Montevideo, March 07th, 2024

Synergia S.A.C
Att: Alexander Thomas

Ref.: Proposal to buy 100 Metric Tons of Refined Metal with Antimony

1. PRODUCT AND QUALITY


The material shall be Refined Lead with min 3% Antimony content in the form of ingots and origin Peru. Material
shall be delivered in the form of ingots and in batches of min 25 mt plus a tolerance of 5 (five) percent,

2. QUANTITY
100 mt plus a tolerance of 5 (five) percent of Refined lead with 3% of Sb content

3. DELIVERY
Delivery shall be FOB Callao basis quarterly deliveries of the material from March to December 2024 (both
months included).

4. PRICE:
Lead as quoted on the London Metal Exchange over the quotational period plus a US Dollar 65.00 (US Dollar
sixty five) premium.

5. QUOTATIONAL PERIOD:
Seller has the option to fix the price of the material until the day before the last day of M (“M” being the month
of delivery). If material hasn’t been fixed by then, pending material will be settled at the average of the official
price published for M+1

6. PAYMENT:
To be done basis FCA Callao at 90%, 3 business days after presentation of below documentation;
• Holding certificate issued by Impala
• Seller's Invoice
• Certificate of Analysis
• Weight certificate

Final payment to be done once final price is known and against below documentation:
o Bill Of Lading
o Certificate of Origin issued by Peru’s chamber of commerce

7. WEIGHT:
The bill of lading weights shall govern. If out turn weights differ by more than 0.2% from the bill of lading weight,
then the Material shall be segregated and a conjointly appointed independent surveyor shall be retained to
weigh the Material. The surveyor's findings to be final and the cost of the surveyor shall be borne by the losing
party.

8. OTHERS
The Contract incorporates Trafigura’s General Terms and Conditions for the Purchase of Physical Non-
Ferrous Metals, including without limitation the arbitration agreement contained therein (the “GTCs”). The
Buyer acknowledges and admits it has full notice of the GTCs. The Contract comprises this Contract
Confirmation and the GTCs. Undefined terms in this Contract Confirmation, which are defined in the GTCs,
shall have the meaning ascribed to them in the GTCs.
9. VALIDITY
Monday 11th March 2024 by 18.00 hrs Montevideo time, thereafter, subject to reconfirmation by the Buyer.