Professional Documents
Culture Documents
Jesco Project Ra
Jesco Project Ra
Area / Activity Assessed: This document shall cover all activities related to installation of Fire Fighting System.
Prepared By: Severity (S) Frequency (F) Risk Rating (RR) Very High High Medium Low
PM-Project Manager R=S x F 15-25 8-12 4-6 1-3
SM-Site Manager
HSE Manager 1 Minor Injury 1 Improbable Unacceptability limits S 5 4 3 2 1 F
SS-Site supervisor ( / Sub-con) 2 Major single injury 2 Possible More than 6 is unacceptable re-assess 5 25 20 15 10 5
SC-Sub-contractor 3 Major multiple injury 3 Occasional task and preventive actions.
4 20 16 12 8 4
SPIC-Site person in charge 4 Single death 4 Frequent
3 15 12 9 6 3
5 Multiple deaths 5 Regular
S = 0 id deemed to be the limit of 2 10 8 6 4 2
practicability of control measures. 1 5 4 3 2 1
Risk Rating Action RR Rating
Job Task Hazard Necessary Control Measures
S F Rating By S L Rating
Slip, trip &fall Ensure easy and open access to all exits (including ladders, staircases,
Site Supervisor &
Lack of supervision scaffolds, and gangways), fire-alarm boxes, fire extinguishing equipment and
House Keeping 3 4 12 Foremen & Safety 2 1 3
Fire hazard fire call stations. Officer
Poorly stacked material
Dispose of oils, paint thinners, solvents, rags, scraps, waste, or other
flammable and combustible substances, or store them in covered fire-
resistant containers, at the end of each work shift or when the job is
complete, whichever occurs first.
Maintain walkways so that they provide adequate passage and are:
Cordon off any portion of a walkway that is being used as a working surface.
Make sure working surfaces are free from all tools, materials, and
equipment not necessary to perform the job in progress. All debris, including
liquid and solid waste, must be cleared at the end of the job or work shift,
whichever occurs first.
Keep working surfaces dry, when possible. If a wet process is used,
drainage must be maintained and dry standing places made available, or
workers provided with protective footgear when such means are not
practicable.
Avoid stringing cords, hoses or lines across walkways. Use "S" and "J" hooks
and cable trees to keep lines out of walkways. If lines must cross walkways,
cover the lines.
Remove, repair, and/or report housekeeping hazards.
Take time to stack materials, boxes and packages properly.
Place all rubbish in skips, don’t let it accumulate.
Check the lighting of passage ways and place of work.
If they are not working or inadequate, tell your supervisor
Installing catch platforms below work areas to catch any fallen materials or
tools.
Ensuring loads are stable and secured before lifting or transferring.
Wearing suitable PPE (Helmet and safety shoes).
All operatives must be site inducted.
Head and physical Do not remove any ceiling yourself without the management permission.
injuries If you have any work inside the ceiling consult with the management, after
Fractures. theirs authorized persons will open the ceiling, then you can proceed your Site Supervisor &
Collapse of
Water leakages inside work. Foremen & Safety
ceiling, Wall 3 4 12 1 2 2
the ceiling. Do not enter inside the ceiling and stand the above of ceiling. Officer
& Floor
Entering inside the Use A type ladder for ceiling work.
ceiling It can collapse. If any water leakages founded inside the ceiling, all joints must have fitted
properly.
Full time supervision is mandatory.
Work permit to be obtained, fall protection system to be in place as required.
Any work above 1.8 meters from ground level should be wear fully body
harness.
All working platforms shall be inspected by competent person and equipped
with low, mid and high rail.
Toe boards to be installed, underneath is to be barricaded and secured.
All persons to be off the tower when it is being moved/repositioning to the
next location.
Fallings form height Remove material and equipment’s while repositioning, ensure scaffold tower
Material falling not touch/contact with energized cables. Site Supervisor &
Working at
Overturn 5 4 20 Accesses and egress walk way shall be maintained & secured. Foremen & Safety 3 1 3
height
Damage structure Use full body harness, shock absorber must not be used below 6 MTR, only Officer
Death harness with lanyard will be allowable, prepared body harness check list
monthly basis.
Only operative with working at height training to use the MTS.
Personal fall protection (full body harness) shall be inspected prior to wear
and worn properly and must be tied to adequate anchor point and 100% tie
off is to be maintained.
Only scaffolding inspector should be inspecting the MTS,
Scaffolding tag must be updated with weekly basis with scaffolding inspector.
Full time supervision required.
Smoking. All Operatives must be site inducted.
Site Supervisor &
Trash. Permit to work
Foremen & Safety
Fire Electrical appliances. 4 4 16 All operative must be trained and competent. 1 2 2
Officer
Storage. Smoking only in designated area.
Heating. If any hot work activity is performing on site, use hot work permit.
10 | P a g e JCI H E A L T H S A F E T Y & E N V I R O N M E N T
Risk Rating Action RR Rating
Job Task Hazard Necessary Control Measures
S F Rating By S L Rating
11 | P a g e JCI H E A L T H S A F E T Y & E N V I R O N M E N T
Risk Rating Action RR Rating
Job Task Hazard Necessary Control Measures
S F Rating By S L Rating
Inadvertently/suddenly Equipment should be in good condition, with double insulated cables and use
increase of pressure proper industrial power plugs, only competent trained persons should work
gauges. on electrical distribution panel.
