out of Excavated Earth AM/PM 14,15
#cityprojectupdate
#cityengineeringoffice_baguio
#monitoring_and_supervisory_works

1.) SUBJECT: A COMMUNICATION INDORSED FROM THE CITY MAYOR’S OFFICE WITH A CONTROL NO. 7441, SENT BY MR. MIGUEL RAFAEL MOLINA, THE COMPLAINANT. RE:
“URGENT APPEAL FOR INTERVENTION REGARDING UNAUTHORIZED ENCROACHMENT AND PROPERTY DAMAGE”.
CONTENT: construction project undertaken by Goldrich Construction Company located at Brgy. Purok Ungasan, Loakan Proper, Baguio City,
which is currently being implemented by the BCDEO-DPWH. Received claims from Mr. Miguel Molina regarding certain issues related to this project on failure to implement the
necessary precautions for soil retention and stabilization.
***ENGR. RENE F. ZARATE, District Engineer, Baguio City District Engineering Office, Department of Works and Highways,
Engineers Hill, Baguio City 7
***MR. RALPH C. PABLO, Regional Executive Director, Department of Environment and Natural Resources, DENR-CAR, Gibraltar Road, Baguio City
***WILLIAM T.
GO,Owner,Gold Rich Construction & Trading, Marcos Highway, Central Poblacion, Tuba, Benguet, CAR, 2603
3a COMMUNICATIONS ***MR. MIGUEL RAFAEL MOLINA, Vice President, ARB Construction Co., Inc., Lot 2- AM/PM
1A Barangay Ungasan, Loakan Proper, Baguio City

2.) CONTENT: Regarding the 15% mobilization amount collected by Mr. Melecio Moyamoy, the contractor for the terminated project entitled, re: ”Repair and Rehabilitation of
Railings, Sidewalks, Median Dividers, Geometric Design, and Steel Grates at CBD." After conducting a thorough evaluation and assessment of the financial breakdown of the
project, it has come to our attention that Mr. Moyamoy has an outstanding balance amounting to Php 26,040.28.
***Ms. FREDA C. JIMENEZ,City Accountant-OIC, City Accounting Office, City Hall, Baguio City 8,11
***MELECIO MOYAMOY, Contractor, Melecio Construction, No.11 Maria Basa Street, Pacdal, Baguio City

3.) CONTENT: Discuss the Supreme Hotel Management proposal to tap into the existing drainage line located at Happy Holmes.
Date: Tuesday, September 12, 2023
Time: 9:00 a.m.
Location: City Engineering Office (2nd Floor Conference Room, Administrative Building)
***SPS PETER LEUNG NG AND EVELYN CHOY
NG,Owner/Proprietor, Hotel Supreme, Magsaysay Avenue, Baguio City 8
***AR. JOHNNY A. DEGAY, City Building Official, City Building Administrative Office (CBAO), DPS
Compound, Baguio City
***JOSEPH A. SACLEY, Punong Barangay, Barangay Hall, Happy Hallow, Baguio City

4.) CONTENT: preparation of program of works (POW) for the projects entitled, “Continuation of Road at Lower Balacbac and Improvement of Slope Protection and Pathway at
Atab, Sto. Tomas Proper, Baguio City.” ***JOSEPHINE T. BALUSDAN, Punong Barangay, Sto. Tomas
Proper Barangay, Baguio City 11

5.) CONTENT: request to conduct ocular inspection and to prepare a detailed cost estimate on the projects with the item description, a.) River Bed located at Purok 3, Guisad
Surong Barangay; b.) Rip Rap with Railing located at Purok 3, Guisad Surong Barangay; c.) Bleacher with Canopy at Purok 5, Badihoy Street, near the Covered Court.
***MARIO L. BENALIO, Punong Barangay, Guisad Surong Barangay, Baguio City
11

3b COMMUNICATIONS AM/PM
6.) SUBJECT: Letter dated August 29, 2023 from Engr. RENE ZARATE, District Engineer, BCDEO-DPWH regarding the Barangay Resolution No. 22, series of 2023, re:
“Requesting the repair of eroded portion at Veterans Compound Camp Henry T. Allen during the onslaught of Typhoon Egay” located along Kayang Street, Baguio City.
CONTENT: indorsing to Maribel A. Estacion, Punong Barangay, Camp Henry T. Allen Baguio City, reiterating the statement enclosed in the said
letter.
***RENE ZARATE, District Engineer, BCDEO-DPWH 15
***HON. BENJAMIN B. MAGALONG, City Mayor, City Mayor’s
Office, City Hall, Baguio City
***GLENN LARDIZABAL, OIC, CDRRMC Officer, City Disaster Risk Reduction and Management Council, Lower Rock Quarry, Baguio
City
7.) SUBJECT: Letter received dated September 4, 2023, regarding RESOLUTION Numbered 511 (Series of 2023), REQUESTING THE CITY BUILDINGS AND ARCHITECTURE OFFICE
(CEO), AND THE CITY ENVIRONMENT ANDF PARKS MANAGEMENT OFFICE (CEPMO) TO SUBMIT ITS RESPECTIVE REPORTS ON UNIMPLEMENTED PROJECTS WITHIN THEIR
JURISDICTION FOR THE LAST THREE (3) YEARS AND TO PROVIDE ITS RECOMMENDATIONS TO THE SANGGUNIANG PANGLUNGSOD (CITY COUNCIL) OF BAGUIO FOR
APPROPRIATE LEGISLATIVE MEASURE. ***Atty. BRENNER L. BENGWAYAN, Secretary
to the Sanggunian II, Office of the Sangguniang Panglungsod, City Government of Baguio 15
ACTIVITIES
1.)POWERPOINT PRESENTATION: HOTEL SUPREME PROPOSED TAPPING OF BUILDING'S DRAINAGE SYSTEM TO HAPPY HOLMES PUBLIC DRAINAGE LINE
***Proposed Drainage Plan
***Project Indicators
***Procurement of data from Sir Aquino and Sir Pe-ang AM 11
***Creation of powerpoint

2.) VIDEO PRESENTATION: PROJECT ACCOMPLISHMENT STATUS UPDATE


CONTENT: A compilation of the office/field work accomplishments of the PPC Division for the whole month of AUGUST
PROJECTS:
1.) Construction of slope protection and rehabilitation of common pathways with railings beside Abgao residence Purok 2
2.) Continuation
of the rehabilitation of canal from Guinid to Dogaong residence at Purok 2
3.)Construction of garage at New Lucban Barangay Multi-Purpose Hall Purok 2
4.) CLUSTER PROJECT: A.) Rehabilitation of cnal at Regidor fronting Aquino to Bautista's residence; B.) Rehabilitation of drainage at Sib-aten's
residence at Maria Basa Street; C.) Construction of canalfrom Allan Docla's to Juan Cario's residence at Tiptop
5.) Construction of pathway and railings at Purok 1,4 & 5, BGH Compound
4a VISUAL PRESENTATION (POWERPOINT AND
VIDEO PRESENTATION) 6.) Rehabilitation of drainage from Marjorie Gaiwen's residence to Dario Pale's residence at Tiptop
7.)Repair of steps from Kiloyen's residence to Iglesia ni kristo and
installation of railings from Aquino residence to INC at Purok 2
8.)Rehabilitation of existing riprap near Cawis residence at Narra Street AM/PM 5,6,7,8,11,12,14
9.) Construction of
drainage canal from creek to Dulnuan residence at Purok 4
10.) Continuation of road improvement at Purok 4, Fairview
11.) CLUSTER: 1.) Rehabilitation of canal and alley at Block 3; 2.) Rehabilitation of canal and alley at Block 2; 3.) Rehabilitation of stair and
steel gratings at Block 1; 4.) installation of fence at Block 7 at Middle Quirino Hill 12.)
Improvement of canal from Lagman residence to Barros residence, City Camp
13.) Restoration of eroded section along Santo Nino road near
Malecdan residence
14.) Rehabilitation of the damage canal in front of Batoon residence, Bengao, Purok 9
15.)
Improvement of Barangay Evacuation Center
16.) Rehabilitation of Barangay Hall of Phil-Am barangay
17.) Improvement/concreting of road, step and canal from Marcos at Purok 7 down to Escorro residnce Upper
Pinget
18.) CLUSTER: A. Construction of railings from Lucaben residence to Pecdasen residence at Purok 2; B.Concreting of footpath from Lannawon residence to Karen Bogbog
……CONTINUATION……
20.) Flood Control Project, South Sanitary Camp
21.) Furnish labor and materials for the project "Continuation of road widening with riprap and road gutter
from Diwag gate to Catholic Church
22.) Construction of concrete stairs near Hilda Mateo's residence at Purok 1
23.) Repair of pathway with canopy from
Cabacungan residence to Lapitan residence
24.) Rehabilitation of riprap and continuation of drainage canal at Purok 1 from Calines residence to
Basawil residence
- OFFICE AND FIELD WORK TALLIES (RE: INVESTIGATIONS, PROJECTS WITH ISSUED "NOTICE TO PROCEED" , REQUEST COMMUNICATIONS RECIEVED BY THE OFFICE FOR
THE MONTH OF AUGUST) -TALLYING OF
COMPLETED INFRASTRUCTURE PROJECTS FOR THE MONTH OF AUGUST (IRA PROJECTS= 15 COMPLETED; LDF PROJECTS=4 COMPLETED; DRRMF PROJECTS: 4COMPLETED)
-TALLYING OF NO. OF INSPECTED PROJECTS (IRA PROJECTS=4 INSPECTED; ldf
projects= 4 INSPECTED; TO BE SCHEDULED FOR INSPECTION=8 PROJECTS)
-TALLYING OF THE NO. OF REQUEST/COMMUNICATIONS/COMPLAINTS/ RECIEVED BY THE PPC DIVISION FOR THE MONTH OF JUNE
4b VISUAL PRESENTATION (POWERPOINT AND (SUMMATION=209 TOTAL QUANTITY; REQUESTS ACTED UPON=208 OUT OF 238) -TALLYING OF THE NO. OF AM/PM 5,6,7,8,11,12,14
VIDEO PRESENTATION) ISSUED "NOTICE TO PROCEED" OF PROJECTS SUBJECT FOR IMPLEMENTATION (QUANTITY=26 AWARDED PROJECTS LINED FOR COMMENCEMENT)
-SUBMITTED PROGRAM OF WORK: 26 PROJECTS
-PRE-CONSTRUCTION MEETINGS
-ACTIVATION OF THE CEO
DISASTER RESPONSE TEAM
***Acquisition of the needed data from the project engineers, Sir King
***Photo Documentations on-site on all projects listed above (QUANTITY=287 PHOTOS)
***Consolidation of all acquired data
***ONE-BY-ONE EDITING of all the 208 photos thru photoshop and filmora
***Creation of the FULL VIDEO-PRESENTATION THRU FILMORA

