Project Name:

BLUE HUB DESIGN &


TENANT FIT-OUT WORKS GUOCCO MIDTOWN UNIT CONSTRUCTION PTE LTD
#01-15

Ref No: RA-BHD&C-005


ACTIVITY– INSTALLATION OF FAN COIL UNITS Rev.No:0
Page 1 of 9

Serial Sub-Activities Risk Rating


No. Hazards Identified Risks Involved Residual
Initial Control Measures
(Generic & Task) (People & Property) Severity Probability Risk
Risk
· TBM shall be conducted by the foreman/
safety officer prior to work commencement
· Task specific safety training to be provided Low
· Unauthorized, untrained · Cuts
1. Prepare work area 2 A L (ALARP)
workers · Abrasions · Authorized personnel to undertake the job
· Daily safety inspection should be carried and
eliminate the hazard.
·Use mechanical aids such as trolley etc.
· Any lifting tasks shall be carried out by
persons those physically capable to do so.
· Incorrect lifting of loads · Back Injuries · Deploy enough number of personnel for
2. Manual Handling · Sharp edges. · Cut to finger lifting Low
3 C M depending upon the type of load to be lifted. (ALARP)
· Placing the object while · Strain
• Load not to be lifted above your shoulder
fingers underneath. • Musculoskeletal height
• Slip/trip/fall ( same level ) Injuries • Keep your fingers away from pinch point
• Unsafe posture while placing the load.
• Materials shall not be carried through
Pedestrian access.
• Area shall be illuminated with adequate
lighting.
· Appropriate personal protective equipments
shall be used while manual handling of
materials and loads.
•Pre check to be carried out by the operator prior
• Unauthorized, Untrained to start the work to ensure that no hydraulic
Workers • Fatality leaks, or other visible damages seen.
Unloading and shifting • Lifting failure. • Fractures • Ensure the crane, forklift and lifting gears shall M
of FCU unit with using • Unsafe lifting. • Property damage 4 C H have valid certificates and the operators has valid (ALARP)
3. crane or forklift • Swinging of material • Injury to personal license and approved 3rd party certificate.
• Damaged sling/wire rope or • Sprain and strain • Trained and third party certified riggers shall be
a chain • Crush provided.
• Cuts
Project Name:
BLUE HUB DESIGN &
TENANT FIT-OUT WORKS GUOCCO MIDTOWN UNIT CONSTRUCTION PTE LTD
#01-15

Ref No: RA-BHD&C-005


ACTIVITY– INSTALLATION OF FAN COIL UNITS Rev.No:0
Page 2 of 9

Serial Sub-Activities Risk Rating


No. Hazards Identified Risks Involved Residual
Initial Control Measures
(Generic & Task) (People & Property) Severity Probability Risk
Risk
• Poor maintenance of vehicle • Colour coded system shall be implemented to
• Speedy operation all lifting gears as per the month.
• Over turn • Use taglines to control the loads.
• Over load • The crane must be stopped when the wind
• Poor communication speed exceeds 38km/hr.
• Poor lighting • Never exceed the SWL marked on the crane.
• All loads shall be secured prior to lifting.
·Vehicle not to be left unattended at site (ie,to be
switch off mode if required and keys removed)
·Vehicle routes kept free of obstructions (with
spillages being cleaned up promptly)
• The crane and trucks inspection shall be
conducted periodically and record maintained.
• Adequate lighting shall be provided for the
work location.
• Barrication and warning signs shall be
provided for the area where lifting operation is
carried out restrict to unauthorized entry.
• Appropriate PPE shall be worn (Reflective
vest, cover all, helmet, shoe.)
· If the material is too heavy, use hydraulic
∙ Unauthorized, untrained • Crush trolley to shift the material.
· All materials shall be stored below 2 meters Low
workers · Cut and abrasion
3 B M (ALARP)
· Material fall from height · Damage to height.
4. Stacking and Storing
• Improper stacking • No materials shall be stored at work place, only
property
• Collapse of materials required quantity to be taken for the job.
• Personnel protective equipment must be worn
at all time during the activity. (Helmet, shoe,
vest, coverall, gloves, goggles, mask.)
Project Name:
BLUE HUB DESIGN &
TENANT FIT-OUT WORKS GUOCCO MIDTOWN UNIT CONSTRUCTION PTE LTD
#01-15

