Professional Documents
Culture Documents
Review of Bid Documents
Review of Bid Documents
Review of Bid Documents
Bid Documents 2
* Why we need to bid documents?
The contractor used it in prepare an estimate and
submit a bid.
- It’s legal documents for construction and completion
of the project.
Bid Documents 3
• Contract Requirements:
1) Competitive contract.
2) Negotiated.
Bid Documents 4
_ The owner and engineer perform the evaluation of bids at
later date.
_ Most governments award contract to the lowest bidder,
provided all conditions of the contract have been met.
_ Private owners are not required to award the contract to
the lowest bidder but may select to the contractor
deemed most desirable for the project.
Bid Documents 5
• Arrangement of contract documents:
1) Legal matters:
- Bid forms.
- Bond requirements.
- Insurance requirements.
- General condition.
- Supplementary conditions of the contract.
Bid Documents 6
2) Technical matters :
- Plans (drawings).
- Specifications that describe the material,
workmanship, and methods of construction that are
required to build the project.
Bid Documents 7
• Building Construction Specifications:
It’s defined :
1) The quality of material.
2) Performance rating of equipment.
3) Level of workmanship.
4) Warranty requirements.
• Construction Specification Institute (CSI) Master
format organizes project information into major
divisions.
Bid Documents 8
A list of the CSI numbers and titles includes:
Bid Documents 10
Bidding requirements
• The information contained in this section of the contract
documents is extremely important to the estimating team . typical
information in the bidding requirements includes:
Bid Documents 11
Bid solicitation
• The bidding solicitation some times called the invitation to bid
contain the time that bids must be submitted . the estimator
must establish a plan to complete all work to meet the deadline
of the bid date , other wise the bid will be disqualified. The bid
solicitation also gives the name and address of the owner and
design organization with instructions on how to obtain the bid
documents.
Bid Documents 12
instruction to bidders
• The instruction to bidders section describes vital information that is
required to submit a bid. For example that may appear in the
instruction to is a statement that the contractor must make a
provision during execution of the contract document to allow the
owner to take advantage of the owner's contract documents to allow
the owner to take advantage of the owner's tax exempt status for
materials and equipment purchased for the project.
Bid Documents 13
Information Available to Bidders
Bid Documents 14
Bid forms
• The bid form defines the format that is required for submission of the
bid.
The format of the bid form impacts the assembly and summary of
costs in the final estimate . the owner may request the bid as lump
sum, unit prices based on predefined pay quantities in the bid
documents , or combination of both.
Bid Documents 15
• For construction project the work may priced by several method or
combination of the pricing method. The method selected depends on
distribution of risk between the owner and contractors.
Bid Documents 16
Bid form for lump-sum contracts
• for project where a complete set of plans and specification have
been prepared prior to construction and quantity of work is well
defined, the estimate is normally prepared for the purpose of
submitting a lump sum bid on the project. Building type project are
usually bid on a lump sum basis .
Bid Documents 17
• Its common practice for project to have one or more "alternates"
attached to the bid documents of lump sum contracts the alternate
may be to add or deduct a work item from the base of lump sum bid.
• A lump sum estimate must include the cost of all material, labor,
equipment, overhead, taxes, bonds and profit.
Bid Documents 18
Unit – Price contracts
Bid Documents 20
Addendum
• It is a change in the contract documents during
the bidding process, before a ward of the
contract.
• Addenda are issued to correct errors in the
contract documents or clarify an issue. May
concern addition to the work at the request of
the owner.
• The estimating team must be certain that the
costs of all addenda are included in the
estimate.
Bid Documents 21
Alternate
• It is an addition or subtraction to a base bid price for
substitutions requested by the owner during the
bidding process.
• Each alternate is listed and numbered separately in
the bid documents.
• For example:
An alternate No.1 may be add the parking lot.
An alternate No.2 may be deduct the sidewalks.
Bid Documents 22
Change order
Bid Documents 23
Warranties
25
Type of bonds
Three type of bonds are commonly
required in construction contracts (as
the book):
1. Bid bond.
2. Performance bond.
3. Payment bond.
26
Bid Bond
• It is ensure the owner that the contractor will sign
the contract for the bid amount, if the bidder refuses
or fails to sign the contract, the owner may retain the
bond or check as liquidated damages.
• Its amount equal to (5-20)% of the amount of the
bid.
27
Performance Bond
• It is ensure the owner that the contractor
will perform all work in accordance with the
contract documents.
• Performance bond last for the period of
construction of a project.
• Its amount 25,50,100% of the contract, but
the cost of the bond usually is based on:
1. Amount of the contract.
2. Duration of the project..
28
Payment Bond
or Material and Labor Payment Bond
29
Maintenance Bond is
not mentioned in this
book.
30
If the contractor:
default,
31
Insurance
• The contractor must secured insurance, because
there are many risks involved in construction.
• The precise losses that are reimbursable from
insurance are based on predetermined losses
named in the insurance policy.
32
Types of Available Insurance for Construction
Projects
1. Basic Builder's Risk Insurance.
2. Public Liability and Property Damage
Insurance.
3. Workmen’s Compensation Insurance.
4. Contractor’s Equipment Floater.
33
Basic Builder's Risk Insurance
• General Builder's Risk which covers damages to the
project due fires, wind, and hail.
• Insurance is based on the estimated completed
value of the project, so the premium rate usually is
set at 60% of the complete value.
• Basic Builder's Risk Insurance varies with the type
and location of the structure.
34
Public Liability and Property Damage Insurance
• It protects the contractor against injuries to the
general public or public property due to actions of
the employees while performing works.
• The cost of this insurance depends on the type of
work and the safety record of the contractor.
• It is range from (2-8)% of the base cost of the labor.