SUPREME HOTEL MANAGEMENT: RE: REQUEST on tapping the buildings drain age system to happy holmes public drain

5 MEETING AM 14

Prepared by: Reviewed by:

Karen T. Guillermo Richard Benjamin L. Lardizabal


Supervising Assistant Division Head

NOTED:

EDGAR VICTORIO R. OLPINDO


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947
Republic of the Philippines
CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: September 1-15, 2023
Supervision and Monitoring of Infrastructure Projects for the given period.
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Expected Date of Date of Percentage of REMARKS (On-going,Lapsed, SWO-date,
Completion Designation Completion RWO- Date, New Expected date of
completion)

ACTIVITIES

1.) Assist SLU Students at their site visitation, RE: Thesis Proposal

***Photo documentation 19
***Data Gathering
2.) SITE INSPECTION AND VISITATION at Aguinaldo Park, Happy Glenn Loop, for the upcoming Php 10,000,000.00 Drainage Project (Time:
8:30 a.m.-11:30p.m.)
***Assisted By: Marquel Cyrille D. Agaceta, OJT; and Johanna Rose G. Perea, OJT
21
***Photo documentation

***Data Gathering
3.) BUYOG WATERSHED Data Acquisition
DATA GATHERING/INQUIRY 22
1 SITE VISITATIONS/INSPECTIONS, ***All feasible data related to Buyog Watershed (Data Inquiry: Sir Brenson, BCDEO-DPWH)
PHOTO DOCUMENTATIONS,
4.) DATA GATHERING/INQUIRY: RE: Boundary Encroachment of Ms. Erlinda S. Munsayac's property concerning the sidfewalk project at
Dominican Mirador, Barangay
29
***Data Acquisition from SIr Jerald and Sir Jhirsie
5.) SITE INPECTION: RE: Severe flooding along MS. SHELLOU MANGATAN property, situated at No. 19, Purok 5, Pinsao Pilot, Tricom Village

***Photo documentation

***Data Gathering 29

***On-site Interview

***Conduct
1.) Preparation of program of works (POW) for the project, re: “Establishment of Stock Room/Bodega at Ongasan Multi-purpose
Covered Court, Prk Ongasan, Loakan Proper Barangay”
***Recipient: EDOUARD EMMMANUEL P. CAYETANO, Punong Barangay, Loakan Proper Barangay, Barangay Hall, Baguio City
2a COMMUNICATIONS 18

2.) Preparation of program of works (POW) for the project with Purchase Request (PR) No.: 2023-09-017, re: “Installation of Steel Grates
at Purok 3”.
***Recipient: JESSIE SALVADOR M. BANDIOLA, Punong Barangay,City Camp Central, Barangay Hall, Baguio City 19

3.) ORDER TO TERMINATE CONTRACT, RE: “CONSTRUCTION OF RIPRAP FRONTING VISAYA’S STORE AT PUROK 2” PART OF CLUSTERED
PROJECT located at Padre Zamora
***Recipient: MR. ALFREDO M. BALABAG, Contractor/Manager, Y Pantalan Builders, 742 San Vicente Baguio City 19

4.) Preparation of program of works (POW) for the following projects entitled:
4.a.) Improvement of Drainage Canal at Parisas amounting to One Million Pesos (Php 1,000,000.00);
4.b.) Rehabilitation of Drainage Canal with Concrete Hallow Block (CHB) at Sarok;
4.c.) Improvement of Alley with riprap located at Sarok near Herminia Pascua;
4.d.) Continuation of the Improvement of Drainage Canal at Monticello. 19
***Recipient: ANGELINA C. RAMOS, Punong Barangay, Camp 7, Baguio City

5.) SUBJECT: List of unimplemented projects carried out by the City Engineering Office for the past three (3) years, as per Resolution
Numbered 511 (Series of 2023).
***Recipient: AR. DONNA RILLERA-TABANGIN,City Planning and Development Officer,City Planning and Development 19
Office,City Hall, Baguio City

5.) SUBJECT: List of unimplemented projects carried out by the City Engineering Office for the past three (3) years, as per Resolution
2b COMMUNICATIONS Numbered 511 (Series of 2023).
***Recipient: AR. DONNA RILLERA-TABANGIN,City Planning and Development Officer,City Planning and Development 19
Office,City Hall, Baguio City

6.) SUBJECT: MINUTES OF THE MEETING


Meeting Date: August 10, 2023; Meeting Time: 9:00 a.m. - 11:30 a.m.; Location: CEO Administrative Building Conference Room
Agenda:
• Discussion of Ongoing Projects
• Exploration of New Construction Innovations
• Recognition and Certificates Awarding 19

7.) Preparation of program of works (POW) for the following projects entitled, “CONTINUATION OF CANAL, ALONG PUROK 1, POLIWES
BARANGAY, BAGUIO CITY”. 19
***Recipient: ANGELINA C. RAMOS, Punong Barangay, Camp 7, Baguio City
8.) Preparation of program of works (POW) for the following projects entitled, “Contiguous Improvement of Drainage Canal located at
Amistad, Camp 7, Baguio City”. 20
***Recipient: RONALD A. SALDAEN,Punong Barangay,Poliwes Barangay, Baguio City
9.) SUBJECT: INTENT TO TERMINATE CONTRACT
PROJECT TITLE: IMPROVEMENT OF PATHWAY ALLEY WITH RAILINGS AND CANAL AT PUROK 7, GABRIELA SILANG BARANGAY
20
***Recipient: DANTLY JORDAN WAYAN, Contractor, DJW Construction, Baguio City

10.) VERIFICATION REPORT: Project Title: IMPROVEMENT OF PATHWAY ALLEY WITH RAILINGS AND CANAL AT PUROK 7 project incurred
a negative slippage of sixteen and one percent (16.1%) as of September 11, 2023 which is above the negative slippage of fifteen percent
(15%) required by RA 9184 (Procurement Law) for the termination of contract for an infrastructure project. 20
***Recipient: EDGAR VICTORIO R. OLPINDO, City Engineer
11.) SUBJECT: INTENT TO TERMINATE CONTRACT
PROJECT TITLE: SIDEWALK RECOVERY AND IMPROVEMENT AT HILLSIDE ROAD TOWARDS BAGUIO CITY NATIONAL HIGH SCHOOL,
HILLSIDE ANNEX, HILLSIDE BARANGAY
***Recipient: GIOVANNI B. SALVADOR,Contractor,GBS Construction and Engineering, Baguio City 20

12.) VERIFICATION REPORT: TERMINATION FOR DEFAULT


Project Title: SIDEWALK RECOVERY AND IMPROVEMENT AT HILLSIDE ROAD TOWARDS BAGUIO CITY NATIONAL HIGH SCHOOL, HILLSIDE
ANNEX, project incurred a negative slippage of sixteen and zero six percent (16.06%) as of September 11, 2023 which is above the negative
slippage of fifteen percent (15%) required by RA 9184 (Procurement Law) for the termination of contract for an infrastructure project.
***Recipient: EDGAR VICTORIO R. OLPINDO, City Engineer 20