Ref No: RA-BHD&C-005


ACTIVITY– INSTALLATION OF FAN COIL UNITS Rev.No:0
Page 3 of 9
Serial Sub-Activities Hazards Identified Risks Involved Risk Rating Residual
No. Initial Control Measures
(Generic & Task) (People & Property) Severity Probability Risk
Risk
• Slip, trip and fall • Defective tools should not be issued or used
Working with Hand • Damaged warn out hand to perform the task, to be checked by store
tools ( Hack saw, tools • Fatigue keeper Low
5. hammer) • Flying objects • Trigger finger 3 C M • Use right tools for the job. (ALARP)
∙ Mushroom Heads • Cuts and abrasions • Don’t extend the spanner by using a pipe as
• Using incorrect type an extension bar.
• Chisel’s head shall have safety cap to avoid
finger injury.
• Never use a file as a lever
• Never use a screw driver as a chisel
•Hand tools shall be free from oil, grease & etc.
• Use eye/ face protection when there is flying
materials hazard, wear gloves while required to
protect the hands
• Defective equipment  Hearing losses • PTW shall be applied and obtained prior to
 Electricity  Eye injury start, If spark producing activity is performed.
6. Use of power tools  Improper use of  Crushing • Operators must be having their training card.
(Grinder, drill ) equipment  Back injury · Defective tools should not be issued or used to M
 Poor maintenance  Burns 3 C M perform a task. (ALARP)
 Untrained workers  Electrocution • Monthly inspection should be carried out by the
 Flying object  Ringing in the electrician and record to be kept at the store.
 Noise and vibration ear / Deafness · All portable power tools should be fitted with
 Fire adequate fuse protection either in the tool body
 Dust or in its electrical plug.
• Don’t lay the cables around the access way, it
should be routed properly.
• Industrial distribution board and socket only
shall be used at site.
• No joints shall be made in electrical cable.
• Cable hangers shall be used to avoid the
direct contact of power tools cable with the
scaffolding members.
Project Name:
BLUE HUB DESIGN &
TENANT FIT-OUT WORKS GUOCCO MIDTOWN UNIT CONSTRUCTION PTE LTD
#01-15

Ref No: RA-BHD&C-005


ACTIVITY– INSTALLATION OF FAN COIL UNITS Rev.No:0
Page 4 of 9
Serial Sub-Activities Hazards Identified Risks Involved Risk Rating Residual
No. Initial Control Measures
(Generic & Task) (People & Property) Severity Probability Risk
Risk
• Electrical connection shall be routed through
ELCB only ( Eg. 30ma )
· Tools should be stored and maintained in
good working condition.
· Appropriate PPE Should be use ( Goggles,
Mask, Ear plug, Gloves, Shoe, Helmet, Overall,
Vest )
·Defective Machine • Polythene sheets to be laid and drip trays to be
·Improper use of Machine • Cuts placed below the machine to prevent spillages.
• Crush • Defective machine should not be used to M
·Poor maintenance
Operating with Thread • Skin Effect 3 C M perform a task. (ALARP)
7. ·Untrained, Unauthorized • Entanglement • Only those persons who have been adequately
Machine Workers • Eye, finger injury trained and experienced in the use of the
• Slip, trip and fall • Fracture machine should be allowed to use the same.
• Spillage • Operator should check the machine condition
prior to start the work.
• Machine should be maintained in good working
condition.
• Machine shall be inspected periodically as per
the checklist.
• All spillages must be clean immediately
• Waste oil should be disposed in an approved
manner.
• Adequate lighting and ventilation to be
Provided.
• Fire extinguisher shall be provided.
• Area shall be barricaded and provide signage.
• Fire •Electric Shock • PTW (Hot work ) shall be applied and obtained
• Untrained, Unauthorized •Burns prior to start welding work is performed Low
8. Welding work (arc) Worker •Skin Effect 4 C H • Certified person only undertake the welding job (ALARP)
• Poor signage and barricade •Eye Injury • All Flammable /combustible materials should
• Lighting and ventilation •Property damage be removed from the area where welding & gas
cutting operations are carried out.
Project Name:
BLUE HUB DESIGN &
TENANT FIT-OUT WORKS GUOCCO MIDTOWN UNIT CONSTRUCTION PTE LTD
#01-15

