Professional Documents
Culture Documents
NENTX-PYE-MS - Method Statement For Silt Fence Erection - I02
NENTX-PYE-MS - Method Statement For Silt Fence Erection - I02
EP/SP/77/15 NENTX
No: NENTX-PYE-MS-E-ZZ-001-I02
Document History
I01 27 Feb 2023 First issue PYE VHK Issue for certification
Submitted in
Included in this
Document Name Package Rev Comment
submission
No.:
CERTIFIED CONSENT
Category DRAWING NO. DRAWING TITLE DATE REV COMMENT DATE DATE
Comment Comment
Date Comment Answered by Date Answer
From No.
METHOD STATEMENT
FOR
SILT FENCE ERECTION
This document contains confidential information of Paul Y. Construction & Engineering Co. Ltd. and shall
not be copied or amended without approval of the Project Manager
Content Page
1. INTRODUCTION ............................................................................................................ 3
2. SCOPE OF WORKS......................................................................................................... 3
4. SAFETY……………………………………………………………………………………………6
5. ENVIRONMENTAL ........................................................................................................ 7
Appendices
APPENDIX A – RISK ASSESSMENT
APPENDIX B – PLANT LIST
APPENDIX C – SILT FENCE INFORMATION
North East New Territories
Landfill Extension
1. Introduction
The following method statement establishes and maintains a standard approach to carry out the
silt fence erection at SBA. This text gives a general guideline for the execution of the works.
2. Scope of Works
This Method Statement outlines construction method and sequence for silt fence erection at the
SBA, which include material delivery, hammering, post installation.
3. Sequence of Works
3.1 Preparation work
Prepare the materials for silt fence erection (e.g. Post, fence material, hand tools)
Deliver the materials from storage area to designated area for silt fence erection by crane
lorry.
1. Silt fence will be erected along the stockpile area, refer to figure 3.2.1.
2. Silt fence shall be erected along the drainage with 10m distance and maximum 2m to stockpile
soil, refer to figure 3.2.2.
3. Electric hand-held Drill will be used to prepare the holes for stablize the post
4. Put the post into the hole and hammer on the post to fix it on the ground
5. Fix the fence material on the post by cable tie
6. Silt fence material 30m per roll, 1m overlapping shall be adopted for collection.
7. Fabrication detail may refer to figure 3.2.3
1. Cut the cable tie and dismantle the silt fence from the post
2. Collect the silt fence and ready for reuse
3. Remove the post and ready for reuse
4. Relocate and erection of silt fence shall return to section 3.2
The purpose of silt fence is for stopping silt materials containing in soil entering drainage system.
The revised arrangement of silt fence will be discussed with IC/ER for approval to ensure the
surface runoff from the stockpiling area being filtered before water running into temporary drainage
system.
North East New Territories
Landfill Extension
Safety
The Risk Assessment attached in Appendix A has been prepared for all general and activities.
Specific safety procedure and precaution have been developed for all site operatives to follow. The
Construction Team Leader, Superintendent together with the Registered Safety Officer (RSO) will
oversee the implementation and make adjustment accordingly to the actual site operations, in order
to ensure a safe and amicable working environment is maintained.
4.1 Site Specific Safety Induction Training Course
All workers will attend the Site Specific Safety Induction Course conducted by the Safety
Officer. The Safety Officer will explain all necessary health and safety requirements and the
use of PPE (Personal Protective Equipment).
Safety officer shall ensure that all workforces were issued with basic personal protective
equipment (e.g. safety helmet, safety boost and reflective vest) and other personal protective
equipment which is suitable to specific task such as safety harness. Sufficient stocks shall be
kept available and record of issuing shall be maintained. All site staff and visitor must equip
the mandatory personal equipment such as safety helmet, safety shoes and reflective vest.
North East New Territories
Landfill Extension
4. Environmental
The following environmental measures will be implemented as advised by Environmental
Manager. Environmental Officer and Environmental Supervisor are responsible for site
inspection to identify potential hazards and rectify the non-conformances if found. The following
environmental mitigation measures for different aspect will be implemented and are as follow:
4.2 Air
5.2.1 Water spraying will be applied during dust generation activities for dust suppression
4.3 Waste
5.3.1 General refuse will be cleared and stored at designated area for further disposal
System.