13.) SUBJECT: INTENT TO TERMINATE CONTRACT


PROJECT TITLE: DRAINAGE REROUTING FROM LOURDES SUBDIVISION RD. TO MYSTICAL ST. NEAR BARANGAY HALL, LOURDES
BARANGAY 20
***Recipient: JOSELITO F. RAMOS, Contractor, JEROS Construction, Baguio City

2c COMMUNICATIONS 14.) VERIFICATION REPORT: TERMINATION FOR DEFAULT


Project Title: DRAINAGE REROUTING FROM LOURDES SUBDIVISION RD. TO MYSTICAL ST. NEAR BARANGAY HALL, project incurred a
negative slippage of fourteen percent (14%) as of September 11, 2023 which is near to the negative slippage of fifteen percent (15%)
required by RA 9184 (Procurement Law) for the termination of contract for an infrastructure project. 20
***Recipient: EDGAR VICTORIO R. OLPINDO, City Engineer

15.) SUBJECT: INTENT TO TERMINATE CONTRACT


PROJECT TITLE: REHABILITATION AND IMPROVEMENT OF DRAINAGE CANAL AT TEACHERS VILLAGE, STO. TOMAS PROPER
***Recipient: GIOVANNI B. SALVADOR, Contractor, GBS Construction and Engineering
Baguio City 20

16.) VERIFICATION REPORT: TERMINATION FOR DEFAULT


Project Title: SIDEWALK RECOVERY AND IMPROVEMENT AT HILLSIDE ROAD TOWARDS BAGUIO CITY NATIONAL HIGH SCHOOL, HILLSIDE
ANNEX, project incurred a negative slippage of sixteen and zero six percent (16.06%) as of September 11, 2023 which is above the negative
slippage of fifteen percent (15%) required by RA 9184 (Procurement Law) for the termination of contract for an infrastructure project.

***Recipient: EDGAR VICTORIO R. OLPINDO, City Engineer 20

17.)SUBJECT: SHOW CAUSE ORDER, RE: “ROAD REHABILITATION”, GABRIELA SILANG


20
* **Recipient: NONITO C. DIO Jr.,Contractor,10-02 Enterprises Co. Inc., Baguio CIty
18.) P4-SC JOB DESCRIPTION
20
***Recipient: Richard Benjamin Lardizabal, PPC Division Head
19.) SUBJECT : SUMMARY OF THE REPORT: KEY POINTS AND DECISIONS MADE DURING THE MEETING INITIATED BY THE BAGUIO CITY
DISTRICT ENGINEERING OFFICE-DEPARTMENT OF WORKS AND HIGHWAYS (BCDEO-DPWH) REGARDING THEIR PROPOSED FY 2024
PROJECT ENTITLED, “CONSTRUCTION OF BY-PASS AND DIVERSION ROAD-QUEZON HILL ROAD 1 TO MAGSAYSAY WEST SERVICE BY-PASS
ROAD, BAGUIO CITY”.
***Recipient: HON. BENJAMIN B. MAGALONG, City Mayor, Office of the City Mayor,

***Recipient: MR.KHADAFFY D. TANGGOL, Regional Director, DPWH-CAR, Engineer’s Hill, Baguio City, 22
***MR. RENE F. ZARATE, District Engineer, Baguio City District Engineering Office, Department of Works and Highways,
Engineers Hill, Baguio City
***Recipient: AR. JOHNNY A. DEGAY, City Building Official, City Building
Administrative Office (CBAO), Baguio City

19.) SUBJECT : SUMMARY OF THE REPORT: KEY POINTS AND DECISIONS MADE DURING THE MEETING INITIATED BY THE BAGUIO CITY
DISTRICT ENGINEERING OFFICE-DEPARTMENT OF WORKS AND HIGHWAYS (BCDEO-DPWH) REGARDING THEIR PROPOSED FY 2024
PROJECT ENTITLED, “CONSTRUCTION OF BY-PASS AND DIVERSION ROAD-QUEZON HILL ROAD 1 TO MAGSAYSAY WEST SERVICE BY-PASS
ROAD, BAGUIO CITY”.
***Recipient: HON. BENJAMIN B. MAGALONG, City Mayor, Office of the City Mayor,

***Recipient: MR.KHADAFFY D. TANGGOL, Regional Director, DPWH-CAR, Engineer’s Hill, Baguio City,
22
2d COMMUNICATIONS ***MR. RENE F. ZARATE, District Engineer, Baguio City District Engineering Office, Department of Works and Highways,
Engineers Hill, Baguio City
***Recipient: AR. JOHNNY A. DEGAY, City Building Official, City Building
Administrative Office (CBAO), Baguio City

20.) Preparation of program of works (POW) for the following projects with Purchase Request (PR) No.:2023-09-10, re:
“REHABILITATION OF GUTTER TYPE CANAL” and “REHABILITATION OF ROADSIDE”, with a total amount of Php621,194.40 .
***Recipient: IGNACIO LABAWIG GALLENTE, Punong Barangay, Middle Quirino Hill Barangay, Baguio City
22

21.) Preparation of program of works (POW) for the following projects with Purchase Request (PR) No. 01, re: “Rehabilitation of
Pathway along Purok 4 and Installation of Canal and Cross Drain (beside Sungduan residence to Ampaguey residence”, with a total
amount of Php1,191,329.96.
22
***Recipient: ROY ALEXANDER F. DAWA JR., Punong Barangay,East Bayan Park, Aurora Hill, Baguio City

22.) Preparation of program of works (POW) for the following projects, re: “Construction of Canal with Steel Gratings along Purok 8
Dongpapen St. Dontogan Baguio City” amounting to Php 400,000.00 and re: “Construction of Alley along Purok 10 (Casionan Residence
to Manodon Residence) Dontogan Barangay, Baguio City” amounting to Php 300,000.00.
25
***Recipient: RENATO P. BONGCOG, Punong Barangay, Dontogan
Barangay, Aurora Hill, Baguio City
23.) Preparation of program of works (POW) for the following projects, re: “Construction Steps with Railings and Drainage Canal along
Purok 5 Balusdan St. Dontogan Barangay, Baguio City” amounting to Php 350,000.00, re: “Construction of Drainage Canal along Purok 8
(from Gallema Residence to Magalgalit Residence)” amounting to Php 300,000.00, and re: “Construction of Alley and Pathways with
Railings along Tello St. Dontogan Barangay, Baguio City” amounting to Php 300,000.00.
25
***Recipient: RENATO P. BONGCOG, Punong Barangay, Dontogan Barangay,
Aurora Hill, Baguio City

24.) Preparation of program of works (POW) for the following projects, re: “Construction Steps with Railings and Drainage Canal along
Purok 5 Balusdan St. Dontogan Barangay, Baguio City” amounting to Php 350,000.00, re: “Construction of Drainage Canal along Purok 8
(from Gallema Residence to Magalgalit Residence)” amounting to Php 300,000.00, and re: “Construction of Alley and Pathways with
Railings along Tello St. Dontogan Barangay, Baguio City” amounting to Php 300,000.00.
25
***Recipient: RENATO P. BONGCOG, Punong Barangay, Dontogan Barangay,
Aurora Hill, Baguio City

25.)SUBJECT: Request the conceptual design that is developed by your office with a project title, “CONSTRUCTION OF DRAINAGE AT
AGUINALDO PARK” with AIP Reference Code, AIP-100-2-1-10-001-015-000 and an allocated budget of Php10,000,000.00.

***Recipient: AR. DONNA RILLERA- 25


TABANGIN, City Planning and Development Officer, City, Planning and Development Office, City Hall, Baguio City

2e COMMUNICATIONS 26.) SUBJECT: Response to Recommendation Item No.3, re: REQUEST FOR ROAD REPAIR ALONG 2nd KAYANG STREET, KAYANG HILLTOP
BARANGAY, BAGUIO CITY.
***Recipient: RENE S. BIAGTAN, Punong Barangay, Kayang Hilltop Barangay, Baguio City 29

27.)SUBJECT: Response to Recommendation Item No.3, re: REQUEST FOR REHABILITATION/REPAIR/MAINTENANCE OF DILAPIDATED
ROADS AT LEXBER HEIGHTS TO AMPARO ROAD, WOODS GATE/PELOTA COURT AND AMISTAD RD.
***Recipient: RENE S. BIAGTAN, Punong Barangay, Kayang Hilltop Barangay, Baguio City 29

28.) SUBJECT: Response to Recommendation Item No.2, re: DAMAGED STEEL GRATES ALONG HAMADA INTERIOR, MRR QUEEN OF
PEACE BARANGAY, BAGUIO CITY.
***Recipient: RAUL S. CARONONGAN, Punong Barangay, MRR Queen of Peace Barangay, Baguio City 29

29.) SUBJECT: Response to Recommendation Item No.2, re: REQUEST FOR REPAIR OF CRACKED AREAS NEAR THE GARBAGE STAGING
AREA AT SUDAYPAN ROAD, UPPER ROCK QUARRY, BAGUIO CITY.
***Recipient:ANGELINA C. RAMOS, Punong Barangay, Camp 7, Baguio City 29

30.) SUBJECT: Re: Request for Dredging/ Declogging of Canal at Loakan Airport Service/Access Road.

