CONTRATO MANO DE OBRA No.013-2023, PARA LA MAMPOSTERIA DE FACHADA DEL PROYECTO VIVO 52 CORTE No. 7
ACUMULADO TOTAL POR EJECUTAR
23-mar-24
12 PAÑETE EXTERIOR IMPERMEABILIZADO M2 M2 622.00 $ 17,801.00 $ 11,072,222.00 3.5728 $ 63,599 24.4 $ 435,166 3.93% 597.55 $ 10,637,055.91
13 PAÑETE EXTERIOR IMPERMEABILIZADO ML ML 119.66 $ 13,351.00 $ 1,597,580.66 0 $ - 40.3 $ 537,872 33.67% 79.37 $ 1,059,708.92
14 PAÑETE INTERIOR M2 M2 622.00 $ 11,797.00 $ 7,337,734.00 50.927 $ 600,786 247.8 $ 2,923,379 39.84% 374.19 $ 4,414,354.82
15 PAÑETE INTERIOR ML ML 119.66 $ 8,258.00 $ 988,152.28 9.6 $ 79,277 143.0 $ 1,180,894 119.51% -23.34 -$ 192,741.72
21.0 BLOQUE CONCRETO M2 M2 250.00 $ 36,000.00 $ 9,000,000.00 44.079 $ 1,586,844 93.5 $ 3,365,748 37.40% 156.51 $ 5,634,252.00
22.0 BLOQUE CONCRETO m m 60.00 $ 25,200.00 $ 1,512,000.00 2 $ 50,400 8.3 $ 209,160 13.83% 51.70 $ 1,302,840.00
LLENADO CONCRETO GROUTING EN DOVELAS
23.0 m 933.00 $ 9,996.00 $ 9,326,268.00 159.85 $ 1,597,861 579.0 $ 5,787,184 62.05% 354.05 $ 3,539,083.80
(BLOQUE DE CONCRETO)
24.0 RECALCE DE PLACA DE 0 A 4CM mano de obra UND 113.00 $ 35,000.00 $ 3,955,000.00 15.8 $ 553,000 64.3 $ 2,250,150 56.89% 48.71 $ 1,704,850.00
25.0 INSTALACION DE PLATINAS UND 724.00 $ 5,000.00 $ 3,620,000.00 0 $ - 36.0 $ 180,000 4.97% 688.00 $ 3,440,000.00
26.0 VIGA CANCHADA M 50.92 $ 36,000.00 $ 1,833,120.00 3.745 $ 134,820 24.4 $ 879,840 48.00% 26.48 $ 953,280.00
27.0 COLUMNETAS DE FACHADA M 61.80 $ 36,000.00 $ 2,224,800.00 4.5 $ 162,000 14.3 $ 514,800 23.14% 47.50 $ 1,710,000.00
28.0 FILOS Y DILATACIONES M 600.00 $ 4,000.00 $ 2,400,000.00 98.32 $ 393,280 360.0 $ 1,439,980 60.00% 240.01 $ 960,020.00
29.0 INSTALACION DE SELLO FACHADAS M 215.00 $ 3,500.00 $ 752,500.00 31.081 $ 108,784 63.8 $ 223,178 29.66% 151.24 $ 529,322.50
30.0 DINTELES PREFABRICADOS UND 69.00 $ 199,000.00 $ 13,731,000.00 0 $ - 7.0 $ 1,393,000 10.14% 62.00 $ 12,338,000.00
31.0 STAND BY EQUIPO Y PERSONAL 1.00 $ 3,000,000.00 $ 3,000,000.00 1 1.0 $ - 100.00% 0.00 $ 3,000,000.00
DESMONTE Y MONTAJE DE GANCHOS POR
32.0 UND 20.00 $ 25,000.00 $ 500,000.00 $ - 0.0 $ - 0.00% 20.00 $ 500,000.00
LOGISTICA DE LA OBRA
33.0 JORNALES EJEROS UND 5.00 $ 120,000.00 $ 600,000.00 $ - 2.0 $ 240,000 40.00% 3.00 $ 360,000.00
34.0 JORNALES OFICIALES UND 5.00 $ 120,000.00 $ 600,000.00 $ - 3.0 $ 360,000 60.00% 2.00 $ 240,000.00
35.0 JORNALES AYUDANTES UND 5.00 $ 85,000.00 $ 425,000.00 $ - 5.0 $ 425,000 100.00% 0.00 $ 0.00
INSTALACIÓN DE ANCLAJES, PARA REFUERZO
UND 1098.00 $ 13,000.00 $ 14,274,000.00 165 $ 2,145,000
NO ESTRUCTURAL PARA DOVELAS CON UN
SON: quin
CONTRATISTA: DIRECTOR DE OBRA: DIRECTOR DE PROYECTOS: SUPERVISIÓN TÉCNICA:
C:\Users\Hp\AppData\Local\Temp\6cb127bd-b180-4a3c-895c-43c4d74a23b8_OneDrive_1_24-3-2024.zip.3b8\ PG 1 DE 1