Ref No: RA-BHD&C-005


ACTIVITY– INSTALLATION OF FAN COIL UNITS Rev.No:0
Page 5 of 9
Serial Sub-Activities Hazards Identified Risks Involved Risk Rating Residual
No. Initial Control Measures
(Generic & Task) (People & Property) Severity Probability Risk
Risk
• Fire blankets should be used to contain sparks
and molten metal’s within the floor and should
not be allowed to fall from height.
• Adequate lighting, ventilation to be provided.
• Appropriate fire extinguisher should be placed
in to the work area ( Dry powder, CO2, Fire
blanket )
• Warning signs and boards should be provided
and area shall be well barricaded.
• Close supervision shall be done at all times
while during welding.
·Appropriate PPE Should use ( Welding
helmet, dust mask, Goggles, Gloves, Shoe,
Helmet, overall, Vest )
• Visual inspection should be carried out before
use (i.e., hand rails, toe board, on the platform
and any opening are there).
• Only trained scaffolders shall be involved in
• Person/ material falling from • Sprain and strain erection & dismantling activities. Low
height • Fracture 3 C M • The ladder should extend minimum one meter (ALARP)
9. Use of ladder/ scaffold • Over reaching • Spinal cord damage from the top for safe movement
• Over loading • Musculoskeletal • Do not erect in slippery, uneven surface
• Obstructing the access way Injury • Should be set up with a 4 vertical to 1
• Slippery or uneven surface • Fatality horizontal slope ( 4:1 )
• Overhead structure and cable • Step ladder must fully open and lock the
• Untrained, unauthorized devices as per manufacturer recommendations.
Workers • Do not work from the top of two rungs of step
• Collapse of scaffold ladders.
• Remember the 3 point contact.
• Ladder shall be used for short duration works
Only limited to 15 min.
• Colour code system shall be implemented.
• Do not stack materials on to the scaffold.
Project Name:
BLUE HUB DESIGN &
TENANT FIT-OUT WORKS GUOCCO MIDTOWN UNIT CONSTRUCTION PTE LTD
#01-15

Ref No: RA-BHD&C-005


ACTIVITY– INSTALLATION OF FAN COIL UNITS Rev.No:0
Page 6 of 9
Serial Sub-Activities Hazards Identified Risks Involved Risk Rating Residual
No. Initial Control Measures
(Generic & Task) (People & Property) Severity Probability Risk
Risk
• Keep walkways free of obstacles, tools and
equipment.
• Work at height is restricted during adverse
weather condition.
• Adequate lighting shall be provided while
working at night.
• Safety harness shall be used above 2mtr height
and anchored in above shoulder height at all
time.
· Authorized personnel to undertake the job
• 3rd party certified chain blocks, hooks to be
used and to follow the colour code.
• Unauthorized, Untrained • Chain pulley block’s hook shall have safety
FCU lifting by using Workers • Fatality Latch.
10. chain blocks and • Uncontrolled movement of • Fractures • Visual inspection shall be carried out prior
lifting gears road • Eye damage 4 B M to use of chain block & lifting gears. Low
• Damaged chain blocks • Skin damage • Ensure the FCU unit are tightly secured (ALARP)
lifting gears • Property damage before starting the hooking up activity.
• Slip, trip and fall • Chain pulley block shall be used to lift the
• Collision object for vertical purpose only.
• Provide padding for the materials at sharp
corners.
• Ensure that all accessories like chain, hooks,
pins, latch & break in good working condition.
• Warning signs and barrication to be provided.
around the area to restrict the other workers
into the hazardous area.
• Close supervision to be done at all times.
• Proper communication shall be maintained
between the workers while doing the activity.
• Appropriate PPE to be worn while during
the installation ( Helmet, shoe, vest, overall,
gloves, goggles.)