***Recipient:HON. BENJAMIN B. MAGALONG, City Mayor, City Mayor’s Office, City Hall, Baguio City
***Recipient:MR. ROSITO G. TAMAYO Jr., Officer-In-Charge, Civil Aviation Authority of the Philippines, Brgy. Loakan, Baguio City 29
***Recipient:RENE F. ZARATE, District Engineer, BCDEO-DPWH, Engineer’s Hill, Baguio City
***Recipient: Edouard Emmanuel Pistola Cayetano, Punong Barangay, Loakan Proper Barangay, Baguio
City
CONSOLIDATION OF DATA'S REGARDING THE MONTH OF SEPTEMBER ACCOMPLISHMENT

***Acquisition of data from the Project Engineers


3 FACEBOOK POST ***Compilation of works 26, 27, 28

***Individual Project Documentations


1.) MEETING THRU ZOOM (ONLINE MEETING): RE: Cascading and Orientation of the Revised RPMES Operational Guidelines
(Meeting: 9:00a.m.-3:00p.m.
AM/ PM 26

2.) (BCDEO-DPWH) REGARDING THEIR PROPOSED FY 2024 PROJECT ENTITLED, “CONSTRUCTION OF BY-PASS AND DIVERSION
ROAD-QUEZON HILL ROAD 1 TO MAGSAYSAY WEST SERVICE BY-PASS ROAD, BAGUIO CITY”.
Meeting Date: SEPTEMBER 21, 2023 (THURSDAY)
Time: 2:00 P.M. IN THE AFTERNOON
4 MEETING Location: MULTIPURPOSE HALL OF THE BCDEO-DPWH BUILDING
Attendees: 17 PARTICIPANTS
o BCDEO-DPWH (Department of Public Works and Highways, Baguio City District Engineering Office)
o Engr. Mario Bildan (Congressman Mark Go representative) PM 21
o Representatives from City Engineering Office
o DENR-MGB (Department of Environment and Natural Resources - Mines and Geosciences Bureau)
o Barangay Captains of Barangay Pinget, West Quirino Hill, and Middle Quirino Hill

Prepared by: Reviewed by:

Karen T. Guillermo Richard Benjamin L. Lardizabal


Supervising Assistant Division Head

NOTED:

EDGAR VICTORIO R. OLPINDO


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC)


Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947
Republic of the Philippines
CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: October 1-15, 2023

Supervision and Monitoring of Infrastructure Projects for the given period.


Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Expected Date of Date of Percentage of REMARKS (On-going,Lapsed, SWO-date,
Completion Designation Completion RWO- Date, New Expected date of
Previous Present completion)

IMPROVEMENT OF LOADING AND


NORBANO BUILDERS by:
1 UNLOADING BAY AREAS ON VARIOUS LDF 2022 5/25/2022 8/18/2023 6/15/2023 67.70% 86.67% Project Suspended as of June 20
Norris Anoyan
ROADS

CONSTRUCTION OF SIDEWALK A.P. NA-OY


RECOVERY AND IMPROVEMNET CONSTRUCTION, SUPPLY
2 IRA 9/20/2023 11/16/2023 2/17/2023 29.51% 30.00% ON-SCHEDULE
FROM JOSE FELIPE STREET TO AND AGGREGATES BY:
LEGARDA ROAD ANTONIO P. NA-OY

ACTIVITIES
1 Creation of Program of Works 1.) Multi-Purpose 2 Storey Building with First Floor and Roof Deck Parking Area at Dominican Mirador fronting the Barangay Hall 7,14,12,13
1.) Conducting Site Inspection, Land Verification, and Investigative Assessment to Develop a Program of Works in Response PM 5
to Dominican Barangay's Request for a Parking Building.
***Photo documentation

***Data Gathering

***On-site Interview
2.) Conducting Site Inspection, Land Verification, and Investigative Assessment to Develop a Program of Works in Response PM 6
to Dominican Barangay's Request for a Parking Building.
***Photo documentation

***Data Gathering
DATA GATHERING/INQUIRY
2 SITE VISITATIONS/INSPECTIONS,
PHOTO DOCUMENTATIONS, ***On-site Interview
3.) Conduct Site Visitation at Jacinto Street to check the accomplishment for the murals together with Sir Darwin Aliga 7

4.) Site inpection at Leonard wood (Verify extent of excavation for the accommodation of the garden design) together with AM/PM 7
Sir Darwin Aliga
5.) PROPOSED COLLAPSIBLE PARKING BUILDING FEASIBILITY INSPECTION AND INVESTIGATION: Site Inspection/Visitation at
Raja Soliman Street/Jacinto Street and C.M. Recto

***Photo documentation
PM 10
***Data Gathering

***On-site
6.) PROPOSED Interview PARKING BUILDING FEASIBILITY INSPECTION AND INVESTIGATION: Site Inspection/Visitation at
COLLAPSIBLE
FORBES PARK/GOVERNOR PACK ROAD/

***Photo documentation
AM 11
***Data Gathering

***On-
site Interview
7.) PROPOSED COLLAPSIBLE PARKING BUILDING FEASIBILITY INSPECTION AND INVESTIGATION: Site Inspection/Visitation at
CABINET-TEACHERS CAMP/GIBRALTAR
DATA GATHERING/INQUIRY
2 SITE VISITATIONS/INSPECTIONS, ***Photo documentation
PHOTO DOCUMENTATIONS, PM 11
***Data Gathering

***On-site
Interview
8.) PROPOSED COLLAPSIBLE PARKING BUILDING FEASIBILITY INSPECTION AND INVESTIGATION: Site Inspection/Visitation at
SOUTHDRIVE

***Photo documentation AM 13
***Data Gathering

1. SUBJECT: Re: Request for Dredging/ Declogging of Canal at Loakan Airport Service/Access Road. ***On-site Interview
***Recipient: HON. BENJAMIN B. MAGALONG, City Mayor, City Mayor’s Office, City Hall, Baguio City
***Recipient: MR. ROSITO G. TAMAYO Jr., Officer-In-Charge, Civil Aviation Authority of the Philippines, Brgy. Loakan, Baguio City

***Recipient: RENE F. ZARATE, District Engineer, BCDEO-DPWH, Engineer’s Hill, Baguio City 4

***Recipient: Edouard Emmanuel Pistola Cayetano, Punong Barangay, Loakan Proper Barangay, Baguio City

2.) Flooding incident inspection report that transpired on September 27,2023 at the residence of Ms. Shellou Mangatan, situated at No.
19, Purok 5, Pinsao Pilot Tricom Village. (Letter dated September 2023 received by this Office on September 28, 2023 from Hon.
Benjamin B. Magalong, City Mayor, City Mayor’s Office, Baguio City in behalf of Ms. Mangatan.)
5
***Recipient: HON. BENJAMIN B. MAGALONG, City Mayor, City Mayor’s Office City Hall, Baguio City
***Recipient: MR. DEXTER O. FAG-AYAN, Punong Barangay, Pinsao Pilot
3 COMMUNICATIONS
3.) SUBJECT: Request to Retain Encroached Structure within the Right-Of-Way

***Recipient: HON. BENJAMIN B. MAGALONG, City Mayor, City Mayor’s Office City Hall, Baguio City 5

***Recipient: RAMZY KAIRUZ, Owner/Resident, Dominican Mirador, Lourdes Proper Barangay, Baguio City
3 COMMUNICATIONS

4.) Request for CCTV installation along the overpass since these structures fall within your office’s jurisdiction. (Letter dated September
22, 2023 from RENE F. ZARATE, District Engineer, Baguio City District Engineering Office-Department of Public Works and Highways
(BCCDEO-DPWH) which was received by the Planning, Programming, and Construction Division of this office on October 2, 2023, RE:
INSTALLATION OF CLOSE-CIRCUIT TELEVISION (CCTV) ON OUR OVERPASSES AND ON SOME IDENTIFIED AREAS IN BAGUIO.)
***Recipient: AR. JOHNNY A. DEGAY, City
Building Official, City Building Administrative Office (CBAO), Baguio City, 5
***Recipient: MR. RENE F. ZARATE,
District Engineer, Baguio City District Engineering Office, Department of Works and Highways, Engineers Hill, Baguio City
5.) SUBJECT: Request concerning the approval of additional work job on the ongoing barangay project entitled: “Improvement of
Barangay Hall, Multi-purpose Hall, Day Care Center of Barangay Fort Del Pilar.”
***Recipient: ROLANDO N. MARTOS, Punong Barangay, Fort Del Pilar Barangay, 6
Baguio City

