Professional Documents
Culture Documents
SM-04 PMP Exercise August 2020
SM-04 PMP Exercise August 2020
SM-04 PMP Exercise August 2020
Certification
Program
Exercise
August 2020
4 The most important project manager skill is his ability to calculate the
schedule
5 The only interests the project manager should protect are the interests of the
customer
1|Page 10
True or False - Answers
False 4. The most important project manager skill is his ability to calculate the
schedule.
False 5. The only interests the project manager should protect are the interests of
the customer.
2|Page 10
Sample Project Charter
Project
Created By Date
Phone Email
Requirements
Business Need
Purpose
Business Case
Functional
Organizations
Stakeholder
Influences
Project
Manager
Summary
Milestone
Schedule
External
Assumptions
External
Constraints
Summary
Budget
Approvals
3|Page 10
Sample Scope Statement
Project
Created By Date
Phone Email
Product
Requirements
Product
Acceptance
Criteria
Project Boundaries
Project
Deliverables
Project Constraints
Project
Assumptions
Initial Project
Organization
Schedule
Milestones
Initial WBS
Order of Magnitude
Cost Estimate
Project
Configuration
Management
Requirements
4|Page 10
Sample Communication Plan
Deliverables/Desc Target Audience Communication Delivery Who’s
ription Method/Type Frequency Responsible?
Project Meetings
Kick Off Meeting GAS Sponsor and PM presents the Once at the Project
Rep, Project startup start of the Manger
Manager document to project
BGS Rep and
Estimated
accepts the
document (If 9/11/2009
applicable).
Project Closure BGS Sponsor and Review and Once at the Project
Meeting Rep, Project accepts (If end of the Sponsor and
Manager and project applicable) the project Project
sponsor project closure Manger
Estimated
report.
11/01/2010
Review Meetings
Requirements BGS Rep and Project Review the initial Once after Requirements
Review Manager and Vision and SRS initial Vision lead
Requirements document BGS and SRS
engineers Rep may add document is
comments to the ready
functionality Estimated
specification 17,23/11/2009
Prototypes Review BGS Users and Review web site Once after Design Lead
Project Manager and prototype, format prepare initial
- Structural Design engineers and graphic. Design
- Behavioral Estimated
- Final 26/11/2009
22/12/2009
Test Plan Review QA lead and Project The lead share Once QA Lead
Manager and Testing the test plans,
Estimated
engineers Review and
update the Test Mon 2/2/09
plan
Documentation BGS users, Project Review and Once after Documentation
Review Manager and update User and develop the Engineer
Documentation Technical manuals
engineers Manuals, BGS Estimated
Rep Accept if 5/8/09
applicable
5|Page 10
Project Reports
Progress Report BGS Rep Project progress Weekly/ Project
report template Thursday Manger
emailed to the
target audience.
Project Closure BGS Sponsor and Before Closure Once Project
Report Rep, project sponsor meeting Sponsor and
At end of the
and manager Manager
project
6|Page 10
Critical Path Exercise
• Early Schedule.
• Late Schedule.
• Total Float.
• Critical Path.
7|Page 10
8|Page 10
Earned Value Exercise
This is our famous fence project. Each side is to take one day and cost one thousand dollars
($1000). Sides are to be done in sequence. Review the status chart above. Today is the end
of day 3.
PV
EV
AC
BAC
CV
CPI
SV
SPI
EAC
ETC
VAC
9|Page 10
Earned Value Exercise - Answers
10 | P a g e 1 0
11 | P a g e 1 0