North East New Territories
Landfill Extension
Appendix A
Risk Assessment
工作危害分析報告 Job Hazard Analysis Report
地盤名稱 (Site): North East New Territories (NENT) Landfill Extension project at Ta Kwu Ling, New Territories, Hong Kong (EPD Contract No. EP/SP/77/15)
工作項目(Work Activities): Silt Fence Erection at SBA
有關風險評估之檔案編號: 修訂版本:
(Refer to Risk Assessment Ref. no): RA_EP/SP/77/15_034 (Revision): 2
報告編寫(Reported by) : Ringo Wong 王浩康 (Safety Officer) 報告審批(Approved by) : 温啓樑 Wan Kai Leung, Kenneth (項目經理 Project Manager)
簽署: 簽署:
Signature: Signature:
危害類別 Risk Identification (在方格內劃上“”號 Put a Tick on the appropriate box) 影響Affect
施工工序(Working Sequences)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 i ii iii iv
人 物 吊 程 埋 超 惡 機 樓 交 扭 壓 跣 絆 夾 割 剌 擊 爆 體 窒 固 遇 釋 磨 噪 吸 眼 異 火 視 觸 中 肺 對鄰 其 工 公 環 資
近活
體 體 具 序 碼 重 劣 械 面 剪 傷 傷 倒 倒 傷 傷 傷 傷 炸 溫 息 體 溺 放 輪 音 入 睛 物 警 野 電 暑 塵 他 人 眾 境 產
動的
下 下 拆 出 失 吊 天 倒 倒 升 上 淹 有 爆 致 有 灼 入 不 或 埃 危害
墮 墮 斷 錯 誤 運 氣 塌 塌 降 升 沒 毒 裂 失 害 傷 眼 清 熱 沉
台 氣 聰 物 衰 着
倒 體 資 竭 病
塌
1 Preparing Work
2 Silt Fence Erection at SBA
3
Legend: Risk Identification:(1) Fall of person(2)Falling Object(3)Failure of Lifting gear(4)Wrong working sequence (5)Wrong rigging method(6)Overload(7)Adverse Climate (8)Overturning of machinery (9)Collapse of structural floor(10) Collapse of scissor platform
(11)Sprain & Strain(12)Crushing(13)Slipping(14)Trip(15)Abrasion(16)Laceration(17)Puncturewound (18) Hit Injury(19)Expolsion(20)Increase body temperature(21)Asphyxiation(22)Entrapment by a free flowing of solid(23)Downing(24)Exposure toxic gas(25)Disintegration of abrasive wheel
(26)Loss hearing(27)Breath in harmful substance(28)Eye burn(29)Things get into eyes(30)Fire(31)Poor eye sight(32)Electric shock(33)Heat Stoke(34)Pneumoconiosis(35)Affect works nearby(36)Other; Affect:(i)Workers(ii)Public(iii)Environmental(iv)Asset
保 華 建 築 工 程 有 限 公 司
PAUL Y. CONSTRUCTION & ENGINEERING CO. LTD.
