Professional Documents
Culture Documents
Kaveh Mobadel
Kaveh Mobadel
1. PURPOSE OF DOCUMENT
3. APPLICABLE DOCUMENTS & REFERENCES
4. PHASED ARRAY INSPECTION PROCEDURE
ATTACHMENT: SAMPLE ,STANDARD
1. PURPOSE OF DOCUMENT
Reference Title
[1] ASME Sec. V 2010 Ed. Nondestructive examination
[2] ASME Sec. VIII div2, 2010 Ed. Alternative Rules for construction of pressure vessel
1.1 Introduction
1.1.1 General
This procedure has been developed as a procedure for the Ultrasonic Phased Array
inspection will be performed to evaluate for pressure vessel welds for the evaluation of
related cracking and welding flaws. All requirements and acceptance criteria in this
procedure are therefore client specific and apply only to this particular inspection.
This procedure describes the general requirements for parameters such as equipment used
inspection procedure and scanning parameters, personnel certification, evaluation and
acceptance and reporting.
Were applicable this procedure was written based on ASME Sec V Article 4 Edition 2010.
All welds made shall be fully examined by Phased array inspection system for 100% of the
weld, in conformance with ASME Sec V. The inspection system shall be capable of locating
and accurately accessing the through-wall height and circumferential length of defects, in
a manner that permits the use of the acceptance criteria defined by the Company in
conformance with ASME Sec VIII Division II or code case 2816.
To obtain 100% coverage, Scans should include offset dimensions, part thickness and beam
coverage of the full body of weld material and HAZ area.
1.4 Equipment
1.4 Equipment calibrations
Equipment checks according to the requirements set in ASME SEC V and at the interval
as described in the table below.
Equipment shall also be checked prior to the start of inspection, after transportation and
arrival on site.
2) Material type(s)
3) Component geometry
5) Assembly geometry
6) Access limitations if any (approx. 1m of room is needed in all directions around the
item under test for optimum testing)
1.5.3 Temperature
The maximum surface temperature when using conventional probes and couplants shall
nning may be performed at higher temperatures, but may require special couplant ,probes
and wedges. If scanning is performed at higher temperatures , the effectiveness of the
technique shall be proven at the required temperature on the calibration block.
1.5.4 Couplant
A couplant shall be used which provides optimum wetting, transmission of ultrasound,
resistance to corrosion, viscosity and removal characteristics. For this type of inspection,
water or the standard ultrasonic gel UCA-2 or equivalent shall be used.
The couplant used for calibration shall be the same as that used in subsequent testing and
post calibrations.
The initial set-ups shall be based upon experience, modelling, or other data and described
in a scan plan. The initial set-ups shall be validated at the start of an inspection on a
reference block containing artificial defects.
If during the scans on the reference blocks changes to the number of set-ups or the set-up
parameters were required during the validation, these equipment parameters shall be used
as reference parameters for the inspection and for the client validation.
The Inspection shall only start if the Client validation has been completed successfully.
1.6.2 System Verification
Place probe onto calibration block and maximize echo from side drill hole which
gives the highest amplitude (1/4 T) and bring this to 80% f.s.h. and record.
Accept TCG
Place probe onto calibration block and maximize echo From bottom surface
notch which gives the highest Amplitude and maximize it.
Maximize and record for bottom surface notch for next Leg and accept TCG.
1.6.2.4 Encoder Calibration
Encoder calibration shall be performed at the start of each working day and after exchange
of the encoder. The encoder shall be calibrated over a length of the item under test. The
positional feedback from the encoder shall not differ more than +/- 1% from the actual
distance moved.
1.6.4 Recalibration
The system shall be recalibrated in the following circumstances.
Change of critical system variable, i.e. sweep angles, gates , Range etc
Change of equipment
Change of Personnel
Change of Couplant
If any point on the T.C.G has shifted more than 3 dB from initial settings.
The inspection shall be carried out as manual scaning, which will guarantee that the sound
beam is always, aimed perpendicular to the weld fusion faces. The collected data shall be
presented in A, S, D, and C-scan format.
For the Root scan the reference reflector shall be set so that the signal to noise ratio of
root roll response is 10% screen height.
The amplitude response shall be determined by placing the cursor on the indication and
recording the displayed values there
Due to the geometry all indications shall be measured longer than actual. A conversion
factor shall be applied to report the correct value for all indications.
The amplitude response shall be determined by placing the cursor on the indication and
recording the displayed values there
Due to the geometry all indications shall be measured longer than actual. A conversion
factor shall be applied to report the correct value for all indications.
1.7.3 Evaluation Techniques
All indications will be evaluated and characterized using the UT STUDIO software by
observing the A-C-S scan .
In the case of a repair, the repaired area and 100 mm either side of this area shall be re-
examined in accordance with this procedure and using the original technique as with the
primary examination.
Phased array examination results can be presented in A, S,C scan views each separately
or a combination, providing views of an indication from every desired angle.
All data will be backed up twice to portable media. The copies will be stored separately.
All Phased array examination data shall be presented to the client for confirmation
purposes.
All Phased array examination data shall be saved in a suitable format, All data backups
shall include details of the type and version of this software.
All recorded data shall be evaluated with the analysis software on the UT STUDIO system
or the analysis software on a separate computer. For analysis different views and
combinations of views will be available. At the discretion of the Level 2 operator data
processing can be applied to optimise the analysis.
1.9 Reporting
A typed report from PLI’C will be handed over, containing all significant indications and
all areas of non-access shall be handed over to the client’s authorized representative as
soon as is practical after data collection. An electronic printout of the equipment settings
shall be attached to each report.
1.9.1 Weld Inspection Record
The Weld Inspection Record shall consist of a complete record showing the reference point,
the direction of scanning, the Weld ID, date and time of inspection, and the Operator
signature. The search unit number in each channel shall also be recorded. The Company
may approve alternate record formats.
The Contractor shall submit ultrasonic reports to the Company daily, as directed by the
Company, using forms approved by the Company.
Project Name
Date
Inspector’s Name
Weld Number