6.) SUBJECT: SUBJECT: Response to Recommendation Item No.2, re: ROAD REHABILITATION AT PUROK 5, LOWER DAGSIAN.
***Recipient: MICHAEL L. 6
3 COMMUNICATIONS LAWANA, Punong Barangay, Lower Dagsian Barangay, Baguio City

7.) SUBJECT: A follow-up request to our previous communication dated August 2, 2023 requesting the cooperation of Barangay officials
in promptly consolidating information regarding their existing drainage system and transmitting it to the City Engineering Office.
***Recipient: MICHELLE AGBUYA, OIC-Community Affair Officer III, Special Service Division, City Mayor’s Office, 6
City Hall, Baguio City

1.) Project Monitoring and Supervision: "Rehabilitation and Improvement of Drainage Canal at Teacher's Village under GBS Construction
"
Contractor: GBS Construction

-7 workforce
-concreting of 27.5m of conc canal flooring 9
-2 x 7.3 m of concrete sidewalls
#cityprojectupdate
#cityengineeringoffice_baguio
#monitoring_and_supervisory_works
2.) Project Monitoring and Supervision:
Contractor: GBS Construction
Project Title: Sidewalk Recovery At Hillside Rd. Going to BCNHS Hillside Annex
4 FACEBOOK POST Manpower
Leadman: 1
Laborer:4
Activities:
-Clearing and Haul-out of Excavated Earth
-Backfilling 9
-Riprap Works
#cityprojectupdate
#cityengineeringoffice_baguio
#monitoring_and_supervisory_works

3.) Project Monitoring and Supervision:


Project Title: Recovery of Road Right-of-way Along Magsaysay Avenue From Lyman Ogilby Centrum Building Towards M. Roxas Road
Contractor: Jeros Construction
Manpower:
Site Project Engr: 1
Foreman: 1
Skilled: 2
Labor: 5
Activities:
1. Demolition of the Existing Encroached Residential Structure 9
2.. Installation of Column Reinforcement Bars
4.Riprap Works
#cityprojectupdate
#cityengineeringoffice_baguio
#monitoring_and_supervisory_works

4.) Project Monitoring And Supervision


“REPAIR AND REHABILITATION OF RAILINGS, SIDEWALK, MEDIAN DIVIDER, GEOMETRIC DESIGN AND STEEL GRATES AT CBD”
Activities:
1. Fabrication and Installation of formworks for bio retension slab (near and infront peliz loy- 2span)
2. Concrete pouring along the bio retension canal wall 1 span, beside vacant lot
3. Rebar installation for bio retension slab (near pelizloy) 1 span
4. Excavation work (close canal from BDO to tionsan)
Manpower:
4 FACEBOOK POST 1 foreman
4 skilled 9
7 labor
#cityprojectupdate
#cityengineeringoffice_baguio
#monitoring_and_supervisory_works

5.) Project Title: CONTINUING CANOPY, REHABILTATION OF ALLEY AND CANAL FROM CASTRO RESIDENCE TOWARDS DAGDAGUI
RESIDENT IN PUROK 4, MIDDLE ROCK QUARRY BARANGAY
Contractor: POKLES CONSTRUCTION
Manpower:
Project Proper
2-Skilled
1 -Labor
Activities:
1. Installation of Pre painted rib type roof. 9
#cityprojectupdate
#cityengineeringoffice_baguio
#monitoring_and_supervisory_works
#monitoring_and_supervisory_works
6.) Project Monitoring And Supervision
“REPAIR AND REHABILITATION OF RAILINGS, SIDEWALK, MEDIAN DIVIDER, GEOMETRIC DESIGN AND STEEL GRATES AT CBD”
Activities:
1. Concrete pouring of box culver canal flooring
2. Fabrication and installation of fomrworks for box culvert
3. Concrete pouring box culvert canal wall
4. Start chipping of bio retension canal wall (adjustment of height
Manpower:
1 foreman
3 skilled 9
10 labor
#cityprojectupdate
#cityengineeringoffice_baguio
#monitoring_and_supervisory_works

7.) Project Monitoring And Supervision


Project Title: Concreting of Montinola Street
4 FACEBOOK POST Manpower: 8
Activities: Concrete Pouring
#cityprojectupdate 9
#cityengineeringoffice_baguio
#monitoring_and_supervisory_works

8.) Project Monitoring And Supervision


Project Title: Continuation of Project Title: Continuation of Construction of Drainage at Purok 5, Gabriela Silang
Contractor: DJB Wayan Construction
Manpower: 8
Activities:
1: Removal of Forms
2. Plastering of Concreted Drainage
3. Excavation for the Drainage 9
#cityprojectupdate
#cityengineeringoffice_baguio
#monitoring_and_supervisory_works

9.) Project Monitoring And Supervision


Project Title:"Road Recovery from military Cut-off road to loakan road via sta scholastica barangay street" at sta scholastica
Contractor: Mhigs Construction
Manpower:
2 Backhoe Operator
3 Flagmen
2 Laborer
Equipment
-2 Backhoe
-3 Dump Trucks
Activities:
-Conducted Joint Inspection with BWD (engr. Brando Escano) regarding the Water pipe that will be affected by the proposed Drainage, and
discussed the strategies that will be executed to minimize further damage on the water pipe on the site.
-Excavation and Hauling out of Debris 9
- Facilitating the Traffic Flow at Hillside Road
-excavation of Soil for Grouted Riprap at Sta. 217 and Laying of Boulder at Sta. 0.16 (which not included part of the project-negligence of
the contractor)
#cityprojectupdate
#cityengineeringoffice_baguio
#monitoring_and_supervisory_works

10.) Project Monitoring And Supervision


4 FACEBOOK POST Project Title: 1.) Installation of Railings at Sector C (Nora Basto Residence going to creek sidewalk) Country Club Village
2.) Installation of Railings and Rehabilitation of Pathwalk at Sector A (infront of Lacson Residence going down to Padaoan Residence)
3.) Continuation of Canal at Sector C (Estal Residence going to Creek)
4.) Continuation of Canal at Sector G (Near Lawan residence cover canal)
#cityprojectupdate 9
#cityengineeringoffice_baguio
#monitoring_and_supervisory_works

11.) Project Monitoring And Supervision


Project Title:Project Title: Sidewalk Recovery At Hillside Rd. Going to BCNHS Hillside Annex
Contractor: GBS Construction
Manpower:
Site Project Engineer
Foreman: 1
Leadman Riprap: 1
Skilled: 3
Laborer:5
Activities: 10
-Riprap Works
-Masonry Works for Planters
-Lay Out of Sidewalk Prior to Pouring
-Clearing of Demolished Structure debris Near Rotunda
#cityprojectupdate
#cityengineeringoffice_baguio
#monitoring_and_supervisory_works
12.) Project Monitoring And Supervision
Project Title: Project Title: Recovery of Road Right-of-way Along Magsaysay Avenue From Lyman Ogilby Centrum Building Towards M.
Roxas Road
Manpower:
Foreman: 1
Skilled: 2
Labor: 4
Activities:
1. Demolition of the Existing Encroached Residential Structure
2. Installation of Column Formworks 10
3. Excavation For Column and Foundation layout
4.Riprap Works
#cityprojectupdate
#cityengineeringoffice_baguio
#monitoring_and_supervisory_works
4 FACEBOOK POST

13.) Project Monitoring And Supervision


Project Title: 1.) Installation of Railings at Sector C (Nora Basto Residence going to creek sidewalk) Country Club Village
2.) Installation of Railings and Rehabilitation of Pathwalk at Sector A (infront of Lacson Residence going down to Padaoan Residence)
3.) Continuation of Canal at Sector C (Estal Residence going to Creek)
4.) Continuation of Canal at Sector G (Near Lawan residence cover canal)
#cityprojectupdate 10
#cityengineeringoffice_baguio
#monitoring_and_supervisory_works

Creation of Visual Aide/Presentation 1.) VARIOUS LOCATION IN BAGUIO CITY FOR THE PROBABLE CONSTRCUTION OF A PROPOSED COLLAPSIBLE PARKING BUILDING 13,14
5
Materials 2.) CONSOLIDATION OF COMPREHENSIVE DRAINAGE MASTER PLAN FOR THE WHOLE BAGUIO 6,7,9,10,12,13,14
Prepared by: Reviewed by:

Karen T. Guillermo Richard Benjamin L. Lardizabal


Supervising Assistant Division Head

NOTED:

EDGAR VICTORIO R. OLPINDO


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC)


Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: October 7 and 14, 2023

Supervision and Monitoring of Infrastructure Projects for the given period.