Serial Sub-Activities Hazards Identified Risks Involved Risk Rating Control Measures Residual
Project Name:
BLUE HUB DESIGN &
TENANT FIT-OUT WORKS GUOCCO MIDTOWN UNIT CONSTRUCTION PTE LTD
#01-15

Ref No: RA-BHD&C-005


ACTIVITY– INSTALLATION OF FAN COIL UNITS Rev.No:0
Page 7 of 9
No. (Generic & Task) (People & Property) Severity Probability Initial Risk
Risk
· Authorized personnel to undertake the job
∙Work location shall be inspected by
concerned supervisor / foreman.
• Untrained, unauthorized • Cut and abrasion
· Deploy enough number of personnel for
Installation of FCU Workers • Back Injuries 3 C M Low
11. units and accessories • Material Fall • Fatigue material lifting shall be appointed to the task (ALARP)
• Sharp edges • Musculoskeletal depending upon the distance
• Unsafe posture Injuries • Materials should not kept in walkways, edge
• Slip, trip and fall of the opening.
• Maintain a good housekeeping policy to
prevent from slip, trip, and fall hazards.
• Close supervision shall be done at all times
• Emergency procedure shall be briefed to all
personnel prior to start the activity.
• Emergency evacuation plan shall be readily
available according to site condition and briefed
to the workforce prior to start.
• Trained first aider, fire warden and emergency
vehicle to be available at the site during the
activity.
• Emergency contact numbers shall be displayed
at work location for easy communication
• PPE shall be worn at all times( Gloves,
goggles, mask, helmet, shoe, vest, overall)

· Work notification to be applied and obtained


prior to start the night work from contractor. Low
3 B M · Proper illumination to be provided (ALARP)
∙ Poor illumination ∙ Fatality
12. While working at night
· Slip/trip/fall • Cuts · light post to be secured from fall
shift
· Proper cable management system to be
Followed
· All materials to be staged in proper manner
without obstacles

Serial Sub-Activities Hazards Identified Risks Involved Risk Rating Control Measures Residual
Project Name:
BLUE HUB DESIGN &
TENANT FIT-OUT WORKS GUOCCO MIDTOWN UNIT CONSTRUCTION PTE LTD
#01-15

Ref No: RA-BHD&C-005


ACTIVITY– INSTALLATION OF FAN COIL UNITS Rev.No:0
Page 8 of 9
No. (Generic & Task) (People & Property) Severity Probability Initial Risk
Risk
· Drink plenty of water
∙ Dehydration ∙ Employees shall be trained about heat
Low
∙ Heat Stress · Sunburn stress symptoms & first aid measures.
13. Working in hot 2 B M (ALARP)
· Skin Cancer · Avoid highly physical tasks during the hottest
weather
part of the day
· Isotonic drinks to be provided
• Provide sufficient rest breaks based on the
humidity & temperature conditions
• Heat stress management plan shall developed
and implement during the activity.
· General housekeeping, Remove all surface,
· Poor housekeeping unwanted waste materials from the building Low
14. Work Completion 2 A L · All necessary precautions will be adopted to (ALARP)
· Slip/trip/fall · Fire
prevent fire

RISK MATRIX
Probability
Project Name:
BLUE HUB DESIGN &
TENANT FIT-OUT WORKS GUOCCO MIDTOWN UNIT CONSTRUCTION PTE LTD
#01-15

Ref No: RA-BHD&C-005


ACTIVITY– INSTALLATION OF FAN COIL UNITS Rev.No:0
Page 9 of 9
A B C D E
Improbable Remote Occasional
Probable Frequent
Severity People Assets Environment Reputation 1 in 100,000 1 in 10,000 1 in 1000
1 in 100 years 1 in 10 years
Years Years years
Multiple
fatalities or
Extensive International
5-Catatrophic permanent Massive effect
damage impact
total
disabilities
Single
fatalities or
4-Severe permanent
Major
Major effect National impact
High Risk
damage
total
disabilities
Major injury
Local Considerable
Medium Risk
3-critical or health Localised effect
effects
damage impact (ALARP)
Minor
Minor
2-Marginal injury or Minor effect Minor impact
damage
health effects
Slight injury
Slight
1-Negligble or health
Damage
Slight effect Slight impact Low Risk
effects

3-E
HIGH 4-C,D,E
5-B,C,D,E
1-D,E
2-B,C,D,E
MEDIUM 3-A,B,C,D
4-A,B
5-A
LOW 1-A,B,C
2A