35
Workmen’s Compensation Insurance
• To protect workers as a result of injury or death on a project.
• It provides medical expenses and payment of lost wages during the
period of injury.
• The cost can range from (10-30)% of the base cost of the labor,
depending on the type of work that is performed by each worker.
36
Contractor’s Equipment Floater
• It provides protection against loss or damages to equipment because
of fire, tornado, flood, perils of transportation, and theft.
• The cost varies with location, it is about $1.50 per $100.00 of
equipment value per year.
37
Building construction drawings
title sheet (This sheet contains the name of the project, owner,
designer, and other pertinent information related to the project).
Bid Documents 38
Title sheet
Bid Documents 39
Building construction drawings
index sheet (which provides a summary of all the remaining sheet in
the drawings, Its shows the list of drawing. For building type project, the
remaining sheets generally follow this arrangement: civil, architectural,
structural, mechanical, electrical, plumbing, and fire protection. A letter
before the sheet number identifies each drawing. For example, the civil
drawing are number C1, C2, C3, etc.; the architectural drawings are
number as S1, S2, S3, etc).
Bid Documents 40
Index sheet
Bid Documents 41
Building construction drawings
Plans, elevations, and sections(he pictorial presentations used in
drawings are shown from several viewing angles).
plane views (Views looking vertically down on the object ).
elevation views (Views looking horizontally at an object ).
Bid Documents 42
Plane views
Bid Documents 43
Building construction drawings
perspective views (Views looking at an object
from a point that is not perpendicular to any face
of the object).
A section view (view of the object as seen by
passing a cutting plane through the object)
A detail (is an enlargement of a specific area of a
project. Connections of structural components are
generally sown as details).
Bid Documents 44
Detail drawing
Bid Documents 45
Building construction drawings
Bid Documents 46
Building construction drawings
Line Work:
Several types of line work that are used in preparing
drawings include:
• Thick lines-outline edges of objects (plans and elevations).
• Thin lines with short dashes-denote the centerline of an
object
• Phantom lines-show the path of moving parts
• Broken lines-denote the object is longer than shown
• Short dashed lines-denote edges on the object that cannot
be seen from the near side surface of the object
Bid Documents 47
Building construction drawings
• Scales
• Usually the type of scale used is identified at the bottom of
the page on the drawings. However, several different scale
may be used on a single sheet. Therefore, it is important to
be certain that the correct scale is used in determining the
quantities for estimating. Occasionally, a portion of the
drawing is shown without any scale. When this condition
exists, there should be a note that states the drawing is not
to scale. The estimator must also be cautious because
sometimes the drawings are reduced in size, such as a half-
size drawing, to permit easier handling during construction.
Bid Documents 48
Building construction drawings
• Scales
• Two types of scales are used in construction drawings, the architect’s scale
and the engineer’s scale. The architect’s scales that are commonly used for
plans and elevations include 1/32 in. = 1 ft and 1/16 in. = 1 ft. Complicated
areas often use the ¼ in. = 1 ft, or ½ in. = 1 ft on the architect’s scale. Special
applications that require high details are 1.5 in. = 1 ft, or 3 in. = 1 ft, or may
be drawn to a half or even a full scale.
• The engineer’s scale, graduated in tenths of an inch, is often used for civil,
structural, and mechanical drawings. The scales are 10, 20, 30, 40, 50, and
60. The higher numbers of 50 or 60 are used for large areas, such as site-
work or plot plans. Details of drawings often use the smaller numbers, such
as 10, 20, or 30. The 40 on the engineer’s scale is equivalent to the ¼ in. on
the architect’s scale.
Bid Documents 49
Building construction drawings
• Schedules
• To simplify the presentation of repetitious items (such as
footings, columns, doors, windows, room finishes, etc.) a
schedule is frequently used. A schedule is a tabular listing
of the repetitive items in the project. For example, a room
schedule is a tabular list of all rooms in the structure,
showing the type of floor covering, wall covering, and type
of ceiling. Likewise, a footing schedule is a listing of all
footings in the foundation, showing the diameter, depth,
type, size, and number of reinforcing bars. Thus, a schedule
is a concise and convenient method to show all common
types of items in one location.
Bid Documents 50
Building construction drawings
• Symbols and abbreviations
• Symbols are used on the drawings to identify the
types of materials and work required during
construction. Examples are valves, pumps, type of
welds, electrical outlets, etc. Abbreviations of
organization that produce technical information
and standards for materials and construction
procedures are frequently referenced in the
specifications of contract documents.
Bid Documents 51
Detail drawing
Bid Documents 52
DETAILED SPECIFICATION
• Nature of work
• Gives description of work in a detailed manner
signifying type /category of work.
• At different levels places structures buildings
etc
• Eg. Masonry in ..., plaster…., Flooring...,
Cladding... Etc for the material used.
DETAILED SPECIFICATIONS
• Materials involved
• Lists out various materials which are used in work
specifying
– Name,
– Class or grade,
– Type,
– Category.
• Tolerances
– Gives limit measured from true level /dimension up to which
material / workmanship could be accepted.
– This is in reference to the provisions under standard I.S. Codes of
practice or other references as per contract.
DETAILED SPECIFICATIONS
• Material specification
Gives physical and chemical composition of the material, it’s
properties according to relevant standards and also extent of
performance required of material viz. Acceptable limits.
• Work procedure
Gives a detailed description of various steps involved in
execution of work including necessary pre-cautions as
required.
• Method of measurement
• Specifies mode of measurements for various kinds of
work.
• This is based on the procedures given in contract
/standard I.S. Codes and others as the case may be.
• METHOD OF PAYMENTS
• Specifies procedures /rules governing terms of payments, stages
of payments, and modus - operandi for payments of various kinds
of works.