SITE 地盤: NENTX (Contract No. EP/SP/77/15 ) Subject 工種: Installation Works Ref. No. 檔案編號: RA_EP/SP/77/15_034 Revision : 2
Works Description 工程敘述: Silt Fence Erection at SBA
LR 可能性等級
SR 嚴重性等級
Situation 危機等級 RATING ACTION
Priority 次 序
FOLLOW
受影響情況 剩餘危機等級 BY UP
Work Sequence Hazard CONTROL MEASURES 負責人 日常跟進
Worker(W)
施工步驟 危 害 控 制 措 施
Public(P) RR= = LR(Residual) x
Environment(E) LR x SR SR(Residual)
Asset (A)
1. Preparing Work Adverse Climate (Lightning etc.) W, A 3 4 12 1st When the thunderstorm signal is hoisted, it is necessary to 1x2=2 Foreman
suspend the lifting work and take shelter in a safe place
Keep contact with the Observatory to receive the most updated
information
Evacuate all workers to the designated gathering points during
thunderstorm, amber rainstorm or red rainstorm signal is hoisted
Heat stroke W, A 3 2 6 3rd Maintain sufficient shelters to avoid long hours of outdoor work 1x2=2 Foreman
and take rest in a cool place at certain time
Provide sufficient drinking water to worker
Sprain & Strain (by awkward posture) W, A 3 2 6 3rd Assign at least 2 workers to delivery materials over 16kg 1x2=2 Foreman
Use proper posture and gesture to lift up the object
Falling objects during lifting operation W, A 4 2 8 2nd Re-check of LG with the objects before lifting 1x2=2 Foreman
Ensure the LALG are in good condition and possess valid
certificates
Lifting zone shall be identified and demarcated
Tags lines must be used to prevent the lifting loads are swinging
or rotating
Fence off the workplace to prevent unauthorized person entry
Failure of lifting gear W, A 4 2 8 2nd Lifting gears shall have valid certificates and checked before use. 1x2=2 Rigger
Ensure the safe working load of the lifting gears are sufficient to
lift the loads
Training requirement : Induction Training, Method statement & Specific Trade Training (by Safety Officer), Rigging Course–Construction materials Rigger (by CICTA/approved parties), Training for Crane Operator(by CICTA)
Competence : Arrange pre-work meeting, assign competent rigger
Emergency situation : Contact emergency coordinator, Mr. Stanley Sin at 6310 8201 for any emergency case.
PPE requirement : Safety helmet(EN397)、Safety shoes(EN345)、Safety Harness (EN361)、Rigging gloves(EN388)、Welding gloves(EN388,EN420)、Chemical gloves(EN374,EN388)
: Disposable Respirators(NIOSH N95)、Reflecting vest and fall arrestor(EN353)。
Others
LR 可能性等級
SR 嚴重性等級
Situation 危機等級 RATING ACTION
Priority 次 序
FOLLOW
受影響情況 剩餘危機等級 BY UP
Work Sequence Hazard CONTROL MEASURES 負責人 日常跟進
Worker(W)
施工步驟 危 害 控 制 措 施
Public(P) RR= = LR(Residual) x
Environment(E) LR x SR SR(Residual)
Asset (A)
1. Preparing Work Overload of lifting operation W, A 4 2 8 2nd The lifting loads cannot exceed the SWL of the crane lorry 1x2=2 Crane operator
Automatic safe load indicator (ASLI) shall be provided to avoid
overload
Crane operator should be appointed and have valid certificate for
lifting operation
nd
Collapse of crane lorry W, A 4 2 8 2 Outriggers should be fully extended and carried out by 1x2=2 Crane operator
competent and experienced operator.
The mats with 3times size of outrigger float shall be used.
Struck by moving crane lorry W, A 4 2 8 2nd Maintain clearance from crane lorry 1x2=2 Foreman
All workers must wear reflective vest / uniform with reflective
tapes
2. Silt Fence Erection at SBA Slipping W, A 3 2 6 3rd Good housekeeping should be maintained 1x2=2 Foreman
Regularly check & maintain access in good condition
Trips W, A 3 2 6 3rd Do not walk on the material / hoes 1x2=2 Foreman
Maintain accesses in good working conditions
Laceration W, A 3 2 6 3rd Wear protective gloves 1x2=2 Foreman
Protective covers should be provided for sharp parts / re-bars
Electric shock W, A 4 2 8 2nd Using cordless tools to avoid electric shock 1x2=2 Foreman
rd
Things get into eyes W, A 3 2 6 3 Wear eye protector 1x2=2 Foreman
Training requirement : Induction Training, Method statement & Specific Trade Training (by Safety Officer), Rigging Course–Construction materials Rigger (by CICTA/approved parties), Training for Crane Operator(by CICTA)
Competence : Arrange pre-work meeting, assign competent rigger
Emergency situation : Contact emergency coordinator, Mr. Stanley Sin at 6310 8201 for any emergency case.