ACTIVITIES
1 Creation of Program of Works 1.) Multi-Purpose 2 Storey Building with First Floor and Roof Deck Parking Area at Dominican Mirador fronting the Barangay Hall 7,14
DATA GATHERING/INQUIRY 1.) Conduct Site Visitation at Jacinto Street to check the accomplishment for the murals together with Sir Darwin Aliga AM 7
SITE VISITATIONS/INSPECTIONS, 2.) Site inpection at Leonard wood (Verify extent of excavation for the accommodation of the garden design) together with Sir PM 7
2 PHOTO DOCUMENTATIONS,

Creation of Visual Aide/Presentation 1.) VARIOUS LOCATION IN BAGUIO CITY FOR THE PROBABLE CONSTRCUTION OF A PROPOSED COLLAPSIBLE PARKING BUILDING 14
4
Materials 2.) CONSOLIDATION OF COMPREHENSIVE DRAINAGE MASTER PLAN FOR THE WHOLE BAGUIO 7,14

Prepared by: Reviewed by:

Karen T. Guillermo Richard Benjamin L. Lardizabal


Supervising Assistant Division Head

NOTED:

EDGAR VICTORIO R. OLPINDO


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC)


Website:http://www.baguio.gov.ph
Republic of the Philippines
CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: October 16-25, 2023

Supervision and Monitoring of Infrastructure Projects for the given period.


Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Expected Date of Date of Percentage of REMARKS (On-going,Lapsed, SWO-date,
Completion Designation Completion RWO- Date, New Expected date of
Previous Present completion)
IMPROVEMENT OF LOADING AND
NORBANO BUILDERS by:
1 UNLOADING BAY AREAS ON VARIOUS LDF 2022 5/25/2022 8/18/2023 6/15/2023 67.70% 86.67% Project Suspended as of June 20
Norris Anoyan
ROADS

CONSTRUCTION OF SIDEWALK A.P. NA-OY


RECOVERY AND IMPROVEMNET CONSTRUCTION, SUPPLY
2 IRA 9/20/2023 11/16/2023 2/17/2023 30.00% 40.00% BEHIND-SCHEDULE
FROM JOSE FELIPE STREET TO AND AGGREGATES BY:
LEGARDA ROAD ANTONIO P. NA-OY

ACTIVITIES
1.) IMPROVEMENT OF THE COMMUNITY MULTI-PURPOSE GROUND OF DOMINICAN MIRADOR BARANGAY. 20,23,24,25
2.b) CONSOLIDATION OF COMPREHENSIVE DRAINAGE MASTER PLAN FOR THE WHOLE BAGUIO 16, 17,18,19,

PHASE 1: DATA GATHERING AND CONSOLIDATION

***Data Gathering:Request drainage-related data from all barangays within the


city.
***Collect data from the DPWH related to regional drainage infrastructure.
***Compile and organize collected data.
CREATION OF PROGRAM OF
1
WORKS/TECHNICAL DRAWINGS PHASE II: DATA VALIDATION (In coordination with the CEO-SURVEY DIVISION)
***Verify the accuracy and completeness of collected data.
***Resolve any discrepancies or missing information through communication with barangays and DPWH.

PHASE III: DATA CONSOLIDATION (In coordination with the CEO-SURVEY DIVISION)
***Integrate all validated data into a central database.
***Establish a standardized format for data storage.

PHASE IV: DATA QUALITY ASSURANCE (In coordination with the CEO-SURVEY DIVISION)
2.b) CONSOLIDATION OF COMPREHENSIVE DRAINAGE MASTER PLAN FOR THE WHOLE BAGUIO 20,23,24,25

PHASE V: ANALYSIS AND


INTERPRETATION (In coordination with the CEO-SURVEY DIVISION)
*** AutoCAD Design: Use AutoCAD software to create detailed engineering drawings and plans based on the consolidated data.
CREATION OF PROGRAM OF Design the city's drainage system with a focus on flood prevention and mitigation.
1 Google Earth GIS Integration
WORKS/TECHNICAL DRAWINGS
***Google Earth GIS: Import the AutoCAD designs into Google Earth GIS for spatial analysis and visualization.
Overlay drainage plans on geographic data to identify potential problem areas.

3.) IMPROVEMENT OF LOADING AND UNLOADING BAY AREAS ON VARIOUS ROADS (V.O.2) 23,24,25
1.) SUBJECT : Response to the Memorandum Report of Engr. Jason T. David, dated October 3, 2023 re: “ACTION TAKEN ON THE ON-
GOING CONSTRUCTION OF SIDEWALK RECOVERY AND IMPROVEMENT AND REHABILITATION OF DRAINAGE ALONG SAN ROQUE
BARANGAY.”

Content: BASIS : Letter dated October 5, 2023 received by the CEO-PPC Division on October 9, 2023 from Engr. Rene F.
Zarate, District Engineer, Baguio City District Engineering Office, Department of Public Works and Highways. (Responses to the statements
2 COMMUNICATIONS on the aforementioned memorandum report of Engr. David.) 17,18
***Recipient: HON. BENJAMIN B. MAGALONG, City Mayor, City Mayor’s Office, City Hall, Baguio City

***Recipient: KHADAFFY TANGGOL, Regional Engineer, DPWH-CAR, Engineer’s Hill

***Recipient: RENE F. ZARATE, District Engineer, BCDEO-DPWH, Engineer’s Hill, Baguio City
3 Meetings Attended 1.) PUBLIC CONSULTATION CONVENTION: (OCT 16,2023) "REDEVELOPMENT OF SESSION ROAD AT BAGUIO CONVENTION CENTER" 16
Prepared by: Reviewed by:

Karen T. Guillermo Richard Benjamin L. Lardizabal


Supervising Assistant Division Head

NOTED:

EDGAR VICTORIO R. OLPINDO


City Engineer

Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC)


Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: October 26-31, 2023
Supervision and Monitoring of Infrastructure Projects for the given period.
Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Expected Date of Date of Percentage of REMARKS (On-going,Lapsed, SWO-date,
Completion Designation Completion RWO- Date, New Expected date of
Previous Present completion)

IMPROVEMENT OF LOADING AND


NORBANO BUILDERS by:
1 UNLOADING BAY AREAS ON VARIOUS LDF 2022 5/25/2022 8/18/2023 6/15/2023 67.70% 67.70% Project Suspended as of June 20
Norris Anoyan
ROADS

CONSTRUCTION OF SIDEWALK A.P. NA-OY


RECOVERY AND IMPROVEMNET CONSTRUCTION, SUPPLY
2 IRA 9/20/2023 11/16/2023 2/17/2023 40.00% 60.00% BEHIND-SCHEDULE
FROM JOSE FELIPE STREET TO AND AGGREGATES BY:
LEGARDA ROAD ANTONIO P. NA-OY

ACTIVITIES
1.) IMPROVEMENT OF THE COMMUNITY MULTI-PURPOSE GROUND OF DOMINICAN MIRADOR BARANGAY. 26,27
2.) CONSOLIDATION OF COMPREHENSIVE DRAINAGE MASTER PLAN FOR THE WHOLE BAGUIO 26,27

CREATION OF PROGRAM OF
1
WORKS/TECHNICAL DRAWINGS

PHASE V: ANALYSIS AND INTERPRETATION (In coordination with the CEO-


SURVEY DIVISION)
*** AutoCAD Design: Use AutoCAD software to create detailed engineering drawings and plans based on the consolidated data.
Prepared by: Design the city's drainage system with a focus on flood prevention and mitigation. Reviewed by:

Karen T. Guillermo Richard Benjamin L. Lardizabal


Supervising Assistant Division Head

NOTED:

EDGAR VICTORIO R. OLPINDO


City Engineer
Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC)
Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: November 1-15, 2023

Supervision and Monitoring of Infrastructure Projects for the given period.


Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Expected Date of Date of Percentage of REMARKS (On-going,Lapsed, SWO-date,
Completion Designation Completion RWO- Date, New Expected date of
Previous Present completion)

IMPROVEMENT OF LOADING AND


NORBANO BUILDERS by:
1 UNLOADING BAY AREAS ON VARIOUS LDF 2022 5/25/2022 8/18/2023 6/15/2023 67.70% 67.70% Project Suspended as of June 20
Norris Anoyan
ROADS

CONSTRUCTION OF SIDEWALK A.P. NA-OY


RECOVERY AND IMPROVEMNET CONSTRUCTION, SUPPLY
2 IRA 9/20/2023 11/16/2023 2/17/2023 60.00% 65.00% BEHIND-SCHEDULE
FROM JOSE FELIPE STREET TO AND AGGREGATES BY:
LEGARDA ROAD ANTONIO P. NA-OY

ACTIVITIES
1.) IMPROVEMENT OF THE COMMUNITY MULTI-PURPOSE GROUND OF DOMINICAN MIRADOR BARANGAY. 7,8,9,10,13,14
2.) CONSOLIDATION OF COMPREHENSIVE DRAINAGE MASTER PLAN FOR THE WHOLE BAGUIO 8, 10,14

PHASE II: DATA VALIDATION (In coordination with the CEO-SURVEY DIVISION)
***Verify the accuracy and completeness of collected data.
***Resolve any discrepancies or missing information through communication with barangays and DPWH.