Substandard supports Rating of fittings, pressure gauges, vent valves, gaskets shall be suitable for
Electrocution hazard the test pressure.
Physical injuries Ensure all fittings, couplings and supports properly fitted.
Slip hazard. Ensure air vent provided at the highest elevation.
Pressure should be raised gradually under control to allow time for pipes to
strain and time for personnel to check for leaks.
There shall be at least two pressure gauges, one at lowest point and another
at the highest point in the system.
Hydro testing crew should not stay in the direction of the blind flanges to
prevent injury in case of flange rapture.
All hoses/ piping/gaskets and connectors/clamps shall be of adequate
rating to withstand pressure.
Whip lash arrestor shall be provided at hose connection.
Personnel shall not approach the system under high Pressure.
Only essential and trained persons shall be allowed at the Hydro test work
location.
After completed work, don’t release the water on walking area or access,
must be release water in drum or any storage container.
Access shall be free from any obstacle.
Supervisors shall be present at work location during hydro testing activities
are done.
Maintain good housekeeping.
All operatives must be site inducted.
Permit to work.
All operatives must be trained for how to safe in chemical emergencies.
In case of any chemical emergency occurred on site, if you come in contact
Exposure to Inhalation with a known or un known chemical you should evacuate the area
Site Supervisor &
chemicals during Irritation. immediately as soon as you can, reach assembly point and calling site
Foremen & Safety
chemical Ingestion hazard 3 4 12 emergency contact responsible person. 1 2 2
Officer
emergencies. Skin allergies. If you are trained and competent, identify the substances and determine the
risk
Protect yourself, stop the spill and minimize the risk, clean up the spill
decontaminated the area and affected equipment.
Wear fully PPE (Cover all and SCBA).
12 | P a g e JCI H E A L T H S A F E T Y & E N V I R O N M E N T
Risk Rating Action RR Rating
Job Task Hazard Necessary Control Measures
S F Rating By S L Rating
Sharp Objective All operatives must be site inducted. Site Supervisor &
during work 3 3 9 Permit to work Foremen & Safety 1 2 2
activity Officer
13 | P a g e JCI H E A L T H S A F E T Y & E N V I R O N M E N T
Risk Rating Action RR Rating
Job Task Hazard Necessary Control Measures
S F Rating By S L Rating
Heat stroke (Confusion, Call the ambulance for emergency medical care.
altered mental status, Permit to work
slurred speech, Loss of Stay with worker until emergency medical services arrive.
consciousness (coma),
Move the worker to a shaded, cool area and remove outer clothing.
Hot, dry skin or profuse
sweating Seizures Very
Cool the worker quickly with a cold water or ice bath if possible; wet the
skin, place cold wet clothes on skin, or soak clothing with cool water.
high body temperature,
Circulate the air around the worker to speed cooling.
Fatal if treatment
delayed). Remove worker from hot area and give liquids to drink.
Remove unnecessary clothing, including shoes and socks.
Adding Insulation of ceilings to minimize solar heat transfer;
Heat Exhaustion &
Dehydration Providing shaded work areas as much as [possible; Site Supervisor &
Heat stress (Headache, Nausea 4 4 16 Providing cooled and air-conditioned rest areas with water or electrolyte Foremen & Safety 1 2 3
Dizziness, Weakness, drinks available (not salt tablets or salt water); Officer
Irritability, Thirst, Heavy Must be arranged air ventilation fans near working area
sweating, Elevated The importance of maintaining good hydration (drinking at least 2 Liters of
body temperature, water every 2-3 hours);
Decreased urine Eating a well-balanced diet and adding a little extra salt to their meals;
output) Check your urine color, it should be pale yellow
Death Get plenty of sleeping in night, when unwell inform your supervisor.
Eat fruits, vegetables and drink more liquids.
Conduct heat stress safety campaigns more on site and explained to
workers about heat related hazards and control measures.
14 | P a g e JCI H E A L T H S A F E T Y & E N V I R O N M E N T
All operatives must be having valid iqama and insurance.
Permit to work.
Un trained employees. Ensure all employees site inducted. Site Supervisor &
Staff Competency Un authorized persons 3 4 12 Ensure all employees competent and trained in their field. Foremen & Safety 1 2 2
entry on site Ensure all employees has site entrance id. Officer
Ensure all employees has specific site internal trainings.
16 | P a g e JCI H E A L T H S A F E T Y & E N V I R O N M E N T
Risk Rating Action RR Rating
Job Task Hazard Necessary Control Measures
S F Rating By S L Rating
Prepared By: Severity (S) Frequency (F) Risk Rating (RR) Very High High Medium Low
PM-Project Manager R=S x F 15-25 8-12 4-6 1-3
SM-Site Manager
HSE Manager 1 Minor Injury 1 Improbable Unacceptability limits S 5 4 3 2 1 F
SS-Site supervisor( / Sub-con) 2 Major single injury 2 Possible More than 6 is unacceptable re-assess 5 25 20 15 10 5
SC-Sub-contractor 3 Major multiple injury 3 Occasional task and preventive actions. 4 20 16 12 8 4
SPIC-Site person in charge 4 Single death 4 Frequent
3 15 12 9 6 3
5 Multiple deaths 5 Regular
S = 0 id deemed to be the limit of 2 10 8 6 4 2
practicability of control measures. 1 5 4 3 2 1
17 | P a g e JCI H E A L T H S A F E T Y & E N V I R O N M E N T