PPE requirement : Safety helmet(EN397)、Safety shoes(EN345)、Safety Harness (EN361)、Rigging gloves(EN388)、Welding gloves(EN388,EN420)、Chemical gloves(EN374,EN388)
: Disposable Respirators(NIOSH N95)、Reflecting vest and fall arrestor(EN353)。
Others
Note: Do not conduct this work unless you have been trained in its safe work
注意:除非您接受過安全工作訓練,否則請勿進行此項工作
North East New Territories
Landfill Extension
Appendix B
Equipment List
North East New Territories
Landfill Extension
Equipment List
Appendix C
流两岸,叫做——Silt Fence(淤泥栅栏)
控制的一种围栏。这些临时屏障的成本相对较低, 特别是与他们可以防止的损失相
比。它们使松散的土壤不受当地水体的影响, 也减少了各种形式的发展对周围野生
动物的冲击。后期由于加入了钢丝网的作用,同事也为加强淤泥栅栏提供了更多的
力度以及稳定性。
淤泥栅栏具有以下的特点:
1. 成本较低,可重复使用
2. PP 布与钢丝网组合,抗拉强度高
3. PP 布加入 UV,使用寿命更长久
4. 不破坏土壤,不受地形影响,安装方便
常用规格如下:
常用规格
铁丝网 PP 编织物
丝径
网孔 宽度 长度 材质 宽度 长度 克重 G/M2
14 70-100
2”X4” 2’ 100’ HDG 3’ 100’
70-100
14 4”X4” 3’ 100’ HDG 3’ 100’
70-100
12.5 2”X4” 4’ 100’ HDG 3’ 100’
让塑料尽享阳光
检 测 报 告
Test Report
报 告 编 号
委 托 单 位
Client 常州市国凯包装有限公司
样 品 名 称
共4页 第1页
宿迁联盛集团塑料防老化研究中心
让塑料尽享阳光
检 测 报 告
Test Report
报告编号 Report No. :LSYY20220923
样品描述
样品编号
A B Description of 2 组编织布
Sample Numbers
Sample
送样日期 完成日期
2022.08.25 2022.09.23
Sample Date Finish Date
试样环境及状态
Test Environment 环境温度(23±2)℃;环境湿度(50±10)%
and Condition
检测项目
抗 UV 测试、最大拉力、单位面积质量
Testing Item
ASTM-G154-2012
检测依据
GB/T1040.5-2006
Testing Method
GB/T4669-2008
灯管类型:UVB-313;
老化条件 辐照度(313nm):0.71W/㎡/nm;
Condition of aging 黑标温度:60±3℃/50±3℃;
光照/冷凝循环:480min/240min。
老化时间
500h
Aging time
试样制备说明
Preparation of
样品由厂家提供
Sample and
Explanation
共4页 第2页
宿迁联盛集团塑料防老化研究中心
让塑料尽享阳光
检 测 报 告
Test Report
报告编号 Report No. :LSYY20220923
检测项目及结果 Test Items and Result
原始样 老化时间
检测项目 检测方法 单位
NO. Original Aging
Test Item Test Method Units
Sample 500h
单位面积质量 GB/T
108.90 g/㎡
Mass per unit area 4669-2008
A 经向
最大拉力 GB/T 43.27 37.56
meridian
Themaximm 纬向 N
1040.5-2006 45.52 38.74
tension parallel
单位面积质量 GB/T
105.50 g/㎡
Mass per unit area 4669-2008
B 经向
最大拉力 GB/T 43.67 39.47
meridian N
Themaximm 纬向 1040.5-2006 47.20 41.93
tension parallel
共4页 第3页
宿迁联盛集团塑料防老化研究中心
让塑料尽享阳光
检 测 报 告
Test Report
报告编号 Report No. :LSYY20220923
检测项目及结果 Test Items and Result
初始样 老化 500h-313
1、报告若为加盖“检验专用章”或检验、审核、批准全部签字,一律无效。
2、本报告不得擅自修改、增加或删减,否则一律无效。
3、报告部分提供或部分复制均视为无效,全复印件未重新加盖“检验专用章”视为无效。
4、报告检测结果仅对受测样品负责,受测样品及样品信息由申请者提供并对其真实性负责,宿迁联盛集团塑料防老化研究中
心未核实其真实性。
共4页 第4页
宿迁联盛集团塑料防老化研究中心