PHASE III: DATA CONSOLIDATION (In coordination with the CEO-SURVEY DIVISION)
CREATION OF PROGRAM OF ***Integrate all validated data into a central database.
1 ***Establish a standardized format for data storage.
WORKS/TECHNICAL DRAWINGS
PHASE IV: DATA QUALITY ASSURANCE (In coordination with the CEO-SURVEY DIVISION)

***Perform quality checks to ensure the data's


consistency and reliability.
***Address any data quality issues.

PHASE V: ANALYSIS AND INTERPRETATION (In coordination with the CEO-SURVEY DIVISION)
*** AutoCAD Design: Use AutoCAD software to create detailed engineering drawings and plans based on the consolidated data.
Design the city's drainage system with a focus on flood prevention and mitigation.
Google Earth GIS Integration
1.) SUBJECT : Response to Mrs. JANIELOU L. AQUINO's request for permission to utilize the road-right-of-way for parking due to the
ongoing city project affecting her road-right-of-way.
CONTENT:

•Certification (Authorization for Road-Right-of-Way Parking)


2 COMMUNICATIONS 8
Notification and Authorization for Road-Right-of-Way

***Recipient: JANIELOU L. AQUINO,Resident,l Purok 3#16-A1 City Camp Proper, Baguio City

***Recipient: JAIME S. BUSTARDE, Punong Barangay, City Camp Proper


1.)Current Updates of Infrastructure Projects funded by DRRM Fund CY 2023 (CEO-PPC)

CONTENT: The City Disaster Risk Reduction and Management Council conducted a 4th QUARTER COUNCIL MEETING last
November 8,2023 held at The Plaza Garden Hotel and Residences at Legarda Road. (Engr. Rodel Q. Lagare from the City Engineering Office
shared the latest developments on infrastructure projects financed by the Disaster Risk Reduction and Management (DRRM)
Fund for the year 2023. According to the data, eight (8) projects have been successfully completed, and there are
currently thirteen (13) construction projects in progress. Ma'am May Grace Palicdon-CBO, a member of the Technical Working Group/Bids 8
and Awards Committee (TWG/BAC), added that all projects planned by the City Engineering Office have already been granted to successful
bidders, and they are now anticipating the issuance of the "Notice to Proceed."

3 FACEBOOK POST
2.)Joint Inspection and discussions for DILG Funded Projects under Local Government Support Fund – Financial Assistance
to Local Government Units (LGSF-FALGU)
CONTENT: A meeting was
conducted in the CEO conference room post-inspection to address matters related to the utilization of the fund by DILG. (The DILG Central
Office emphasized that the LGSF-FALGU fund's validity, including disbursement, extends only until
December 31, 2023, as outlined in the General Appropriations Act, FY 2022 Section 68.To comply with DILG requirements, 14
essential documents such as the Project Completion Report, updated quarterly Fund Utilization Report, and Documentary
Compliance (Aid Memoir) are necessary. Additionally, project status updates, accompanied by documentary pictures, are to
be regularly uploaded to the Subaybayan website on a weekly basis.

Prepared by: Reviewed by:

Karen T. Guillermo Richard Benjamin L. Lardizabal


Supervising Assistant Division Head

NOTED:

EDGAR VICTORIO R. OLPINDO


City Engineer
Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: November 16-30, 2023

Supervision and Monitoring of Infrastructure Projects for the given period.


Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Expected Date of Date of Percentage of REMARKS (On-going,Lapsed, SWO-date,
Completion Designation Completion RWO- Date, New Expected date of
Previous Present completion)
IMPROVEMENT OF LOADING AND
NORBANO BUILDERS by:
1 UNLOADING BAY AREAS ON VARIOUS LDF 2022 5/25/2022 8/18/2023 6/15/2023 67.70% 67.70% Project Suspended as of June 20
Norris Anoyan
ROADS ACTIVITIES
CREATION OF PROGRAM OF 1.) IMPROVEMENT OF THE COMMUNITY MULTI-PURPOSE GROUND OF DOMINICAN MIRADOR BARANGAY. 17,21,29
1
WORKS/TECHNICAL DRAWINGS 2.) CONSOLIDATION OF COMPREHENSIVE DRAINAGE MASTER PLAN FOR THE WHOLE BAGUIO 21,30
1.) SUBJECT : Response to Mrs. JANIELOU L. AQUINO's request for permission to utilize the road-right-of-way for parking due to the
ongoing city project affecting her road-right-of-way.
CONTENT:

•Certification (Authorization for Road-Right-of-Way Parking)


17
Notification and Authorization for Road-Right-of-Way

***Recipient: JANIELOU L. AQUINO,Resident,l Purok 3#16-A1 City Camp Proper, Baguio City

***Recipient: JAIME S. BUSTARDE, Punong Barangay, City Camp Proper


3.) Acknowledging the initiative of PHILSURV to aid the government of Baguio in the collection and mapping of data through LIDAR.

2 COMMUNICATIONS 1. TRAFFIC AND TRANSPORTATION MANAGEMENT DIVISION (TTMD) /+/ ELECTRICAL DIVISION
"Integrated Digital Mapping for Enhanced Urban Mobility: A Comprehensive Approach for Baguio City's Traffic and Transportation
Management"
2.) MAINTENANCE DIVISION
"Infrastructure Resilience Mapping for Sustainable Urban Maintenance: A Comprehensive Strategy for Baguio City"
21
3.) SURVEY DIVISION
"Geospatial Mapping for Informed Development” ***Sent to
PHILSURV email

3.)Indorsement Letter to CBAO; re: ILLEGAL DEMOLITION anD BuilDING; ILLEGAL BLOCKAGE OF RIGHT-OF-WAY
29
***Recipient: AR JOHNNY DEGAY
1.) FILING: LATEST UPDATE REGARDINGTHE SUBMISSION OF PROJECT PROPOSALS FOR 2025 ROADS LEVERAGING LINKAGES OF
INDUSTRY AND TRADE (ROLL IT) 2.0 - "LOGISTICS EFFICIENCY AND TRANSPORT SEAMLESSNESS TO ENHANCE AGRIBUSINESS TRADE
"LETS EAT PROGRAM" in PARTNERSHIP WITH DPWH 17
CONDUCTED ***REFORMULATED DTI-DPWH CONVERGENCE PROGRAM REVISED GUIDELINES AND PROCESSES
ASSISTANCE/COORDINATION WITH
3 2.) COORDINATION WITH MRS. RODRIGUEZ RE: PROPOSED PROJECT OF BARANGAY FOR THE CONSTRUCTION OF THE COVERED COURT
FOCAL
PERSONS/FILING/INVESTIGATIONS SITUATION JUST ADJACENT TO THEIR PROPERTY. 17

3.) Investigation at Carino Street for illegal RROW with Ar Darwin Aliga 29
4.) COMPILATION, REASSESSMENT AND EVALUATION OF THE RECEIVED DRAINAGE MASTERPLANS OF EACH BARANGAY 17,21,29,30
MEETING WITH THE DIVISION HEADS RE: PHILSURV to aid the government of Baguio in the collection and mapping of data through
LIDAR. To systematically enumerate the necessary data through a comprehensive approach in addressing the data requirements of the
City Engineering Office in the creation of the interconnected mapping system poised to enhance decision-making processes, improve
4 MEETING maintenance strategies, and promote sustainable urban development in Baguio City. 17

Prepared by: Reviewed by:

Karen T. Guillermo Richard Benjamin L. Lardizabal


Supervising Assistant Division Head

NOTED:

EDGAR VICTORIO R. OLPINDO


City Engineer
Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947
Republic of the Philippines
CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: December 1-15, 2023

Supervision and Monitoring of Infrastructure Projects for the given period.


Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Expected Date of Date of Percentage of REMARKS (On-going,Lapsed, SWO-date,
Completion Designation Completion RWO- Date, New Expected date of
Previous Present completion)

IMPROVEMENT OF LOADING AND


NORBANO BUILDERS by:
1 UNLOADING BAY AREAS ON VARIOUS LDF 2022 5/25/2022 8/18/2023 6/15/2023 67.70% 67.70% Project Suspended as of June 20
Norris Anoyan
ROADS
ACTIVITIES
1.) IMPROVEMENT OF THE COMMUNITY MULTI-PURPOSE GROUND OF DOMINICAN MIRADOR BARANGAY. 4,5,6,7,13,14,15
2.) CONSOLIDATION OF COMPREHENSIVE DRAINAGE MASTER PLAN FOR THE WHOLE BAGUIO 4,5,6,7

CREATION OF PROGRAM OF
1
WORKS/TECHNICAL DRAWINGS
PHASE V: ANALYSIS AND
INTERPRETATION (In coordination with the CEO-SURVEY DIVISION)
*** AutoCAD Design: Use AutoCAD software to create detailed engineering drawings and plans based on the consolidated data.
Design the city's drainage system with a focus on flood prevention and mitigation.
Google Earth GIS Integration
1.) SUBJECT : Subject: Urgent Request for Assistance Regarding Pine Tree Evaluation in Diverging Road Construction Project

CONTENT: Seek your valuable assistance in evaluating a situation concerning a pine tree located at the center isle of the
diverging road where Claro M. Recto Road intersects with Legarda Road.
***Recipient: ENGR. JEAN C. BORROMEO, OIC-Regional Director, Environmental Management Bureau-CAR, DENR-CAR, Gibraltar 5
Road, Baguio City
***Recipient: ATTY. RHENAN G. DIWAS, Department Head, City Environment and Parks Management Office, CEPMO, City Hall,
Baguio City

2.) Subject: Evaluation of Drainage System Plan for their parcel of land at Maryland Subdivision, Irisan.
2 COMMUNICATIONS ***Recipient: Mrs. BEATRIZE CABANNAG ET AL. Constituent, 328 Purok 14 UP Village, Irisan, Baguio City 6
2 COMMUNICATIONS

3.)Subject: Urgent: Meeting Request for Critical Project Design Discussion Concerning Aguinaldo Park, Session Road, Jacinto and
Carantes Street including the Proposed Steel Parking
AGENDA:

1.) Establishing a sequential Order for the Design Process, 13

2.) Feasibility Study Evaluation,

3.) Proposed
3.) ASSIST ENGINEERING STUDENTS OF SLU RE: FACILITIES LAY-OUT AND DESIGN Steel Parking
LABORATORY AT THE CITY ENGINEERING OFFICE MAIN
BUILDING 13

COMMUNICATIONS 4.) Assisted in Admin works at the PPC Division in lieu of the absenceof Sir King 14
5.) Assisted in the Decoration of the Stage at the Maintenance Division for the 2023 CEO CHRISTMAS PARTY 14
6.) COMPILATION, REASSESSMENT AND EVALUATION OF THE RECEIVED DRAINAGE MASTERPLANS OF EACH BARANGAY 4,5,6,7,13,15
MEETING WITH THE BARANGAY OFFICIALS, PUJ ASSOCIATIONS AND THE CITY ENGINEERING OFFICE FOCAL PERSONNELS RE: REPAIR OF
THE BARANGAY ROAD FROM MT. CREST HOTEL TO THE BOUNDARIES OF CITY CAMP PROPER AND LOWER ROCK QUARRY AT JOSE
4 MEETING FELIPE STREET. 5

Prepared by: Reviewed by:

Karen T. Guillermo Richard Benjamin L. Lardizabal


Supervising Assistant Division Head

NOTED:

EDGAR VICTORIO R. OLPINDO


City Engineer
Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947

Republic of the Philippines


CITY ENGINREERING OFFICE
City Government of Baguio

ACCOMPLISHMENT REPORT
For the Period: December 16-31, 2023

Supervision and Monitoring of Infrastructure Projects for the given period.


Title of Supervised Projects Source of Fund Name of Contractor Date of NTP Expected Date of Date of Percentage of REMARKS (On-going,Lapsed, SWO-date,
Completion Designation Completion RWO- Date, New Expected date of
Previous Present completion)

IMPROVEMENT OF LOADING AND


NORBANO BUILDERS by:
1 UNLOADING BAY AREAS ON VARIOUS LDF 2022 5/25/2022 8/18/2023 6/15/2023 67.70% 67.70% Project Suspended as of June 20
Norris Anoyan
ROADS

ACTIVITIES
1.) IMPROVEMENT OF THE COMMUNITY MULTI-PURPOSE GROUND OF DOMINICAN MIRADOR BARANGAY. 18,19
2.) CONSOLIDATION OF COMPREHENSIVE DRAINAGE MASTER PLAN FOR THE WHOLE BAGUIO 20

CREATION OF PROGRAM OF
1
WORKS/TECHNICAL DRAWINGS
PHASE V: ANALYSIS AND
INTERPRETATION
*** AutoCAD Design: Use AutoCAD software to create detailed engineering drawings and plans based on the consolidated data.
Design the city's drainage system with a focus on flood prevention and mitigation.
1.) SUBJECT : REQUEST FOR DETAILED BUDGETARY LIQUIDATION OF CITY ENGINEERING OFFICE CHRISTMAS PARTY EXPENSES

CONTENT: The objective is to provide clarity on how the allocated funds were utilized and to ensure transparency within our
2 COMMUNICATIONS department. This information will not only enhance transparency but will also contribute to a culture of accountability within our 18
organization. We kindly request the submission of the detailed budgetary liquidation for the City Engineering Office Christmas party
expenses by Friday, December 22, 2023.
***Recipient: EDGAR VICTORIO R.OLPINDO, City Engineer

2.) Subject: SUMMARY OF THE REPORT: SUMMARY OF THE REPORT: KEY POINTS AND DECISIONS MADE DURING THE MEETING
INITIATED BY THE CITY ENGINEERING OFFICE (CEO) CONCERNING THE UPCOMING CRITICAL PROJECTS AT AGUINALDO PARK, SESSION
ROAD, JACINTO AND CARANTES STREET INCLUDING THE PROPOSED STEEL PARKING.
CONTENT: 1. REDEVELOPMENT OF AGUINALDO PARK (Master Plan Development/Collaboration with SAN
MIGUEL CORPORATION/Collaboration with CEPMO/Drainage System Integration/Sewerage System Consideration/Moat
ProposalD/Drainage Rerouting/Submission and Funding; 2. PROPOSED STEEL PARKING PROPOSAL (GIBRALTAR ROAD/GOVERNOR PACK
ROAD/ RAJA SOLIMAN ROAD) 3. ROAD DEVELOPMENT AT CARANTES AND E. JACINTO STREET
***Recipient: ATTY. ALTHEA ROSANNA V. ALBERTO, Legal Officer, Legal Office Department City Hall, Baguio City
***Recipient: AR. JOHNNY A. DEGAY, City Building Official, City
Building Administrative Office (CBAO) DPS Compound, Baguio City
***Recipient: AR. DONNA RILLERA-TABANGIN, City Planning and Development Officer, City Planning and Development Office City Hall, 19,20,27
Baguio City
***Recipient: ATTY. RHENAN G. DIWAS, Department Head, City Environment and Parks Management Office CEPMO, City Hall, Baguio City
***Recipient: MS.
NORMITA B. RAMON, Officer-In-Charge, Assessor’s Office, City Hall, Baguio City, submitted by KAREN T. GUILLERMO,
***Recipient: ENGR. LEANDRO L. DE JESUS,
2 COMMUNICATIONS Department Head, City Environment And Natural Resources Office (CENRO-DENR), DENR Compound, Gibraltar, Baguio City

3.)Subject: Subject: Notice of Violation - Illegal Construction or Erection of Any Kind of Structure on Public Land
***Recipient: MS. CHRISTINE MAE PATALIN, Homeowner Representative, 10C Apostol St. Gibraltar, Baguio City 27

4.)Subject: Subject: Notice of Violation - Illegal Construction or Erection of Any Kind of Structure on Public Land
***Recipient: SPS. MR. and MRS. GUILLERMO, Homeowner, 20C Apostol St. Gibraltar, Baguio City 27
4.)Subject: Subject: SHOW CAUSE ORDER- 2ND AND FINAL NOTICE
RE: "SIDEWALK RECOVERY AND IMPROVEMENT AND REHABILITATION OF DRAINAGES at DOMINICAN HILL ROAD, LOURDES PROPER, SAN
ROQUE" 27
***Recipient: JOSELITO F. RAMOS, Contractor, JEROS CONSTRUCTION, Baguio City

Coordinate with Sir Joel for the content of the 8 supervising assistnt job vacancy posting
18
Coordinate with Sir Wilbur Laguinday on the pre-assessment of the CEO Facebook page for the inclusion and participation of the PPC
Division on the postings herewith 20,21,22
COORDINATION
Coordinate with AR Bruce Layugan and AR Daryl Lardizabal of CPDO Regarding the conceptual content and paradigms that may be
applicable for the Aguinaldo Park Redevelopment 20,22

1. POSTING: JOB SEEKERS : EIGHT (8) JOB VACANCIES FOR SUPERVISING ASSISTANTS
***Creation and editing of Official Post
FACEBOOK 18
***Coordinate with SAO for the content and offiicial FB Posting
Meeting for Critical Project Design Discussion for 2024
Meeting Date: December 19, 2023 (TUESDAY)
Time: 2:00 IN THE AFTERNOON
Location: MULTIPURPOSE HALL OF THE BCDEO-DPWH BUILDING
Attendees: 10 PARTICIPANTS
o CEO (City Engineering Office)
4 MEETING o CPDSO (City Planning Development and Sustainability Office) 19
o CEPMO (City Environmental and Parks Management Office)
o CLO (City Legal Office)

Prepared by: Reviewed by:

Karen T. Guillermo Richard Benjamin L. Lardizabal


Supervising Assistant Division Head

NOTED:

EDGAR VICTORIO R. OLPINDO


City Engineer
Tel. Nos. (O74) 442-8930 (CE ) 445-2058 (Admin.) 445-3667 (PPC) Website:http://www.baguio.gov.ph
Telefax No.(O74)445-2947